Professional Documents
Culture Documents
Number: CAPM
Passing Score: 800
Time Limit: 120 min
File Version: 1
CAPM
Sections
1. Volume A
2. Volume B
3. Volume C
4. Volume D
5. Volume E
VCEConvert.com
Exam A
QUESTION 1
Which document defines how a project is executed, monitored and controlled, and closed?
A. Strategic plan
B. Project charter
C. Project management plan
D. Service level agreement
QUESTION 2
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
QUESTION 3
Which tool or technique is an examination of industry and specific vendor capabilities?
A. Independent estimates
B. Market research
C. Analytical techniques
D. Bidder conferences
QUESTION 4
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of
which tool or technique?
A. Expert judgment
B. Forecasting methods
C. Earned value management
D. Analytical techniques
QUESTION 5
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
A. Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses
QUESTION 6
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and
controlling the project schedule is known as:
VCEConvert.com
QUESTION 7
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
A. Issue log
B. Change log
C. Expert judgment
D. Change requests
QUESTION 8
An input to the Plan Cost Management process is:
A. Cost estimates
B. Resource calendars
C. The project charter
D. The risk register
QUESTION 9
A technique used to determine the cause and degree of difference between baseline and actual performance is:
A. Product analysis.
B. Variance analysis.
C. Document analysis.
D. Decomposition.
QUESTION 10
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and
creating a staffing management plan is known as:
QUESTION 11
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical
limitations?
A. Mandatory
B. Discretionary
C. Internal
D. External
QUESTION 12
An input to the Manage Project Team process is:
VCEConvert.com
QUESTION 13
Which input provides suppliers with a clear set of goals, requirements, and outcomes?
QUESTION 14
A project manager providing information to the right audience, in the right format, at the right time is an example of which
type of communication?
A. Efficient
B. Effective
C. Push
D. Pull
QUESTION 15
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the
earned value (EV) is $50?
A. 0.50
B. 0.67
C. 1.50
D. 2.00
QUESTION 16
Which item is an input to the Define Activities process?
A. Schedule data
B. Activity list
C. Risk register
D. Scope baseline
QUESTION 17
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
A. Interactive communication
B. Claims administration
C. Conflict management
D. Performance reporting
QUESTION 18
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition
hierarchy that uses a systematic set of rules that define a nesting relationship?
A. Interrelationship digraphs
B. Tree diagram
C. Affinity diagram
D. Network diagram
VCEConvert.com
QUESTION 19
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle
is:
A. Planning.
B. Executing,
C. Monitoring and Controlling.
D. Closing.
QUESTION 20
Organizational theory is a tool used in which Project Human Resource Management process?
QUESTION 21
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team
members. This situation describes which type of organizational structure?
A. Projectized
B. Weak matrix
C. Functional
D. Balanced matrix
QUESTION 22
Which document describes the necessary information to determine if a project is worth the required investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
QUESTION 23
Plan Schedule Management is a process in which Knowledge Area?
QUESTION 24
The Perform Integrated Change Control process occurs in which Process Group?
A. Initiating
B. Executing
C. Monitoring and Controlling
D. Planning
QUESTION 25
VCEConvert.com
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
QUESTION 26
Which input may influence quality assurance work and should be monitored within the context of a system for configuration
management?
QUESTION 27
Change requests are processed for review and disposition according to which process?
A. Control Quality
B. Control Scope
C. Monitor and Control Project Work
D. Perform Integrated Change Control
QUESTION 28
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the
contract is known as:
QUESTION 29
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
A. Scope baseline
B. Organizational process assets
C. Enterprise environmental factors
D. Risk register
QUESTION 30
The process of confirming human resource availability and obtaining the team necessary to complete project activities is
known as:
QUESTION 31
VCEConvert.com
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group
QUESTION 32
The Plan Stakeholder Management process belongs to which Process Group?
A. Executing
B. Initiating
C. Planning
D. Monitoring and Controlling
QUESTION 33
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved
in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
QUESTION 34
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually
building is known as:
A. Benchmarking.
B. Context diagrams.
C. Brainstorming.
D. Prototyping.
QUESTION 35
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in
the project?
A. Power/influence grid
B. Power/interest grid
C. Influence/impact grid
D. Salience model
QUESTION 36
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the
project?
A. Facilitation techniques
B. Expert judgment
C. Analytical techniques
D. Variance analysis
VCEConvert.com
QUESTION 37
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform
each activity is known as:
A. Collect Requirements.
B. Conduct Procurements.
C. Estimate Activity Durations.
D. Estimate Activity Resources.
QUESTION 38
The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing
QUESTION 39
Which item is a formal proposal to modify any document, deliverable, or baseline?
A. Change request
B. Requirements documentation
C. Scope baseline
D. Risk urgency assessment
QUESTION 40
The definition of when and how often the risk management processes will be performed throughout the project life cycle is
included in which risk management plan component?
A. Timing
B. Methodology
C. Risk categories
D. Budgeting
QUESTION 41
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
QUESTION 42
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a
previous similar project as the basis for estimating the same parameter or measurement for a current project describes
which type of estimating?
A. Bottom-up
B. Parametric
C. Analogous
D. Three-point
VCEConvert.com
QUESTION 43
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive
plan?
QUESTION 44
Inputs to the Plan Schedule Management process include:
QUESTION 45
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a
project?
QUESTION 46
Which tool or technique is used to manage change requests and the resulting decisions?
QUESTION 47
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
A. Work packages.
B. Accepted deliverables.
C. The WBS dictionary.
D. The scope baseline.
QUESTION 48
The ability to influence cost is greatest during which stages of the project?
A. Early
B. Middle
C. Late
D. Completion
VCEConvert.com
QUESTION 49
Which process involves developing an approximation of the monetary resources needed to complete project activities?
A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management
QUESTION 50
When should quality planning be performed?
QUESTION 51
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and
structured within a project is described in the:
QUESTION 52
An output of the Manage Stakeholder Engagement process is:
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log
QUESTION 53
Which process numerically analyzes the effect of identified risks on overall project objectives?
QUESTION 54
An input to the Plan Procurement Management process is:
QUESTION 55
Reserve analysis is a tool and technique used in which process?
VCEConvert.com
A. Plan Risk Management
B. Plan Risk Responses
C. Identify Risks
D. Control Risks
QUESTION 56
A regression line is used to estimate:
QUESTION 57
Which tool or technique is used to develop the human resource management plan?
A. Ground rules
B. Expert judgment
C. Team-building activities
D. Interpersonal skills
QUESTION 58
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
A. Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates
QUESTION 59
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are
examples of items that are established in the:
QUESTION 60
The Monitoring and Controlling Process Group includes processes that:
QUESTION 61
Which Control Quality tool is also known as an arrow diagram?
A. Matrix diagram
VCEConvert.com
B. Affinity diagram
C. Tree diagram
D. Activity network diagram
QUESTION 62
When does the project team determine which dependencies are discretionary?
QUESTION 63
A temporary endeavor that creates a unique product or service is called a:
A. Project
B. Plan
C. Program
D. Portfolio
QUESTION 64
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
QUESTION 65
The number of potential communication channels for a project with 5 stakeholders is:
A. 10.
B. 12.
C. 20.
D. 24.
QUESTION 66
An input to Close Project or Phase is:
A. Accepted deliverables.
B. Final products or services.
C. Document updates.
D. Work performance information.
QUESTION 67
An output of the Direct and Manage Project Work process is:
A. Deliverables.
B. Activity lists.
C. A work breakdown structure.
VCEConvert.com
D. A scope statement.
QUESTION 68
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A. Develop Schedule
B. Create VVBS
C. Estimate Activity Resources
D. Define Scope
QUESTION 69
In a project, total float measures the:
QUESTION 70
Stakeholder satisfaction should be managed as a key project:
A. Benefit
B. Initiative
C. Objective
D. Process
QUESTION 71
Which cost is associated with nonconformance?
A. Liabilities
B. Inspections
C. Training
D. Equipment
QUESTION 72
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on
where it is in the project life cycle?
A. Historical relationships
B. Dependency determination
C. Bottom-up estimating
D. Rolling wave planning
QUESTION 73
An output of the Create WBS process is:
A. Scope baseline.
B. Change requests.
C. Accepted deliverables.
D. Variance analysis.
VCEConvert.com
QUESTION 74
Which Define Activities output extends the description of the activity by identifying the multiple components associated with
each activity?
QUESTION 75
An input to the Identify Stakeholders process is:
QUESTION 76
Identify Risks is part of which Process Group?
A. Planning
B. Executing
C. Closing
D. Initiating
QUESTION 77
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to
temporarily or partially resolve the conflict?
A. Force/direct
B. Withdraw/avoid
C. Compromise/reconcile
D. Collaborate/problem solve
QUESTION 78
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
A. Start-to-start (SS).
B. Start-to-finish (SF).
C. Finish-to-start (FS).
D. Finish-to-finish (FF).
QUESTION 79
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
VCEConvert.com
QUESTION 80
The business needs, assumptions, and constraints and the understanding of the customers’ needs and high-level
requirements are documented in the:
QUESTION 81
In the Plan Stakeholder Management process, expert judgment is used to:
QUESTION 82
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
A. Analysis
B. Appetite
C. Tolerance
D. Response
QUESTION 83
An output of the Perform Integrated Change Control process is:
A. Deliverables.
B. Validated changes.
C. The change log.
D. The requirements traceability matrix.
QUESTION 84
The process of monitoring the status of the project and product scope as well as managing the changes to the scope
baseline is known as:
A. Validate Scope.
B. Plan Scope Management.
C. Control Scope.
D. Define Scope.
QUESTION 85
Which output is the approved version of the time-phased project budget?
A. Resource calendar
B. Scope baseline
C. Trend analysis
D. Cost baseline
QUESTION 86
VCEConvert.com
The purpose of the Project Communications Management Knowledge Area is to:
A. Monitor and control communications throughout the entire project life cycle.
B. Maintain an optimal flow of information among all project participants.
C. Develop an appropriate approach for project communications.
D. Ensure timely and appropriate collection of project information.
QUESTION 87
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
A. Salience
B. Influence/impact
C. Power/interest
D. Power/influence
QUESTION 88
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
A. Checksheets
B. Histograms
C. Flowcharts
D. Control charts
QUESTION 89
The following is a network diagram for a project.
