You are on page 1of 2

because of the large unloading area.

Therefore, it is difficult to con- Application Results of the DAEM


trol the final deformation of the metro tunnels using conventional
excavation methods, and the uplift of the metro tunnels is likely Application of the DAEM
to be greater than it was in Yanggao Road Undercrossing and
Dongfang Road Undercrossing. According to previous construction practice and the previous analy-
In the case of DAEM, many dividing walls are constructed in the sis, both unloading and excavation duration should be reduced to
proposed construction scheme so that unloading is localized and the control the uplift of the underlying metro tunnels of Line #2. There-
unloading time is shortened. Thereafter, the DAEM proposed in this fore, the DAEM is determined to be used in this project. In this
paper has the advantage of reducing metro tunnel deformation. method, firstly, the soft soil surrounding metro tunnels is improved
by the deep soil mixing method, and the soil mixing wall (SMW)
Construction Safety method with shaped steel inserted is adopted to construct the
Unlike all the analogous cases, the skew angle between tunnel protecting walls at both sides of the two underlying tunnels (Chen
Downloaded from ascelibrary.org by California Institute of Technology on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.

excavation and the existing metro tunnel in this project was only et al. 2013). The SMW method is also used to construct retaining
26°. Thereafter, the shape of the five divided small excavations in walls and dividing walls; thus, the overcrossing area is divided into
the PIEM construction scheme is irregular and it is difficult to 21 small pits and the width of each pit is between 6 and 8 m. Secondly,
install the temporary struts between the two retaining walls and on top of the dividing wall, the reinforced concrete beams with a sec-
impossible to coordinate the construction joints and deformation tion of 800 × 1,000 mm join the shaped steel sections in the
joints for the main structure. cement–soil mixing columns together so that the dividing walls
In the PPEM construction scheme, the excavation slope is wide can act as retaining walls for the small segment excavations as shown
and the construction duration is quite long because of the large in Fig. 7(a). Thirdly, the small pits are excavated in layer. Fig. 7(b)
excavation depth and strip length, which results in a high construc- presents a photo at the construction site when the first soil layer is
tion risk. Furthermore, the width of each small strip in this scheme excavated. Three-level struts are installed during the excavation in
is only 3 m and just one strut can be installed within each strip. each small pit, including one reinforced concrete beam with a section
Because each strut is 27 m long, steel lattice columns must be of 800 × 800 mm and two steel pipes with diameter of 609 mm as
installed to support these struts and increase the stability of steel shown in Fig. 7(c). Finally, the underground structure of the new tun-
struts. Therefore, both construction difficulty and construction nel, including slab, inner wall, and roof, can be constructed rapidly
uncertainty are increased as a result of these adverse factors. after the excavation was completed. Fig. 7(d) is a photo of the con-
In the proposed DAEM construction scheme, the acute angle of struction site after the steel section is cut and the construction of the
the two skew walls is avoided and the number of construction joints base slab is completed.
and deformation joints is decreased so that the stiffness and imper- The excavation of all pits is not sequential based on their serial
meability of the tunnels are improved significantly. Moreover, the numbers but is divided into four groups to be constructed. Because
large excavation is divided into several small discrete excavations of space, equipment, and contractual limitations, small pits
and this helps in the installation of the struts and improves their numbered 2, 8, 15, 17, 19, and 21 are constructed first, and then
stability so construction safety is improved. construction of pits 1, 4, 10, 12, and 20 are carried out. In the third

Shaped steel Dividing wall

Retaining wall
Protecting wall

(a) (c)
Steel strut Dividing wall Shaped steel RC strut

Retaining wall

(b) (d)

Fig. 7. Pictures of the construction site with DAEM: (a) SMW walls constructed; (b) first RC struts constructed; (c) steel struts installation; (d) the
bottom slab constructed

© ASCE A4014003-5 J. Aerosp. Eng.

