Professional Documents
Culture Documents
Name Surname,
2 .
02 E
Advisor:
Prof. Salah-Eddine Abstract: Manufacturers are always required to innovate and take special care
MESSEKHER on optimizing their company organization and make time critical decisions to keep
/2 F.
Co-advisors:
costs low thus increasing profit margin. Researchers are equivaly playing their part
Rabiaa BOUNEMEUR keeping their solutions effective and up to date. In this context the most common
Ichrak RADJAI production planning method in the industry is MRP, but it is not flawless. We
21 .
noticed that the MRP algorithm does have a major flaw that it does not take into
Academic year:
20 f M
2021-2022 account the production capacity we will be suggestion other methods that could
be used alongside MRP to fill in its gaps and establish the best production plan
.- so
Contents
.I d
1 Introduction 2
2 Material Requirement Planning MRP 2
G cee
1
1. Introduction what is the Prerequisite for setting up an MRP?
2 .
In other words, production planning makes it possible The MRP method appeared in the United States in the
02 . E
on the one hand to anticipate for its meeting demand, sixties, initially very simple, MRP-0 (1960) could be
forecasting supplies, and planning the use of resources called "production replenishment method" , has high-
Production. On the other hand, it can also be used lighted the type of product, the product with the inde-
as a way to optimize the production by seeking, for pendent need and the product with need depend [ , A
example, to minimize costs while respecting deadlines. system that from the request forms estimates the fin-
/2 F
There are different production planning systems: ished products and the current stock levels, calculates
Hierarchical planning (Hax et Meal, 1975), MRP (J. the component requirements (how much and when )
Orlicky,1975)[4], OPT (E. Goldratt,1969) Kanban (T. to meet the demand, the production capacities are not
Ohno, 1959) [2] taken into account, but in (1970) MRP0 to which we
21 .
In this article, production planning, we will focus Only added the calculation of the loads generated on the
20 f M
for MRP methods., The MRP method (Material Re-
quirement Planning) or component requirements plan-
ning is the best known of the existing techniques in
production management. The MRP method appeared
production by the result of the MRP. Planning always
proceeds at infinite capacity, and is called MRP-1, and
Evolution of MRP-1 which integrates the calculation
of production costs and a load capacity adjustment al-
in the United States in the sixties, initially very sim- gorithm. This allows the desired load to be adjusted
ple, MRP-0 (1960) could be called "production replen- to the available load for each production center, the
o
ishment method" , has highlighted the type of prod- process is called MRP-2 what is the Prerequisite for
uct, the product with the independent need and the setting up an MRP?
product with need depend , A system that from the
.- s
2
2.4. Industrial and Commercial Plan:
2.2. The logic of MRP: The PIC is drawn up jointly by the general manage-
ment, the management of the production and commer-
cial management based on the order book and business
the planning goal is described (a production plan for a forecasts. It defines sales volumes, inventory levels,
time scale defined by a planning horizon and a refresh equipment and resource requirements, plan production
period. capacities or long term from 2 to 12 months.
A production plan answers the following questions, the input data to establish the commercial industrial
among others: plan are:
• what to produce? • the resources
• when to produce? • Nomenclature
• haw much to produce? • the articles
• the ranges
2 .
The MRP method makes the answers to these ques-
02 E
tions coherent, and ensures their logical sequence by the articles: An article is a product of the company
measuring the consequences in the short term. or an element entering the composition of a product,
There are four steps involved in the MRP2 logic: which we want to manage. It is a general term cor-
/2 F.
responding to a finished product, a sub-assembly, a
1. The Industrial and Commercial Plan (PIC).
component or a raw material
2. The Production Master Plan (PDP) .
Nomenclature (BOM): a hierarchical list that repre-
3. The Calculation of Needs.
sents all the components of a product (sub-assembly,
4. Supply staking and management of production
21 .
intermediate product, part), called article-parent, the
resources.
20 f M relationship that we establish between a compound and
a component is called a nomenclature link, each link is
characterized by coefficient indicating the quantity of
component necessary for the production of a compound
.
.- so
2.3. The general diagram of the MRP2
g
ages production, from the long term to the very short Figure 3: Nomenclature.
term, using five planning levels:
G cee
cessing times
Pr
3
2.6. Needs planning: 3. Production capacity planning
2 .
gross requirements and material availability, starting
02 E
from the projected stock
/2 F.
2.7. Production schedule:
21 .
20 f M
The result of the net requirements calculation is a set
of production orders. Each order is characterized by a
quantity and a date. These 0F (forecasts) were devel-
oped without taking into account the actual capacity
of the production system. R le but to adjust the load
.- so
capacity
4
The manufacturing time of an item includes the manu- 3.2.1 Global factors approach
facturing times of all these Components. Resources are
This technique, also called CPOF (Capacity Planning
also grouped by work center the method used in this
Using Overall Factors), is the older. It relies on the fol-
one is much more precise and detailed. It is based on
lowing information to establish a provisional schedule
a production plan and resource profiles established for
of charges: – a production master plan – the total time
each product. These profiles take into account the exe-
needed to produce each part of a product – the propor-
cution times on each resource. A profile is presented in
tion of time used by each workstation in the workshop
the form of a 2-dimensional table: (resource, deadline)
the columns represent the production times from the • a production master plan
• the total time needed to produce each part of a
date of availability of the article, the lines the resources
needed for a product P The intersection of a straight product
• the proportion of time used by each workstation
line and a indicates the resource time required to man-
ufacture a unit of products if it must be available on in the workshop
date t. The App:
2 .
