You are on page 1of 17

IPA18-584-E

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Forty-Second Annual Convention & Exhibition, May 2018

PRECISION PLACEMENT FOR SUCCESSFUL HORIZONTAL WELLS IN HETEROGENOUS


RESERVOIRS: A CASE STUDY IN ALPHA FIELD, CENTRAL SUMATERA BASIN

Usman Jauhari*
Ahmad Syahputra*
Bangun Yulianto*

ABSTRACT production targets. After production for decades of


field life, the condition is reversed. The good
Producing oils from heterogenous and tight reservoirs have become watered out and produced
reservoirs is a common challenge experienced in with high water cut. Producing oils from the good
most mature oil fields. Oils in good quality reservoirs quality reservoirs with low oil cut then become
generally had been completed first in the early life of unencouraging. Production targets then shift focus to
the fields. Meanwhile, major remaining oils are still heterogenous and tight reservoirs in which most oil
locked in unfavorable heterogenous and tight remains. However, producing remaining oil from the
reservoirs. To produce the oils from the heterogenous reservoirs may face challenges. Efforts to complete
and tight reservoirs with favorable rates, there could the reservoirs using normal directional completions
be situations in which conventional directional and even fracturing technology could end up not
drilling completion and even fracturing technology being successful.
might be unsuccessful. This paper gives examples of
horizonal wells with precise lateral section Similar condition is also experienced in the Alpha
placement that enabled economic production of oil field in the Central Sumatra. High quality reservoirs
locked in heterogenous reservoirs. have been depleted and currently produced with
unfavorable low oil rates and high water-cuts.
The precise horizontal placement had been applied in However, efforts to produce oils from heterogenous
Alpha Field by targeting a heterogenous and low- low-quality reservoirs have shown unsuccessful.
pressure Alpha-sand reservoir. Oil productions from Both normal completion from directional drillings
the horizontal wells have shown encouraging and and even fracturing have produced with short-term
stable rates. The production performances also low oil productions (Figure 2).
surpassed those from normal perforation and even
fracturing completion in directional wells. The This paper’s objective is to provide examples of how
success had provided a lesson learned that precise precise placement of a horizontal well can provide an
horizontal well placement can provide an alternative alternative solution to unlock oil in heterogenous and
solution to unlock oils residing in heterogenous and low-pressure reservoirs in mature Alpha field. The
low-pressure reservoirs. The lesson learned can be discussion is arranged according to the following
leveraged to improve oil production and recovery order: 1) Planning for precise placement of a
across mature fields in Central Sumatra Basin and horizontal well. The planning includes building
also to other basins in Indonesia. strong geological characteristic understanding of
reservoir target, planning landing point for horizontal
Keywords: Precise horizontal well placement, well trajectory, and understanding tool and
mature fields, heterogenous reservoirs. equipment constraints that impact to the overall
trajectory plan. The trajectory plan is also
INTRODUCTION exercised with scenario games as contingency plan
to prepare for potential deviations from plan. 2).
Majority of oil fields in Indonesia are mature fields. Execution monitoring. The monitoring is proactive
Early production of the oil fields generally comes action to any deviations from the planning during
from homogenous and good quality reservoirs which execution. The deviation can be sourced from non-
are able to produce with encouraging rates and geological and geological uncertainty factors.
reserves (Figure 1). Meanwhile, the heterogenous Updating geological model and trajectory plan are
and tight reservoirs had only become secondary required to ensure achieving horizontal well target
* Chevron Pacific Indonesia
 
