You are on page 1of 46

CHAPTER 3

IMPLEMENTATION OF WORK
3.1 MATERIAL
Tools and materials are an important element in a construction
work. In practice, good management is necessary for the efficiency
of the use of tools and materials themselves. Procurement of work
equipment and building materials should be adjusted to the stages
of a work in progress. The placement of the right and efficient
worktools and building materials needs to be considered by the
team to accelerate and facilitate the work.
The location of building materials and heavy equipment providers
need to be considered also, so that the implementation of work is
optimally biased. In addition, the availability of building materials
must always be controlled so that there is no running out of building
materials. The placement of materials must also be adjusted to the
nature so that the risk of damage to building materials can be
reduced before use, especially in building materials that are
sensitive to environmental conditions such as cement and steel
joints.
Working tools play an important role in supporting the
implementation of the project. Tools to help carry out the heavy
work done by human beings. The use of tool work can also speed
up time and facilitate the implementation of projects.
The information needed in material planning is as follows:
1. The quality of the material needed in accordance with the
specifications of the plan.
2. Delivery time to be adjusted to the time schedule.
3. Termin and payment conditions to material logistics. Schedule of
material use. (Abrar,2010)
Building materials used in the Patimban Port Development Project
(I) Package 3 :Connecting Bridges , as follows
3.1.1 Fine Aggregate

The fine aggregate for concrete shall consist of natural sand


or, subject to approval of the engineer, other inert materials with
similar characteristic, having clean, hard and durabble particles,
and it shall be free from objectionable quantities of dust, silt ,
clay, organic matter , and other impurities
the fine aggregate shall be uniformly graded and shall met
the following grading requirements
Table 3.1 Fine Aggregate Specification

Sieve Size (mm) Cumulative Passing


Percentage by Weight

9.5 100

4.75 95 – 100

2.36 80 – 100

1.18 50 – 85

0.600 25 – 60

0.300 10 – 30

0.150 2- 10

Sieve analysis of fine aggregate shall be made in accordance with


JIS A 1102 (Method of Test for Sieve Analysis of Aggregate) or
AASHTO T 27.
The gradation requirement given above are the extreme limits to
be used in determining the suitability of material from all possible
source of supply. The gradation of material from any one source
shall not vary in composition beyond range of the values that
govern the selection of a source of supply. for the purpose of
determining the degree of uniformity, a fineness modulus
determination shall be made upon representative samples,
submitted by the contractor, from such sources as he proposes to
use. If fineness modulus of fine aggregate varies more than
0.2 from the value used in selecting concrete proportions, the fine
aggregate shall be rejected unless suitable adjustment of the mix
proportions are made with the approval of the engineer
 The amount of deleterious substances in fine aggregate
shall not exceed the limits specified in table 10-4. Treatment
of Other deleterious subtances with are not show in the
above table shall be determined by the direction of the
engineer
 Tests for material finer than 0.075 mm sieve shall be made
in accordance with JIS A 1103 (Method of Test for amount of
Material passing Standard Sieve 0.074 mm in aggregates)
or AASHTO 11

Table 3.2 Limits for deleterious Subtances in Fine Aggregate


(percentage by weight)

Item Max

Clay lumps 1.0

Material finer than 0.075 mm


Sieve:
3.0
Concrete subject to abrasion
All other concrete
5.0
Material coarser than 0.300 mm
Sieve floating on a liquid having a 0.5
specific gravity of 1.95

Figure 3.1 Fne Aggregate (sand)

Note :

1) in the case of the crushed aggregate, if the material finer


than 0.075 mm sieve consist of the dust of fracture essentialy
free from clay or shale, these precentage may be increased
to 5 and 7 percent respectively

2) this requirement does not apply to manucfatured sand


produced from blast furnance slag

all fine aggregate shall be free from injuirious amount or organic


impurities. approximate determination of the presence of injurious
organic impuruties in natural sand shall be in accordance with JIS
A ( Method of test for Organic Impurities in Sand). Aggregate
subjected to the colorimetric test for oraganic impurities, and
producing a color darked than the standar shall be rejected

however, any sand the fails to meet the above requirement may
be used provided that the compressive strenght of mortar
specimens using such sand is more than 95% of that of mortar
specimens using the same sand which is washed by 3% solution
of sodium hydroxide and than by water. and approved by the
engineer. testing age of mortar specimens shall be 7 and 28
3.1.2 Coarse Aggregate
Coarse aggregate is a mixture of concrete in the form
ofgravel / broken stone which is the process of solving
using the coarse aggregate shall consist of one or more of the
following:
1. Crushed stone, gravel, blast furnance slag, or other approved
inert materials of similar characteristic having clean
2. Hard durable pieces. it shall be free from objectionable
quantities of flat or elongated particles, organic matter or other
deleterious matter
3. The coarse aggregate shall be uniformly graded and shall meet
the grading requirement shown in tabel