The first step is to calculate the number of workshop
02 E
hours required per month by multiplying the PDP
machining assembly packaging quantities by the average time to produce a product.
Then simply divide that time by the historical propor-
/2 F.
A 314 197 90 tion of time used by each work center to get its forecast
B 100 86 56 load.
The validation of the PDP then consists in checking
C 57 38 25
for each period and each workstation that the avail-
21 .
20 f M able capacities are sufficient.
This method is particularly well suited to workshops
Table 1: Example of resource profiles for 3 item
manufacturing products of a same family because in
families. this case it is easy to obtain the temporal proportions
of each work center in relation to the workshop.
.- so
required by the long-term PDP. profile presented in the section previous. The only dif-
ference is that at this level, we no longer process prod-
These results are compared to the capacities available
ucts by family and by type but by reference. Moreover,
.I d
ter plan
Pr
5
date of availability of the article, The main interest of this method is the consideration
the lines the resources needed for a product P of production times. The method is thus more precise,
The intersection of a straight line and a indicates the at the cost of more computation time.
resource time required to manufacture a unit of prod-
ucts if it must be available on date t.
t1 t2 t3
R1 a112 a111 a110 3.3. Planning of production capacity
R2 a112 a111 a110 needs:
2 .
02 E
orders on the resources of a workshop by simulating
their execution. On the snapshot as well for each pe-
t1 t2 t3 riod of the planning horizon, the load and capacity of
each resource.
/2 F.
R1 a212 a211 a210
Generally, the CRP is used in conjunction with the
R2 a112 a111 a220
MRP because it helps to verify that all scheduled
production orders can actually be processed by pro-
21 .
20 f M duction without causes an overflow. Thus, it is of-
Table 3: Caption of the Table.
ten the last test before validating a production plan.
belfig:quadtree
3 months.
.I d
resource1 c11 c12 c13 The CRP uses the production orders generated by the
resource2 c21 c22 c23 MRP and breaks them down according to the work
centers they must cross. For each of the sub-orders
obtained, it calculates the load generated on the work-
Table 5: estimated load of resource 1 and 2 over station and adds it to the load removed since the be-
3 months. ginning of the period. The same is true with the firm
and/or manual planned OFs in order to obtain load
information that is as precise as possible.
The distribution of a production order to the worksta-
tions is obtained from the range of the product to be
c11 = a110 b11 +a111 b12 +a112 b13 +a210 b21+a211 b22 +a212 b23
produced. This is why the existence of a range file has
c21 = a120 b11 +a121 b12 +a122 b13 +a220 b21+a221 b22 +a222 b23become Mandatory from MRP1 systems.
CRP Results: The CRP produces workload diagrams
c12 = a110 b12 + a111 b13 + a210 b22 + a211 b23 per workstation. These diagrams present for each pe-
c22 = a120 b12 + a121 b13 + a220 b22 + a221 b23 riod the capacity available in number of hours and the
load emitted by the Schedule. These diagrams identify
c13 = a110 b13 + a210 b23
overcharges when the load created exceeds the avail-
c23 = a120 b13 + a220 b23 able capacity and underutilization otherwise
6
“serial” smoothing (time lag of the operation) may can-
cel the surcharge. There are then two possibilities: the
shift to the right and the shift left. The shift to the
right can only be considered in an exceptional way, by
playing on safety stock
2 .
between the requested loads and the available resource namely the failure to take production capacities into
02 E
capacities. In case of overload, you had to go back account when drawing up planning. However, there are
to the production master plan and adapt it until the a number of methods for planning production capacity
problems disappeared. However, an overload is not needs at different times in the production management
/2 F.
always synonymous with redesigning the PDP, there system production.
are methods to make it disappear on temporary loads.
these methods cannot guarantee that there will be no
Typically, these methods are only found in MRP-II sys-
overruns of ability. There are therefore load smoothing
tems under the name of Load Capacity Tuning.
techniques that can be applied to results of the MRP to
21 .
20 f M try to eliminate the problems of overflows temporary.
This type of process only appeared with type MRP-2
• Serial smoothing deals with operations that use [1] Gérard Baglin, Olivier Bruel, Alain Garreau,
the overloaded resources. Michel Greif, and Christian van Delft. Manage-
. M in
Parallel smoothing: Parallel smoothing is the quickest [2] Pierre Béranger. Les Nouvelles Règles de la produc-
G cee
solution to implement when faced with an overflow. tion: vers l’excellence industrielle. Dunod, 1995.
Temporary capacity because it consists of increasing
the capacity of overloaded resources at the price of a [3] Irawan Irawan, Titin Nasiatin, Suhroji Adha, Oc-
higher cost of production. toberry Julyanto, Citra Puspita Rani, and Ra-
o
Smoothing by capacity adjustment: Smoothing by in- hardian Dimas PK. Analysis of production capac-
Pr
creasing capacity consists of directly increasing the ca- ity planning and control in pt. krakatau wajatama
pacity of overloaded resources by increasing their avail- with rought cut capacity planning (rccp). Journal
ability as much as possible. In this case, the production of Industrial Engineering & Management Research,
manager can either increase the working time by plac- 1(2):207–218, 2020.
ing it in the place of overtime or increase the pace with
the risk that this entails.
[4] Georges Javel and Joel Le Bert. L’Organisation
Smoothing by capacity transfer: Also called parallel
et la Gestion de Production, volume 138. Masson,
smoothing, it consists of calling on subcontractors to
1993.
reduce production costs or transfer the operation or
operations that overload a position to equivalent posi-
tions. [5] Nigel Slack, Stuart Chambers, and Robert John-
ston. Operations management. Pearson education,
2010.