Professional Documents
Culture Documents
Page 2 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
TABLE OF CONTENTS
SECTION PAGE
1.0 SCOPE............................................................................................................................4
Page 3 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
1.0 SCOPE
This specification defines the requirements and procedures for Field Pressure Testing
of aboveground and underground pressure piping systems, connected equipment and
integral components to assure mechanical strength and tightness. Any deviation from
this Specification requires written approval from Chevron Geothermal Indonesia Ltd.
(CGI) and Chevron Geothermal Salak Ltd. (CGS).
1.1 Exclusions
1.1.3 Plumbing systems, which are tested in accordance with the applicable
plumbing codes.
1.1.4 Lines and systems open to the atmosphere and will not (cannot) be
plugged or capped off later without alteration.
1.1.5 Instrument piping lead lines between the root valve at the process or
utility line and the connected instrument and control piping used to
connect air or hydraulically operated control apparatus, which will be
tested in accordance with SP-CGI-IN-017 General specification for
instrument piping field pressure test
The latest edition and applicable revisions of codes and standards will be used
as referenced in this specification. References beginning with "ST" or "SP" are
Company standard drawings and specifications respectively.
This procedure shall refer to the publications listed below. Each publication
shall be the latest revision and addendum. Except as modified by the
requirements specified herein or the details of the drawings. Work included in
this procedure shall according to the applicable provisions on these following
publications:
Page 4 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
3.0 TERMINOLOGY
In this specification, the following words and terms shall have the meanings
hereby assigned to them, unless noted otherwise.
3.1 COMPANY
Refer to Chevron Geothermal Indonesia Ltd. (CGI) and Chevron
Geothermal Salak Ltd. (CGS) as the ultimate user and owner, the
authorized representative of COMPANY or COMPANY third part
inspection.
3.2 CONTRACTOR
3.3 Vendor
Note:
Page 5 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
5.0 DEFINITIONS
5.1 Calculated Test Pressure - The test pressure determined in accordance with
Section 6.0.
5.2 Minimum Test Pressure - The lowest allowable test pressure gauge reading
(the calculated test pressure plus the additional pressure resulting from the
static head of the test fluid).
5.3 Maximum Test Pressure - The highest allowable test pressure gauge reading
(the pressure test rating of the "weakest" component in the test system).
6.0 GENERAL
6.1 This Specification complies with the requirements of ASME B31.3-1993, "Code
for Pressure Piping, Chemical Plant and Petroleum Refinery Piping"' and
ASME B31.1-1992, "Power Piping."
6.2 This specification for inspection and test complies with requirements of ASME
Section VIII, UG-99 to UG-101.
6.3 The minimum test pressure for each line will be specified on the Pipe Line List.
Page 6 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
6.4 Prior to initial operation, all installed piping will be pressure tested except where
otherwise qualified in this Specification.
6.5 The test will be hydrostatic using water except if the operating fluid or piping
material would be adversely affected by water, other suitable liquids will be
used. Testing of feritic piping, however, is limited to the temperature restrictions
in Paragraph 10.2.7.
6.5.1 If a flammable liquid is used, its flash point will not be less than 4gC
and consideration will be given to the test environment. Approval for
use by Company is required for each line.
6.6.1 Gas, steam, or vapor lines when the weight of the hydro test liquid
would overstress supporting structures or pipe wall.
6.6.2 Piping with linings subject to damage by the hydro test liquid.
6.7 The instrument air headers will be tested with dry air.
7.1 Care will be taken to ensure the use of clean water for these tests. A suitable
filter will be provided in the fill line to the systems if foreign matter such as
sand, rust or other particles are suspected or in evidence in the proposed test
water. Use of sea water or process water is prohibited.
7.2 Water used for hydrostatic testing of austenitic stainless steel piping, vessels
and equipment, including those with austenitic stainless steel claddings, linings
or internals (excluding valve trim) will conform to the requirements listed below.
7.2.1 Water containing more than twenty-five (25) ppm chlorides will not be
used.
7.2.2 Piping, vessels and equipment must be drained thoroughly after testing.
Where complete drainage is impossible, the system will be flushed free
of all test water using boiler condensate or demineralized water
containing less than ten (10) ppm chlorides, alcohol, petroleum distillate
or other suitable flushing solutions. Hot air drying is not acceptable in
lieu of flushing, but water may be blown out of pockets using air.
7.3 Piping that is to be chemically cleaned after installation will be tested and all
repairs made prior to cleaning.
