Professional Documents
Culture Documents
Degree
of
BACHELOR OF TECHNOLOGY
In
ELECTRICAL ENGINEERING
i
SELF CERTIFICATION
ii
COMPANY Certificate
iii
ACKNOWLEDGEMENT
(Mr. Abhishek
Karwasra
Roll No.
20EJIEE002
iv
LIST OF FIGURE
v
LIST OF TABLES
vi
INDEX
Certificate ii
Acknowledgement iv
List of Figures v
List of Tables vi
vii
4.2 Combustors 11
4.3 Transition Pieces 11
4.4 Turbine 11
4.5 Exhaust 12
viii
6.6 Current Transformer 25
6.7 Potential Transformers (PT)/Voltage Transformer (VT) 25
6.8 Lightning Arrestors 25
6.9 Current Voltage Transformers 26
6.10 Wave Trap 26
6.11 Bus Coupler 26
CONCLUSION 27
BIBLOGRAPHY 28
ix
Chapter: 1
RGTPP is located near Ramgarh Town at about 60 km from district head quarter,
Jaisalmer (Rajasthan), which is largest district of the state. Its installed capacity is 270
MW. And this plant is located in largest state of India, based on area
Seeing the increasing demand of electricity in this region for various purposes like for
providing drinking water in desert area, flood lighting on INDO-PAK Border fencing
etc.., state Govt. found it essential to raise the capacity of RGTPP and therefore
Rajasthan Vidyut Utpadan Nigam Ltd. established here two more units in second phase
of the project. In second phase, one gas turbine of 50 MW capacities and one steam
turbine of 37.5 MW capacities were installed.
1
1.1 First Unit
Necessary equipments for this power plant were supplied by Bharat Heavy Electrical
Ltd. (BHEL), and building construction was carried out by Rajasthan State Bridge
Construction Corporation. This unit is capable to generate power using both gas and
diesel. In power plant 12 underground tanks are constructed for storage of diesel having
total capacity of 2520KLt. In This Stage Gas Turbine (GT-1) Is Used Which Includes
Unit Of 50 MW and steam turbine (ST-1) is used which include unit of 37.5
MW.
2
In this system, electricity will be generated by a steam turbine utilizing heat obtained
from exhaust of gas turbines through a Heat Recovery Boiler. Thus, no additional fuel
will be required for operating Steam Turbine.
Under stage-II, one Gas Turbine Unit (110 MW) was commissioned and synchronized
with the grid on June 2010 The Steam Turbine Unit (50 MW) was also commissioned
and synchronized with the grid on June 2010 and thus the plant has been made
operational in combined cycle mode with a total capacity of 270 MW.
The details of total energy generated from this power station during years are as under:
3
Table 1.1: Total Energy Generated
4
Dandewala Terminal, is approximately 67 km from Ramgarh Terminal. This pipe line is
being maintained by GAIL.
GAS PERCENTAGE
NITROGEN 31.9064 %
METHANE 48.5668 %
ETHAN 0.5009 %
PROPANE 0.0333 %
ISO-BUTANE 0.0285 %
N-BUTANE 0.0513 %
ISO-PENANE 0.0185 %
N-PENANE 0.0130 %
HEXANE 0.0000 %
5
Chapter- 2 POWER PLANT CYCLE
By utilizing the heat of gas turbine exhaust HRSG (Boiler) generates Steam which is
used to run Steam Turbine Generator (STG).
Thus we can generate an additional power (about 50 % of the gas turbine generation)
in Steam Turbine Generator without any extra fuel cost. Thus we can get 30% extra
efficiency by running the gas turbine in combined cycle.
As gas turbine is operated on Brayton Cycle principle and Steam Turbine is rotated
on Rankine cycle principle that is why it is called Combined Cycle.
6
• Compact in size.
7
2.5 Rankine Cycle
8
Chapter-3 BRIEF INTRODUCTION OF PLANT OPERATION
At RGTPP gas to the turbines is being supplied through GAIL terminal from oil wells of
ONGC and OIL, which are attached to discover oil and natural gas recourses in Western
Rajasthan. The quantity of the gas is 9.5 Lac SCM per day. From GAIL Terminal gas is
supplied to Gas Booster Compressor (GBC motor) at pressure of 10-15kg/cm2 and
quantity of gas is 9.5 Lac SCM/day.
