Commissioning Procedures

Agitators

RIG/PLANT REFERENCE REFERENCE DESCRIPTION


PPL Hull 2026 7250851976 Mud Equipment
ADDITIONAL CODE SDRL CODE TOTAL PGS
4 This document contains proprietary and confidential National Oilwell Varco-Brandt
REMARKS
information which belongs to National Oilwell Varco, it is 2800 North Frazier
loaned for limited purposes only and remains the property
OUR WO 195373 of National Oilwell Varco. Reproduction, in whole or in Conroe, Texas 77303
MAIN TAG NUMBER DISCIPLINE part, or use of this design or distribution of this information
to others is not permitted without the express written Phone 936-756-4800
consent of National Oilwell. This document is to be
CLIENT PO NUMBER returned to National Oilwell Varco upon request and in Fax 936-788-7367
PO08/09349 any event upon completion of the use for which it was
loaned.
© Copyright National Oilwell Varco - 2005

CLIENT DOCUMENT NUMBER DOCUMENT NUMBER REV

BC-P2026-01-012 01

www.nov.com
REVISION HISTORY

01 14.01.2010 For Information GMJ GMJ JP


Rev Date (dd.mm.yyyy) Reason for issue Prepared Checked Approved

CHANGE DESCRIPTION

Revision Change description


01 For Information

www.nov.com
Commissioning Procedure – MA/MARG Agitators

The Brandt MA/MARG-XX Agitators should be installed according with Brandt


specifications.

- Check the Installation and complete the attached Installation checklist.

- Energize the motor to check the shaft rotation. The impeller should rotate
clockwise when viewed from above. To change the direction of impeller
rotation, simply switch any two lead wires at the starter controls or at the
motor.

- Run the Agitator for 15 minutes, and complete the attached Commissioning
checklist.

Notes:
- Agitator should operate with no vibration.

- During Normal Operation, there is no cause for alarm unless the temperature
exceeds 100F over ambient temperature for long-terms periods.

- Some contact between shaft and stabilizer is normal during operation, but
immediately correct any hard striking

NOTE: IF ANY OF THE CHECK POINTS FAIL (N), PLEASE REFER TO THE
MANUAL TO SOLVE THE PROBLEM OR CONTACT BRANDT.
INSTALLATION – COMMISSIONING CHECKLIST

MOTOR INFORMATION
VOLTAGE AMPS

OIL-FILL-BREATHER PLUG IS INSTALLED YES / NO


OIL-FILL-BREATHER PLUG IS CLEAR OF OBSTRUCTION YES / NO
GEARBOX OIL LEVEL IS OK? YES / NO
ROTATION STICKER APPLIED? YES / NO
SHAFT-STABILIZER ALIGNMENT (IF APPLICABLE) IS OK YES / NO

RUN AGITATOR FOR 15 MINUTES.

MEASURED AMPS: ______________________

RUNNING AMPS ARE LESS THAN MOTOR NAMEPLATE? YES / NO

AMBIENT TEMP: F GEARBOX TEMP: ______ F

THE GEARBOX TEMPERATURE IS OK YES / NO

AGITATOR IS FREE OF SIGNS OF LEAKS YES / NO

AGITATOR IS FREE OF VIBRATION YES / NO

NOTE: IF ANY OF THE CHECK POINTS FAIL (N), PLEASE REFER TO THE
MANUAL TO SOLVE THE PROBLEM OR CONTACT BRANDT.