Table 3.3 Table Grading of Coarse aggregate Specification

Item Maximum

Clay lumps 2.0


Soft Particles
Material finer than 0.075 mm sieve 5.0

Material floating on a liquid having a 1.0


specific gravity of 1.95
1.0
Figure 3.2 Coarse Aggregate
3.1.3 Water
Water is a very important base material in the manufacture of
building materials construction, in the construction of water
concrete is required to act with cement so that it can become an
adhesive material between fine aggregates and coarse
aggregates.

1) all water used in concrete shall be subject to the


engineer's approval, water used in mixing, curing, or other
designated applications shall be reasonably clean and free
from oil, salt, acid, alkali, sugar, vegetable or any other
subtance injurious to the finished product. If required by the
engineer, water shall be tested by comparison with distilled
water

2) comparasion shall be made by means of standard semen


tset for soudness, time of setting mortar strenght . Indication
of unsoundness, change in time of setting of plus or minus
30 minute or more, or decrease of mortar strenght more then
10 percent compared with distilled water shall be sufficient
cause for rejection of the water that is being tested
3) where the sources of water is relatively shallow, the intake
shall be sho enclosed as to exclude silt, grass or other
foreign materials
Table 3.4 Water Specification
Specifications
Kation
Groundwater
Anion
elements
Fe, Mn , Al , B, F dan Se
Absorption of gas
CO2 , H2S dan NH
and organic matter

3.1.4 Cement

Cement is a hydraulic adhesive building material, meaning it


will become an adhesive when mixed with water, and in some
time it will harden. This cement material is usuallyused in the
manufacture of concrete and mortar for masonry, plastering and
wall cleaning. in addition, the use of cement material is also a
mixture of adhesive materials
The cement used in the work shall be ordinary Portland Cement
except when otherwise shown on the drawings, or directed by
engineer. Cement shall conform to the requirements of SNI 15-
2049-1994 or JIS R 5210 “Portland Cemennt” or AASTHO M 85
(type 1).
Figure 3.3 Portland Cement

3.1.5 Reinforcing Bar

Steel rebar for shall be Reinforcement Iron is a type of material


that serves to overcome the tensile strength of concrete. If the
structure is not given sufficient reinforcement iron reinforcement
there will be structural failure.

Concrete Reinforcement Iron construction serves to carry the


tensile voltage on concrete. The physical condition of the iron

should be new, gray, and not rusty. Work or fabrication of cutting


and bending of iron joints is carried out according to the needs in
the fabrication. So before doing the cutting and bending of
concrete reinforcing iron required reference or guidelines
containing detailed images along with the number of fabriced bone
needs.
1)Steel rebar for reinforcement ꬹ < 12 BJTP – 24 = 235 MPa

2)Stell rebar for reinforcement D > 13 BJTD 40 fy = 390 MPa

Figure 3.4 Rebar

A. Slump Test
The Laboratory issues a concrete mix design in accordance to the
concrete mix design f’c 60 Mpa to the batching plant teams. Then
batching plant teams provides ready mix f’c 60 Mpa according to field
requirement. Before casting the batching plant do testing as follows :
1. Japanese concrete standard Specifications(JIS A5308-2019}
2. Make sure slump test value, temperature before casting as
planned (slump 60±10 cm)
3. samplingof cylindrical specimens with dimensions of 15 x 30
4. Slump Flowing test (JIS A1150)
Table 3.5 Concrete Specification

Figure 3.4 Slump (60 ±5 cm)

B. Testing Strong Press Concrete


The concrete used in this project is using f’c 60 MPa concrete.
F’c 60 MPa shows the characteristics of maximum press strength of
concrete in kg/cm2 which is 600 kg/cm2, meaning that if the
concrete is pressed more than 600 kg/cm2 the concrete will be
crushed. In a building planning for concrete is usually the resulting
output is fc' in units of Mpa. Concrete is used for concrete with
cube-shaped press strong test measuring 15 cm x 30 cm