A. 2
B. 3
C. 5
D. 8
QUESTION 90
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others
describes which of the five general techniques for managing conflict?
A. Smooth/accommodate
B. Withdraw/avoid
C. Compromise/reconcile
D. Force/direct
VCEConvert.com
QUESTION 91
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
A. management
B. response
C. tolerance
D. appetite
QUESTION 92
The zero duration of milestones in project planning occurs because milestones:
QUESTION 93
Which type of graphic is displayed below?
QUESTION 94
The following is a network diagram for a project.
VCEConvert.com
The shortest non-critical path for the project is how many days in duration?
A. 10
B. 12
C. 14
D. 16
QUESTION 95
The component of the human resource management plan that includes ways in which team members can obtain
certifications that support their ability to benefit the project is known as:
QUESTION 96
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
A. Continuous
B. Discrete
C. Regulated
D. Arbitrary
QUESTION 97
A graphic display of project team members and their reporting relationships is known as a:
A. Resource calendar.
B. Project organization chart.
C. Resource breakdown structure (RBS).
D. Responsibility assignment matrix (RAM).
QUESTION 98
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal
skills to convince others to cooperate toward common goals?
VCEConvert.com
A. Collaboration
B. Negotiation
C. Decision making
D. Influencing
QUESTION 99
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
A. Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget
QUESTION 100
Which document in the project management plan can be updated in the Plan Procurement Management process?
A. Budget estimates
B. Risk matrix
C. Requirements documentation
D. Procurement documents
QUESTION 101
Perform Integrated Change Control is the process of:
QUESTION 102
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
A. lead
B. lag
C. mandatory dependency
D. internal dependency
QUESTION 103
Which action is included in the Control Costs process?
A. Identify how the project costs will be planned, structured, and controlled
B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
C. Develop an approximation of the monetary resources needed to complete project activities
D. Monitor cost performance to isolate and understand variances from the approved cost baseline
QUESTION 104
Project management processes ensure the:
VCEConvert.com
C. performance of the project team
D. effective flow of the project throughout its life cycle
QUESTION 105
An element of the modern quality management approach used to achieve compatibility with the International Organization
for Standardization (ISO) is known as:
A. Forecasting,
B. Brainstorming.
C. Historical databases.
D. Cost of quality.
QUESTION 106
Which items are components of a project management plan?
A. Change management plan, process improvement plan, and scope management plan
B. Agreements, procurement management plan, and work performance information
C. Schedule management plan, project schedule, and resource calendars
D. Scope baseline, project statement of work, and requirements traceability matrix
QUESTION 107
Which project document is updated in the Control Stakeholder Engagement process?
A. Project reports
B. Issue log
C. Lessons learned documentation
D. Work performance information
QUESTION 108
A project manager should communicate to stakeholders about resolved project issues by updating the:
A. project records
B. project reports
C. stakeholder notifications
D. stakeholder register
QUESTION 109
Which Project Time Management process includes bottom-up estimating as a tool or technique?
QUESTION 110
Progressively elaborating high-level information into detailed plans is performed by the:
VCEConvert.com
QUESTION 111
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to
it, and develop preventative actions?
A. Inspection
B. Quality audits
C. Design of experiments
D. Root cause analysis
QUESTION 112
In which phase of team building activities do team members begin to work together and adjust their work habits and
behavior to support the team?
A. Performing
B. Storming
C. Norming
D. Forming
QUESTION 113
Which project risk listed in the table below is most likely to occur?
A. 1
B. 2
C. 3
D. 4
QUESTION 114
Which is an enterprise environmental factor?
A. Marketplace conditions
B. Policies and procedures
C. Project files from previous projects
D. Lessons learned from previous projects
QUESTION 115
Project Stakeholder Management focuses on:
VCEConvert.com
C. managing conflicting interests
D. communication methods
QUESTION 116
A risk that arises as a direct result of implementing a risk response is called a:
A. contingent risk
B. residual risk
C. potential risk
D. secondary risk
QUESTION 117
The purpose of developing a project scope management plan is to:
QUESTION 118
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
A. 0.83
B. 0.9
C. 1.11
D. 1.33
QUESTION 119
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into
VCEConvert.com
smaller, more manageable parts?
A. Decomposition
B. Inspection
C. Project analysis
D. Document analysis
QUESTION 120
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual
performance?
QUESTION 121
A project’s purpose or justification, measurable project objectives and related success criteria, a summary milestone
schedule, and a summary budget are all components of which document?
QUESTION 122
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the
deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
QUESTION 123
Those who enter into a contractual agreement to provide services necessary for a project are:
A. buyers
B. sellers
C. business partners
D. product users
QUESTION 124
Project managers who lead by example and follow through on the commitments they make demonstrate the key
interpersonal skill of:
A. influencing
B. leadership
C. motivation
D. coaching
VCEConvert.com
QUESTION 125
Which items are an output of the Perform Integrated Change Control process?
QUESTION 126
The Project Human Resource Management process that involves confirming human resource availability and obtaining the
team necessary to complete project activities is:
QUESTION 127
At the start of a typical project life cycle, costs are:
A. low, peak as work is carried out, and drop as the project nears the end.
B. low, become steady as work is carried out, and increase as the project nears the end.
C. high, drop as work is carried out, and increase as the project nears the end.
D. high, become low as work is carried out, and drop as the project nears the end.
QUESTION 128
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
QUESTION 129
The process of defining how the project scope will be validated and controlled is known as:
A. Define Scope.
B. Develop Project Management Plan.
C. Plan Scope Management.
D. Plan Quality Management.
QUESTION 130
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
A. triangular distribution
B. tornado diagram
C. beta distribution
D. fishbone diagram
QUESTION 131
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational
VCEConvert.com
structure with which type of matrix?
A. Strong
B. Weak
C. Managed
D. Balanced
QUESTION 132
Project Scope Management is primarily concerned with:
QUESTION 133
Which schedule method allows the project team to place buffers on the project schedule path to account for limited
resources and project uncertainties?
QUESTION 134
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
A. work package
B. deliverable
C. milestone
D. activity
QUESTION 135
The scope management plan and scope baseline are contained in:
QUESTION 136
Which Manage Communications tool or technique focuses on identifying and managing barriers?
A. Communication methods
B. Information technology
C. Communication models
D. Information management systems
QUESTION 137
Which type of organizational structure is displayed in the diagram provided?
VCEConvert.com
A. Balanced matrix
B. Projectized
C. Strong matrix
D. Functional
QUESTION 138
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical
methodologies, techniques, solutions, and services meet the procurement documents requirements?
A. Technical approach
B. Technical capability
C. Business size and type
D. Production capacity and interest
QUESTION 139
Which element does a project charter contain?
A. Management reserves
B. Work breakdown structure
C. Stakeholder list
D. Stakeholder register
QUESTION 140
The following is a network diagram for a project.
VCEConvert.com
What is the critical path for the project?
A. A-B-C-F-G-I
B. A-B-C-F-H-I
C. A-D-E-F-G-I
D. A-D-E-F-H-I
QUESTION 141
The following is a network diagram for a project.
A. 3
B. 4
C. 6
D. 7
QUESTION 142
The following is a network diagram for a project.
A. 4
B. 5
VCEConvert.com
C. 10
D. 11
QUESTION 143
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder
involvement in projects is:
A. adaptive
B. reflexive
C. predictive
D. iterative
QUESTION 144
Whose approval may be required for change requests after change control board (CCB) approval?
A. Functional managers
B. Business partners
C. Customers or sponsors
D. Subject matter experts
QUESTION 145
The primary benefit of the Plan Schedule Management process is that it:
QUESTION 146
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes
which classification model for stakeholder analysis?
A. Influence/impact grid
B. Power/influence grid
C. Power/interest grid
D. Salience model
QUESTION 147
An intentional activity to modify a nonconforming product or product component is called:
A. defect repair
B. work repair
C. corrective action
D. preventive action
QUESTION 148
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
A. Control chart
B. Flowchart
C. Checksheet
VCEConvert.com
D. Pareto diagram
QUESTION 149
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
A. Business case
B. Work breakdown structure
C. Requirements documentation
D. Risk register
QUESTION 150
In complex projects/ initiating processes should be completed:
QUESTION 151
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A. Communication models.
B. Stakeholder participation.
C. Expert judgment
D. Enterprise environmental factors.
QUESTION 152
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
A. appetite
B. tolerance
C. threshold
D. management
QUESTION 153
Completion of the product scope is measured against the product:
A. prototypes
B. requirements
C. analyses
D. benchmarks
QUESTION 154
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the
corresponding independent variable?
A. Cause-and-effect diagram
B. Histogram
C. Control chart
D. Scatter diagram
VCEConvert.com
QUESTION 155
High-level project risks are included in which document?
A. Business case
B. Risk breakdown structure
C. Project charter
D. Risk register
QUESTION 156
The scope management plan and scope baseline are contained in:
QUESTION 157
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
A. portfolio
B. program
C. selection
D. sub portfolio
QUESTION 158
Which enterprise environmental factors may influence Plan Schedule Management?
A. Cultural views regarding time schedules and professional and ethical behaviors
B. Historical information and change control procedures
C. Risk control procedures and the probability and impact matrix
D. Resource availability and organizational culture and structure
QUESTION 159
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential
logic, or soft logic?
A. Internal
B. External
C. Discretionary
D. Mandatory
QUESTION 160
When the business objectives of an organization change, project goals need to be:
A. realigned.
B. performed.
C. improved.
D. controlled.
QUESTION 161
VCEConvert.com
A project manager who communicates to the project team though email is using which type of communication?
A. Formal
B. Informal
C. Horizontal
D. Unofficial
QUESTION 162
Which tool or technique is required in order to determine the project budget?
A. Cost of quality
B. Historical relationships
C. Project management software
D. Forecasting
QUESTION 163
Which process involves the creation of a document that provides the project manager with the authority to apply resources
to a project?
