Subject: Delay of progress due to unavailability of Land Clearance for the Job of
“Laying of Approach Road from SH 10 to Talabira Mines (Talabira II & III) OCP in
Talabira of Odisha”
Dear Sir,
With due respect we refer to the trailing mail, and regretfully inform
you that, the NLC technical team has provided the C/Line along with coordinates (from
Ch 00 to CH 1147) for this Road Job (cited by Ref. above) on dated 22.07.2020 & Cross
section of Drg. (released for construction) on dated 16.07.2020. Still dated as per
mentioned above only 1147 RM from SH 10 (from CH 00) had been provided to us to
execute the work.
However, in this period to current dated we are already executed activities along
with site hindrance (Land Payment Related & Other Local issues), Front Clearance
(Land acquisition) & Heavy rain fall impacts (as per recorded in site hindrance
register) & Limitations related to Covid 19 (Pandemic situation). The site
activities are mentioned in below:-
Henceforth, we are almost completed 95% job of this said area (from Ch 00 to Ch
1147), which has been provide by NLC personnel only.
Thus, in the view of the above we request your kind intervention with final decisive
resolution to the above points enabling us to execute the balance job within stipulated
time frame and avoid idle resources losses being incurred by us. Once again, we can
assure you to render dedicated & best efforts to complete the project with emphasis on
quality adherence and progress within the stipulated time frame.
Warm Regards,
Kailash Sharma
GM
JP Autoclavers & Co