as per plan, 3). Production results. Example of Bed Dipping Trend
production results from precise placement of
horizontal wells are shown and compared with those Bed dipping evaluation is part of structural
from normal directional completions and fracturing geological characterization of the reservoir target. A
technology. horizontal is recommended to be placed in well
understood structural geology area and avoid
PLANNING for PRECISE PLACEMENT OF A uncertain complex faulted area. This is to mitigate
HORIZONTAL WELL surprises of penetrating unwanted oil saturation,
exiting to shale, also problems in drilling and
Understanding Geological Characteristics of completion that those all will put the well into
Reservoir Target production risks. The bed dipping will determine the
inclination of both landing point and lateral section
Understanding geological characteristics of the of a horizontal well. A proper plan for landing point
reservoir target is basic for successful planning and lateral section trajectory at right inclination and
and execution of a horizontal well. The more depth will ensure optimum lateral length in the sweet
holistic the understanding of the reservoir target, spot and avoid unwanted water or gas risk interval.
the higher the probability of success for the Otherwise, improper plan for landing point and
horizontal well. Key geological factors that need lateral section trajectory plan will risk the horizontal
deep understanding and modeling are of 1). Fluid well placement out of the sweet spot and drive into
risk zone 2). Sweet spot zone 3). Bed dipping trend fluid risk interval that eventually and detrimentally
and 4). Mapping for marker surfaces above impact production. In addition, the improper
reservoir target trajectory plan will also risk actual well trajectory
geometry that can lead to operational problems and
Fluid Risk Zone cost overruns.

Fluid risk zone identification is top geological Mapping for Marker Surfaces above Reservoir
factor that will determine a successful horizontal Target
well. The fluid risk is unwanted water or gas that
In addition to characterization and modeling for
can give detrimental impact to oil production of
reservoir target, key markers located above reservoir
the horizontal well. The fluid risk interval may
target need to be mapped to create marker surfaces.
include distinctive water and or gas contact or high
The marker surfaces are important to give early
water-saturation intervals indistinctively dispersed
warning for structural deviations during drilling
in the reservoir target. It is recommended that a
execution prior to entering reservoir target. With the
horizontal well is proposed in the reservoir in
early warning, geological model and well trajectory
which fluid risk distribution is well understood.
can be remodeled to fit actual drilling data.
Sweet Spot Zone Landing Point as the Key for Precise Horizontal
Well Planning
After fluid risk identification, the next is sweet
spot interval and distribution characterization. Landing point is the key consideration for a
Sweet spot is interval in the reservoirs in which horizontal trajectory plan in order to precisely place
rock properties and fluid saturations are favorable lateral section inside sweet spot of reservoir target
for production. A horizontal well that can and avoid unwanted oil or gas interval. Successful
optimally stay in the sweet spot interval will landing point plan and placement will not only
ensure strong production performance. Example of significantly reduce failure probability in
fluid risk and sweet spot interval identification in productions but also ensure smooth operations
the reservoir target of a horizontal well is shown in during drilling in the lateral section. Two key
Figure 3. A homogenous thick sweet spot type elements of a landing point that need to be precisely
reservoir (~50 ft) without fluid risk interval will and carefully planned and executed are: 1) depth of
give flexibility for horizontal well placement. landing point and 2) inclination angle of landing
Meanwhile, precise and careful planning is point.
required for a thin sweet spot (10-15 ft) especially
with a water risk zone at the bottom of the reservoir Depth of Landing Point (LP)
and also for complex thin sweet spot (10-15 ft)
with indistinct water risk interval dispersed in Depth of landing point is recommended to be tied
heterogenous reservoirs. with true vertical depth (TVD) below top of sand

