PROGRESS FISIK KEGIATAN PPK PENGEMBANGAN AIR MINUM TAHUN ANGGARAN 2015

NO PEKERJAAN PROGRESS
1 PENGADAAN DAN PEMASANGAN PIPA HDPE 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep
DAN ME LOKASI PDAM TIRTA KAMPAR PERIODE
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct
KABUPATEN KAMPAR, UPTD KABUPATEN RENCANA 0.01 0.03 0.04 0.05 0.06 0.08 0.09 0.12 0.15 1.82 3.51 5.18 10.66 20.88 38.48 56.07 68.67 79.54 95.37 98.22 100.00
ROKAN HULU, PDAM TIRTA INDRA KABUPATEN
INDRAGIRI HULU, DAN UPTD KABUPATEN SIAK REALISASI 0.00 0.01 0.02 0.04 8.28 79.80 81.66 83.29 83.29 83.29 83.29 83.29
(PAKET-01/APBN 2015) DEVIASI -0.01 -0.02 -0.02 -0.01 8.21 79.72 81.57 83.17 83.14 81.48 79.78 78.12

2 PENGADAAN DAN PEMASANGAN PIPA PVC DAN 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec
ME LOKASI PDAM TIRTA SIAK KOTA PERIODE
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28-Dec
PEKANBARU (PAKET-02/APBN 2015) RENCANA 0.02 0.04 0.06 0.08 0.10 0.11 0.13 0.15 0.74 1.33 1.92 2.50 3.09 3.68 7.54 11.40 15.26 19.12 22.97 26.83 34.58 42.32 50.07 57.81 65.82 73.82 85.17 96.80 99.96 100
REALISASI 0.00 0.03 0.10 0.15 0.15 15.39 76.12 77.84 77.84 77.84 77.84 77.84
DEVIASI -0.02 -0.01 0.04 0.07 0.05 15.28 75.99 77.70 77.11 76.52 75.93 75.34

3 PENGADAAN DAN PEMASANGAN PIPA HDPE 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec
DAN PVC LOKASI IKK TAPUNG HULU, IKK KOTO PERIODE 18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28-Dec
KAMPAR HULU, DAN IKK KAMPAR KABUPATEN
RENCANA 0.02 0.05 0.07 0.10 0.13 0.15 0.18 0.21 0.23 0.93 1.63 2.87 4.15 6.12 12.10 20.49 30.53 42.67 54.73 65.45 74.22 78.38 84.81 88.13 92.74 97.01 99.24 99.64 99.86 100
KAMPAR (PAKET-03/APBN 2015)
REALISASI 0.00 0.05 0.10 0.13 0.17 0.20 0.20 21.62 21.62 21.62 21.62 21.62
DEVIASI -0.02 0.00 0.02 0.03 0.04 0.05 0.02 21.42 21.39 20.69 19.99 18.75

4 PENGADAAN DAN PEMASANGAN PIPA PVC 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun 26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct 30-Oct 6-Nov 13-Nov 20-Nov 27-Nov 4-Dec 11-Dec 18-Dec 25-Dec
LOKASI IKK BANGKINANG SEBERANG PERIODE
21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec 24-Dec 31-Dec
KABUPATEN KAMPAR (PAKET-04/APBN 2015)
RENCANA 0.05 0.10 0.16 0.21 0.31 0.42 0.52 0.63 0.64 1.33 3.48 4.71 16.65 27.86 39.08 50.30 61.52 72.74 84.65 99.54 100.00
REALISASI 0.00 0.05 0.10 0.26 0.31 0.42 0.42 0.42 0.42 0.42 0.42
DEVIASI -0.05 -0.05 -0.05 0.05 0.00 0.00 -0.10 -0.21 -0.22 -0.91 -3.06

5 PENGADAAN DAN PEMASANGAN PIPA PVC 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec
LOKASI IKK KELAYANG DAN IKK RAKIT KULIM PERIODE 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec
KABUPATEN INDRAGIRI HULU (PAKET-05/APBN
2015) RENCANA 0.08 0.16 0.24 0.32 0.38 0.44 0.50 0.56 0.62 4.72 10.02 16.41 22.80 29.19 35.58 41.98 48.37 54.76 61.15 69.95 77.80 89.84 99.19 99.57 100
REALISASI 0.00 0.32 0.47 0.54 0.62 53.31 55.77 62.55 70.52 #NAME? #NAME? #NAME?
DEVIASI -0.08 0.16 0.23 0.23 0.24 52.87 55.27 61.99 69.90 #NAME? #NAME? #NAME?