A. Define Activities
B. Direct and Manage Project Work
C. Develop Project Management Plan
D. Develop Project Charter
QUESTION 164
The stakeholder register is an output of:
A. Identify Stakeholders.
B. Plan Stakeholder Management.
C. Control Stakeholder Engagement.
D. Manage Stakeholder Engagement.
QUESTION 165
The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:
A. Methodology
B. Risk category
C. Risk attitude
D. Assumption analysis
QUESTION 166
Outputs of the Control Communications process include:
QUESTION 167
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified
management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining
VCEConvert.com
budget is known as the:
QUESTION 168
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
A. plan
B. process
C. program
D. portfolio
QUESTION 169
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
A. quality audits
B. process analysis
C. statistical sampling
D. benchmarking
QUESTION 170
Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any
areas in which changes to the plan are required; and initiate the corresponding changes?
QUESTION 171
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is
known as:
A. Define Activities.
B. Sequence Activities.
C. Define Scope.
D. Control Schedule.
QUESTION 172
Which document includes the project scope, major deliverables, assumptions, and constraints?
A. Project charter
B. Project scope statement
C. Scope management plan
D. Project document updates
QUESTION 173
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed
VCEConvert.com
into more detail using which type of estimating?
A. Bottom-up
B. Parametric
C. Analogous
D. Three-point
QUESTION 174
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are
examples of which input to the Close Project or Phase process?
QUESTION 175
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in
ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
A. Supportive
B. Leading
C. Neutral
D. Resistant
QUESTION 176
Which of the following is a narrative description of products, services, or results to be delivered by a project?
QUESTION 177
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
QUESTION 178
Projects are undertaken by an organization to support the:
A. Product performance.
B. Budget process.
C. Collective capabilities.
D. Organizational strategy.
QUESTION 179
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
VCEConvert.com
A. start-to-start (SS)
B. start-to-finish (SF)
C. finish-to-start (FS)
D. finish-to-finish (FF)
QUESTION 180
Work performance information and cost forecasts are outputs of which Project Cost Management process?
A. Estimate Costs
B. Plan Cost Management
C. Determine Budget
D. Control Costs
QUESTION 181
The procurement process that documents agreements and related documentation for future reference is known as:
A. Plan Procurements.
B. Control Procurements.
C. Close Procurements.
D. Conduct Procurements.
QUESTION 182
The scope of a project cannot be defined without some basic understanding of how to create the specified:
A. objectives
B. schedule
C. product
D. approach
QUESTION 183
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
A. Push
B. Pull
C. Interactive
D. Iterative
QUESTION 184
Which component of the human resource management plan describes when and how project team members are acquired
and how long they will be needed?
QUESTION 185
The process of formalizing acceptance of the completed project deliverables is known as:
A. Validate Scope.
VCEConvert.com
B. Close Project or Phase.
C. Control Quality.
D. Verify Scope.
QUESTION 186
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
QUESTION 187
Most experienced project managers know that:
A. every project requires the use of all processes in the PMBOK® Guide.
B. there is no single way to manage a project.
C. project management techniques are risk free.
D. there is only one way to manage projects successfully.
QUESTION 188
What is an objective of the Develop Project Team process?
QUESTION 189
Which technique is used in Perform Quantitative Risk Analysis?
A. Sensitivity analysis
B. Probability and impact matrix
C. Risk data quality assessment
D. Risk categorization
QUESTION 190
Which of the following is TRUE about most project life cycles?
QUESTION 191
An input required in Define Scope is an organizational:
A. structure.
B. process asset.
C. matrix.
VCEConvert.com
D. breakdown structure.
QUESTION 192
When is a Salience Model used?
QUESTION 193
Which of the following is contained within the communications management plan?
A. An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors
QUESTION 194
Which schedule network analysis technique modifies the project schedule to account for limited resources?
QUESTION 195
Which of the following is an output of the Monitor and Control Project Work process?
A. Change requests
B. Performance reports
C. Organizational process assets
D. Project management plan
QUESTION 196
Which of the following statements correctly characterizes pull communication?
QUESTION 197
When would resource leveling be applied to a schedule model?
VCEConvert.com
QUESTION 198
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection,
distribution, storage, retrieval, and ultimate disposition of project information?
QUESTION 199
Which of the following tools or techniques is used for Estimate Activity Durations?
QUESTION 200
Information collected on the status of project activities being performed to accomplish the project work is known as what?
QUESTION 201
What is the number of stakeholders, if the project has 28 potential communication channels?
A. 7
B. 8
C. 14
D. 16
QUESTION 202
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
A. Mitigate
B. Transfer
C. Share
D. Avoid
QUESTION 203
Taking out insurance in relation to risk management is called what?
A. Transference
B. Avoidance
C. Exploring
D. Mitigation
QUESTION 204
What is the difference between the critical path and the critical chain?
VCEConvert.com
A. Scope changes
B. Resource limitations
C. Risk analysis
D. Quality audits
QUESTION 205
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
QUESTION 206
The Define Scope process is in which of the following Process Groups?
A. Initiating
B. Planning
C. Monitoring and Controlling
D. Executing
QUESTION 207
Organizations perceive risks as:
QUESTION 208
In an organization with a projectized organizational structure, who controls the project budget?
A. Functional manager
B. Project manager
C. Program manager
D. Project management office
QUESTION 209
Which enterprise environmental factors are considered during cost estimating?
QUESTION 210
Who selects the appropriate processes for a project?
A. Project stakeholders
B. Project sponsor and project stakeholder
VCEConvert.com
C. Project manager and project team
D. Project manager and project sponsor
QUESTION 211
Which is an example of Administer Procurements?
QUESTION 212
An input to the Create WBS process is a:
A. project charter.
B. stakeholder register.
C. project scope statement.
D. requirements traceability matrix.
QUESTION 213
An input of the Control Schedule process is the:
A. resource calendar.
B. activity list.
C. risk management plan.
D. organizational process assets.
QUESTION 214
Which action should a project manager take to ensure that the project management plan is effective and current?
QUESTION 215
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product
delivery. What is the MOST appropriate approach to managing this situation?
QUESTION 216
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
A. Scope audits
B. Scope reviews
C. Quality audits
D. Control chart
VCEConvert.com
QUESTION 217
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Project Management
QUESTION 218
Which process documents the business needs of a project and the new product, service, or other result that is intended to
satisfy those requirements?
QUESTION 219
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
A. Identify Risks
B. Perform Qualitative Risk Analysis
C. Plan Risk Management
D. Perform Quantitative Risk Analysis
QUESTION 220
What is one of the objectives of Project Risk Management?
QUESTION 221
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary
plans?
A. Collect Requirements
B. Direct and Manage Project Execution
C. Monitor and Control Project Work
D. Develop Project Management Plan
QUESTION 222
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform
Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Closing
VCEConvert.com
QUESTION 223
Which tool is used to develop technical details within the project management plan?
A. Expert judgment
B. Project management methodology
C. Project management information system (PMIS)
D. Project selection methods
QUESTION 224
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the
future is planned at a higher level?
A. Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination
QUESTION 225
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
QUESTION 226
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built
into the model?
A. Bottom-up
B. Three-point
C. Parametric
D. Analogous
QUESTION 227
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time
advances?
QUESTION 228
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
VCEConvert.com
QUESTION 229
A procurement management plan is a subsidiary of which other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
QUESTION 230
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the
industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
A. Customer request
B. Market demand
C. Technological advance
D. Strategic opportunity
QUESTION 231
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance
criteria?
A. Decomposition
B. Benchmarking
C. Inspection
D. Checklist analysis
QUESTION 232
Cost baseline is an output of which of the following processes?
A. Control Costs
B. Determine Budget
C. Estimate Costs
D. Estimate Activity Resources
QUESTION 233
An output of the Create WBS process is:
A. Scope baseline.
B. Project scope statement.
C. Organizational process assets.
D. Requirements traceability matrix.
QUESTION 234
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A. Estimate Costs
B. Estimate Activity Resources
C. Control Costs
D. Determine Budget
VCEConvert.com
QUESTION 235
Plan Risk Management is the process of defining how to:
QUESTION 236
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14
weeks, how many weeks is the expected duration of the activity?
A. One
B. Five
C. Six
D. Seven
QUESTION 237
Which type of analysis is used to examine project results through time to determine if performance is improving or
deteriorating?
A. Control chart
B. Earned value
C. Variance
D. Trend
QUESTION 238
Which is one of the major outputs of Sequence Activities?
QUESTION 239
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
A. Budget plan
B. Resource plan
C. Scope plan
D. Strategic plan
QUESTION 240
When does Monitor and Control Risks occur?
A. At project initiation
B. During work performance analysis
C. Throughout the life of the project
D. At project milestones
VCEConvert.com
QUESTION 241
Conflict should be best addressed in which manner?
QUESTION 242
The project management processes presented in the PMBOK Guide® should:
QUESTION 243
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and
is not subject to change unless the scope of work changes?
QUESTION 244
Which schedule compression technique has phases or activities done in parallel that would normally have been done
sequentially?
A. Crashing
B. Fast tracking
C. Leads and lags adjustment
D. Parallel task development
QUESTION 245
What is the definition of Direct and Manage Project Execution?
QUESTION 246
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
A. Pareto
B. Ishikawa
C. Shewhart-Deming
D. Delphi
QUESTION 247
VCEConvert.com
A project management office manages a number of aspects including the:
A. Project scope, schedule, cost, and quality of the products of the work packages.
B. Central coordination of communication management across projects.
C. Assignment of project resources to best meet project objectives.
D. Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.
QUESTION 248
Which of the following techniques is used during Control Scope?
A. Cost-benefit analysis
B. Variance analysis
C. Reserve analysis
D. Stakeholder analysis
QUESTION 249
Which type of chart is a graphic representation of a process showing the relationships among process steps?
A. Control
B. Bar
C. Flow
D. Pareto
QUESTION 250
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV =
$40,000
A. 1
B. 0.4
C. 0.5
D. 0.8
QUESTION 251
What provides information regarding the ways people, teams, and organizational units behave?
A. Organizational chart
B. Organizational theory
C. Organizational structure
D. Organizational behavior
QUESTION 252
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives
and create the required deliverables?
QUESTION 253
Which of the following is an output of the Distribute Information process?
VCEConvert.com
A. Project calendar
B. Communications management plan
C. Organizational process assets updates
D. Project document updates
QUESTION 254
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
A. Team meetings
B. Subcontracting teams
C. Virtual teams
D. Teamwork
QUESTION 255
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what
type of contract?