Meanwhile use f’c usus test objects cylindrical shape with a


diameter of 15 cm and a height of 30 cm.
Here's a strong concrete press test:

Equipment

1. Cylindrical mold concrete (diameter 15 cm and height 30 cm).


2. Compression Machine.
3. Scales with thoroughness of 1 gram.

Testing Procedure :

1) Input ready mix concrete to be tested into cylinders that have


previously been smeared by lubricant / oil,
2) Put ready mix concrete little by little while in the skewers
using a stick / stick.
3) The mold is opened after 24 hours, then soaked in water,

4) Then tested (ages 3, 7, 14, 21 and 28 days) against cylindrical


concrete, concrete is weighed first then placed in the middle of the
compression machine,
5) Run the press machine, so that the test object is destroyed, note
the force to break up the sample test object seen from the tool

Figure 3.5 Sample for Testing Strong Press Concrete


3.1.6 Ducts
Duct is one of the materials for Post-Tensioning prestressing
which serves as a place to put strands.

Figure 3.6 Duct ID/OD (63/66 mm)

3.1.7 Sterofoam
Strorofoam function is to fill the space in the middle of the
ready mix concrete, then the middle girder is not filled with liquid
concrete and becomes hollow, this is a new type of girder that was
first used in Indonesia and was used for the Patimban bridge
Figure 3.7 Sterofoam

3.1.8 Strand

This strand is made of steel cable, the strand must be installed


so that no strand is twisted when stressed. Apply tape or tape to
the ends of the strands for easy insertion into the tendon.

steel reinforcement for prestressed steel conduits shall be :

 PC Strand 12,7 mm

 Standard SNI 1154 – 2005


Figure 3.8 PC Strand ꬹ 12.7 mm
3.2 WORK EQUIPMENT
3.2.1 Bar Cutter

Bar cutter is a tool used to cut iron joints as needed. At the time of
installation of iron joints are often found the length of the joints that
have been attached differently and the surface of each joint is uneven.
These barcuts are used to spruce up the bones that have been
attached or to equalize the display of each of these bones. SNI
GQ46A maximum capacity of cut steel joints is 32 mmand minimum
capacity is 12mm.\

Figure 3.9 Bar cutter

3.2.2 Bending Rebar Machine

SNI 03-2847-2002 explains that bar bender is a tool used to


bend joints. In general, the joints have a straight shape, but not
always the use of looping in a straight-shaped field because there
are some construction jobs that require theshape of the joints to be
bent according to their needs such asbarges and column joints. The
diameter of 12 mm man canstill bend manually, but for diameters
larger than 12 mm it is very effective when using a bar bender to
speed up work
Maximum bender bar capacity can bend steel with a diameter of 32
mm., so for the bending of the joints that are 8

to 12 mm in diameter is done manually with bending thatis not too


small the crooked angle while for the joints morethan 12 to
30mm using a bar bender (for a bending angle that is quite small
and complicated

Figure 3.10 Bending Rebar Machine

3.2.3 Arrangement Rebar


1. Assembly the reinforcement cage appropriate with shop drawing
the put the concrete cover in the reinforcement cage before
placing it into the base mold
2. Install the Endplate and then apply the anchor block connect
with endplate
3. Install duct based on the position of tendon coordinate (Shop
drawing) and for the edge part
4. Install void forming material into the position based on the shop
drawing. Ensure the concrete cover are finished install bottom &
side part reinforcement

Figure 3.11 Arrangement Rebar

3.2.4 Bucket

Concrete bucket is a too to transport concrete from the concrete


truck to the location

Concrete buckets can be used to open, close and lock materials so


they don't spill while on site
so this pumping is the most flexible and easily accessible method
to the foundry. the advantage of this method is that the risk of
segregation is smaller and can save time when compared to other
methods, it's just that what needs to be considered is the time to
return to the first layer to avoid cold joint
Figure 3.12 Bucket

3.2.5 Tape

The meter is also known as a measuring tape or tape or can


also be referred to as a Roll Meter, which is a length measuring
instrument that can be rolled up, with a length of 25-50 meters. This
meter is often used by builders or road width gauges. The accuracy
of measurement with a rollmeter is up to 0.5 mm. Roll meters are
generally made of plastic or thin iron plates. The units used in the
Roll Meter are mm or cm, feet or inches. Tape measure or Roll
Meter is available in lengths of 10 meters, 15 meters, 30 meters to
50 meters. The measuring tape is generally divided at 5 mm or 10
mm intervals