Page 7 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
8.1 Hydrostatic Testing of Piping Designed for Internal Pressure (ASME B31.3,
Resource Production Facility)
1.5P
P T
S
ST
where:
8.2 Where the test pressure as defined above would produce a stress in excess of
the yield strength at test temperature, the test pressure will be reduced to the
pressure at which the stress will not exceed the yield strength at the test
temperature.
The maximum test pressure at which the stress produced will not
exceed the yield strength will be calculated by the following equation:
2St
P M
14.5D
8.3 Where:
8.3.1 If the test pressure of piping attached to a vessel is equal to or less than
the test pressure of the vessel and it is not possible to isolate the piping,
then the piping and vessel may be tested together at the test pressure
of the piping. If the test pressure of piping attached to a vessel is higher
than the vessel test pressure and it is not practical to isolate the vessel
from the piping test, the piping test pressure (with the approval of
theCompany) may be reduced to the vessel test pressure, provided the
vessel test pressure is not less than 77 percent of the piping test
pressure (See Paragraph 6.1.1 for formula definitions). If the test
pressure of the piping after applying the reduced factor is still higher
Page 8 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
8.4.1 The hydrostatic test pressure at any point in the system to be not less
than 1-1/2 times the design pressure.
8.4.2 Where the test pressure as defined above would produce a stress in
excess of 90% of the yield strength at test temperature, the test
pressure shall be reduced.
The maximum test pressure at which the stress produced will not
exceed 90% of the yield strength will be calculated by the following
equation:
.9X 2sT
P M
14.5d
where:
8.4.3 If the test pressure of piping attached to a vessel is equal to or less than
the test pressure of the vessel and it is not possible to isolate the piping,
then the piping and vessel may be tested together at the test pressure
of the piping. If the test pressure of piping attached to a vessel is higher
than the vessel test pressure and it is not practical to isolate the vessel
from the piping test, the piping test pressure (with the approval of
theCompany) may be reduced to the vessel test pressure. Company's
preference is that equipment and vessels not be included in pressure
testing of piping systems.
8.6.1 If the piping is tested pneumatically, the minimum test pressure will be
110 percent of the design pressure for piping designed to ASME B31.3.
8.6.2 If the piping is tested pneumatically, the minimum test pressure will be
120 percent and 150 percent maximum of the design pressure for
piping designed to ASME B31.1.
Page 9 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
8.9.1 The hydrostatic test pressure at any point in the system will be not less
than 1-1/2 times the design pressure.
9.1 For ASME B31.3 piping, utility systems can be commodity tested in accordance
with ASME B31.3 for category "D" service provided that the fluid is nontoxic,
nonflammable and not damaging to human tissues. The design pressure shall
not exceed 11.2 bar and the design temperature is from -29°C through 186°F.
The following systems meet the requirements of category "D" service and can
be commodity tested.
9.2 For ASME B31.1 piping, an initial service test and examination in accordance
with ASME B31.1 is acceptable when other types of tests are not practical or
when leak tightness is demonstrable. An initial service test is not permitted for
boiler external piping.
The commodity test or initial service test is performed with the service fluid.
The pressure shall be gradually increased until half of the operating pressure or
2.58 bar reached, then the joints are visually examined. The pressure is then
increased in steps until the operating pressure is reached and continuously
held for 10 minutes while the joints are examined for leakage.
Page 10 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
10.1.2 Vessels or equipment not capable of sustaining the hydro test load, and
those with internals or linings that would be damaged by the test fluid.
10.3 The pressure on any point in vessels or equipment included in the pressure
test will not be greater than the shop test pressure for that equipment as stated
on the vessel drawing, Seller's equipment drawing or specification sheets. In
the event the piping test pressure is greater than the vessel or equipment test
pressure, the piping will be disconnected, blinded and tested separately. If the
piping cannot be disconnected (welded connection) one of the following will be
implemented:
10.3.1 The appropriate commodity engineer will request written approval from
the Seller to test at the required piping test pressure.
10.3.2 Reduce piping test pressure as necessary after review and approval of
Company.
10.4 Certain types of exchangers are specifically designed for a low allowable
differential pressure between shell and tubes, as stated on the Seller drawings
and specification sheets. These will be checked, and if necessary test both
shell and tubes simultaneously as one system with the same pressure or
exclude both sides from the test.
10.5 Pressure vessels with two or more pressure chambers are specifically
designed for a low allowable differential pressure between pressure chambers
as stated on the manufacturers' drawings. These will be checked, and if
necessary test all adjacent pressure chambers simultaneously as one system
with the same pressure or exclude all pressure chambers from the test.
Page 11 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
11.0 INSTRUMENTS
11.1 All instruments will be protected from damage when hydrotesting process and
utility piping systems. Appendix "B" outlines the status of instruments during
testing to insure protection. Instrument piping lead lines between the root valve
at the process or utility line and the connected instrument and control piping
used to connect air or hydraulically operated control apparatus will be tested by
Company.