6 PENGADAAN DAN PEMASANGAN PIPA PVC DAN 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec
HDPE LOKASI IKK TAMBUSAI UTARA, IKK PERIODE
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28-Dec
KEPENUHAN HULU, IKK ROKAN IV KOTO, DAN
IKK PENDALIAN KABUPATEN ROKAN HULU RENCANA 0.03 0.05 0.08 0.10 0.14 0.18 0.22 0.27 1.19 3.81 7.47 11.70 16.13 20.94 26.12 30.98 37.13 43.22 48.87 54.52 60.78 68.01 74.73 79.00 84 89.42 94.81 98.12 99.71 100
(PAKET-06/APBN 2015) REALISASI 0.00 0.01 0.03 0.05 16.22 18.38 54.59 55.17 55.17 55.17 55.17 55.17
DEVIASI -0.03 -0.04 -0.05 -0.06 16.08 18.19 54.36 54.91 53.98 51.37 47.70 43.47

7 PENGADAAN DAN PEMASANGAN PIPA PVC 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec
LOKASI IKK UJUNG BATU DAN IKK TANDUN PERIODE
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28-Dec
KABUPATEN ROKAN HULU (PAKET-07/APBN
2015) RENCANA 0.04 0.09 0.13 0.17 0.25 0.34 0.51 1.25 1.52 5.04 8.11 11.33 21.30 31.08 40.74 50.41 60.07 71.48 86.89 98.56 100.00
REALISASI 0.00 0.05 0.09 0.14 0.24 0.30 0.30 0.30 0.30 0.30 0.30 0.30
DEVIASI -0.04 -0.04 -0.04 -0.04 -0.01 -0.03 -0.21 -0.94 -1.22 -4.74 -7.81 -11.03

8 PENGADAAN DAN PEMASANGAN PIPA HDPE 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec
LOKASI IKK PUSAKO KABUPATEN SIAK (PAKET- PERIODE 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec
08/APBN 2015)
RENCANA 0.03 0.06 0.09 0.12 0.17 0.21 0.26 0.31 0.36 0.36 0.50 0.66 1.50 3.18 7.91 12.67 18.70 25.08 31.47 37.85 44.43 51.01 58.47 64.99 71 81.55 87.53 93.65 99.78 100
REALISASI 0.00 0.03 0.06 0.15 0.21 0.27 0.33 0.33 0.33 0.33 0.33 0.33
DEVIASI -0.03 -0.03 -0.03 0.03 0.04 0.05 0.07 0.02 -0.03 -0.04 -0.17 -0.33

9 PENGADAAN DAN PEMASANGAN PIPA HDPE 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec
LOKASI IKK SIAK DAN IKK DAYUN KABUPATEN PERIODE 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec
SIAK (PAKET-09/APBN 2015)
RENCANA 0.05 0.10 0.16 0.21 0.31 0.41 0.52 0.62 1.68 5.54 9.41 13.27 18.01 22.75 27.48 32.22 36.96 41.70 46.44 51.17 55.91 60.65 65.39 70.12 76 80.80 85.78 93.22 99.02 100
REALISASI 0.00 0.05 0.10 0.16 0.30 0.44 0.55 0.55 0.55 0.55 0.55 0.55
DEVIASI -0.05 -0.05 -0.05 -0.05 -0.01 0.02 0.03 -0.07 -1.13 -4.99 -8.86 -12.72