A. Cost-reimbursable
B. Time and material
C. Fixed price or lump-sum
D. Cost-plus-fixed-fee
QUESTION 256
What risk technique is used to quantify the probability and impact of risks on project objectives?
A. Expert judgment
B. Risk registry
C. Risk response planning
D. Interviewing
QUESTION 257
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A. WBS directory
B. Activity list
C. WBS
D. Project schedule
QUESTION 258
Which of the following processes audits the quality requirements and the results from quality control measures to ensure
appropriate quality standards and operational definitions are used?
QUESTION 259
How is the schedule variance calculated using the earned value technique?
VCEConvert.com
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
QUESTION 260
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
A. Control chart
B. Flowchart
C. Run chart
D. Pareto chart
QUESTION 261
Which of the following tools and techniques is used in the Verify Scope process?
A. Inspection
B. Variance analysis
C. Expert judgment
D. Decomposition
QUESTION 262
Which activity involves ensuring that the composition of a projects configuration items is correct?
A. Configuration Identification
B. Configuration Status Accounting
C. Configuration Verification and Audit
D. Configuration Quality Assurance
QUESTION 263
Change requests, project management plan updates, project document updates, and organizational process assets updates
are all outputs of which project management process?
QUESTION 264
Which process involves identifying and documenting the logical relationships between project activities?
A. Develop Schedule
B. Sequence Activities
C. Create WBS
D. Applying leads and lags
QUESTION 265
Which of the following is an example of the simplest fixed-price contract?
A. Purchase requisition
B. Purchase order
VCEConvert.com
C. Verbal agreement
D. Request for quote
QUESTION 266
A method to manage stakeholder expectations in the scope statement is to clearly:
QUESTION 267
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
A. Project
B. Functional
C. Program
D. Portfolio
QUESTION 268
One of the tools and techniques of the Manage Project Team process is:
A. organization charts.
B. ground rules.
C. organizational theory,
D. conflict management.
QUESTION 269
The process of monitoring the status of the project to update project progress and manage changes to the schedule
baseline is:
A. Control Schedule.
B. Quality Control.
C. Perform Integrated Change Control.
D. Develop Schedule.
QUESTION 270
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
A. updates.
B. defect repairs.
C. preventive actions.
D. corrective actions.
QUESTION 271
Which provides the basic framework for managing a project?
VCEConvert.com
QUESTION 272
A tool and technique used during the Perform Qualitative Risk Analysis process is:
QUESTION 273
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
QUESTION 274
The milestone list is an input to which process from the Planning Process Group?
A. Define Activities
B. Estimate Activity Durations
C. Estimate Activity Resources
D. Sequence Activities
QUESTION 275
Quality metrics are an output of which process?
QUESTION 276
An input to the Perform Quantitative Risk Analysis process is the:
QUESTION 277
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally
be:
VCEConvert.com
QUESTION 278
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the
project work. What is the earned value of the work completed to date?
A. US$5000
B. US$9500
C. US$10,000
D. US$12,500
QUESTION 279
Which piece of information is part of the WBS Dictionary?
A. Responsible organization
B. Change requests
C. Validated deliverables
D. Organizational process assets
QUESTION 280
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the
areas of:
QUESTION 281
Which of the following is a tool or technique of the Define Activities process?
QUESTION 282
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or
service?
A. Portfolio
B. Process
C. Project
D. Program
QUESTION 283
Which of the following is an information gathering technique in Identify Risks?
A. Influence diagrams
B. Brainstorming
C. Assumption analysis
D. SWOT analysis
VCEConvert.com
QUESTION 284
Documented identification of a flaw in a project component together with a recommendation is termed a:
A. corrective action.
B. preventive action.
C. non-conformance report,
D. defect repair.
QUESTION 285
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is
to be included within a related contract?
QUESTION 286
Tools and techniques used for Plan Communications include the communication:
QUESTION 287
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
A. Compromising
B. Collaborating
C. Smoothing
D. Problem Solving
QUESTION 288
A tool or technique in Perform Quality Control that a project manager would use is:
A. quality audits.
B. process analysis.
C. benchmarking.
D. inspection.
QUESTION 289
Change request status updates are an output of which process?
QUESTION 290
The risk management team of a software project has decided that due to the lack of adequate talent in the company,
VCEConvert.com
development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example
of which risk response?
A. Transfer
B. Share
C. Avoid
D. Accept
QUESTION 291
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost
baseline is:
A. Determine Budget.
B. Baseline Budget.
C. Control Costs.
D. Estimate Costs.
QUESTION 292
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan.
This describes:
A. scope creep.
B. a change request.
C. work performance information.
D. deliverables.
QUESTION 293
The definition of operations is a/an:
A. organizational function performing the temporary execution of activities that produce the same product or provide
repetitive service.
B. temporary endeavor undertaken to create a unique product, service, or result.
C. organization that provides oversight for an administrative area.
D. organizational function performing the ongoing execution of activities that produce the same product or provide repetitive
service.
QUESTION 294
Which type of estimating is used to improve the accuracy of an activity's duration?
A. Analogous
B. Parametric
C. Three-point
D. What-if scenario analysis
QUESTION 295
Which of the following are outputs of Develop Project Team?
VCEConvert.com
QUESTION 296
Which tool or technique is used in Manage Stakeholder Expectations?
QUESTION 297
Which of the following project documents is an input to the Control Scope process?
QUESTION 298
In which Project Management Process Group is the project charter developed?
QUESTION 299
Which can be used to determine whether a process is stable or has predictable performance?
A. Matrix diagram
B. Histogram
C. Control chart
D. Flowchart
QUESTION 300
When sequencing activities, what does the common acronym FF stand for?
A. Fixed Fee
B. Free Float
C. Fixed Finish
D. Finish-to-Finish
QUESTION 301
Which is the correct formula for calculating expected activity cost for three-point estimating?
QUESTION 302
The project manager needs to review the templates in use. The templates are part of the:
VCEConvert.com
A. Enterprise environmental factors.
B. Historical information,
C. Organizational process assets.
D. Corporate knowledge base.
QUESTION 303
Which of the following Project Communication Management processes uses performance reports as an input?
QUESTION 304
Which of the following is an input to Control Scope?
A. Project schedule
B. Organizational process assets updates
C. Project document updates
D. Work performance information
QUESTION 305
The key benefit of the Monitoring and Controlling Process Group is the ability to:
A. establish and manage project communication channels, both external and internal to the project team.
B. influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.
C. monitor the ongoing project team against the team performance assessments and the project performance baseline.
D. observe and measure project performance regularly and consistently to identify variances from the project management
plan.
QUESTION 306
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
A. Project sponsor
B. Project manager
C. Person responsible for project scheduling
D. Person who is most familiar with the task
QUESTION 307
Which of the following is the primary output of the Identify Risks process?
QUESTION 308
Which of the following is an example of schedule compression?
A. Activity sequencing
VCEConvert.com
B. Resource leveling
C. Lead and lag adjusting
D. Crashing
QUESTION 309
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
QUESTION 310
During which process would stakeholders provide formal acceptance of the completed project scope?
QUESTION 311
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
A. 1.33
B. 2
C. 0.75
D. 0.5
QUESTION 312
What is the primary benefit of meeting quality requirements?
A. Quality metrics
B. Less rework
C. Quality control measurements
D. Benchmarking
QUESTION 313
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
QUESTION 314
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
A. -8000
B. -2000
C. 2000
VCEConvert.com
D. 8000
QUESTION 315
Which of the following statements is true regarding project and product lifecycles?
QUESTION 316
Which of the following is an output of Direct and Manage Project Execution?
QUESTION 317
Which of the following is an input to Develop Human Resource Plan?
QUESTION 318
Testing falls into which of the following categories of cost of quality?
QUESTION 319
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
QUESTION 320
Which characteristic do projects and operational work share in common?
A. Performed by systems
B. Constrained by limited resources
C. Repetitiveness
D. Uniqueness
VCEConvert.com
QUESTION 321
Which of the following is an output from Control Scope?
A. Change requests
B. Variance analysis
C. Accepted deliverables
D. Requirements documentation
QUESTION 322
Managing procurement relationships and monitoring contract performance are part of which process?
A. Conduct Procurements
B. Plan Procurements
C. Administer Procurements
D. Close Procurements
QUESTION 323
Which of the following Process Groups covers all Project Management Knowledge Areas?
A. Executing
B. Monitoring and Controlling
C. Planning
D. Initiating
QUESTION 324
What is the most accurate rough order of magnitude (ROM)?
QUESTION 325
Project contracts generally fall into which of the following three broad categories?
QUESTION 326
Which of the following events would result in a baseline update?
A. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
B. A customer has approved a change request broadening the project scope and increasing the budget.
C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
D. One of the key project team resources has left the team and no replacement is available.
QUESTION 327
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been
completed and resources availability is critical?
VCEConvert.com
A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management
QUESTION 328
"Tailoring" is defined as the:
A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
B. act of creating a project team with the specialized skills required to produce a required product or service.
C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.
QUESTION 329
Which is an input to the Verify Scope process?
A. Performance report
B. Work breakdown structure (WBS)
C. Requested changes
D. Project management plan
QUESTION 330
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope.
Which of the following can result from fast tracking?
QUESTION 331
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which
process?
A. Control Scope
B. Collect Requirements
C. Create WBS
D. Define Scope
QUESTION 332
Which of the following is a strategy to deal with positive risks or opportunities?
A. Mitigate
B. Transfer
C. Exploit
D. Avoid
QUESTION 333
Which statement is true about the project management body of knowledge?
VCEConvert.com
A. Recognized by every project manager
B. Constantly evolving
C. The sum of all knowledge related to project management
D. A sum of knowledge that should be applied on every project
QUESTION 334
The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
QUESTION 335
Which technique is utilized in the Control Schedule process?
A. Performance measure
B. Baseline schedule
C. Schedule network analysis
D. Variance analysis
QUESTION 336
What happens to a stakeholder's project influence over time?
A. Increases
B. Decreases
C. Stays the same
D. Has no bearing
QUESTION 337
Which process requires implementation of approved changes?
QUESTION 338
Which quality control technique illustrates the 80/20 principle?
A. Ishikawa diagram
B. Control chart
C. Run chart
D. Pareto chart
QUESTION 339
At the end of the project, what will be the value of SV?