Used to measure distance or length. The meter is also useful


for measuring angles, making right angles, and can also be used to
make circles. At the end of the tape is equipped with a hook and is
magnetized to make it easier when taking measurements,
Figure 3.13 Tape

3.2.6 Caliper

A caliper is a measuring instrument capable of


measuring the distance, depth, and 'inner diameter' of an object
with a very good level of accuracy and precision (±0.05 mm). The
measurement results of the three functions of the tool are read in
the same way. This tool is widely used in various fields of the
engineering industry (engineering), starting from the design/design
process, manufacturing/manufacturing, to final product checking.
This tool is widely used because it has a fairly high level of
accuracy and precision, is easy to use, easy to carry, and does not
require special care. It is for this reason that the caliper is
preferred by engineers (engineers) over conventional measuring
tools such as rulers
Figure 3.14 Caliper

3.2.7 Mold

mold or container into which the concrete material is poured to


obtain the planned shap
Figure 3.15 Mold

3.2.8 Mixing Concrete

1. Take some fresh concrete to make sample & slump test before
casting.

2. Casting truck mixer to bring fresh concrete from batching plant to


bucket.
3. Arrange the bucket on the product mold location.

4. Bucket on the over head crane then pour fresh concrete into
molds.

5. Cast PC Hollow Slab girder per segment starting from segment 1


to segment 5
6. Casting use at least 3 units of vibrators. Use vibrator with needle
60 for make fresh concrete easy to fill the mold & use vibrator
with needle 40 for external vibrator every 3 m.
7. Stick neddle distance of at least 30 cm from the separator

The concrete shall be compacted such as manner as to produce


dense any homogeneous & all surface of the concrete shall be
smooth
8. `Flatten the top surface especially on the edge part of the product.

9. `Leveling the upper surface & grooving when concrete half


hardened.

10.Cleaning the edge of mold from the remaining concrete droplets.

Figure 3.16 Mixing Concrete


3.2.9 Oil

in order to keep the mold clean and avoid damage when


pouring concrete into the formwork.
1. before setting steel duct according to the coordinates in
approved shopdrawing, measured coordinates from bottom
reinforcement to center line of steel duct (Y1) or to the bottom of
steel duct (Y2) as drawn in approved shopdrawing. Then make
marked the coordinates point in stirrup reinforcement use maker
2. Install support bar to marked stirrup reinforcement use plain steel
wire. Support bar used for holder steel duct
3. Install steel duct to concrete reinforcement and then if steel duct
is cut off in the middle of segment ,connect between steel duct with
steel duct use masking tape then tape.
Setting steel duct to concrete reinforcement and support bar which
coordinates have been asjusted. Then tie using plain steel wire
4. Install casting in the anchor position

5. Install bursting steel near anchor position. Bursting steel is an


additional reinforcement that functions as retaining radial force to
prevent cracking or rupture during stressing.
6. Connect steel duct to anchor cast use making tape. Masking
tape function is to prevent water cement entry into the steel duct.
Setting pin connector according the coordinates of the holes
provided on the separator
Figure 3.17 Oil
3.3 IMPLEMENTATION OF WORK
3.3.1 Fabrication
fabrication is a place where the main component
manufacturing process for bridges, in this manufacturing all
components are made but not all main components are made
in this factory (ADHIMIX) because to speed up the
manufacturing process it takes several factories

Figure 3.18 Work Flow Chart


Figure 3.18 shows the field work location of supplier Factory (Jl. Nasional 5
Burujul Kulon, Distric Jatiwangi, Regency Majalengka, West Java 45454)

Figure 3.19 Working in Factory


3.3.2 Preparation Mold
Mold installation is the process of gluing formwork to later pour
ready mix concrete, this process has provisions that must be
obeyed and applied in order to get maximum results, from
installing iron to holding and pulling it must be appropriate.
Figure 3.20 Preparation mold

3.3.3 Setting Steel Duck and Pin Connector


Setting still duck is a process where before ready mix concrete
is poured into the formwork, a check is carried out where this must
be in accordance with the drawings.