10 PENGADAAN DAN PEMASANGAN PAKET IPA 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
BAJA KAPASITAS 20 L/DET LENGKAP DENGAN PERIODE
29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
PRASARANA PENDUKUNG LOKASI IKK KAMPAR
KABUPATEN KAMPAR (PAKET-10/APBN 2015) RENCANA 0.09 0.30 0.52 0.74 1.81 2.62 3.45 4.34 4.79 5.44 7.39 9.34 11.62 14.97 18.28 22.17 28.19 34.01 39.11 43.36 48.43 55.13 62.15 66.66 71 76.86 82.06 88.94 94.09 98 99.746 100
REALISASI 0.00 0.00 0.01 1.02 2.95 6.06 10.66 13.52 15.28 17.58 19.25 19.25 19.25 19.25
DEVIASI -0.09 -0.30 -0.52 0.28 1.14 3.44 7.20 9.17 10.49 12.14 11.86 9.91 7.63 4.28

11 PENGADAAN DAN PEMASANGAN PAKET IPA 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
BAJA KAPASITAS 20 L/DET LENGKAP DENGAN PERIODE
29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
PRASARANA PENDUKUNG LOKASI IKK KOTO
KAMPAR HULU KABUPATEN KAMPAR (PAKET- RENCANA 0.04 0.18 0.37 0.55 1.39 2.85 3.44 4.09 4.54 6.67 8.60 10.53 12.80 16.82 20.70 25.22 31.43 37.36 43.05 48.11 54.06 59.62 62.58 66.20 69 73.40 79.44 86.00 92.61 97 99.52 100
11/APBN 2015) REALISASI 0.00 0.02 0.04 0.06 0.08 0.10 0.11 0.78 6.80 9.85 13.08 13.08 13.08 13.08
DEVIASI -0.04 -0.16 -0.33 -0.49 -1.31 -2.75 -3.33 -3.31 2.25 3.18 4.48 2.55 0.28 -3.74

12 PENGADAAN DAN PEMASANGAN PAKET IPA 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
BAJA LENGKAP DENGAN PRASARANA PERIODE
29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
PENDUKUNG LOKASI IKK KELAYANG
KAPASITAS 10 L/DET DAN IKK RAKIT KULIM RENCANA 0.05 0.28 0.99 1.65 2.47 3.09 3.98 4.74 6.28 8.34 10.06 13.13 15.28 18.14 20.89 24.39 30.22 36.52 41.87 47.27 52.00 56.29 58.94 60.87 65 68.55 75.51 82.64 89.54 96 99.03 100
KAPASITAS 10 L/DET KABUPATEN INDRAGIRI REALISASI 0.00 0.02 0.05 0.10 0.33 2.07 2.61 3.76 4.50 5.62 8.47 8.47 8.47 8.47
HULU (PAKET-12/APBN 2015) DEVIASI -0.05 -0.27 -0.93 -1.55 -2.14 -1.02 -1.37 -0.98 -1.78 -2.72 -1.59 -4.66 -6.81 -9.67

13 PENGADAAN DAN PEMASANGAN PAKET IPA 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
BAJA KAPASITAS 20 L/DET LENGKAP DENGAN PERIODE
29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
PRASARANA PENDUKUNG LOKASI IKK
TAMBUSAI UTARA KABUPATEN ROKAN HULU RENCANA 0.09 0.44 0.80 1.08 2.50 3.46 4.35 5.34 8.04 10.84 12.97 14.48 16.74 20.21 23.21 26.37 30.74 34.72 39.07 42.38 46.91 50.30 55.14 59.01 65 69.78 77.41 84.97 90.61 97 99.56 100
(PAKET-13/APBN 2015) REALISASI 0.00 0.03 0.06 0.21 0.30 1.87 2.13 3.06 4.60 6.98 21.34 21.34 21.34 21.34
DEVIASI -0.09 -0.41 -0.74 -0.88 -2.20 -1.60 -2.22 -2.28 -3.44 -3.86 8.37 6.86 4.60 1.13

