Sl Particulars YES NO NA
1 Location:
2 Description of work
Checking of conduits in slab, fan boxes and deep junction boxes for clearness by
5
passing the spring wire.
Checking the wall conduits, junction boxes and terminal boxes for clearness by
6
spring wire
1.5sq.mm 10 10
2.5sq.mm 10 10
4.0sq.mm 10 10
Ensure wiring has been done as per colour code for light: Circuit Phase - red,
10
yellow, blue; Neutral - black; Earth - green
Ensure wiring has been done as per colour code for power: Circuit Phase - red,
11
yellow, blue; Neutral - black; Earth - green
Testing of wiring by short circuit and recording the results should not be less
13
than 1mega ohm)
Connecting the incoming of the MCB DB and MCB's and testing of building
17
circuit wiring and control wiring.
Connecting the earth wire to fan boxes, terminal boxes and in DB earth terminal
19
with proper lug.
Signature Signature
Name:____________________________________ Name:___________
Client/ Consultant Contractor
CATION WORKS AFTER PLASTERING