Professional Documents
Culture Documents
Static frequency converters are today the equipment of choice for the links that exchange
energy between railway power supplies and national electricity grids. At 100 MW, the
'Bremen' static frequency link in Germany is currently the world´s highest rated installation
of its kind to employ GTO thyristor technology. Further development of the GTO thyristors,
which are connected in series, plus a new type of gate unit, made the high rating and good
economy of the link - between a 16 2/3-Hz and a 50 Hz system - possible. The advantages of
the new installation over earlier links include high availability and a considerably better
efficiency over the full power range.
Static traction power links built in the past have featured converter units with a rating no higher
than about 15 MVA. ABB recently took a first step towards higher ratings with the 2 x 25-MVA
installation for Swiss Federal Railway's converter station at Giubiasco, in southern Switzerland.
This installation was placed in commercial operation in 1994 [1, 3].
2
The new installation is located directly behind the 110-kV substation of Stadtwerke Bremen AG
and immediately next to German Railway's 110-kV substation. The converter and the control and
3
The layout of the rooms in the 54 m by 15 m large building is practically the same on the ground
and upper floors, since the main components (both converter units, the DC link capacitors and the
common turn-off circuits) are evenly divided between the two floors and arranged identically. The
chosen configuration ensures that the connecting buses are kept as short as possible.
Transparency and good access to the station components was given a high priority during the
planning. In this respect, the installation benefits in full from the inherent advantages of the
converter's modular design: ease of maintenance, low service costs, short repair times in the event
of equipment failure, all of which add up to high availability. The room in which the converter on the
16 2/3-Hz side is installed has been dimensioned to ensure good access to all the components.
Half of the converter modules and the voltage-limiting modules are on each floor of the building.
The control system cubicles are situated on the top floor, in a central position to ensure short
cables to the power components. Also on the top floor is the MMI station for local control.
The transformers as well as the compensation, filter and smoothing reactors are all located outside
of the building, but close to their associated power components.
4a,b
The vector diagram in (Image 4b) illustrates the principle of operation of the converter with GTO
thyristors. A key role is played by the short-circuit reactance XT of the single-phase converter
transformer (Image 4a). The internal converter voltage UBi can be freely chosen within certain
limits (grey area). This defines the voltage drop DUT and with it the amplitude and phase of the
current IB.
The availability of reactive power is limited by the maximum internal voltage that can be set. This is
defined by the direct voltage of the DC link and the converter control procedure described in the
following. In connection with this, it should be noted that the restrictions on the switching time do
not allow the full control voltage ust to be utilized (the maximum control voltage factor is 0.96).
7
The output voltage is controlled by means of adjustment of the amplitude of the control voltage ust
and its phase relation d, referred to the traction system voltage UB at the point where the frequency
link is connected.
Protection
The three-stage protection concept comprises prevention, protection firing, and damage
containment in emergency situations. The overriding philosophy is that everything has to be done
to prevent fault situations from occurring in the first place. This end is served by redundant GTO
thyristors as well as controlled shut-down in the event of failure of a second thyristor in the same
branch. In addition, the two branches of a GTO thyristor phase are interlocked to prevent them
from becoming conductive simultaneously.
If the preventive measures fail, shoot-through is detected within just a few microseconds by a
measuring device (also provided in redundant mode). To relieve the defective GTO thyristor phase,
all the other phases of the converter are turned on (protection firing). The design of the converter
ensures such that this causes no damage. Besides, the integrated preventive measures ensure
that protection firing occurs on only very rare occasions.
Commissioning
During commissioning, high priority was given to step-by-step verification of the correct electrical,
thermal and mechanical design of all parts of the installation. After all the standard pre-
commissioning tests had been carried out (voltage tests, tests on the control system and
protection, etc), the subsystems were tested in the following order:
• No-load test, 50-Hz infeed
The filter and compensation equipment, converter transformer, thyristor converter and DC
link had voltage applied to them for the first time. Converter control system components
(eg, the triggering equipment) were tested by means of a high-ohm converter load.
• Short-circuit test, 50-Hz infeed
A continuous test at the maximum direct current of 10.5 kA was carried out to verify the
correct thermal design of all the subsystems, and particularly the 50-Hz cooling plant. Also
tested was the control, including the supervisory control system of the thyristor converter.
• No-load test, GTO thyristor converter
The voltage formed by the GTO thyristor converter voltage was tested initially with a
reduced DC link voltage and with an open circuit-breaker on the 16 2/3-Hz side.
• Protection-related tests
Vital protection functions, such as protection firing of the GTO thyristor converter,
overvoltage limitation in the DC link and operation of the common turn-off circuit in cases of
inverter commutation failure, were tested under real-world conditions.
• Short-circuit testing, GTO thyristor converter
A continuous test was carried out (16 2/3-Hz side short-circuited and a maximum load
current corresponding to 100 MVA) to verify the correct thermal design of the converter, 16
2/3-Hz transformer and cooling plant.
• System tests, 16 2/3-Hz side
These tests included testing and optimization of the control system under real-world
operating conditions. In addition, all the guarantee values (power output, efficiency, mains
pollution, etc) were verified.
The oscillogram in Image 14 shows, as an example, the DC link voltage, DC link current and
voltage, and current at the point of connection of the traction power supply during switching from
normal transmission to phase shift mode. This sequence is switched on automatically whenever
there is a disturbance in the three-phase AC system. The reversal sequence (right-hand side of the
oscillogram) is also automatic, being carried out as soon as the AC network conditions have been
restored to normal.
References
[1] O. Gaupp, G. Linhofer, G. Lochner, P. Zanini: Powerful static frequency converters for
transalpine rail routes. ABB Review 5/95, 4-10.
[2] D. Lönard, J. Northe, D. Wensky: Statische Bahnstromrichter - Systemübersicht ausgeführter
Anlagen. Elektrische Bahnen 6/95, 179-190.
[3] P. Mathis: Statischer Umrichter Giubiasco der Schweizerischen Bundesbahnen. Elektrische
Bahnen 6/95, 194-200.
[4] P. Steimer, H. Grüning, J. Werninger, P. Dähler, G. Linhofer, R. Boeck: Series connection of
GTO thyristors for high-power static frequency converters. ABB Review 5/96, 14-20.
[5] P. Steimer, P. Hartmann, C. Perrin, A. Rufer: PSR - the world's fastest programmable controller
with function block language. ABB Review 2/93, 21-28.