14 PENGADAAN DAN PEMASANGAN PAKET IPA 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
BAJA LENGKAP DENGAN PRASARANA PERIODE
29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
PENDUKUNG LOKASI IKK ROKAN IV KOTO
KAPASITAS 20 L/DET DAN IKK PENDALIAN RENCANA 0.07 0.28 0.48 0.72 1.59 3.25 3.92 5.54 6.92 8.64 10.44 13.04 14.99 17.11 19.37 20.72 24.44 29.45 34.55 39.70 43.00 48.54 54.07 59.43 66 71.99 80.84 90.24 94.73 99 99.71 100
KAPASITAS 10 L/DET KABUPATEN ROKAN HULU REALISASI 0.00 0.02 0.04 1.01 6.34 7.72 10.23 14.49 29.60 55.56 56.66 56.66 56.66 56.66
(PAKET-14/APBN 2015) DEVIASI -0.07 -0.26 -0.44 0.30 4.75 4.47 6.30 8.95 22.68 46.92 46.21 43.62 41.67 39.55

15 PENGADAAN DAN PEMASANGAN PAKET IPA 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
BAJA KAPASITAS 20 L/DET LENGKAP DENGAN PERIODE
29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
PRASARANA PENDUKUNG LOKASI IKK PUSAKO
KABUPATEN SIAK (PAKET-15/APBN 2015) RENCANA 0.02 0.04 0.12 0.31 0.92 1.74 2.43 3.46 4.87 7.98 10.06 12.54 15.01 17.52 19.09 21.25 25.24 29.45 34.36 38.58 42.93 48.96 55.31 61.01 68 76.13 85.09 92.37 95.54 99 99.78 100
REALISASI 0.00 0.01 0.02 0.03 0.04 0.04 0.04 0.04 0.07 0.07 0.07 0.07 0.07 0.07
DEVIASI -0.02 -0.04 -0.11 -0.28 -0.88 -1.70 -2.39 -3.43 -4.80 -7.91 -9.99 -12.46 -14.94 -17.45

16 PENGADAAN DAN PEMASANGAN PIPA PVC 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec
LOKASI CABANG RUMBAI PESISIR PDAM TIRTA PERIODE
13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec
SIAK KOTA PEKANBARU (PAKET-16/APBN 2015)
RENCANA 0.01 0.02 0.03 0.04 0.10 0.16 0.22 0.28 0.28 0.56 0.84 1.68 3.30 4.65 9.72 19.65 29.70 39.88 50.26 61.62 72.62 82.84 93.06 99.43 99.71 100
REALISASI 0.00 0.02 0.04 0.16 0.22 29.77 29.77 33.16 77.44 77.44 77.44 77.44
DEVIASI -0.01 0.00 0.01 0.12 0.12 29.60 29.54 32.88 77.15 76.88 76.60 75.76

