Professional Documents
Culture Documents
IMPLEMENTATION OF WORK
3.1 MATERIAL
Tools and materials are an important element in a construction
work. In practice, good management is necessary for the efficiency
of the use of tools and materials themselves. Procurement of work
equipment and building materials should be adjusted to the stages
of a work in progress. The placement of the right and efficient
worktools and building materials needs to be considered by the
team to accelerate and facilitate the work.
The location of building materials and heavy equipment providers
need to be considered also, so that the implementation of work is
optimally biased. In addition, the availability of building materials
must always be controlled so that there is no running out of building
materials. The placement of materials must also be adjusted to the
nature so that the risk of damage to building materials can be
reduced before use, especially in building materials that are
sensitive to environmental conditions such as cement and steel
joints.
Working tools play an important role in supporting the
implementation of the project. Tools to help carry out the heavy
work done by human beings. The use of tool work can also speed
up time and facilitate the implementation of projects.
The information needed in material planning is as follows:
1. The quality of the material needed in accordance with the
specifications of the plan.
2. Delivery time to be adjusted to the time schedule.
3. Termin and payment conditions to material logistics. Schedule of
material use. (Abrar,2010)
Building materials used in the Patimban Port Development Project
(I) Package 3 :Connecting Bridges , as follows
3.1.1 Fine Aggregate
9.5 100
4.75 95 – 100
2.36 80 – 100
1.18 50 – 85
0.600 25 – 60
0.300 10 – 30
0.150 2- 10
Item Max
Note :
however, any sand the fails to meet the above requirement may
be used provided that the compressive strenght of mortar
specimens using such sand is more than 95% of that of mortar
specimens using the same sand which is washed by 3% solution
of sodium hydroxide and than by water. and approved by the
engineer. testing age of mortar specimens shall be 7 and 28
3.1.2 Coarse Aggregate
Coarse aggregate is a mixture of concrete in the form
ofgravel / broken stone which is the process of solving
using the coarse aggregate shall consist of one or more of the
following:
1. Crushed stone, gravel, blast furnance slag, or other approved
inert materials of similar characteristic having clean
2. Hard durable pieces. it shall be free from objectionable
quantities of flat or elongated particles, organic matter or other
deleterious matter
3. The coarse aggregate shall be uniformly graded and shall meet
the grading requirement shown in tabel
Item Maximum
3.1.4 Cement
A. Slump Test
The Laboratory issues a concrete mix design in accordance to the
concrete mix design f’c 60 Mpa to the batching plant teams. Then
batching plant teams provides ready mix f’c 60 Mpa according to field
requirement. Before casting the batching plant do testing as follows :
1. Japanese concrete standard Specifications(JIS A5308-2019}
2. Make sure slump test value, temperature before casting as
planned (slump 60±10 cm)
3. samplingof cylindrical specimens with dimensions of 15 x 30
4. Slump Flowing test (JIS A1150)
Table 3.5 Concrete Specification
Equipment
Testing Procedure :
3.1.7 Sterofoam
Strorofoam function is to fill the space in the middle of the
ready mix concrete, then the middle girder is not filled with liquid
concrete and becomes hollow, this is a new type of girder that was
first used in Indonesia and was used for the Patimban bridge
Figure 3.7 Sterofoam
3.1.8 Strand
PC Strand 12,7 mm
Bar cutter is a tool used to cut iron joints as needed. At the time of
installation of iron joints are often found the length of the joints that
have been attached differently and the surface of each joint is uneven.
These barcuts are used to spruce up the bones that have been
attached or to equalize the display of each of these bones. SNI
GQ46A maximum capacity of cut steel joints is 32 mmand minimum
capacity is 12mm.\
3.2.4 Bucket
3.2.5 Tape
3.2.6 Caliper
3.2.7 Mold
1. Take some fresh concrete to make sample & slump test before
casting.
4. Bucket on the over head crane then pour fresh concrete into
molds.
After Checking all of the part then setting mold. Make sure mold
have to precision and very tight to avoid leakage incorfect dimension
c. Rebar assembly and inner mold shall certaily strong and does not
shift
d.Make sure the mold doesn’t leak during casting
Equipment Specification
i) Move hydraulic jack toward anchor head again and press gripper
Plate
j) Stress cable to 30% of jacking force and take reading. Calculate
elongation between 20% and 30%. Record Elongation
k) Stress cable to 40% of jacking force and take reading. Calculate
elongation between 30% and 40%. Record Elongation
l) Stress cable to 50% of jacking force and take reading. Calculate
elongation between 40% and 50%. Record Elongation
m) Stress cable to 60% of jacking force and take reading. Calculate
elongation between 50% and 60%. Record Elongation
n) Stress cable to 70% of jacking force and take reading. Calculate
elongation between 60% and 70%. Record Elongation
o) Stress cable to 80% of jacking force and take reading. Calculate
elongation between 70% and 80%. Record Elongation
p) Stress cable to 90% of jacking force and take reading. Calculate
elongation between 80% and 90%. Record Elongation
q) Stress cable to 100% of Jacking Force then hold for some
minute to check gap between joint segment (check gap between
joint segment is only applied on the first sequence of stressing
tendon) and take reading. Calculate elongation between 90%and
100%. Record elongation
r) Realease preasure to zeroand remove hydraulic jack. Check
uniformity of spray mark at active and passive end to locate
possible slippage. Measure from wedges to spray mark and
record value
s) Proceed to next tendon and repeat step b to r
3.4,3 Erection
Erection is the process of installing girder beams to the erection
location. The erection process is a high-risk job so you have to
prepare such as good access land and a good crane position. Bad
land is one of the inhibiting factors because the soil must be solid and
not sink during the erection process. The erection process is
completed in 2 days based on analysis and 3 days based on filed
implementation
Figure 3.28 Erection Girder