PACKAGE 1 MATRIX OF COMMENTS AND RESPONSES FOR REQUEST FOR INSTRUCTION AND LETTER BATCH NO.

57
DATE : September 24th2022

PACKAGE 1 RFIs AND LETTERS

NO. RFI NO. IPMS NO. DATE SUBJECT COMMENTS RESPONSES ANNEX
1. Package 1 RFI's

243/RFI/PPWIKABRL- RFI of River Training Works


A B1-P001-PMD-3391-0243-0 September, 5th 2022
MUTIP/IX/2022 and Gate Work Omission

Technical Query:

Yes, this is to confirm The Gate and River


According to Weekly Coordination Meeting Week 63 held at 30th August 2022, OE said that River Training works ommited from Package 1
1 Training Works shall be omitted from P1 scope No.Annex
contract because it will work by BWS and Gate werks would be ommitted too because it will work by Package 2.
of works.
We want to clarify those information.

2.Package 2 Letters

184/EXT/PPWIKABRLKSO/MUTIP
A B1-P001-PMD-3390-0184-0 June, 10th 2022 Notice of Project Obstacle
I/VI/2022
In accordance with

1. Letter No. 034/EXT/PP WIKA BRL KSO/MUTIP 1/VII/2021 on July 1st 2021 with subject Information about Field Obstacles;
2. Letter No. 044/EXT/PP WIKA BRL KSO/MUTIP 1/VII/2021 on July 17th 2021 with subject Notice of Suspended Work Condition;
3. Letter No. 059/EXT/PP WIKA BRL KSO/MUTIP 1/VII1/2021 on August 24th 2021 with subject Request for Design, Social, Environment Issues
Solution and Instruction;
Letter no. 084/EXT/PP WIKA BRL KSO/MUTIP 1/IX/2021 on September 30th 2021 with subject Notice of Project Obstacles;
5. Package 1 Matrix of Comments and Responses for Request for Instruction and Letters Batch No. 17 on October 25th 2021;
6. Letter No. 101/EXT/PP WIKA BRL KSO/MUTIP 1/VII/2021 on October 27h 2021 with subject Notice of Project Obstacles.
7. Package 1 Matrix of Comments and Responses for Request for Instruction and Letters Batch No. 19 on October 25th 2021;
8. Letter No. 130/EXT/PP WIKA BRL KSO/MUTIP 1/11/2022 on January 27th 2022 with subject Notice of Project Obstacles;
9. Package 1 Matrix of Comments and Responses for Request for Instruction and Letters Batch No. 31 on February 3rd 2022;
10. Letter No. 141/EXT/PP WIKA BRL KSO/MUTIP 1/I/2022 on February 23rd 2022 with subject Notice of Project Obstacles;
11. Package 1 Matrix of Comments and Responses for Request for Instruction and Letters Batch No. 36 on March 3rd 2022;
12. Letter No. 150/EXT/PP WIKA BRL KSO/MUTIP 1/II1/2022 on March 24 2022 with subject Notice of Project Obstacles;
13. Package 1 Matrix of Comments and Responses for Request for Instruction and Letters Batch No. 39 on April 4rd 2022
14. Letter No. 159/EXT/PP WIKA BRL KSO/MUTIP 1/IV/2022 on April 14th 2022 with subject Nofice for Parking 6 Area Affected by Cafe:
15. Letter No. 163/EXT/PP WIKA BRL KSO/MUTIP 1/IV/2022 on April 14th 2022 with subject Notice for Suspended Works; ITDC Land Acquisition team and PMC ESHS specialist
16. Package 1 Matrix of Comments and Responses for Request for Instruction and Letters Batch No. 41 on April 22nd 2022. have provided a regular weekly update concerning
1 No.Annex
Herewith, we would like to inform you the obstacles which still remain unsolved or partially solved as follows: these obstacles. The P1 Contractor will receive a
weekly update report about these obstacles

In respect to the obstacles mentioned, we would like to give notice on the holdback of works in some areas that will affect our work progress
again, because based on schedule R2, some areas affected by obstacles will begin to progress in the near future. We also would like to inform you
that there are two new obstacles at the Parking 6 area (in front of villa) and Bukit Petiwung area (utility duct type l works) which result in idle on
the heavy equipment (2 excavators and I breaker) that work at Bukit Petiwung area. Further details of the GRM for those obstacles are attached.

204/EXT/PPWIKABRLKSO/MUTIP Notice for Confirmation


B B1-P001-PMD-3390-0204-0 July, 25th 2022
I/VII/2022 Omission Work
Dear Sir,

In accordance with the omission work plan, we would like to request for legitimate confirmation regarding the items/areas that will be omitted,
which include the obstacle areas. We need this kind of legitimate confirmation because our cumulative progress after MotoGP event up to week
58 is-2,02%, where one of the causes is we cannot work at the area that will be omitted. As an information, as per our revision 2 schedule, we
supposed to start our work at the omitted area as follow

1. West GWT (will be constructed 2 out of 3 tanks)


2. East GWT (will be constructed 1 out of 3 tanks)
3. GAI-GA2
4. GB1-GB2 The contractor shall follow the official list of
1 5. TES I omissions that was issued by the OE last 16 No.Annex

6. TES 2 September.
7. TES 3
8. TES 5
9. TES 9
10. River Iraining Works
11. Amenity Core Facilities
12. Gate & Security Booth

As per the works mentioned above, we hope Owner's Engineer can give us a legitimate confirmation whether those works will be omitted or not
and which part of the area mentioned above that Contractor can start their work in order for us to catch up the progress.