17 PENGADAAN DAN PEMASANGAN PIPA HDPE 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec
LOKASI SPAM PEKAN KAMPAR (PAKET-17/APBN PERIODE 18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28-Dec
2015)
RENCANA 0.02 0.04 0.05 0.06 0.09 0.21 0.75 1.29 2.54 4.79 7.04 11.29 15.54 19.79 24.04 29.29 34.54 42.79 51.54 60.29 69.04 77.89 86.74 97.29 99.82 100 99.93 100
REALISASI 0.00 0.02 0.04 0.06 70.28 70.28 70.69 85.56 85.56 85.56 85.56 85.56
DEVIASI -0.02 -0.02 -0.01 -0.01 70.18 70.06 69.94 84.27 83.02 80.77 78.52 74.27
PROGRESS FISIK KEGIATAN DAK AIR MINUM KAB. INHU PROVINSI RIAU TA. 2022
PPK : AIR MINUM PROGRAM
NO NAMA PAKET PRO
KABUPATEN INDRAGIRI HULU M1 M2 M3 M4 M5 M6 M7
1 DAK AIR MINUM DESA KEPAYANG 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
SARI,BATANG CENAKU PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.16 1.98 2.89 3.80 4.71 6.53 6.52
Nomor : 03/PKS/PUPR-CK/PPSPAM/DAK-AIR JUMLAH 0.162 2.143 5.033 8.834 13.544 20.074 26.598
MINUM/VII/2022 KOMULATIF
REALISASI % 0.000 0.000 0.000 4.984 3.208 2.480 2.680
JUMLAH 0.000 0.000 0.000 4.984 8.191 10.671 13.351
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % -0.16 -2.14 -5.03 -3.85 -5.35 -9.403 -13.247
PROGRESS 0.000 0.000 0.000 14.640 0.000 25% 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 34.000 21.000 30.000 28.000
JUMLAH ORANG 0.000 0.000 0.000 3.000 3.000 5.000 5.000
KERJA M1 M2 M3 M4 M5 M6 M7
2 DAK AIR MINUM DESA PEMATANG 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
MANGGIS,BATANG CENAKU PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.16 2.43 3.57 4.70 4.70 4.70 4.70
Nomor : 06/PKS/PUPR-CK/PPSPAM/DAK-AIR JUMLAH 0.162 2.593 6.160 10.862 15.564 20.266 24.968
MINUM/VII/2022 KOMULATIF
REALISASI % 0.00 0.00 0.00 0.00 0.00 5.20 5.03
JUMLAH 0.00 0.00 0.00 0.00 0.00 5.200 10.230
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % -0.16 -2.59 -6.16 -10.86 -15.56 -15.066 -14.738
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 0.000 10.490 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 0.000 24.000 39.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 0.000 4.000 0.000
KERJA M1 M2 M3 YG M5 M6 M7
3 DAK AIR MINUM DESA KUALA 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
GADING,BATANG CENAKU PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.226 0.226 0.226 2.968 8.454 8.454 8.325
Nomor : 05/PKS/PUPR-CK/PPSPAM/DAK-AIR JUMLAH 0.226 0.451 0.677 3.645 12.099 20.553 28.879
MINUM/VII/2022 KOMULATIF
REALISASI % 0.00 0.00 0.00 0.00 1.61 2.01 2.73
RENCANA
JUMLAH 0.00 0.00 0.00 0.00 1.61 3.620 6.350
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % -0.23 -0.45 -0.68 -3.65 -10.49 -16.933 -22.529
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 7.290 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 0.000 0.000 0.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 0.000 0.000 0.000
KERJA M1 M2 M3 M4 M5 M6 M7
4 DAK AIR MINUM DESA SERESAM,SEBERIDA 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.000 0.000 1.983 1.983 2.173 19.210 4.541
Nomor : 08/PKS/PUPR-CK/PPSPAM/DAK-AIR JUMLAH 0.000 0.000 1.983 3.966 6.139 25.349 29.891
MINUM/VII/2022 KOMULATIF
REALISASI % 0.00 0.00 0.00 0.65 3.20 3.24 6.94
RENCANA
JUMLAH 0.00 0.00 0.00 0.65 3.85 7.086 14.026
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % 0.00 0.00 -1.98 -3.32 -2.29 -18.263 -15.865
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 9.890 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 30.000 20.000 55.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 3.000 3.000 4.000
KERJA
M1 M2 M3 M4 M5 M6 M7
5 DAK AIR MINUM DESA TITIAN 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
RESAK,SEBERIDA PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.000 0.000 2.332 2.332 2.639 18.081 17.581
JUMLAH 0.000 0.000 2.332 4.664 7.303 25.383 42.964
Nomor : 10/PKS/PUPR-CK/PPSPAM/DAK-AIR KOMULATIF
REALISASI % 0.00 0.00 0.00 1.18 8.86 5.75 2.93
MINUM/VII/2022 RENCANA