The work of the Gas Boost Compressor is to compress gas and to supply required pressure
of gas for power production to gas turbine. In compressing process by GBC the pressure of
the gas increases from 10-15kg/cm2 to 18-23kg/cm2. The output of the GBC motor is first
merged and then is divided further, before blowing into the Combustion Chamber. There
are two GBC motor in RGTPS, GT-1 and GT-2. The blowing pressure is 18-23 kg/cm2.
Combustion Chamber is a place where ignition of fuel mixed with air occurs with the help
of the sparkplugs, the voltage on both of the sparkplugs is 15000 V dc. On combustion, the
gas gets mixed with air then the gas will expand and air pressure will increases. This air
exhausts on the gas turbine buckets & nozzles and gas turbine starts to rotate. There are
two generators of 35.5 MW and 37.5 MW attached with GT-1 and GT-2 respectively,
mounted on the same shaft as the turbine. So GT-1 and GT-2 produces 35.5 and 37.5 MW
electricity respectively.
The exhaust of GT is flue gases. The temperature of flue gas is near about 500 deg C. This
exhaust may also be relieved into the atmosphere with the help of controlled valves.
But this exhaust is taken in use to produce electricity. So this power plant is called
Combined Cycle Power plant. This exhaust (flue gas) of the gas turbine is further passed
into the Heat Recovery Steam Generator (HRSG). It is a boiler. Water circulating in
drum is superheated with the help of flue gases. This superheated steam runs the Steam
Turbine Generator, so it is called unfired combined cycle.
The generator is mounted on the same shaft as of the steam turbine, produces 37.5 MW
electricity. The steam which is blowing on the gas turbine should be superheated.
9
The generator is mounted on the same shaft as of the steam turbine, produces 37.5 MW
electricity. The steam which is blowing on the gas turbine should be superheated. Steam
Power generation is also done at low voltage because of the insulation problem.
If the power generation is done at high voltage then there are following disadvantages-
10
Chapter: 4 GAS TURBINE
Turbine Equipments
4.1 Compressor
The atmosphere air is compressed to the 17 stage compressor and before it passes through
the filter. The compressor ratio is 10 and this air is routed to the combustors. The
compressor used in the plant is of rotatory type. The air at atmospheric pressure is drawn
by the compressor via the filter which removes the dust from the air. There are 396 no. of
filters connected in different rows. These filters are made up of cellulose fiber. The rotatory
blades of the compressor push the air between stationary blades to raise its pressure
4.2 Combustors
The fuel (gas) is provided to ten equal flow lines, each terminating at a fuel nozzle centered
in the end plate of a ten separate combustion chamber and prior to being distributed to the
nozzles, the fuel is actually controlled at a rate consistent with the speed and load
requirements of gas turbine. The nozzle introduces the fuel into the combustion chambers
where it mixes with the combustion air and is ignited by the sparkplugs. At instant when
fuel is ignited in one combustion chamber, flame is propagated through connecting
crossfire tubes to all other combustion chambers.
4.4 Turbine
There are three stages of the turbine and each consists of a row of fixed nozzles followed
by a row of rotating turbine buckets. In each nozzle row, the kinetic energy of the jet is
increased with an associated pressure drop and in each following row of a moving buckets,
a portion of the kinetic energy of the jet is absorbed as useful work on the turbine rotor.
11
4.5 Exhaust
After passing through the third stage buckets, the gases are directed into the exhaust hood
diffuser which contains a series of turning vanes to turn the gases from an axial direction
to a radial direction, thereby minimizing exhaust hood losses. The gases then pass into the
exhaust plenum and are introduced to atmosphere through the exhaust stack or to the
H.R.S.G.
12
Chapter: 5 CONSTRUCTION DETAILS OF GENERATOR
AND EXCITER
Generator:
The generator is two pole, cylindrical rotor, air cooled type-TARI, Siemens, Designs of
BHEL make.
5.1 Stator
5.2 Rotor
5.2.1 Rotor Shaft
5.3 Bearings
13
5.1 Stator:
The laminations are hydraulically compressed and located in frame by means of camping
bolts and pressure plates.
