Professional Documents
Culture Documents
Critical Assessment
Purpose: To define a procedure that identifies the criticality of plant equipment and
systems and details the method of entering the criticality on the site
Computerised Maintenance Management System (CMMS) - Frontline.
Criticality This procedure is not deemed to be Safety Critical due to unidentified potential
failure of plant or equipment
Page 1 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
SCOPE
The methodology in this procedure shall be normally be applied to all new plant equipment
and systems to be assessed for criticality at Total Bitumen Preston
The Engineering Manager shall approve any other procedure used and ensure that it is
appropriate and addresses statutory requirements and good practice e.g. Pressure Systems
equipment, equipment which requires assessment for risk of Legionella.
.
REFERENCES
OPD-OM-MS-UK-PRE-ENG-603 SAFETY CRITICAL MEASURES AND EQUIPMENT
DSEAR
RESPONSIBILITIES
The Engineering Manager shall ensure that the requirements of this procedure and the
relevant statutory requirements are complied with at all times.
DEFINITIONS
5.1 Criticality
This is the level of the SHEQ consequences of an item of equipment or a system failing in
terms of any SHEQ hazard such failure may cause, and also the impact of any lost production
and the cost of restoring plant to its original condition. The level of criticality varies in
ascending order: C1, C2, C3 with special attention given to scores of C4 and C5 in terms of
why an item is deemed critical (Safety, Environmental, Quality and Production). Criticality is
based on the Total UK Risk and Consequence Matrix CPR126 – see Appendix 1
5.2 DSEAR
DSEAR is a set of regulations concerned with protection against risks of fire, explosion arising
from dangerous substances used or present in the work place.
The ATEX rating for equipment situated within a DSEAR zone is carried out during the design
phase of the project it is part of. The DSEAR zones on site have all been identified and labelled
Page 2 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
and the report is available within the Explosion Protection Documentation of the HSEQ
department.
5.5 Trip
A trip is an SIS. A trip by definition is the automatic plant response to an excursion above or
below normal process parameters leaving the plant in a safe state e.g. the action of tripping
the pump and closing of the inlet valves for the loading tank reaching “hihi” and activating the
level switch.
5.8 Alarm
An alarm is an unexpected occurrence that requires a timely operator action e.g. a tank alarm
reaching “hi” on the radar allowing the operator to stop the relevant pumps etc… before the
“hihi” SIS trip stops loading automatically.
Page 3 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
5.9 Frontline
Frontline is the Computerised Maintenance Management System (CMMS) installed at Total
Bitumen. Each item of equipment, system, plant or building entered into Frontline requiring
regular maintenance or examination has a routine Plan established with an associated
schedule that generates work requests automatically. For all unplanned works onsite, a work
request is generated through Frontline by Operations.
Page 4 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
PRINCIPLES
All new plant equipment and systems shall be considered for critical assessment using the
methodology/spread sheet in this procedure.
Existing Equipment may be assessed using other agreed procedures provided this is
approved by the Engineering Manager.
All opportunities to bring existing equipment critical assessment into this procedure shall be
longer term aim and reviewed by the Engineering Manager.
It should be noted that the final results of the critical assessment are always at the discretion
of the Critical Assessment Team and that this policy serves as a guide to the assessment
procedure
The “Critical Assessment spread sheet” itself is split up into the following sections
7.2 DSEAR
Does the equipment require an ATEX / DSEAR inspection i.e. is it located in a hazardous
area? (type in y or n)
7.3 SIS
7.3.1 Is the equipment part of a Safety Instrumented System (SIS)? (type in y or n)
Page 5 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
7.3.2 If the equipment is part of an SIS, what is the Functional Location of the SIS initiator?
(type in FL tag)
7.4 Critical Assessment What is the likelihood of failure? (1 to 5) (Probability of Failure PF)
When estimating the banding of the functional failure probability, consideration should be
given to aspects such as:
Operational failure history (where available)
Generic reliability data
Equipment redundancy
Mode of equipment operation
Equipment stress variations, etc.
The assessment should be a group exercise using historical data, engineering and on site
knowledge and the Site Risk and Consequence Matrix CPR 126
The following categories are assessed in terms of potential consequence of failure. The
consequence is based upon guidance derived from the risk and consequence matrix. Note
the consequence should be the most probable not the worst case.
When the correct level of consequence has been decided, the figure “1” must be placed in the
chosen column on the “Criticality Assessment Spreadsheet”.
7.5 Injury / Safety (S): impact of loss of function upon safety (1 to 5)
7.6 Environment (E): impact of loss of function upon environment (1 to 5)
7.7 Quality (Q): impact of loss of function upon quality (1 to 5)
7.8 Production Impact (P): impact of loss of function upon production (1 to 5)
Safety RA matrix
1 2 3 4 5
1 C1 C1 C2 C3 SC4
likelihood
2 C1 C2 C3 SC4 SC4
3 C2 C2 C3 SC4 SC4
4 C2 C3 C3 SC4 SC5
5 C3 C3 SC4 SC5 SC5
consequence
Page 6 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
The asset category “Criticality” on Frontline has a main heading and two subgroups:
7.9.1 DSEAR - if the equipment is located in a hazardous area and requires inspection. In
this field all equipment is either DSEAR or nonDSEAR.
7.9.2 Overall Criticality level (C1, C2, C3, PC4, PC5, QC4, QC5, EC4, EC5, SC4, SC5) - is
generated automatically from the summary data and prioritised to give an overall criticality
score i.e. SC5 is the highest score an item of equipment can have and overrides all other
results for Environment, Production and Quality. See priority table below.
final priority
criticality order
rating
Safety SC5 1
Safety SC4 2
Environmental EC5 3
Environmental EC4 4
Quality QC5 5
Quality QC4 6
Production PC5 7
Production PC4 8
critical score C3 9
critical score C2 10
critical score C1 11
Page 7 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
Trip
SIL Trip
Alarm
Pressure System Regs
Piping
Tanks
HV Electrical
Electrical
Thermal Oil
LEV
Lifting Equipment
Bund/Drain
Structure
N/A
Once the critical assessment is complete, the Critical Team must then choose the most
appropriate “Service Category” from the list above. For all items C3 or above, a “Service
Category” is mandatory.
7.11 Maintenance Cost Impact (CI) is the estimated cost to the business to repair and
replace equipment (assess as 1 to 5 – based on cost bands indicated)
Page 8 of 9
OPD-OM-MS-UK-PRE-ENG-
Bitumen Operating Document
620
Critical Assessment
The Critical Team must review the level of criticality for the equipment and thus decide from
the list below which Maintenance regime/type is required (note the explanations are in the
definitions chapter of this policy):
Preventive Maintenance Replacement
Preventive Maintenance Systematic
Preventive Maintenance Conditional
Run to Fail
The Maintenance regime required remains for the Critical Team to review, though the following
list can be used as guidance:
(C5 / C4) Preventive Maintenance Replacement / Systematic
(C3 / C2) Preventive Maintenance Conditional
(C2 / C1) Run to Fail
8. DOCUMENTATION
The Critical assessment Spread sheet shall be used to document the
assessment – see Appendix 2 for template and example.
10. AUDIT
HSEQ shall ensure that compliance with this procedure is regularly audited.
Page 9 of 9