Cumulative
Balance Achvd till Previous Planned Achieved This Cummulative %
Sr. No Item Description Unit Total Scope Achieved Today Achieved as on Remarks
Scope Month This Month Month Achieved
date
A ELEVATED VIADUCT WORK
1 Piling Nos 88 28 60 4 60 68% P17-P21 utility trenching wip
3 Pier Nos 21 21
C ELEVATED RAMP
1 Excavation Rmt 309 277 32 32 10% Ramp area dewatering wip
E UG STATION WORK
1 Secant Pile Nos 615 425 146 100 44 190 31% SP-349, 344 concrete done
a Hard Pile Nos 308 233 56 65 19 75 24% Capping beam dressing for PCC
b Soft Pile Nos 307 192 90 35 25 2 115 37% Capping beam 15m. PCC done
G UG STATION (LS+SB)
1 Secant Pile Nos 852 425 368 100 59 427 50%
H CASTING ELEMENTS
Tunnel Ring segments Nos 2935 2919 1 50 15 5 16 1%