Clamping bolts run through the core and are made of non magnetic steel and are insulated
from the core to prevent short circuiting of the core. Clamping fingers are provided at the
ends which ensure compression in teeth area. The clamping fingers are made up of non
magnetic steel to avoid eddy current losses.
Each bar consists of number of separately insulated strands. In slot portion the strands are
transposed to ensure uniform distribution of current over entire cross section of the bar.
The high voltage insulation is epoxy cast resin type bonded with mica. The insulation is
continuous, void free, extremely low moisture absorbent, oil resistant and exhibits excellent
electrical, mechanical and thermal properties. A coat of semi conducting varnish is applied
over the surface of all bars within the sot range to minimize corona discharges between and
slot wall.
All the bars are additionally provided with end corona protection to control the field at that
location and to prevent formation of creep age sparks. Several layers of semi conductive
varnish are applied at varying lengths to ensure uniform electric field. A final wrapping of
14
glass fabric tape impregnated with epoxy resin is provided which serves as surface
protection. The stator bars are inserted in slots with very small clearances. At the top they
are secured by slot wedges and ripple springs. In the end windings the bars are firmly lasted
to supporting brackets. Spacer blockers are placed between the bars to take care of
electromagnetic forces that may be produced during short-circuits. The beginning and the
ends of the three phase winding are solidly bolted to output leads with flexible.
Output leads are copper flats inserted into insulating sleeve.
15
Fig. 5.2- Bearing
16
5.2 Rotor:
To protect the winding against the effects of centrifugal forces the winding is secured in
the slots with wedges. Slot wedges are made from alloy high strength and high electrical
conductivity material. This also acts as damper winding. At the ends, slot wedges are short
circuited through the retaining ring which acts as short circuiting ring to induced currents
in damper windings.
Retaining rings of high strength of non magnet steel are provided.
5.3 Bearings
The rotor is supported in two sleeve bearings. To eliminate shaft currents the exciter end
bearing is insulated from the foundation frame & oil piping. Temperatures of the bearing
are monitored by two RTDs embedded in the lower half of the sleeve bearing. Bearings
also have provision of fixing vibration pickups to monitor bearing vibrations transmitted
from the shaft.
17
Table 5.1: Steam Turbine Generator
TURBINE MW 37.5 MW
18
Table 5.2: Insulation Level
PHASE 3
FREQUENCY (Hz) 50
19
TRANSPORT WEIGHT (Kg) (GAS 45000
FILLED)
The cooling air directed into the rotor end winding and cools the windings. Some air flows
in the rotor slots at bottom duct from where it is discharged into the air gap via radial
ventilating slots in the coil and bores in the rotor wedges.
Part of the flow is directed over the stator overhang to the cold air duct and to the gap
between the stator frame and stator core. Air then flows through ventilating ducts in the
core into the air gap.
The balanced air is directed into the air gap over the retaining rings cooling it.
3. rectified wheel
20
The three phase pilot exciter is a permanent magnet type. Three phase output from the pilot
exciter is fed into the AVR (Automatic Voltage Regulator).From the AVR regulated dc
output is fed to the stationary field coils of main exciter. The three phase output from the
rotating armature of the main exciter is fed to the rectifier wheel, from where it is fed to the
field winding of the generator rotor through dc leads in the rotor shaft.
Pilot exciter is six pole units. The stator is consists of laminated core and carries three phase
winding. Rotor consists of hub on which six permanent magnets poles are mounted.
21
Chapter : 6
132 KV SWITCH YARD
Ramgarh GTPP contains 132 KV switch Yard. The switchyard houses transformers, circuit
breakers, and switches for connecting and disconnecting the transformers and circuit
breakers. It also has lightning arrestors for the protection of power station against lightning
strokes.
The supply to the bus bars from alternators is taken through the transformers and circuit
breakers of suitable ratings.
There are two buses of 132 KV, 800A, in Ramgarh GTPP to which incoming and outgoing
feeders, Bus Couplers, Isolators, Circuit Breakers, protective Relays, Current Transformers
(CT) and Potential Transformers (PT) are connected are connected.