JUMLAH 0.00 0.00 0.00 1.18 10.04 15.80 18.73
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % 0.00 0.00 -2.33 -3.48 2.74 -9.585 -24.236
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 25.000 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 20.000 10.000 6.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 4.000 4.000 4.000
KERJA M1 M2 M3 M4 M5 M6 M7
6 DAK AIR MINUM DESA SEKO LUBUK 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
TIGO,LIRIK PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.000 0.000 2.495 2.495 2.710 17.524 5.571
JUMLAH 0.000 0.000 2.495 4.990 7.699 25.223 30.795
Nomor : 07/PKS/PUPR-CK/PPSPAM/DAK-AIR KOMULATIF
REALISASI % 0.00 0.00 0.00 0.73 2.77 3.75 7.48
MINUM/VII/2022 RENCANA
JUMLAH 0.00 0.00 0.00 0.73 3.50 7.25 14.73
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % 0.00 0.00 -2.49 -4.26 -4.20 -17.972 -16.064
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 11.1 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 15.000 20.000 0.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 3.000 4.000 0.000
KERJA M1 M2 M3 M4 M5 M6 M7
7 DAK AIR MINUM DESA SUNGAI SAGU,LIRIK 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.000 0.000 1.946 1.946 2.140 19.274 5.389
JUMLAH 0.000 0.000 1.946 3.892 6.033 25.307 30.695
Nomor : 09/PKS/PUPR-CK/PPSPAM/DAK-AIR KOMULATIF
REALISASI % 0.00 0.00 0.00 0.66 1.00 3.00 8.00
MINUM/VII/2022 RENCANA
JUMLAH 0.00 0.00 0.00 0.66 1.66 4.66 12.66
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % 0.00 0.00 -1.95 -3.24 -4.37 -20.650 -18.038
REALISASI
PROGRESS 0.000 0.000 0.000 10.08 0.000 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 15.000 20.000 40.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 3.000 4.000 4.000
KERJA M1 M2 M3 M4 M5 M6 M7
8 DAK AIR MINUM DESA JATI REJO,PASIR 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
PENYU PERIODE
8 DAK AIR MINUM DESA JATI REJO,PASIR
PENYU PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.19 1.54 2.22 2.89 2.89 2.89 2.89
JUMLAH 0.193 1.737 3.957 6.852 9.746 12.641 15.536
Nomor : 02/PKS/PUPR-CK/PPSPAM/DAK-AIR KOMULATIF
REALISASI % 0.00 1.05 0.00 5.38 1.42 1.05 5.07
MINUM/VII/2022 RENCANA
JUMLAH 0.00 1.05 1.05 6.43 7.85 8.90 13.97
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % -0.19 -0.69 -2.91 -0.42 -1.90 -3.741 -1.566
REALISASI
PROGRESS 0.000 0.000 0.000 12.112 12.112 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 20.000 20.000 25.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 4.000 4.000 5.000
KERJA
M1 M2 M3 M4 M5 M6 M7
9 DAK AIR MINUM DESA BATU SAWAR,RAKIT 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
KULIM PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.23 0.23 0.23 0.23 0.23 0.23 0.23
JUMLAH 0.230 0.461 0.691 0.921 1.152 1.382 1.612
Nomor : 01/PKS/PUPR-CK/PPSPAM/DAK-AIR KOMULATIF
REALISASI % 0.00 0.00 0.00 1.60 4.74 0.00 0.00
MINUM/VII/2022 RENCANA
JUMLAH 0.00 0.00 0.00 1.60 6.34 6.34 6.34
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % -0.23 -0.46 -0.69 0.68 5.19 4.958 4.728
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 7.880 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 0.000 0.000 0.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 0.000 0.000 0.000
KERJA M1 M2 M3 M4 M5 M6 M7
10 DAK AIR MINUM DESA KOTA 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug
MEDAN,KELAYANG PERIODE
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep
Kontrak PKS : RENCANA % 0.166 0.166 0.166 0.166 0.166 2.100 2.100
JUMLAH 0.166 0.332 0.498 0.664 0.830 2.931 5.031
Nomor : 04/PKS/PUPR-CK/PPSPAM/DAK-AIR KOMULATIF
REALISASI % 0.00 0.00 0.00 1.17 4.53 0.00 0.00
MINUM/VII/2022 RENCANA
JUMLAH 0.00 0.00 0.00 1.17 5.70 5.70 5.70
Tanggal : 15 Juli 2022 KOMULATIF
DEVIASI % -0.17 -0.33 -0.50 0.51 4.87 2.769 0.669
REALISASI
PROGRESS 0.000 0.000 0.000 0.000 6.990 0.000 0.000
KEUANGAN
HOK % 0.000 0.000 0.000 0.000 0.000 0.000 0.000
JUMLAH ORANG 0.000 0.000 0.000 0.000 0.000 0.000 0.000
KERJA

