Professional Documents
Culture Documents
for Stamp: IP/OE
RETURN CODE
Revision History
Rev. Revision Issued by Checked by Released by Brief Description
Date
Description current Revision
Owner
Owner’s Engineer: Contractor:
Project:
TAMBAK LOROK COMBINED CYCLE
POWER PLANT BLOCK 3 PROJECT
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW.
SEMARANG – CENTRAL JAVA
Subject: COMMISSIONING AND TESTING PROCEDURES
Issue Purpose: Responsible Dept.:
Originator:
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
t ID:
GE ENERGY PRODUCT
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
Table of contents
1. INTRODUCTION ................................................................................................... 3
2. SAFETY ................................................................................................................ 4
6. COMMISSIONING TESTS................................................................................... 10
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
1. INTRODUCTION
This document is provided only for the use of appropriately trained and Marioff
Corporation Oy authorized commissioning engineers.
The purpose of this document is to enable a safe and efficient method for the start up
and commissioning of the HI-FOG® sprinkler system, with a specific regard to the safety
of persons and equipment in the vicinity of the system being tested. All information
included in this document is only for the use of qualified personnel and has to be used
together with the component manufacturers and commissioning engineers work
procedures.
Marioff Corporation Oy and/or their representatives cannot be held responsible for the
systems incorrect installation if the relevant installation guidelines and the relevant
authority’s requirements have not been followed.
Note that all the information and details in this manual may not reflect exactly the unit
version supplied. Project specific information can be found in the project documents.
This document, and all the information it includes are the property of Marioff Corporation
Oy and therefore confidential. The document shall not, in whole or in part, be
reproduced, copied, disclosed or used as the basis for manufacture or sale without a
written approval from Marioff Corporation Oy.
Project manager
Authority
Commissioning location and
date
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
2. SAFETY
HI-FOG® water mist systems contain mechanical and electrical components and the
system’s high pressure pumps and gas cylinders are used for water pressurization.
Therefore it is crucial that all safety issues are addressed before carrying out any system
pressurization or testing.
Care must be taken to ensure that all relevant procedures, in accordance with
recognized national codes of the country of installation, are followed. Only competent,
appropriately trained personnel, who are fully experienced with the equipment being
tested, are permitted to carry out system commissioning.
It is the responsibility of the system installation company to ensure that the installed
distribution piping has been pressurized to the minimum required test pressure of either
105/210/300 bars according to the system installed. All pressure test results should be
documented and made available for the review of the supervising commissioning
engineer.
It is the responsibility of the system installation company to ensure that the electrical
installation has been carried out in accordance with the recommendations of Marioff
Corporation Oy and the relevant minimum site specific requirements. All electrical test
documentation should be made available for the review of the supervising
commissioning engineer.
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
The following tasks and/or equipment should be completed and/or supplied by the
customer/installer before the HI-FOG® system can be commissioned and tested (where
applicable).
1. All distribution piping should be completed and pressure tested in accordance with
the pressure test requirements. All pressure tests should be documented and the
documents should be available for the review of the commissioning supervisor,
prior to commissioning.
2. All sprinklers and spray heads should be in place or alternatively plugged with the
correct blanking plugs.
3. A source of clean feed water shall be available in sufficient quantity to allow full
system testing.
4. The pumps unit and gas/water cylinders should be in place and adequately secured.
5. All gas cylinder release valves to be fitted (Do not open gas cylinder valves).
6. All interconnection piping between the pumps unit, distribution piping and the
gas/water cylinder bank (if applicable) should be completed and pressure tested.
7. Stand-by pumps to be connected to a permanent clean air 4-8 bar minimum supply,
(Isolated, Do Not Open).
9. All low power alarm and signaling cabling to be completed and tested, (point to
point). All cabling to be suitably marked and identified.
10. All equipment to be properly earthed in compliance with the latest edition of the
local electrical regulations.
NOTE:
Non completion of the before mentioned preconditions will delay the full commissioning
of the system.
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
NOTE:
All deviations and/or damages must be recorded, and where necessary all remedial work
must be completed before system commissioning.
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
16. Check that drain valves’ amount and position match
the ones in drawings (if applicable).
17. Check availability of power supply.
18. Visual inspection of control panel installation or
equivalent. Check that all cores are identified.
19. Check the location and connections of the fire
alarms.
20. Visual inspection of all interconnection junction
boxes. Check that all cores are identified.
21.
22.
Engineer’s comments:
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
The following procedure is based on the preferred order of equipment start up, taking
into consideration the interface requirements between equipment and components.
Where problems occur, deviations are found, or where there is any doubt on the integrity
of the component or installation being tested, DO NOT PROCEED until the problem has
been corrected. If in doubt, STOP, and ask.
5.1 GPU 1
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
18. Fill each wet pipe section by opening each relevant
section valve in turn. Check for leakage.
19. Bleed each wet pipe section by opening the
flushing valve. Allow water to flow freely.
20. Adjust the pump unit flow monitor (if applicable).
21. Check all gas cylinder pressures. Check settings of
all gas cylinder pressure switches (if applicable).
Open all gas cylinder valves and check for leakage.
22. Check the operation of the gas release valve.
23. Test the activation of the pump unit from water flow
(if applicable).
24. Test the activation of the pump unit from low
pressure.
25. Check the pump unit’s water filter.
26. Check the operation of the fire alarm.
27.
Engineer’s comments:
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
6. COMMISSIONING TESTS
Once it has been established that the system and all components are fully operational
and all piping/cylinders have been filled and physically tested, the following
commissioning tests should be carried out. The commissioning test verifies full system
operation against the original design.
NOTES:
These tests are to be carried out to the satisfaction of the commissioning engineer and
they are done prior to forwarding of the system for third party acceptance. Some or all of
these tests may be included in the third party test requirements. Where tests include
system alarms, alarm activation must be checked both at the pump unit and the bridge
panel.
Complete
Test d
N/A Comments
1. System fault in control panel/building management
system or equivalent from low gas pressure and
broken wire.
2. Wet pipe area indication and HI-FOG connected
3. Test the sprinklers in the wet pipe areas.
4. Dry pipe area indication and HI-FOG activated
indication .
5. Check the spray heads in the dry pipe areas.
6. Special valve tests .
7. Reset function from control panel or equivalent (if
applicable).
8. Test release the system by using external gas
cylinder. Check that water mist concentration is
satisfying. Check that all the release valves
(Release, Delta-P and slave) are operating correctly.
Check the correct operation of the fire alarm
pressure switch. Check the settings of the pressure
regulator during test release.
9. Reset the system after test release. Replace empty
gas cylinder(s), check cylinder connections for
leakages and check that the operation of stand by
pump is stable.
10. Perform the fourth water test with tester and write
down the figures.
11. Check the number of the spare sprinklers and
sprinkler keys.
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
12. Check that the system is left in stand-by mode and
write down the commissioning date.
13. Write the commissioning date to the commissioned
sticker and attach the sticker near the pump unit to a
visible place.
14. System operation training given. Include participant
names in comments below.
15.
Engineer’s comments:
Marioff s.r.l.
Headquarter : 24, via Matteotti
20016 PERO (MI) - ITALY
Tel. +39 (02) 33915300
Fax +39 (02) 33915293
SDI Code: K1L1030
V.A.T. IT10802490150
www.marioff.it
Authority acceptance tests may include all or some parts of the commissioning test and
will be at the sole discretion of the representative of the relevant authority, all of which
will have been previously documented, approved and agreed.
Authority:
……………………………………………………………………………
Authority Representative:
…………………………………………………………
Client Representative:
…………………………………………………………….
Commissioning Engineer:
…………………………………………………..