Pipe
Diameter (mm)
Length (m)
Roughness (mm)
AB
450
2500
0.03
BC
100
1100
0.03
CA
300
2100
0.03
The discharge entering the system at point A is 150 l/s and this meets the demand at B of 60 l/s
and at C of 90 l/s. Calculate the discharges in each pipe and the pressures at B and C if A is
supplied at a pressure of 80 m head of water.