A. Positive
B. Zero
VCEConvert.com
C. Negative
D. Greater than one
QUESTION 340
What is project management?
QUESTION 341
Resource calendars are included in the:
QUESTION 342
An input to the Collect Requirements process is the:
A. stakeholder register.
B. project management plan.
C. project scope statement.
D. requirements management plan.
QUESTION 343
Projects are separated into phases or subprojects; these phases include:
QUESTION 344
Which of the following is an input to the Develop Project Charter process?
QUESTION 345
Who is responsible for initiating a project?
A. Project sponsor
B. Project manager
C. Program manager
D. Project management office (PMO)
VCEConvert.com
QUESTION 346
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
A. Affinity
B. Scatter
C. Fishbone
D. Matrix
QUESTION 347
Activity cost estimates are quantitative assessments of the probable costs required to:
A. Create WBS.
B. complete project work.
C. calculate costs.
D. Develop Project Management Plan.
QUESTION 348
Who determines which dependencies are mandatory during the Sequence Activities process?
A. Project manager
B. External stakeholders
C. Internal stakeholders
D. Project team
QUESTION 349
Risk exists the moment that a project is:
A. planned.
B. conceived.
C. chartered.
D. executed.
QUESTION 350
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
QUESTION 351
In the basic communication model, which term refers to the method that is used to convey the message?
A. Decode
B. Encode
C. Medium
D. Noise
QUESTION 352
The staffing management plan is part of the:
VCEConvert.com
A. organizational process assets.
B. resource calendar.
C. human resource plan.
D. Develop Project Team process.
QUESTION 353
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months,
and the pessimistic duration is one year, how many months is the expected activity duration?
A. Two
B. Four
C. Five
D. Twelve
QUESTION 354
A project lifecycle is defined as:
QUESTION 355
Administer Procurements is part of which Process Group?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing
QUESTION 356
The process to ensure that appropriate quality standards and operational definitions are used is:
A. Plan Quality.
B. Perform Quality Assurance.
C. Perform Quality Control.
D. Total Quality Management.
QUESTION 357
Which Process Group contains the processes performed to complete the work defined in the project management plan to
satisfy the project specifications?
A. Initiating
B. Planning
C. Executing
D. Closing
QUESTION 358
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is
VCEConvert.com
written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start
relationship with a 15-day delay?
A. Slack
B. Float
C. Lag
D. Lead
QUESTION 359
The completion of the project scope is measured against the:
A. requirements documentation.
B. project scope statement.
C. project management plan.
D. work performance measurements.
QUESTION 360
Which input will be used when tasked with developing the human resource plan?
QUESTION 361
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
QUESTION 362
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
A. Scope baseline
B. Scope management plan
C. Change management plan
D. Cost baseline
QUESTION 363
Which process is responsible for monitoring the status of the project and product scope and managing changes to the
scope baseline?
A. Variance Analysis
B. Define Scope
C. Verify Scope
D. Control Scope
QUESTION 364
Plan-do-check-act is also known as:
VCEConvert.com
A. prevention over inspection.
B. statistical sampling.
C. management responsibility.
D. continuous improvement.
QUESTION 365
Which of the following is a tool or technique used in the Determine Budget process?
A. Variance analysis
B. Three-point estimating
C. Bottom-up estimating
D. Historical relationships
QUESTION 366
The risk shared between the buyer and seller is determined by the:
A. assumption log.
B. quality checklist.
C. risk register.
D. contract type.
QUESTION 367
The project management processes are usually presented as discrete processes with defined interfaces, while in practice
they:
A. operate separately.
B. move together in batches,
C. overlap and interact.
D. move in a sequence.
QUESTION 368
The process for performing variance analysis may vary, depending on:
QUESTION 369
A tool and technique used during the Define Scope process is:
A. facilitated workshops.
B. observations.
C. questionnaires and surveys.
D. group creativity techniques.
QUESTION 370
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting
relevant information regarding their interests in, involvement in, and impact on the project:
VCEConvert.com
A. manager.
B. success.
C. deadline.
D. scope.
QUESTION 371
The cost benefit analysis tool is used for creating:
A. Pareto charts.
B. quality metrics.
C. change requests,
D. Ishikawa diagrams.
QUESTION 372
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as
well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
QUESTION 373
Funding limit reconciliation is a tool and technique used in which process?
A. Control Costs
B. Determine Budget
C. Estimate Costs
D. Control Budget
QUESTION 374
Inputs to the Plan Risk Management process include the:
QUESTION 375
Which of the following is an output of Define Scope?
QUESTION 376
After Define Activities and Sequence Activities, the next process is:
VCEConvert.com
C. Develop Schedule.
D. Control Schedule.
QUESTION 377
Risk responses reflect an organization's perceived balance between:
QUESTION 378
The three processes of Project Cost Management are:
QUESTION 379
Which of the following is an output of the Conduct Procurements process?
QUESTION 380
The technique of subdividing project deliverables into smaller, more manageable components until the work and
deliverables are defined to the work package level is called:
A. a control chart.
B. baseline.
C. Create WBS.
D. decomposition.
QUESTION 381
Which baselines make up the performance measurement baseline?
QUESTION 382
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes
management of which of the following?
A. Project
B. Scope
C. Contract
VCEConvert.com
D. Program
QUESTION 383
One of the objectives of a quality audit is to:
QUESTION 384
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
A. Acquisition
B. Negotiation
C. Virtual team
D. Pre-assignment
QUESTION 385
Which of the following is a group decision-making technique?
A. Brainstorming
B. Focus groups
C. Affinity diagram
D. Plurality
QUESTION 386
Which statement correctly describes the value of a business case?
A. It provides the necessary information to determine if a project is worth the required investment.
B. It provides for alternative dispute resolution procedures in event of contract default.
C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
D. It is used to help a project manager understand the scope of commercial advantages.
QUESTION 387
Which of the following includes how requirements activities will be planned, tracked, and reported?
QUESTION 388
Which type of dependency is contractually required or inherent in the nature of the work?
A. External
B. Lead
C. Discretionary
D. Mandatory
VCEConvert.com
QUESTION 389
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee
based upon achieving certain performance objectives is called a:
QUESTION 390
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization
is called the:
QUESTION 391
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
A. Forming
B. Storming
C. Norming
D. Performing
QUESTION 392
A project manager has created an issue log to document issues communicated by project team members during weekly
team meetings. This is an input of:
QUESTION 393
Which of the following is a tool and technique used to monitor risk?
QUESTION 394
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that
may or may not happen?
A. Sensitivity analysis
B. Three-point estimate
C. Modeling and simulation
D. Expected monetary value analysis
VCEConvert.com
QUESTION 395
Which of the following is an output of Close Procurements?
A. Accepted deliverables
B. Organizational process assets updates
C. Managing stakeholder expectations
D. Performance reports
QUESTION 396
The probability and impact matrix is primarily used to:
QUESTION 397
A car company authorized a project to build more fuel-efficient cars in response to gasoline shortages. With which of the
following strategic considerations was this project mainly concerned?
A. Market demand
B. Legal requirements
C. Strategic Opportunity
D. Technological advance
QUESTION 398
A risk may be graded into different priorities by which process?
QUESTION 399
Activities on the critical path have which type of float?
QUESTION 400
An imposed date for completion of the project by the customer is an example of a project:
A. deliverable
B. assumption
C. constraint
D. exclusion
QUESTION 401
VCEConvert.com
An output of the Manage Project Team process is:
QUESTION 402
Budgets reserved for unplanned changes to project scope and cost are:
A. Contingency reserves.
B. Management reserves.
C. Authorized budgets.
D. Cost baselines.
QUESTION 403
Cost aggregation is typically performed by aggregating work packages in accordance with the:
QUESTION 404
Cost variance (CV) is equal to earned value:
QUESTION 405
Decomposition, rolling wave planning, and templates are all tools and techniques for which of the following?
A. Define Activities
B. Estimate Activity Durations
C. Develop Schedule
D. Sequence Activities
QUESTION 406
Design of experiments (DOE) should be used during which of the following processes?
QUESTION 407
In the Initiating Process Group, at what point does the project become officially authorized?
VCEConvert.com
B. When all the stakeholders agree on the scope of the project
C. When the project manager is appointed
D. When the necessary finance or funding is obtained
QUESTION 408
Inputs to the Define Activities process include:
QUESTION 409
On what is project baseline development established?
QUESTION 410
One of the fundamental tenets of modern quality management states that quality is:
QUESTION 411
Organizational process assets can be divided into which of the following two categories?
QUESTION 412
Overlooking negative stakeholders can result in a/an:
QUESTION 413
PMBOI Guide is a standard that describes:
A. product-oriented processes.
B. project management processes.
C. product-oriented and project management processes.
VCEConvert.com
D. program management and project management processes.
QUESTION 414
Project Management Process Groups are linked by:
QUESTION 415
Project management processes are:
QUESTION 416
Projects are authorized by which of the following individuals?
A. Project managers
B. Stakeholders
C. Functional managers
D. Sponsors
QUESTION 417
Schedule milestones and a predefined budget are examples of:
A. Project constraints.
B. Requirements documentation.
C. Organizational process assets.
D. Activity cost estimates.
QUESTION 418
Scope verification is PRIMARILY concerned with which of the following?
QUESTION 419
Soft logic is also known as what type of dependency?
A. External
B. Discretionary
C. Mandatory
D. Internal
VCEConvert.com
QUESTION 420
The Process Group in which the internal and external stakeholders interact and influence the overall outcome of the project
is the:
QUESTION 421
The Process Group that involves coordinating people and resources, as well as integrating and performing the activities of
the project in accordance with the project management plan is known as:
A. Initiating.
B. Planning.
C. Executing.
D. Monitoring and Controlling.
QUESTION 422
The project governance approach should be described in the:
QUESTION 423
The three types of estimates that PERT uses to define an approximate range for an activity's cost are:
QUESTION 424
The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down
format is called a:
QUESTION 425
Using the following data, what is the Schedule Performance Index (SPI)?
EV= $500 PV= $750 AC= $1000 BAC= $1200
A. 0.67
B. 1.5
C. 0.75
D. 0.5
VCEConvert.com
QUESTION 426
What are the five Project Management Process Groups?