11.2 Instruments not listed in Appendix "B" will not be subjected to the pressure test
unless authorization is obtained from the Company Control Systems Engineer.
12.1.1 All joints, including field weld joints, are to be left uninsulated and
exposed for examination during the test, except that joints previously
tested in accordance with this Specification may be insulated or
covered. If a sensitive leak, mass-spectrometer or halide test
(Paragraph 6.6) is required, all field weld joints will also be left unprimed
and unpainted.
12.1.3 Piping designed for vapor or gas will be provided with additional
temporary supports, if necessary, to support the weight of the test liquid.
Page 12 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
12.1.6 The field test staff will review all vessels and internals in order to
determine best method to prevent air entrapment when filling and to
prevent vacuum when draining.
12.1.8 Lines containing check valves will have the source of pressure located
in the piping upstream of the check valve so that the pressure is applied
under the seat. If this is not possible, remove or jack up the check valve
closure mechanism or remove check valve completely and provide
necessary filler piece or blinds.
12.1.9 Systems that include expansion joints will be investigated to verify that
any required temporary restraints, anchors, guides, etc., are installed
prior to test.
12.1.13 Installed open valves in pressure test systems shall be observed for
packing gland leakage. If leaking, packing gland shall be tightened only
enough to stop leakage.
12.2.2 The minimum test pressure for a system test will be such that each line
in the system is subjected to a test pressure in accordance with
Paragraphs 6.1 or 6.2.
12.2.3 The maximum system test pressure will not exceed the pressure test
rating of any piping component (see Appendix "A") or the shop test
pressure of any vessels or equipment included in the test system.
(Maximum test pressures for flanges and valves conforming to ASME
B16.5 are given in Appendix "A").
Page 13 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
12.2.6 The normal location for the pressure test gauge is at grade near the
pressure test pump. Readings may be made at higher points providing
the gauge pressure reading plus the static head (.01 bar/meter)
between grade and the point of measurement does not exceed the
maximum test pressure. Pressure test gauges will be calibrated once a
month, using a dead weight tester. The gauge will be tagged with the
date last calibrated and this activity will be recorded.
12.2.7 Hydrostatic test pressure will not be applied until the metal surface and
internal test liquid are at approximately the same temperature. To
minimize the risk of brittle fracture, pressure tests through vessels and
equipment will not be conducted when the test liquid and/or metal
temperature is below 15.6°C. Pressure tests in ferritic and austenitic
stainless steel piping systems that do not include vessels or equipment
may be conducted below 15.6°C but will not be conducted when the
test liquid and/or metal temperature is below 4.4°C.
Page 14 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
Clear test area while bringing line up to and while holding at full
pneumatic test pressure. It may be desirable to conduct test during
the weekend when fewer personnel are present.
12.3.1 During pneumatic testing care will be exercised not to exceed the
specified test pressure by the lesser of ten (10) percent or 3.4 bar for
ASME B31.3 piping and as limited by 6.4.2 for ASME B31.1 piping.
12.3.2 When pneumatic testing at over 1.03 barg, a preliminary check at 1.03
barg will be made to locate major leaks. The pressure will be increased
in gradual steps of .345 barg or 10 percent of the test pressure,
whichever is greater.
12.3.3 A double block and bleed valve arrangement will be included in the
pressurizing line to the system being tested. A test pressure gauge to
be downstream of the double block. After each pressure step has been
reached, close the block valves and open the bleeder to atmosphere. If
after a five minute period the "Step Pressure" is held, proceed to the
next "Step Pressure"; if not, examine the entire system for leakage.
12.3.4 Prior to soaping the joints, the entire line will be "Walked" to determine if
there is any audible evidence of leakage. Any leaks found at the time
will be marked, and repaired after first depressuring the line.
12.3.5 When the system has been brought up to the test pressure shown on
the pipe line list, all joints and welds will be covered with a bubble
forming solution in order to detect any leakage. The solution will be a
commercial preparation made specifically for leak detection.
12.3.6 Bolting will not be tightened while systems being tested are pressured
above 2.07 barg.
12.4.1 Records will be made of each piping system test, utilizing the form titled,
"Field Test Record Piping Pressure Test." These forms, when
completed, will be retained in the Field Quality Control file by Company
as a permanent record. These records to include:
Page 15 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
12.4.2 Upon completion of the piping installation, the only retained records will
be a letter of certification by Company's authorized inspector that all
piping has been pressure tested as required by these procedures.