1. before setting steel duct according to the coordinates in


approved shopdrawing, measured coordinates from bottom
reinforcement to center line of steel duct (Y1) or to the bottom of
steel duct (Y2) as drawn in approved shopdrawing. Then make
marked the coordinates point in stirrup reinforcement use maker
2. Install support bar to marked stirrup reinforcement use plain
steel wire. Support bar used for holder steel duct
3. Install steel duct to concrete reinforcement and then if steel duct
is cut off in the middle of segment ,connect between steel duct with
steel duct use masking tape then tape.
Setting steel duct to concrete reinforcement and support bar which
coordinates have been asjusted. Then tie using plain steel wire
4. Install casting in the anchor position
5. Install bursting steel near anchor position. Bursting steel is an
additional reinforcement that functions as retaining radial force to
prevent cracking or rupture during stressing
6. Connect steel duct to anchor cast use making tape. Masking
tape function is to prevent water cement entry into the steel duct.
Setting pin connector according the coordinates of the holes
provided on the separator

Figure 3.21 Setting steel duct

3.3.4 Setting Pin Connector


pin connector setting is the process of setting to ensure that there
is no damage to the connector pins and their placement. because
the pin connector is a connector between girders to become 1 span
girder with a length of 39.95 meters and 24.95 meters
Figure 3.22 Setting pin connector And Segmental Separator

3.3.5 Setting Mold


For first of all, need to be inspected from the dimension and visual
(must be well condition), and cleanliness of the mold from all dirt
kind, then, ansure the applying of formwork oil not excessive, thin is
enough but evenly throughout along the product mold
a. Work Sequence :

1. Clean the side form then apply oil to it

2. Assembly 1 side form using gentry crane and stting it with


support of jack brace
3. Clamping the side form using wedge ‘baji’ to connect with bottom
part of mould (bed)
4. Install match cast (divider or separator between girder segment)
include the shear connector in every segment joint or separator
5. Setting jack brace until the side form straight clearly and
verticality. Use the yarn which is already tie to the control at both
edge / ens side of the mould
6. Insstall and connecting the remaining side after the
reinforcement cage set and fix clearly into the mould

7. Connecting or stiffening both of the upper sides with separator tie


rod bar and setting until it is aligned perpendicular to the widht of the
beam width distance
Figure 3.23 Setting Mold

After Checking all of the part then setting mold. Make sure mold
have to precision and very tight to avoid leakage incorfect dimension

Quality control checking position and conditions of mold, rebar


assembly and mold before process following:
a.Mold have to clean from dirt and sticking concrete

b.Rebar is installed in according to shopdrawing

c. Rebar assembly and inner mold shall certaily strong and does not
shift
d.Make sure the mold doesn’t leak during casting

The laboratory issues a concrete mix design in accordance to the


concrete mix design f’c 60 MPa to the Batching Plant teams. Then
batching plant teams provides ready mix f’c 60 Mpa according to the
field requirement. Before casting the batching, plant staff and QC, do
testing as follow :
a.Make sure slump test value, temperature before casting as
planned;
b.Make sampling of cylindrical speciment with dimensions of 15 x 30
3.3.6 Curing

Concrete curing is a concrete treatment process that is usually


carried out after the concrete has hardened, there are several ways to
cure concrete
a. Work Sequence :
1. Spray liquid curing compound on the top surface of
concrete (as needed)
2. Cover along the top of the product with a terpaulin Waiting
until the result of the NDT (Non-Destructive test) with Hammer
Test Method was meet the requirement (≥50% f’c) Curing use
material curing compound by spraying to the concrete surface.
A curing compound is applied to the just casied concrete after
bleeding water has evaporated. Curing is Concrete treatment
for maintaining moisure and temperature the concrete. Prevent
excessive evaporation of water in order the bond between
water and cement can be maximized and reach concrete
compressive strenght as palned
Figure 3.24 Curing

When the concrete reaches minimum concrete compressive


strenght for open bracing and open molding, then bracing and
molding can be opened but de-molding cannot be done. To avoid
damage the mold not be stacked the mold and clean the mold from
concrete letflovers.
When thhe product is in the stockyard, the curing process is
carried out by special workers for 7 days
3.3.7 De – Molding

The product is accepted to de-molding process. If the NDT (Non-


Destructive tests) with Hammer Test Method was meet the
requirement (≥50% f’c)
a. Work Sequence :
1. Open the separator, jack brace, shoring, and wedge
2. Open the bolt which are connect in the side form and plate
3. Lift the side form one by one, and palced on another safety
place to stacking the side form
4. Lift the produst segment by segment, and be careful
regarding the separator or match cast (must be open or take
out from the product
5. Lift the product on the place which was prepared
Figure 3.25 De-Molding
3.4 WORKING LOCATION

