CHECK LIST FOR ELECTRIFICATION WORKS AFTER PLASTERING

BOQ Item No.

Sl Particulars YES NO NA
1 Location:

2 Description of work

3 Contractor's inspection request no.

4 Contractors drawing or sketch No.

Checking of conduits in slab, fan boxes and deep junction boxes for clearness by
5
passing the spring wire.

Checking the wall conduits, junction boxes and terminal boxes for clearness by
6
spring wire

7 Cleaning the terminal boxes thoroughly and applying non-rusting materials

Wiring to be carriedout as per plan & specification given by the Consultants in


8
the drawing. Light - 1.5sq.mm, Power - 2.5sq.mm, A/C - 4sq.mm

9 The maximum no.of wires drawn in a 25mm conduit are as follows


250/440V 650/1100V

1.5sq.mm 10 10

2.5sq.mm 10 10

4.0sq.mm 10 10

Ensure wiring has been done as per colour code for light: Circuit Phase - red,
10
yellow, blue; Neutral - black; Earth - green

Ensure wiring has been done as per colour code for power: Circuit Phase - red,
11
yellow, blue; Neutral - black; Earth - green

12 To combining of power circuits and light circuits being done

Testing of wiring by short circuit and recording the results should not be less
13
than 1mega ohm)

14 Provision of fitting and switches in the building and connecting up.

15 Provision of MCB - DB as per layout and MCB's

16 Connecting each circuits to the MCB's as per drawing and testing

Connecting the incoming of the MCB DB and MCB's and testing of building
17
circuit wiring and control wiring.

18 Usage of lugs in connecting the circuits to MCB's

Connecting the earth wire to fan boxes, terminal boxes and in DB earth terminal
19
with proper lug.

Signature Signature

Name:____________________________________ Name:___________
Client/ Consultant Contractor