QUESTION 427
What are the key components of the communication model?
QUESTION 428
What entity is assigned various responsibilities related to the centralized and coordinated management of those projects
under its domain?
QUESTION 429
What process determines which risks might affect the project?
QUESTION 430
When a control chart is used to monitor performance of a process, which of the following will be set by the project manager
and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the
specification limits?
QUESTION 431
Which characteristic is unique to project work and does not apply to operational work?
A. Performed by individuals
B. Limited by constraints
C. Temporary
D. Performed to achieve organizational objectives
VCEConvert.com
QUESTION 432
Which is a tool used in monitoring and controlling project work?
QUESTION 433
Which is an input to the Scope Verification Process?
A. Performance report
B. Work breakdown structure
C. Requested changes
D. Project scope statement
QUESTION 434
Which of following could be organizational process assets?
A. Historical information
B. Industry standards
C. Organization infrastructure
D. Marketplace conditions
QUESTION 435
Which of the following buffers protects the target finish date from slippage along the critical chain?
A. Critical buffer
B. Project buffer
C. Duration buffer
D. Feeding buffer
QUESTION 436
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of
risk?
A. Risk analysis
B. Risk tolerance
C. Risk management
D. Risk attitude
QUESTION 437
Which of the following is a means of reaching a group decision in which everyone agrees on a single course of action?
A. Dictatorship
B. Majority
C. Plurality
D. Unanimity
QUESTION 438
VCEConvert.com
Which of the following is a schematic display of the project's schedule activities and the logical relationships among them?
A. Gantt chart
B. Project schedule network diagram
C. Project milestone list
D. Activity list
QUESTION 439
Which of the following is an example of a risk symptom?
QUESTION 440
Which of the following is an example of a technique used in quantitative risk analysis?
A. Sensitivity analysis
B. Probability and impact matrix
C. Risk data quality assessment
D. Risk categorization
QUESTION 441
Which of the following is an example of contract administration?
QUESTION 442
Which of the following is an input into the Develop Project Team process?
QUESTION 443
Which of the following is an input to the Plan Risk Responses process?
QUESTION 444
Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?
VCEConvert.com
B. Sequence Activities
C. Define Activities
D. Activity Attributes
QUESTION 445
Which of the following methods is a project selection technique?
A. Flowcharting
B. Earned value
C. Cost-benefit analysis
D. Pareto analysis
QUESTION 446
Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project
work?
A. Activities
B. Milestone list
C. Work breakdown structure (WBS)
D. Work packages
QUESTION 447
Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and
schedule constraints?
QUESTION 448
Which standard examines an enterprise's project management process capabilities?
A. PMBOK Guide
B. The Standard for Program Management.
C. Organizational Project Management Maturity Model "OPM3"
D. The Standard for Portfolio Management
QUESTION 449
Which tool or technique is used to develop a project charter?
QUESTION 450
Which tool or technique measures performance of the project as it moves from project initiation through project closure?
A. Resource leveling
B. Parametric measuring
VCEConvert.com
C. Pareto chart
D. Earned value
QUESTION 451
Who is responsible for reviewing change requests and approving or rejecting the change requests?
QUESTION 452
Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing
this dual reporting relationship factor?
A. Functional manager
B. Project manager
C. Functional manager supported by the project manager
D. Project management office
QUESTION 453
Which tool or technique is used in the Develop Project Management Plan process?
A. Pareto diagram
B. Performance reporting
C. SWOT analysis
D. Expert judgment
QUESTION 454
Which action should the project manager take after the team finishes executing the scope?
A. Verify the deliverables to ensure that they are correct and meet the customer’s satisfaction
B. Accept all the deliverables and deliver them to the customer for final acceptance
C. Conduct a joint session with the customer, change the deliverables, and then request approval
D. Check that all change requests were implemented and release deliverables to the customer
QUESTION 455
Which tools and techniques will a project manager use to develop a project charter?
QUESTION 456
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of
a specific stakeholder group. Which plan should the project manager consult?
VCEConvert.com
D. Stakeholder engagement plan
QUESTION 457
Which statement describes the Monitor Communications process?
A. Evaluates the differences between the communications management plan and the reality of communications in a project
B. Ensures that the information needs of the project and the stakeholders are met
C. Ensures that project information is created, collected, and distributed in a timely and appropriate manner
D. Develops an appropriate and plan for communication of project activities
QUESTION 458
Which conflict resolution technique is based on bringing some degree of satisfaction to all parties?
A. Smooth/Accommodate
B. Collaborate/Problem Solve
C. Compromise/Reconcile
D. Withdraw/Avoid
QUESTION 459
The activity of tailoring is necessary because:
A. The members of the project team need to select the appropriate order of every tool, technique, input, and output listed in
the PMBOK Guide; this is required for all projects.
B. Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and
outputs from the PMBOK Guide.
C. The members of the project team need to understand the PMBOK Guide processes, which are applied to all projects.
D. Each project is unique, and the project team must plan how to apply all the tools, techniques, inputs, and outputs in the
PMBOK Guide.
QUESTION 460
Which are the competing constraints that a project manager should address when tailoring a project?
QUESTION 461
Given the following information:
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
A. 8 weeks
B. 9 weeks
C. 10 weeks
D. 11 weeks
VCEConvert.com
QUESTION 462
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring
some degree of satisfaction to all parties in order to temporarily or partially resolve the problem.
A. Withdraw/Avoid
B. Smooth/Accommodate
C. Compromise/Reconcile
D. Collaborate/Problem Solve
QUESTION 463
Which is the order of steps in the Procurement Management process?
A. Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting
with selected vendors, and controlling procurements.
B. Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors,
obtaining quotes or proposals, and controlling procurements.
C. Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating
with vendors, and contracting with selected vendors.
D. Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting
with selected vendors, and controlling procurements.
QUESTION 464
After defining activities in project schedule management, which processes should a project manager follow?
QUESTION 465
Which is an example of analogous estimating?
QUESTION 466
In a project using agile methodology, who may perform the quality control activities?
QUESTION 467
A project manager is considering whether or not to procure a new vendor. What can the project manager use to determine a
make-or-buy decision?
VCEConvert.com
A. Data analysis
B. Interpersonal skills
C. Bidder conferences
D. Bid documents
QUESTION 468
Which tools and techniques should a project manager use to monitor risks?
QUESTION 469
Which of the following is a category of organizational process assets?
A. Government standards
B. Organizational culture
C. Employee capabilities
D. Organizational knowledge bases
QUESTION 470
Which document can help a project manager to leverage historical project information?
QUESTION 471
Which are required to create the schedule management plan?
A. Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list
B. Resource management plan, organizational process assets, activity list, and business case
C. Enterprise environmental factors, organizational process assets, project charter, and project management plan
D. Activity list, project statement of work, project charter, and communications management plan
QUESTION 472
In Project Resource Management, which process uses recognition and rewards as a tool and technique?
A. Control Resources
B. Develop Team
C. Manage Team
D. Monitor Team
QUESTION 473
The project manager is distributing project communications, collecting and storing project information, and retrieving
documents when required. In which process is the project manager involved?
A. Monitor Communications
B. Plan Communications Management
VCEConvert.com
C. Manage Communications
D. Manage Stakeholder Engagement
QUESTION 474
A new project manager wishes to recommend creating a project management office to senior management. Which
statement would the project manager use to describe the importance of creating the project management office?
A. It will give the project manager independence to make decisions without other departmental input.
B. It integrates organizational data and information to ensure that strategic objectives are fulfilled.
C. The project management office can execute administrative tasks.
D. The project management office can coordinate projects.
QUESTION 475
In which project cost management process is work performance data an output?
QUESTION 476
Perform Quantitative Risk Analysis focuses on:
QUESTION 477
Why is tailoring required in a project?
QUESTION 478
What are the project management processes associated with project quality management?
QUESTION 479
Which of the following are inputs for the Plan Quality Management processes?
VCEConvert.com
QUESTION 480
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this
process:
A. Develop Schedule
B. Define Activities
C. Define Scope
D. Collect Requirements
QUESTION 481
Which set of activities should a project manager use as part of the Develop Team process?
QUESTION 482
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the
project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the
project deliverables.
A. Manage Quality
B. Plan Quality Management
C. Control Quality
D. Plan Scope Management
QUESTION 483
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions
are required. At this point the project manager is able to estimate costs and activities for each element.
A. Project activities
B. Work packages
C. Planning packages
D. Project deliverables
QUESTION 484
Which two processes should be used to influence costs in the early stages of a project?
QUESTION 485
Which statement is related to the project manager’s sphere of influence at the organizational level?
VCEConvert.com
A. A project manager interacts with other project managers to detect common interests and impacts their projects.
B. A project manager facilitates communication between the suppliers and contractors on the project.
C. A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.
D. A project manager may inform other professionals about the value of project management.
QUESTION 486
The project manager is working with some functional managers and stakeholders on the resource management plan. Which
elements may be included in this plan?
QUESTION 487
The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is
the result of this inspection?
A. Accepted deliverables
B. Planning packages
C. Verified deliverables
D. Work packages
QUESTION 488
Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?
QUESTION 489
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can
result in a win-win situation?
A. Collaborate/Problem Solve
B. Compromise/Reconcile
C. Smooth/Accommodate
D. Withdraw/Avoid
QUESTION 490
Which is the correct hierarchy in a project environment, from most to least inclusive?
QUESTION 491
Company A’s accountant sends notification about a change in the company’s tax classification. Why would a project have to
be initiated?
VCEConvert.com
A. To change business and technological strategies
B. To improve processes and services
C. To meet regulatory and legal requirements
D. To satisfy stakeholder requests
QUESTION 492
With regard to a project manager’s sphere of influence in a project, which of the following does the project manager
influence most directly?
A. Suppliers
B. Customers
C. Governing bodies
D. Project team
QUESTION 493
Which is a major component of an agreement?
QUESTION 494
The features and functions that characterize a result, product, or service can refer to:
A. project scope
B. product scope
C. service scope
D. product breakdown structure
QUESTION 495
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project
manager’s key responsibility during this phase?
QUESTION 496
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive
environment?
A. Defining, sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are
viewed as a single process.
B. The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
C. An iterative scheduling and on-demand, pull-based scheduling will be required.
D. To address the full delivery schedule, a range of techniques may be needed and then need to be adapted.
QUESTION 497
VCEConvert.com
In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with
changes?