 
target. Recommended TVD of a landing point below upslope bedding of 20 requires LP inclination
top of sand target depends on the fluid risk and sweet angle of 900-910.
spot interval characteristics. Example of how fluid
risk and sweet spot characteristics impact to landing Understanding Tool and Equipment Constraints
point placement of TVD below top of sand target in
oil-water reservoir system is shown in Figure 4. It is recommended also to understand constraints
Case-1 gives example of a thick sweet spot (~50 ft) on Logging While Drilling (LWD) / Measurement
in homogenous reservoir with OWC still located at While Drilling (MWD) tools, drilling and
the edge of field boundary. This reservoir type gives completion equipment while planning trajectory
flexibility for landing point depth. To mitigate early for a horizontal well. The constraints may limit
water contribution during production, landing point flexibility of the horizontal well trajectory. Three
needs to be placed high away from latest OWC data. typical constraints may include: 1) tangent section
Standoff or distance of wellbore to OWC can delay for pump placement interval, 2) casing exit MWD
the time at which water reaches the well measurement, 3) maximum dogleg severity in
(Wagenhofer et al.1). Simulation can also be used to lateral section. Collaborative works with
help to generate production sensitivity for optimum multidiscipline teams are required to characterize
landing point depth. Case-2 gives example of a the constraints. Example of impacts for tool and
reservoir with thin oil column (10-15 ft) on top of equipment constraints on well trajectory plan is
water zone. This reservoir type requires a precise shown in Figure 6.
landing point plan to ensure optimum standoff in the
lateral section. The optimum standoff is intended to Tangent Section for Pump Placement Interval
mitigate early water contribution during production.
The approach of maintaining optimum standoff to Electric Submersible Pump needs interval
mitigate early water break through in thin oil column placement with certain criteria for it to operate
reservoirs is also suggested by Xin et al.2 reliably. One criterion is the tangent section
interval in which the allowable maximum dogleg
Inclination Angle of Landing Point (LP) is required. An example is that dogleg <2 deg/100
ft within minimum of 100 ft MD tangent section.
Compared to depth of landing point, inclination Impact to the trajectory plan is that the longer the
angle is an even more critical element of a landing tangent section required, the deeper the resulting
point. Failure in the placement of LP depth can still TVD drop in the trajectory. It needs discussion
be corrected by modifying inclination angle of LP with ESP providers to determine the safe allowable
but it would be difficult for vice versa. The maximum dogleg.
inclination angle is determined by bed dipping of
a reservoir target. The recommended rule is that
Casing Exit MWD Measurement
inclination angle of landing point needs to be as
close as the reservoir dipping angle. A small gap
MWD requires a minimum distance to casing shoe
between landing point angle and reservoir bed
to conduct first survey to avoid magnetic
dipping one will ensure lateral section to stay long
interference with casing steel. The clearance
inside sweet spot interval in addition to also
distance is variable and operator needs to consult
smoothen operations during drilling and
with the MWD provider. For example, a MWD
completion installations. The recommended angle
provider recommends minimum 120 ft MD
gap between LP inclination and reservoir bed
distance to conduct first survey after exiting from
dipping is in the range of 10-20. With the angle gap
casing shoe of landing point. Impact to the
number, the lateral section will be smooth and need
trajectory plan is that the longer the tangent section
only a maximum dogleg of 10-20 to catch up
required, the deeper the resulting TVD drop in the
reservoir bedding trend. It needs to be noted that
lateral section trajectory.
reservoir bed dipping is measured from horizontal
line meanwhile well trajectory inclination angle is
Dogleg Severity in Lateral Section
measured from vertical line. Example of plan for LP
inclination angle in relation to bed dipping
characteristics is shown in the Figure 5. A reservoir Dogleg in lateral section is commonly restricted to
with flat or gently bed dipping of ±10 requires LP a maximum number of dogleg severity i.e. 2
inclination angle of 880-890. A reservoir with deg/100 ft. A small dogleg in the lateral section
downslope bedding of 100 requires LP inclination will smoothen not only drilling operations but also
angle of 780-790. Meanwhile, a reservoir with installations of completions. However, the