Upon completion of the project, these records will be sent to the
Company home office as specified in the Job Closeout Procedure.
12.5.1 In the event that repairs or additions are made to ASME B31.3 piping
following the pressure test, the affected piping will be retested at the
pressures originally specified for the test. Testing of minor repairs,
additions or tie-ins to existing lines may possibly be waived provided the
welding is nondestructively examined as follows; however, hydrotest is
still the best assurance of a system integrity:
12.5.2 Repairs or additions to ASME B31.1 following the pressure test shall be
pressure tested.
12.5.3 After completion of testing, all temporary blanks and blinds will be
removed, all operating blinds returned to proper position and all lines
and piping components (except those tested pneumatically) will be
completely drained. Valves, orifice plates, expansion joints and short
pieces of piping which have been removed will be reinstalled with
proper gaskets in place. All valves that were closed during hydrotest
Page 16 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
will be opened to insure draining the bonnet cavity. Lines being drained
after testing will have all vents open. Piping systems downstream of
check valves will be inspected to insure complete drainage.
12.5.5 Care will be exercised in controlling the rate of drainage from vessels
with respect to the inflow of air through the vent to insure that the vessel
is not subjected to vacuum. After vessels are completely drained,
vents, cyclones and other internal closures which were opened prior to
testing will be closed.
12.5.6 After lines have been drained, temporary supports will be removed and
insulation and painting completed. Spring hangers provided with stops
to carry the test load will have these stops removed in accordance with
the "Field instructions" provided on Form E-326, "Constant Support
Spring Hanger," and Form E-327, "Variable Support Spring Hangers,"
for each hanger.
12.5.7 Flanged joints at which test blinds have been removed will not be
retested. Special length bolting and flat non-asbestos gaskets will be
removed and replaced with line class bolts and gaskets.
12.5.8 Instruments which were removed or blocked out for test will be
reinstalled and blocks placed in the normal operating position.
13.1 Plain test blanks with 1/16 inch flat non-asbestos gaskets will be used for
blanking flat face, raised face, ring joint, male and female, and tongue and
groove type flanges. Full face blanks and gaskets at 125 lb. Cast Iron
connections will be used. However, where permanent operational blinds are
installed, they may be used for field pressure testing.
13.2 Plate material, extra length bolts and gaskets for testing will be furnished by the
field unless directed otherwise by contract requirements. See Appendix "C" for
maximum test pressures at various thicknesses.
Page 17 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
APPENDIX A
MAXIMUM HYDROSTATIC TEST PRESSURE (PSIG) FOR FLANGES AND VALVES
NOTES:
1. The above chart is based on ASME B16.5-1988, and provides the maximum allowable hydrotest pressures
of 1/2 inch through 24 inch flanges (shell test) and flanged and standard class weld end valves (shell test,
with valve open and seat test, with valve closed).
2. Flanged valves manufactured per API-600, API-602 and API-604 may be tested in accordance with the
above chart. 800 lbs. screwed or scoketweld valves manufactured per API-602 and API-606 may be tested
to 3000 lbs. (shell test) or 2200 lbs.
3. For valves not conforming to the above standards or ASME B16.5-1088, the manufacturer's recommended
test pressure limits for both shell and seat will be used.
4. Maximum test pressures for flanges and valves over 24 inches and piping components not covered by this
chart will be provided by the engineering contract as applicable.
5. The maximum test pressure for pneumatic testing will not exceed 75 percent of the stated values.
Page 18 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
APPENDIX B
STATUS OF INSTRUMENTS DURING PRESSURE TEST
Page 19 of 20
General Piping – Process and Utility Pressure Testing
CHEVRON GEOTHERMAL INDONESIA LTD
CGI-022-PIP-003 Rev. 0
APPENDIX C
SCHEDULE OF MAXIMUM ALLOWABLE HYDROSTATIC TEST PRESSURES (PSIG)
FOR THE LISTED TEST BLIND THICKNESS
NOTES:
1. The Tabulated Pressures above are based on the formula stated in ASME B31.3, Paragraph 304.5.3 using
a. Flat nonasbestos gaskets conforming to ANSI B16.2.1.
b. Structural grade carbon steel plate, ASTM A36 having a minimum specified yield strength of 36,000
psi
2. For plate which is identified as having a lower minimum yield strength, the allowable hydrostatic pressure
must be reduced in accordance with the following formula:
y
Pma = X
y
Where: Pma = Maximum
Y = Minimum Specified Yield Strength, ASTM A36
Yx = Minimum Specified Yield Strength for Material Selected
3. Pneumatic test pressures shall not exceed 50 percent of the values indicated.
Page 20 of 20