Ket
Warna Merah di Isi Manual
Di Isi Setiap Hari Kamis
Mengetahui,

YENNI MULYADI, ST, MT


NIP. 19780805 200502 1 001
A. 2022 format A.5

PROGRESS
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 11-Dec
8.34 9.24 8.34 12.30 12.30 10.48 8.66 3.58 0.16
34.935 44.176 52.513 64.814 77.115 87.597 96.259 99.838 100.000
2.140 5.270 0.000 0.000 0.000 0.000 0.000 0.000 0.000
15.491 20.761 20.761 20.761 20.761 20.761 20.761 20.761 20.761
-19.444 -23.415 -31.752 -44.053 -56.354 -66.836 -75.498 -79.077 -79.239
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
15.000 55.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
4.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 11-Dec
8.26 8.26 9.47 11.55 11.55 11.55 9.28 4.59 0.52
33.229 41.489 50.961 62.512 74.062 85.613 94.893 99.480 100.000
2.55 7.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.780 20.380 20.380 20.380 20.380 20.380 20.380 20.380 20.380
-20.449 -21.109 -30.581 -42.132 -53.682 -65.233 -74.513 -79.100 -79.620
25.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
33.000 113.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 11-Dec
8.325 10.940 10.940 10.940 10.940 10.402 7.659 0.750 0.226
37.204 48.144 59.084 70.023 80.963 91.365 99.024 99.774 100.000
1.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7.460 7.460 7.460 7.460 7.460 7.460 7.460 7.460 7.460


-29.744 -40.684 -51.624 -62.563 -73.503 -83.905 -91.564 -92.314 -92.540
25.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 31-Dec 7-Jan 14-Jan 21-Jan
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 6-Jan 13-Jan 20-Jan 23-Jan
4.541 4.541 4.541 4.541 4.541 10.556 10.556 4.541 12.872 8.521 0.355
34.432 38.974 43.515 48.057 52.598 63.154 73.711 78.252 91.124 99.645 100.000
6.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

20.966 20.966 20.966 20.966 20.966 20.966 20.966 20.966 20.966 20.966 20.966
-13.466 -18.008 -22.549 -27.091 -31.632 -42.188 -52.745 -57.286 -70.158 -78.679 -79.034
15.110 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
55.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
4.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov
17.581 2.639 2.639 2.639 2.639 2.639 5.356 8.800 8.300 3.024 0.783
60.545 63.183 65.822 68.461 71.099 73.738 79.094 87.894 96.193 99.217 100.000
2.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
21.67 21.67 21.67 21.67 21.67 21.67 21.67 21.67 21.67 21.67 21.67
-38.877 -41.515 -44.154 -46.793 -49.431 -52.070 -57.426 -66.226 -74.525 -77.549 -78.332
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
6.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
4.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov
5.571 5.571 5.571 5.571 5.571 5.571 8.922 8.922 11.445 6.088 0.402
36.366 41.937 47.508 53.079 58.651 64.222 73.144 82.065 93.510 99.598 100.000
7.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
22.21 22.21 22.21 22.21 22.21 22.21 22.21 22.21 22.21 22.21 22.21
-14.155 -19.726 -25.297 -30.868 -36.440 -42.011 -50.933 -59.854 -71.299 -77.387 -77.789
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov
5.389 5.389 5.389 5.389 5.389 5.389 9.429 9.429 11.475 6.280 0.361
36.084 41.472 46.861 52.249 57.638 63.026 72.455 81.884 93.359 99.639 100.000
8.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
21.12 21.12 21.12 21.12 21.12 21.12 21.12 21.12 21.12 21.12 21.12
-14.967 -20.355 -25.744 -31.132 -36.521 -41.909 -51.338 -60.767 -72.242 -78.522 -78.883
14.921 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
40.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
4.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov
7.28 7.28 9.13 13.58 13.58 13.58 12.23 7.17 0.64
22.813 30.090 39.221 52.800 66.379 79.958 92.186 99.357 100.000
5.40 1.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00