J. Aerosp. Eng.
20
Outbound

Verticle displacement (mm)


16
O x Stage1
Stage2
12 Stage3
Stage4
8

4
Excavation width
0
-80 -60 -40 -20 0 20 40 60 80
x (m)
Downloaded from ascelibrary.org by California Institute of Technology on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.

20
Inbound
Verticle displacement (mm)

16 Stage1
Stage2
Stage3
12 Stage4
O x
8

4
Excavation width
0
-80 -60 -40 -20 0 20 40 60 80
x (m)

Fig. 8. Tunnel displacements at each excavation stage

construction stage, Pits 3, 5, 7, 14, and 16 are excavated and the conventional excavation methods, construction duration can also
remainder pits are constructed last. be shortened because the small pits spaced at intervals can be
The construction of the cross segment had to be finished within constructed simultaneously in the DAEM.
260 days according to the contract. The actual construction time This excavation method was applied in the case of tunnel
for this project was 230 days which was 30 days less than the excavation above the metro tunnels of Line #2 in Shanghai. Actual
planned construction duration. Prior to excavation, retaining wall construction duration was only 230 days with the DAEM, which
construction and soil improvement took 89 days. The durations of was 30 days less than the planned construction duration. Field data
each of the four excavation stages were 40, 34, 29, and 28 days, of the maximum final uplifts of the Inbound and the Outbound
respectively. tunnels were 14.9 and 13.7 mm, respectively, both of them being
controlled to within the permitted value, i.e., 20 mm.
Displacement of the Metro Tunnels
Two automatic monitoring systems were installed in the tunnels to Acknowledgments
monitor the displacements. An extensive field monitoring program
was carried out during the excavation. The automatic results were The financial support from the National Natural Science Founda-
also checked with the results of manual surveying to make sure that tion of China (NSFC Grant No.s 41172251, 41372282, 41330633)
the automatic system was performing satisfactorily. is gratefully acknowledged. This research is also sponsored by the
Fig. 8 illustrates the uplift distributions of the metro tunnels. As Shanghai Pujiang Program (No. 13PJD017).
shown in this figure, the maximum heave of the Inbound and the
Outbound tunnels were 14.9 and 13.7 mm, respectively. Therefore,
using the proposed DAEM construction method, the heave References
displacements of tunnels were controlled within the permitted
value, i.e., 20 mm. Andromalos, K. B., and Bahner, E. W. (2003). “The application of various
deep mixing methods for excavation support systems.” Proc., Third Int.
Conf.: Grouting and Ground Treatment, ASCE, Reston, VA, Vol. 120,
515–526.
Conclusions Brown, D. C. (2003). “Novel method of excavation.” J. Constr. Eng.
Manage., 10.1061/(ASCE)0733-9364(2003)129:2(222), 222–225.
A novel construction method is presented in this paper for excava-
Chang, C. T., Sun, C. W., Duann, S. W., and Hwang, R. N. (2001).
tions crossing underlying tunnels. This construction method was “Response of a Taipei rapid transit system (TRTS) tunnel to adjacent
applied in a case of tunnel excavation above the metro tunnels excavation.” Tunnelling Underground Space Technol., 16(3), 151–158.
of Line #2 in Shanghai. The following conclusions can be obtained Chen, J. J., Zhang, L. Y., Zhang, J. F., Zhu, Y. F., and Wang, J. H. (2013).
based on the field data. “Field tests, modification, and application of deep soil mixing method
The DAEM decreases the unloading effect of soil during in soft clay.” J. Geotech. Geoenviron. Eng., 10.1061/(ASCE)GT.1943-
a single excavation and increases the uplift stiffness of the tunnel 5606.0000746, 24–34.
and surrounding soil, so that the deformation of the existing Doležalová, M. (2001). “Tunnel complex unloaded by a deep excavation.”
tunnel induced by overlying excavation is reduced. Compared to Comput. Geotech., 28(6), 469–493.

© ASCE A4014003-6 J. Aerosp. Eng.

J. Aerosp. Eng.

You might also like