A. Having control over the planning and delivery of the products without delegating decisions
B. Giving access to information to the team and frequent team checkpoints
C. Selecting different team members to take the project manager role during reviews with stakeholders
D. Asking the control change board to approve changes before notifying the team
QUESTION 498
What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of
the organization?
A. Expert judgment
B. Interpersonal skills
C. Team agreements
D. Communication skills
QUESTION 499
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
A. Hybrid methodologies
B. Risk register updates
C. Outsourced project resources
D. Reliance on lessons learned documents
QUESTION 500
What is the difference between iterative scheduling and on-demand scheduling practices?
A. Iterative scheduling is based on adaptive cycles; on-demand scheduling is based on the theory of constraints.
B. Iterative scheduling is based on the theory of constraints; on-demand scheduling is based on adaptive cycles.
C. Iterative scheduling is usually used in Kanban system.
D. There are no relevant differences between these scheduling practices.
QUESTION 501
Company A has just been notified about a new legal requirement for its business operations. What is the classification of
this item?
QUESTION 502
How can a project manager represent a contingency reserve in the schedule?
QUESTION 503
VCEConvert.com
What is the difference between verified and accepted deliverables?
A. Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally
approved by the customer or authorized stakeholder.
B. Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate
Scope process.
C. Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables
have been completed and checked for correctness.
D. Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from
the Control Quality process
QUESTION 504
Which factors should be considered for cross-cultural communication?
QUESTION 505
After an internal deliverable review session with the team, the project manager identifies some issues that need to be fixed
before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and time
for the required rework.
A. Appraisal costs
B. Management reserves
C. Cost of nonconformance
D. Cost of conformance
QUESTION 506
A stakeholder is reading project documents given by the project manager. The stakeholder is curious about the difference
between a verified deliverable and an accepted deliverable.
Which of the following definitions can the project manager use to explain the difference?
A. An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the
customer or sponsor.
B. An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified
deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.
C. An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor a
verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the
Control Quality process.
D. An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets
acceptance criteria and is signed off by the customer or sponsor.
QUESTION 507
A junior team member has been promoted to the position of project manager. The first task to execute is the Quality
Management Plan.
Which tools and techniques will help the project manager to complete this task?
VCEConvert.com
C. Inspection, brainstorming, and quality audits
D. Networking, brainstorming, and negotiation
QUESTION 508
The project manager has the following information about the estimated duration for an activity:
Most likely [tM] – 15 days
Pessimistic [tP] – 20 days
Optimistic [tO] – 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
A. 10 days
B. 15 days
C. 12.5 days
D. 5 days
QUESTION 509
Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?
QUESTION 510
A project is in the planning phase. The project manager is considering different elements that may influence or constrain the
project.
Which of the following internal enterprise environmental factors should the project manager consider?
A. Industry standards
B. Market conditions
C. Legal restrictions
D. Employee capability
QUESTION 511
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which
diagram should the project manager reference?
QUESTION 512
What are the two most common contract types used in a project?
A. Cost plus award fee (CPAF) contract and fixed price contract
B. Fixed price contract and cost-reimbursable contract
C. Cost-reimbursable contract and time and material (T&M) contract
D. Time and material (T&M) contract and cost plus award fee (CPAF) contract
VCEConvert.com
QUESTION 513
Which statement about identification and engagement of stakeholders during a project is correct?
A. Project stakeholders should be identified and engaged in every phase of the project to influence the success of the
project directly.
B. Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but
refrain from making inputs during the project.
C. Project stakeholders should be identified when the project charter is being completed and engaged during requirements
gathering.
D. Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope
process
QUESTION 514
In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team
member wants to know how project cost will be determined at this early stage.
QUESTION 515
To which knowledge area does the Collect Requirements process belong?
A. Quality Management
B. Scope Management
C. Cost Management
D. Integration Management
QUESTION 516
The project manager released a report. A few stakeholders express the view that the report should not have been directed
to them.
Which of the 5Cs of written communications does the project manager need to address?
QUESTION 517
Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project
team?
QUESTION 518
Which of the following documents should the project manager update as a result of implementing the Plan Risk Responses
VCEConvert.com
process?
A. Risk Report
B. Issue Log
C. Assumption Log
D. Risk Management Plan
QUESTION 519
Which format can a network diagram take?
A. Flow chart
B. Control chart
C. Affinity diagram
D. Cause-and-effect diagram
QUESTION 520
According to PMBOK, the definition of Plan Risk Management is:
A. Develop strategies and agreeing on actions to address overall and individual risk and exposure
B. Define how to conduct risk management activities for a project
C. Implement agreed-upon risk response plans
D. Analyze the impact of identified individual risk and other sources of uncertainty on overall project objectives
QUESTION 521
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches
for applying Project Integration Management in this environment.
How can the project manager ensure that this will work for the project?
QUESTION 522
Which of the following tasks focuses on decomposing work packages?
QUESTION 523
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the
project manager to:
VCEConvert.com
QUESTION 524
Which is a difference between leadership and management?
A. Management influences and focuses on relationships with people; leadership focuses on systems and structure.
B. Leadership and management are the same thing and can be used interchangeably.
C. Management focuses on systems and structure; leadership focuses on relationships with people.
D. Management focuses on motivation and long-range vision; leadership focuses on near-term goals and problem solving.
QUESTION 525
At what stages of a project should the Identify Stakeholders process be performed?
QUESTION 526
How can a project manager evaluate project team development?
QUESTION 527
A company must implement sales software because it is opening a new branch in a foreign market. Although this software is
used in every domestic branch, multiple changes are expected during the implementation because it is a foreign location.
Which type of life cycle would the project manager use in this case?
QUESTION 528
A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project
manager check in order to make a qualitative risk analysis?
QUESTION 529
Which are examples of processes that may be used once or at predefined points in the project life cycle?
VCEConvert.com
QUESTION 530
What is one of the main purposes of the project charter?
QUESTION 531
Which of the following set of items belongs to the communications management plan?
QUESTION 532
A project manager is working on project cost management. The following information is current:
Planned value = 30
Actual cost = 35
Earned value = 28
QUESTION 533
Which knowledge area includes the processes to identify, define, and unify the various project management processes?
QUESTION 534
A project team member is estimating the cost of an activity and is checking documentation from previous similar projects.
Which estimation method is the project manager using to complete this task?
A. Bottom-up estimating
B. Three-point estimating
C. Analogous estimating
D. Parametric estimating
QUESTION 535
Under which circumstances should multiple projects be grouped in a program?
A. When they are needed to accomplish a set of goals and objectives for an organization
B. When they have the same project manager and the same organizational unit
VCEConvert.com
C. When they have the same scope, budget, and schedule
D. When they are from the same unit of the organization
QUESTION 536
Which is a list of organizational systems that may have an impact on a project?
QUESTION 537
What are the inputs of the Estimate Costs process?
A. Project management plan, work performance data, enterprise environmental factors, and organizational process assets
B. Project management plan, project documents, enterprise environmental factors, and organizational process assets
C. Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
D. Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets
QUESTION 538
For which kind of quantitative risk analysis chart can a tornado diagram represent values?
A. Sensitivity analysis
B. Monte Carlo analysis
C. Expected monetary value analysis
D. Decision tree analysis
QUESTION 539
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques
can the project manager use to capture stakeholder interest?
QUESTION 540
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
QUESTION 541
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing.
The feedback was used to refine the requirements.
VCEConvert.com
B. Feedback analysis
C. Progressive elaboration
D. Requirements documentation
QUESTION 542
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager
using?
QUESTION 543
Responsible, accountable, consult and inform (RACI) is an example of which of the following?
A. Text-oriented format
B. Resource management plan
C. Organization chart
D. Responsibility assignment matrix (RAM)
QUESTION 544
An organizational structure that standardizes the project-related governance and facilitates the sharing of resources,
methodologies, tools, and techniques is referred to as:
QUESTION 545
Which of the following sets are inputs to the Collect Requirements process?
QUESTION 546
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A. List of identified risks, potential risk owners, list of potential risk response
B. List of identified risks, list of causes, list of risk categories
C. Short risk titles, list of potential risk owners, list of impacts on objectives
D. List of activities affected, list of potential risk responses, list of causes
QUESTION 547
A construction project is underway, and during the progress review the painter complained that the task could not be started
because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting
work?
VCEConvert.com
A. Finish-to-Finish (FF)
B. Start-to-Finish (SF)
C. Finish-to-Start (FS)
D. Start-to-Start (SS)
QUESTION 548
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and
differences in one single place. What technique was followed?
QUESTION 549
The primary purpose of the stakeholder register is to:
QUESTION 550
Why is tailoring in a project necessary?
QUESTION 551
The project team is brainstorming on approaches to deliver the upcoming product launch for which the project has been
chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
A. Co-location
B. Life-cycle
C. Diversity
D. Management
QUESTION 552
Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
QUESTION 553
What can the project manager find among the factors that could lead a project to be tailored?
A. Company culture
VCEConvert.com
B. Return on investment
C. Earned Value
D. Schedule Performance Index
QUESTION 554
What is the order of the stages of project team development?
QUESTION 555
Project managers play a key role in performing integration on a project. What are the three different levels of integration?
QUESTION 556
What communication methods would a project manager use for overall effective project communication?
QUESTION 557
The document that guides project execution, monitoring and control, and closure is called:
QUESTION 558
Recognition and rewards are tools and techniques of which process?
A. Develop Team
B. Manage Team
C. Control Resources
D. Plan Resource Management
QUESTION 559
A project report completed an earned value (EV) of US $45 for work with an actual cost (AC) of US $40. What is the cost
performance index (CPI)?
A. 0.88
B. 1.12
C. 0.58
VCEConvert.com
D. 1.58
QUESTION 560
A project manager is writing a document that obligates the seller to provide the specified products, services, or results, and
obligates the buyer to compensate the seller. This document represents a legal relationship that is subject to remedy in the
courts.
A. General terms
B. Contract agreement
C. Change request
D. Statement of work
QUESTION 561
What is the difference between quality metrics and quality measurements?