 
required maximum dogleg will limit flexibility to exercise is conducted by generating sensitivity to 1).
plan and steer lateral section during drilling. LP depth relative to top Alpha Sand, 2). LP
inclination angle.
Example of Landing Point and Lateral Section
Plan in Alpha Sand For LP depth sensitivity, a deeper LP than base case
(i.e. 5’ deeper) will push the lateral section closer to
A horizontal well trajectory planning can be started water risk zone. This closer to water risk zone will
after having strong understanding on the above potentially impact to earlier water production
requirements consisting of geological characteristics contribution than base case. If this case occurs during
of the reservoir target, key elements of horizontal execution, then lateral section needs to be
well trajectory and constraints on tools and aggressively optimized to build angle up from the
equipment impacting to the horizontal well trajectory plan.
plan. Example of horizontal well trajectory plan
conducted in Alpha Sand is shown in Figure 7. The For LP inclination angle sensitivity, base case
horizontal well is purposed to optimally produce trajectory’s LP of 890 is compared with 870 and 850.
remaining oils residing in the heterogenous Alpha If during execution the well has to land at 870 instead
Sand. The target zone is oil saturated low- of 890 as plan, then some section of the lateral section
permeability zone at upper part of reservoir target will close to water risk zone. The lateral section
while in the same time keeping distance vertically needs aggressive re-plan to ensure stay away from
and laterally from water risk zone in high the water risk. If the well forcefully lands at 850, then
permeability part of the lower reservoir target. the lateral section will physically touch water risk
zone. This scenario is probably destructive to the
Reservoir bed dipping in the lateral section is well production. To avoid this, sidetrack plan is
estimated 10 downslope in the first quarter and needed to correct the well to land at 890 as plan.
climbing 10-20 upslope in the rest of lateral section.
The Landing Point (LP) is planned to be landed on 7’ From the above sensitivity to LP depth and
TVD below top of reservoir. LP inclination angle is inclination angle, it is known that precision in LP
planned 890. With this inclination angle, the lateral angle is highly critical and more critical than LP
section will easily catch up the above bedding depth. The failure to land the LP at inclination angle
dipping changes. It needs only a maximum dogleg of plan will put the horizontal well into high risk of
2 deg/100 ft to follow the bedding geometry change. production.
In addition, this small dogleg tolerance is intended
also to smoothen drilling operation and completion PROACTIVE EXECUTION MONITORING
installation.
Close monitoring is required to ensure successful
The LP depth and angle plan will provide sufficient execution of the horizontal well plan. Immediate
standoff (~18’) from water risk zone. The thin tight actions are needed for any deviations from plan for
streak zone (~1’) with close to zero permeability both geological model and trajectory plan.
dispersed in the heterogenous sand is also expected Deviations to plan are not always caused by
to provide vertical sealing from the water risk zone. geological uncertainty factors and non-geological
Tangent section interval for pump placement is ones need also to be carefully considered. The
planned 170’ in length prior to landing the well. The following section is illustration of deviations and
trajectory plan also considers 130’ tangent section required immediate responses to ensure précise
from LP prior to acquire first directional survey as placement of a horizontal well. This illustration is
recommended by MWD tool provider. shown in Figure 9 and 10.

Trajectory Sensitivity Exercises for Contingency Non-Geological Factors


Plan
During monitoring of drilling execution for a
The above trajectory plan then is exercised in various horizontal well, key markers are identified
scenarios as contingency plan to mitigate potential surprisingly coming low in the range of ~10 ft
deviations to plan. The scenarios serve as early (deeper than prognosis) in relatively consistent
guidance of how far deviation window to plan that is manners. Existing well data are enough dense to
acceptable and not harmfull to future production of control gridding of surface model and to estimate key
the hrorizontal well. Figure 8 illustrates exercises marker depth along trajectory plan. If surfaces of the
conducted for trajectory plan in Alpha sand. The key markers are updated using the actual marker

