Question 1

i. Avery the newly appointed CEO should ask for the following information from the

Consultant Firm before accepting their proposal.

Avery now being the head of the Plymouth Zoo that had already hired a consultancy Firm

to determine the cost saving methods for the zoo to make profits. After the Consultancy firm

hand in their proposal. It is important for Avery to ask for information from the enterprise about

the causes of increased costs in the business.

ii. What project planning tools will you suggest AVERY ask the consultants to use to outline

the project more specifically and address his concerns?

1. Work Break down tools

Work breakdown structure (WBS) is a tool used by project managers to break down the

project into small manageable pieces. It is usually the start of the planning process. And it's often

called Foundation of project planning.

WBS is of great importance to an organization since it provides a solid foundation for

planning and scheduling, estimates the project’s cost accurately, makes sure that all deliverables

are in place and helps in resources allocation

2. RAID LOG

Raid Log helps in tracking anything you know now and in future during a project life.

Raid log is prepared at the start of the project life. Raid Log is an acronym standing for Risks,

Assumptions, Issues, and Dependencies.

Risks- circumstances that have an adverse impact on your project on their happening. If the

likelihood of the event happening and change to the project are both high, you identify the event

as a risk. The log includes explanation of each risk, full analysis and a plan to mitigate them
Assumptions - factors that you are assuming to be in place that will contribute to the favorable

effect of your project. The log includes details of the hypothesis, the reason it is believed, and the

action needed to confirm whether the assumption is valid.

Issues - events that are happening but wrongly on your project and needs controlling.

Failure to manage issues may cause a poor delivery and even complete failure. The log involves

descriptions of each issue, its effects, its seriousness and steps needed to put it under control.

Dependencies Any occurrences that are either reliant on the result of your project, or on

which your project will be dependent. The log obtains whom you are dependent on, what they

should deliver and when. It may also include who is relies on you.

3. SWOT Analysis

SWOT analysis is a strategic tool used to evaluate strengths, weaknesses, opportunities,

and threats to a project it entails specifying the objectives of the project and identifying the

internal and external factors that are favorable and unfavorable to achieving that project. The

strengths and weaknesses usually arise from within an organization, and the opportunities and

threats from external sources.

4. Using Feedback as a tool

It’s important as a project manager to give and receive feedback effectively from all

customers both internal and external. Feedback is in use to motivate people, help with personal

development, uncover risks and issues and solve problems. An environment of frequent, honest

and relevant feedback foster open communication.


Question 2

Read the case “Friendly Assisted Living Facility-3

1. Define project Deliverables

In problem management, Deliverables the tangible, measurable and expected results for a

project service toward a customer either internal or external and have a due date. Milestones

also represent the accomplishment of a major component in the project.

2. Define constraints and assumptions

Assumptions are beliefs that what you believe to be true in the future depending on the

knowledge, experience or the information at hand. These assumptions are expected to happen

during the lifecycle of the product.

Constraints are difficulties imposed on the project like increased cost, fixed schedule, and

limited resources’. All projects work have to work within the boundaries restricted by these

constraints that are defined at the beginning of the project.


1. Develop a preliminary Level 1 WBS

Construction of the
Assisted Living
Facility

Define the needsDevelop


of the project Create
individual payroll andTelecommunication
budgets accounting system and Design
Information
a Medical
needsNeeds Identify
Tools gover
Set up
Building
Design
2. Develop the RACI matrix for this project based on the Level 1 WBS

Hospital CEO IS V.P Medic Fre

Construction Directo business al d

Project r developmen directo

Manager t r

Set up Building R A A A A A

Design

Define the needs of the R A A A A A

project

Develop individual A/I R A A A A

budgets

Create payroll and A R A A A A

accounting system

Define and Set up all A/I A R A A A

Telecommunication

and Information
systems

Create a marketing A A A R A A

plan

Organize Ground A A A R A A

Breaking Event

Design a Medical A A A A R A

Needs Tools

Develop management A A A A A R

Structure

Identify government A A A A A R

regulations and

Industrial Standards

3. Would a project Charter have been useful hear

A project charter is stil important to the firm since it ensures that all project stakeholders

agree formally on the project definition and have it recorded in writing. The charter

provides the team from uncontrolled disasters and they begin their work with a full

understanding of the project scope and other requirements.

Question 3

Exercise 1
Finding the best option

Calc the accumulated weights for each option

a. (0.3*6)+(0.2*3)+(0.5*4) =4.4

b. (0.3*2)+(0.2*4)+(0.5*5) =3.9

c. (0.3*5)+(0.2*4)+(0.5*3) =3.8

d. (0.3*5)+(0.2*4)+(0.5*3) =3.8

The best conditions is a because it has higher accumulated weights

Exercise 2

Exercise 3

a. Find the Frequency Distribution of sales

Frequency Cumulative frequency

1-15 0 1

16-30 5 6

31-45 0 6

46-60 0 6

61-75 0 6

76-90 2 8

91-105 0 8

106-120 0 8
121-135 0 8

136-150 3 11

R- RESPONSIBLE C-CONSULTED

A- ACCOUNTABLE I- INFORMED

b. Find the total number of laptops sold daily

Total number of laptops sold in 141 days = 11

Therefore, 11/141

0.0780 laptops

c. Find the yearly profit of the assuming the store is only open on weekdays 50 weeks an

year and the average profit per laptop is $65?

Number of laptops sold daily 0.078

Therefore yearly profits are

0.780*5*50*65= 1267.73

Question 4

Exercise 1

Total number of sessions expected 8

85% learning rate

50 hours for the first sessions


Billing rate $100/hour

Fixed overheads $600 per session

Nominal profits 20%

Total number of hours 8*50 400 hours

Total billing 400*100 $40,000

Total Overheads $600*8 4800

Nominal profits 20%

20/100*44800= 8960

Total expected bid price $53760

Break even point

At BEP total revenue= total cost

TR= 100*50=5000

TC= 600

Bep= Fixed costs/ contricution margin

Contribution margin= (100-0)

600/100= 6

The organization will break even At session 6

Exercise 2
1 unit requires 200 hrs

Airforce project

50 units

1 unit requires 63.1 hrs

Total number of hours 50*63.1=3155

Total addition number of hours required

(50*200)- (50*63.1)= 6845hrs.

Average labor content of the second contract

50*63.1= 3155

Cost of producing the units 1st contract(200*50*10) 100000

Air force contract 550*50 27500