A. Quality metrics are product attributes and the measurement is the result of the Monitor and Control Project process
B. Quality metrics are the result of the Monitor and Control Project process and the measurements are product attributes
C. Quality metrics and measurements are the same concept
D. Quality metrics is the general objective and the measurements are the specific objectives
QUESTION 562
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of
project, program, and portfolio management?
A. Leadership management
B. Technical project management
C. Strategic management
D. Business management
QUESTION 563
Which of the following is an example of the objective of a quality audit?
QUESTION 564
A firm contracted an event management company to conduct the annual sales day event. The agreement that the event
management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract is this?
QUESTION 565
Which tool is critical for the team to adapt to a high variability benefit project?
A. Colocation
VCEConvert.com
B. Collaboration
C. Flexibility
D. Specialization
QUESTION 566
What organizational asset can influence the Plan Risk Management process?
A. Corporate policies and procedures for social media, ethics, and security
B. Organizational risk policy
C. Stakeholder register templates and instructions
D. Organizational communication requirements
QUESTION 567
What is the role of project management in terms of organizational strategy?
QUESTION 568
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager
apply?
A. Diversity background
B. Stakeholder’s relationships
C. Technical expertise
D. Knowledge management
QUESTION 569
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
A. Predictive
B. Adaptive
C. A mix
D. Agile
QUESTION 570
A functional manager is delegating a key project to a project team without a project manager. Which communication method
will be most effective?
A. Interactive
B. Push
C. Verbal
D. Oral
QUESTION 571
What is the first step in the Stakeholder Management process?
VCEConvert.com
C. Manage Stakeholder Responsibility
D. Monitor Stakeholder Activity
QUESTION 572
Which of the following is an example of an internal factor that influences the outcome of the project?
A. Legal restrictions
B. Financial considerations
C. Commercial database
D. Geographic distribution of facilities
QUESTION 573
A project manager is monitoring and recording results of executing the quality management activities to assess performance
and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager
using?
QUESTION 574
What is the purpose of tailoring in project management?
QUESTION 575
During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct
documentation, begins the task necessary to repair the defect. What process was applied?
A. Change request
B. Risk response
C. Risk management plan
D. Lessons learned
QUESTION 576
A new project has been set. Four main stakeholders besides the project manager and four other team members have been
identified.
A. 8
B. 18
C. 36
D. 40
QUESTION 577
The Agile principle “welcome changing requirements, even late in development” relates to which agile manifesto?
VCEConvert.com
A. Working software over comprehensive documentation
B. Individuals and interactions over processes and tools
C. Customer collaboration over contract negotiation
D. Responding to change over following a plan
QUESTION 578
Which conflict resolution technique produces the most lasting results?
A. Withdraw/avoid
B. Smooth/accommodate
C. Compromise/reconcile
D. Collaborate/problem solve
QUESTION 579
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is
estimated that at completion, the project will incur US$250,000.
If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
A. US$-30,000
B. US$120,000
C. US$370,000
D. US$400,000
QUESTION 580
Which of the following are processes associated with Project Cost Management?
QUESTION 581
Creating the project scope statement is part of which process?
A. Manage Scope
B. Collect Requirements
C. Define Scope
D. Validate Scope
QUESTION 582
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include
in the report. Which document best details the information the project manager needs to make this decision?
QUESTION 583
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify
VCEConvert.com
all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated.
QUESTION 584
A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this
project require?
QUESTION 585
Which of the following describes the similarities of the process groups and project life cycle?
QUESTION 586
Which of the following are outputs of the Define Scope process in Project Scope Management?
QUESTION 587
Which tasks should a project manager perform in order to manage the project schedule effectively?
A. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of
Activities, Develop Schedule
B. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule,
Control Schedule
C. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of
Activities, Develop Schedule
D. Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Estimate Cost of Activities,
Develop Schedule
QUESTION 588
A project manager is estimating project activities using an algorithm to calculate costs or durations. What is this technique
called?
A. Analogous estimating
B. Three-point estimating
C. Parametric estimating
VCEConvert.com
D. Bottom-up estimating
QUESTION 589
The project manager is working in the processes of Project Resource Management. Which process is the project manager
developing if they are using parametric estimation?
QUESTION 590
Which contract type is least desirable to a vendor?
QUESTION 591
A construction project team has just had an inevitable delay due to a natural calamity. What should the project manager do
next?
QUESTION 592
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
A. Operations management
B. Project management
C. Program management
D. Portfolio management
QUESTION 593
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which
source selection method is being used?
A. Least cost
B. Qualifications only
C. Sole source
D. Fixed budget
QUESTION 594
Stakeholder identification and engagement should begin during what phrase of the project?
VCEConvert.com
D. After the communications management plan is completed
QUESTION 595
Which process is engaged when a project team member makes a change to project budget with the project manager’s
approval?
QUESTION 596
Which of the following is an example of tacit knowledge?
A. Risk register
B. Project requirements
C. Expert judgment
D. Make-or-buy analysis
QUESTION 597
What type of risk is Variability risk?
A. Emerging risk
B. Non-event risk
C. Ambiguity risk
D. Integrated risk
QUESTION 598
Which of the following best correspond to the organizational process assets (OPAs) that affect the project?
QUESTION 599
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
QUESTION 600
Which component of the project charter defines what the project's success will look like?
A. Project objective
B. Project approval requirements
C. Project exit criteria
D. High-level requirements
VCEConvert.com
QUESTION 601
What tool or technique uses an algorithm or statistical relationship between historical data and other variables to calculate
an activity's needed resource quantities?
A. Expert judgment
B. Bottom-up estimating
C. Parametric estimating
D. Analogous estimating
QUESTION 602
What is the aim of portfolio management?
QUESTION 603
In which Project Cost Management process is work performance data included?
QUESTION 604
What should a project manager reference to understand where responsibility, accountability, and authority reside within a
company?
A. Project charter
B. Scope of work
C. Project management system
D. Organizational system
QUESTION 605
What is the main benefit of the lessons learned register?
QUESTION 606
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of
enterprise environmental factors should the project manager refer?
A. Resource availability
B. Infrastructure
C. Academic research
D. Corporate knowledge base
VCEConvert.com
QUESTION 607
What is an example of an emerging trend in procurement management?
A. Online technologies enable projects to postpone ordering long lead items until the items are needed.
B. Online technologies allow a project's progress to be viewed by all stakeholders to build better relations.
C. Online procurement tools provide buyers with multiple sources to advertise to sellers.
D. Online procurement tools provide sellers with designated sources for procurement documents and the resources to
complete them.
QUESTION 608
What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?
QUESTION 609
What major skill sets comprise the PMI Talent Triangle?
A. Technical project management, technology management, and strategic and business management
B. Technical project management, leadership, and strategic and business management
C. Leadership, operational management, and technical project management
D. Organizational management, operational management, and technology management
QUESTION 610
What three strategies are used to respond to threats?
QUESTION 611
What characteristic of servant leadership supports resource management in an agile environment?
A. Lecturing
B. Controlling
C. Measuring
D. Coaching
QUESTION 612
What tool or technique will establish expected behaviors for project team members?
A. Ground rules
B. Decision making
C. Power/influence grid
D. Stakeholder engagement assessment matrix
QUESTION 613
VCEConvert.com
What organizational process asset (OPA) might impact a project's outcome?
QUESTION 614
A project team of telecommuters located in three different time zones regularly misses project deadlines. Daily meetings
often start and end with the same person talking and the rest of the team listening. The project manager determines that
communication among team members must be addressed.
A. Interpersonal communication
B. Feedback/response communication
C. Push communication
D. Pull communication
QUESTION 615
What organizational process asset (OPA) can impact a project?
A. Marketplace conditions
B. Preapproved supplier lists
C. Physical environmental elements
D. Legal restrictions
QUESTION 616
Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should
be implemented to generate a make-or-buy decision?
A. Conduct Procurements
B. Plan Procurement Management
C. Plan Risk Responses
D. Plan Risk Management
QUESTION 617
What is a tailoring consideration for Project Scope Management?
QUESTION 618
In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process?
A. Assumption log
B. Milestone list
C. Business case
D. Risk register
VCEConvert.com
QUESTION 619
What risk response strategy involves removing high-risk scope elements from a project?
A. Transfer
B. Avoid
C. Exploit
D. Accept
QUESTION 620
What is the Project Schedule Management practice used to deliver incremental value to the customer?
A. Resource optimization
B. Iterative scheduling with a backlog
C. On-demand scheduling
D. Critical path method
QUESTION 621
Select three elements that apply to agile/adaptive environments? (Choose three.)
QUESTION 622
After winning a large government contract, a company needs to hire a portfolio manager. What vital qualification should
candidates possess?
QUESTION 623
What process is used to identify quality requirements and/or standards for a project and its deliverables?
A. Manage Quality
B. Plan Quality Management
C. Control Quality
D. Perform Qualitative Risk Analysis
QUESTION 624
What describes the relationship between projects, programs, and portfolios?
VCEConvert.com
QUESTION 625
What term describes an intentional activity to modify a nonconforming product or product component?
A. Preventive action
B. Corrective action
C. Defect repair
D. Updates
QUESTION 626
A project reports an earned value (EV) of US$45 for work completed with an actual cost (AC) of US$40. What is the cost
performance index (CPI)?
A. 0.88
B. 1.12
C. 0.58
D. 1.58
QUESTION 627
What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?
QUESTION 628
What is the most important skill that project managers should possess to lead stakeholders throughout a project?
A. Communication
B. Problem-solving
C. Negotiating
D. Trust-building
QUESTION 629
What is the key benefit of the Monitor Stakeholder Engagement process?
A. Ensures that the informational needs of the project and its stakeholders are met through implementation and the
development of artifacts
B. Ensures that the project includes all the work required – and only the work required – to complete the project
successfully
C. Increases the probability and/or impact of positive risks, and decreases the probability and/or impact of negative risks or
issues
D. Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves
QUESTION 630
During a project’s execution phase, the project manager reviews the communications management plan for communication
technology factors. What can affect the choice of communications?
A. Legal requirements
B. Politics and power structures
C. Internal information needs
D. Sensitivity and confidentiality of the information
VCEConvert.com
QUESTION 631
What estimating technique is used when there is limited information?
A. Analogous estimating
B. Parametric estimating
C. Bottom-up estimating
D. Three-point estimating
VCEConvert.com