 
depths, then very local low structure will be encouraging results. The resulted initial productions
generated. The big miss-depth and coming low of the have beaten the forecasts and proved superior in the
key markers is thought as geologically unreasonable. range of 3-4 times higher than normal completions
The phenomena could be caused by non-geological and fracturing technology (Figure 11). The initial
factors. The non-geological factors needed to production from horizontal wells are in the range of
consider may include errors in surface elevation and 450 to 700 BOPD compared to 100-180 from
coordinate measurements, directional survey fracturing and perforation in directional wells. The
accuracy, drillpipe tally measurement, other production from horizontal wells also show
operational parameter related uncertainties or sustainable rates through time
combination of the all factors. Operational parameter
uncertainties that impact to depth measurement in CONCLUSIONS
horizontal wells had been discussed and published in
several papers (Brooks et al.3, Cheatham et al.4, Precise placements of horizontal wells applied in the
Dashevskiy et al.5, DeVerse et al.6, Grindrod et. al.7, Alpha Sand have been proven to become a strong
Stockhausen et al.8,). alternative solution to produce oils locked in the
typical heterogenous reservoirs. Other completions
After ensuring root causes as non-geological factors, (perforation and fracturing in directional wells) have
dummy marker surfaces need to be generated by bulk been tried in the Alpha Sand but the production
shifting in the amount of coming low (10’ as stated results are unsuccessful. The horizontal wells show
above) for marker surfaces ahead of drilling bit. The strong production performance in the range of 3 to 4
new dummy marker surfaces are then utilized to re- times than perforation and fracturing in directional
plan the horizontal well trajectory. The re-plan wells. A holistic understanding to the reservoir target
results in a new LP coordinate which is located 10’ especially characterization to fluid risk and sweet
below top dummy Alpha Sand with the same spot intervals integrated with careful planning and
inclination angle as previous plan. The new LP execution is the key for precise placement of the
position will ensure lateral section penetrate horizontal wells. This lesson learned can be
reservoir properties as original plan. Without leveraged to improve oil productions and recoveries
updating LP target in respect to the dummy surfaces, across mature fields not only in the Central Sumatra
the horizontal well will land on shale above top Basin but also in other mature basins in Indonesia.
Alpha Sand and lateral section will spent long in the
shale section. Trajectory sensitivity exercises ACKNOWLEDGEMENT
conducted during planning is helpful in anticipating
this scenario (see Figure 8). I would like to acknowledge Management of PT
Chevon Pacific Indonesia for releasing permission to
Geological Uncertainty Factors publish the work results. I would to thank all Teams
in PT Chevron Pacific Indonesia who have
In combination with non-geological factors, contributed and supported this work starting from
geological uncertainty factors need to be reviewed maturation of the horizontal well pilots until to the
when deviations to plan are identified during works are completed.
executions. Trajectory re-planning could be required
to accommodate the deviations. However, if ranges REFERENCES
of geological uncertainties are incorporated in the
horizontal well trajectory planning, deviations to the Brooks, A.G., Gurden, P.A., and Noy, K.A., 1998,
plan could be still within the uncertainty ranges and Practical Application of a Multiple-Survey Magnetic
only minor re-planning is needed. Therefore, it is Correction Algorithm. Presented at the 1998 SPE
recommended to have a holistic understanding on the Annual Technical Conference and Exhibition. New
geological characteristics and uncertainty ranges of Orleans, Lousiana, 27-30 September. SPE 49060.
the reservoir target. The more holistic our
understanding, the less re-planning and intervention Cheatham, C.A., Shih, S., Churchwell., Woody, J.
efforts during execution the horizontal well will be. M., and Rodney, P. F., 1992, Effets of Magnetic
Interference on Directional Surveys in Horizontal
PRODUCTION RESULTS Wells. Presented at the 1992 IADC/SPE Drilling
Conference. Lousiana, 18-21 February. SPE-23852.
Precise horizontal planning and placement execution
have been applied to Alpha sand in the Alpha field. Dashevskiy, D., Dahl, T., Brooks, A. G., Zurcher, D.,
Production from the horizontal wells have shown Lofts, J. C., and Dankers, S., 2006, Dynamic Depth