One Bus is usually is called ‘main’ bus and the other ‘auxiliary’ or ‘transfer’ bus.
The switches used for connecting feeders or equipment to one bus or the other are called
selector or transfer switches.
6.2 Insulators:
The porcelain insulators employed in switch yard of the post and bushing type. They serve
as supports and insulation of the bus bars.
6.3 Isolators:
Isolator is a off load switch. Isolators are not equipped with arc quenching devices and
therefore, not used to open circuits carrying current. Isolator isolates one portion of the
circuit from another and is not intended to be opened while current is flowing. Isolators
must not be opened until the circuit is interrupted by some other means. If an isolator is
opened carelessly, when a heavy current, the resulting arc could easily cause a flash over
22
to earth. This may shatter the supporting insulators and may even cause the fatal accident
to the operator, particularly in high voltage circuits.
While closing a circuit, the isolator is closed first, then circuit breaker. Isolators are
necessary on supply side of circuit breakers in order to ensure isolation (disconnection) of
the circuit breaker from the live parts for the purpose of maintenance.
A circuit breaker must carry normal load currents without over heating or damage and must
quickly open short-circuit currents without serious damage to itself and with a minimum
burning contacts. Circuit breakers are rated in maximum voltage, maximum continuous
current carrying capability, and maximum interrupting capability, maximum momentary
and 4-second current carrying capability.
To make and break the short circuit currents of magnitude up to which it is designed for.
23
6.5 Protective Relays:
The protective relay is an electrical device interposed between the main circuit and the
circuit breaker in such a manner that any abnormality in the current acts on the relay, which
in turn, if the abnormality is of dangerous character, causes the breaker to open and so to
isolate the faulty element. The protective relay ensures the safety of the circuit equipment
from any damage, which might otherwise caused by fault.
(a) Primary winding of the CT connected in series with the main circuit to be protected.
(b) Secondary winding of the CT and the relay operating winding and
Under normal operating conditions, the voltage induced in the secondary winding of the
CT is small and, therefore, current flowing in the relay-operating coil is insufficient in
magnitude to close the relay contacts. This keeps the trip coil of the circuit breaker
deenergized. Consequently, the circuit breaker contacts remain closed and it carries the
normal load current. When a fault occurs, a large current flows through the primary of the
CT. this increases the voltage induced in the secondary and hence the current flowing
through the relay operating coil. The relay contacts are closed and the trip coil of the breaker
gets energized to open the breaker contacts.
24
6.6 Current Transformers (CT)
A current transformer basically consists of an iron core on which are wound a primary and
one or two secondary windings. The primary is inserted in the power circuit (the circuit in
which the current is to be measured) and the secondary winding of the current transformer
is connected to the indicating and metering equipments and relays are connected.
At GTPP, current transformers are provided in switchyard to measure the current of the
feeders. There are five cores in current transformers. The 1st, 2nd, 4th and 5th cores are
provided for protection and the third core is used for measurement purpose.
These CT are of the ratio of 200/1, 400/1, and 1200/1. When the rated current of CT flows
through its primary winding, according to transformation ratio the current in the secondary
of the CT will flow and will be measured by the indicating instruments connected to the
secondary of the CT.
25
6.9 Current Voltage Transformers (CVT)
CVT are provided for synchronization purpose at feeders to measure phase angle, voltage
and frequency. For joining the feeders coming from different places or for synchronization
of feeder’s voltage, phase angle and frequency at the joining place must be of same value.
All the telephone lines in RGTPP are connected through Wave Trap to ensure effective
communication in emergencies.
26
CONCLUSION
After analyzing the RGTPP 270.5 MW combined cycle power plant, I can describe that
this power plant is a very efficient one as compared to other power plants in its series.
Also, I would like to add up that it is very compact in size, less pollute to nature, easily
controlled & decent power plant that is had ever seen.
I really had nice time here & got a treasure of practical knowledge from the RGTPP
employees. In future I am sure that this vocational training in RGTPP is going to help me
in our rest of the studies
27
BIBLIOGRAPHY
Books collected:
Power System by J.B. Gupta
Websites:
• www.ntpc.co.in
• https://en.wikipedia.org/wiki/Ramgarh_Gas_Thermal_Power_Station
28