19.37 21.06 21.06 21.06 21.06 21.06 21.06 21.06 21.06


-3.443 -9.030 -18.161 -31.740 -45.319 -58.898 -71.126 -78.297 -78.940
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
30.000 25.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
6.000 5.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov
5.17 5.17 7.64 15.67 15.67 18.79 18.79 10.73 0.76
6.780 11.949 19.586 35.255 50.925 69.716 88.507 99.239 100.000
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.34 6.34 6.34 6.34 6.34 6.34 6.34 6.34 6.34
-0.440 -5.609 -13.246 -28.915 -44.585 -63.376 -82.167 -92.899 -93.660
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov
8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov
2.100 4.035 4.035 16.463 17.386 18.904 18.904 12.594 0.548
7.131 11.166 15.201 31.663 49.050 67.954 86.858 99.452 100.000
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.70 5.70 5.70 5.70 5.70 5.70 5.70 5.70 5.70
-1.431 -5.466 -9.501 -25.963 -43.350 -62.254 -81.158 -93.752 -94.300
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

Di Buat,
DAK AIR MINUM

ALFI ZONDRA.ST
KTFL
37.262622

74.53
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 50%
1 PEMATANG MANGGIS/BATANG CENAKU
1 TOWER RESERVOIR S : 00°44' 14.4"

E : 102° 12'57.8"

2 PERPIPAAN S : 00°44' 13.1"

E : 102° 12'57.4"

3 SAMBUNGAN RUMAH S : 00°44' 13.3"

E : 102° 12'57.5"
si
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 50%
1 KEPAYANG SARI/BATANG CENAKU
1 TOWER RESERVOIR S : 00°47' 22.7"

E : 102° 11'11.9"

2 PERPIPAAN S : 00°47' 22.9"

E : 102° 11'12.2"

3 SAMBUNGAN RUMAH S : 00°47' 22.9"

E : 102° 11'13.3"
si
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 50%
1 KEPAYANG SARI/BATANG CENAKU
1 TOWER RESERVOIR

2 PERPIPAAN

3 SAMBUNGAN RUMAH
si
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan
No Titik Koordinat
0%
1 SERESAM/SEBERIDA
1 MENARA S : 0° 35' 6.82''

E : 102° 21' 37.33''

2 POMPA & PERLENGKAPAN S : 0°35'3.53"

E : 102°21'37.39"

3 JARINGAN PIPA S : 0° 35' 6.59''

E : 102° 21' 38.83'

4 SAMBUNGAN RUMAH S : 0° 35' 6.37''

E : 102° 21' 40.16'


Dokumentasi
25% 50% 75%
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan
No Titik Koordinat
0%
1 TITIAN RESAK/SEBERIDA
1 Bak Penampung & Pengolahan Air S : 0° 32' 9.12''

E : 102° 23' 19.06''

2 Pompa & Perlengkapan S : 0° 32' 9.15''

E : 102° 23' 19.06''

3 Sambungan Rumah S : 0° 32' 10.56''

E : 102° 23' 18.48'''


Dokumentasi
25% 50% 75%
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 25%
1 SUNGAI SAGU/LIRIK
1 PEMBANGUNAN MENARA

2 PENGADAAN POMPA DAN


PERLENGKAPAN

3 PEMBANGUNAN JARINGAN
PERPIPAAN

4 SAMBUNGAN RUMAH
Dokumentasi
50% 75% 100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 25%
1 SEKO LUBUK TIGO/LIRIK
1 PEMBANGUNAN MENARA

2 PENGADAAN POMPA DAN


PERLENGKAPAN

3 JARINGAN PERPIPAAN

4 SAMBUNGAN RUMAH
Dokumentasi
50% 75% 100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 50%
1 JATI REJO/PASIR PENYU
1 TOWER RESERVOIR

2 PERPIPAAN

3 SAMBUNGAN RUMAH
Dokumentasi
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 50%
1 KOTA MEDAN/KELAYANG
1 TOWER RESERVOIR

2 PERPIPAAN

3 SAMBUNGAN RUMAH
si
100%
FOTO KEGIATAN DESA DAK AIR MINUM TAHUN 2022
KABUPATEN : INDRAGIRI HULU
PROVINSI : RIAU

Desa/Kecamatan Dokumentasi
No Titik Koordinat
0% 50%
1 BATU SAWAR/RAKIT KULIM
1 TOWER RESERVOIR

2 PERPIPAAN

3 SAMBUNGAN RUMAH
si
100%