 
Correction to Reduce Depth Uncertainty and Stockhausen, E., Ball, R., Clark, P., Mongan, R., and
Improve MWD/LWD Log Quality. Presented at the Rice, P., 2016, Placement Matters: Improving
2006 SPE Annual Technical Conference and Survey Accuracy by Using Continuous Directional
Exhibition. Texas, 24-27 September. SPE 103094. Data and Drilling Parameter Setting. Presented at the
AAPG Annual Convention and Exhibition. Alberta,
DeVerse, S., and Maus, S., 2016, Improving Canada, 19-22 June. Article #41856 (2016)
Directional Survey Accuracy through Real-Time
Operating Centers. Presented at the 2016 IADC/SPE Wagenhofer, T., and Hatzignatiou, D. G., 1998,
Asia Pacific Drilling Technology Conference and Optimization of Horizontal Well Placement.
Exhibition. Singapore, 22-24 August. SPE-180652- Presented at the 1996 SPE Western Regional
MS. Meeting. Alaska, 22-24 May 1996. SPE 35714.

Grindrod, S. J., Clark, P.J., Lightfoot, J. D., Xin, S. Y., Lin, D. H., Qing, L., Hua, Z. Z.,
Bergstrom, N., and Grant, L. S., 2016, OWSG Halomoan, P. M., Bin, Y., Mi, Z., Yang, L., and
Stardard Survey Tool Error Model Set for Improved Koon, L. T., 2010, Thin Oil Columns Horizontal
Quality and Implementation in Directional Survey Wells Optimization Through Advance Well
Management. Presented at the 2016 IADC/SPE Placement Application in West China. Presented at
Drilling Conference and Exhibition. Fort Worth, the 2010 SPE Production and Operation Conference
Texas, 1-3 March. SPE-178843-MS. and Exhibition. Tunisia, 8-10 June 2010. SPE
133660.

 
Figure 1 - Common challenges in mature fields. Homogenous high-quality reservoirs have been produced and watered-out. Remaining oils reside in the heterogenous
reservoirs.

 
Figure 2 – Typical log of heterogenous reservoir of Alpha Sand. Most oil remains in the low-perm interval meanwhile the high-perm interval was watered-out. Efforts
to produce oils in the typical heterogenous reservoir using normal perforation completion have shown unsuccessful.

 
Figure 3 - Example of fluid risk and sweet spot interval identification as reservoir target of a horizontal well. Fluid risk is unwanted fluid to be produced, in this case
is water.

 
Figure 4 - Example of fluid risk and sweet spot characteristics impacting to landing point placement (TVD below top of sand target). A reservoir without or away
from water has flexibility to place landing point below top sand target. In contrast, a reservoir with thin oil column requires a precise placement for landing
point with optimum standoff.

 
Figure 5 - Example of plan for landing point (LP) inclination angle in relation to bed dipping characteristics. The landing point inclination angle needs close to bed
dipping angle trend. It is intended to easily stay lateral section away from potential water risk zone during drilling execution.

 
Figure 6 - Example of impact of tool and equipment constraints on a well trajectory plan. The constraints will limit flexibility of well trajectory during planning and
execution.

 
Figure 7 - Example of horizontal well trajectory planning in the Alpha Sand. The lateral section is targeting oil residing in the low quality part of Alpha.

 
Figure 8 – Trajectory sensitivity conducted for contingency plan to anticipate deviations during executions. The sensitivity is conducted by varying LP depth and
inclination angle. The sensitivity gives guidance in the case immediate decisions are required during executions.

 
Figure 9 - Illustration of deviations to plan caused by non-geological factors and required immediate responses to update geological model and trajectory plan. The
update is to ensure the horizontal well to be landed on the targeted reservoir properties.

 
Figure 10 - Illustration of deviations to plan caused by non-unique geological model factors. Sensitivity in planning phase will give guidance of window whether the
the actual geological deviations during lateral section drilling are acceptable or need intervention.

 
 
Figure 11 - Example of productions resulted from précise placement of horizontal wells in the Alpha Sand compared to perforation and fracturing completions in
directional wells.

You might also like