3.4,1 Install Jack Hydraulic


The tool used for the post-tension installation method is 1 set of
Hydraulic Jacks, both Multi Jack and Mono Jack types. Posttension
has several types of Multi Jacks with respective capacities of
3000kN, 4000kN, 5000kN, and 6500 kN and Mono Jacks for
capacities of 250 kN and 1500kN

Equipment Specification

Stressing Name : ZPE-12 ST2


jack for
Type : Double Acting
longitudinal
Stroke :100mm
tendon
Piston Area : 325.70 cm2
Capacity : 1850 kN
Weight :130 kg
Max
pushing
force :
4kW 3000
rpm Max
pushing
speed :
1.46m/s
Weight
:122 kg

Figure 3.26 Stressing Jack ZPE-12

3.4,2 Stressing Longitudinal

Stressing must be carried out by experienced personnel who


have good knowledge of the troll used during stressing. withdrawal of
the tendon is pulled from end to end and the force of the jacking force
is determined by the stressing proposal. there must be no cable that
is pulled in part, then left
Stressing shall not commence unsless the concrete in the
element to be stressed has attained a minimum concrete strenght as
shown in the drawing. the stressing method will be one end stressing
primary measurement of stressing result is based on the force
applied by calibrated stressing equipment as recorded in the
stressing report form and that elongation measurement is used as
secondary measurement (counter check) with acceptance deviation
in elongation measurement shall be ±7% as stipulated in SNI
(Indonesia Standard ) if deviation more than acceptable criteria,
VSL Technical department will reviewing the result Stressing
operation is summarized as below :

a) Preparation prior to stressing works, I,e : working access,


stressing platform, warning sign
b) Clean up area at stressing anchorage

c) Install anchor head and wedges for each strand


d) Setting hydraulic jack, press gripper plate and install benchmark
measuring device at one strand behind the hydraulic jack
e) Ensure compressive concrete strength value is according to
design prior to stressing works
f) Stress cable 10% of jacking Force, take datum reading. Check
wedge draw in on passive side (if any)
g) Calculate elongation between 10% and 20%. Record elongation.
Check the gap between joint segment before do the step h
h) Realise preasure at zero and retract piston, move hydraulic jack
backward and spray mark bundle strand in front on anchor head
VSL system taking the first elongation reading at about 25% of
jacking force (ussualy 10 Mpa / 100 bar) typically permits to take
out the stack.
If in a particular case (significant stack, low specified target
preasure etc) it cannot be ensured that all stack is taken at 25%
of jacking force, it is recommended to take more intermediate
readings to produce the complete load-elongation

i) Move hydraulic jack toward anchor head again and press gripper
Plate
j) Stress cable to 30% of jacking force and take reading. Calculate
elongation between 20% and 30%. Record Elongation
k) Stress cable to 40% of jacking force and take reading. Calculate
elongation between 30% and 40%. Record Elongation
l) Stress cable to 50% of jacking force and take reading. Calculate
elongation between 40% and 50%. Record Elongation
m) Stress cable to 60% of jacking force and take reading. Calculate
elongation between 50% and 60%. Record Elongation
n) Stress cable to 70% of jacking force and take reading. Calculate
elongation between 60% and 70%. Record Elongation
o) Stress cable to 80% of jacking force and take reading. Calculate
elongation between 70% and 80%. Record Elongation
p) Stress cable to 90% of jacking force and take reading. Calculate
elongation between 80% and 90%. Record Elongation
q) Stress cable to 100% of Jacking Force then hold for some
minute to check gap between joint segment (check gap between
joint segment is only applied on the first sequence of stressing
tendon) and take reading. Calculate elongation between 90%and
100%. Record elongation
r) Realease preasure to zeroand remove hydraulic jack. Check
uniformity of spray mark at active and passive end to locate
possible slippage. Measure from wedges to spray mark and
record value
s) Proceed to next tendon and repeat step b to r

t) Proceed the stressing until all tendon had been stressed


u) For multistrand tendon, an equivalent or higher capacity
multistrand jack is recommended for tensioning operation. In the
case of site constraint, a monostrand jack might be used to ease
the site operation
Figure 3.27 Stressing Longitudinal

3.4,3 Erection
Erection is the process of installing girder beams to the erection
location. The erection process is a high-risk job so you have to
prepare such as good access land and a good crane position. Bad
land is one of the inhibiting factors because the soil must be solid and
not sink during the erection process. The erection process is
completed in 2 days based on analysis and 3 days based on filed
implementation
Figure 3.28 Erection Girder

You might also like