NO. INTRODUCTION 1 1 FACTORS AFFE- CTING RATE ANA- 2 LYSIS 2 3 ELEMENTS 3 4 ANALYSIS OF 5 RATES 5 REFFERENCE 13 6 CONCLUSION 14 INTRODUCTION In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item. This process of determining the rates of an item is termed as analysis of rates or rate analysis. The cost of materials in rate analysis is calculated as combination of cost of material at origin, its transportation costs, taxes. The rate of labour is based on skill of the labour, such as skilled labour, semi- skilled and unskilled labour. The cost of materials and labours vary from place to place. Thus, the cost of each construction work varies from place to place. The capacity of doing work by an artisan or skilled labour in the form of quantity of work per day is known as the task work or out turn of the labour. The cost of any construction project is calculated based on each works associated with every construction activity. Thus it is essential to calculate cost of each small works. What are the Factors Affecting Analysis of Rates of Civil Works? Factors which affect the rate analysis of civil works are: o Specification of the civil work and materials such as quality of materials, proportion of mortar or concrete, thickness of plastering, number of coats of painting, depth of excavation, type of soil etc. o Location of the construction site – Distance of construction site from source of materials, availability of labours, availability of water, machinery etc. influence the rate analysis of construction work. o Quantity of materials, number of different types of labours and rates of materials and labours influence the rate analysis. o Profit of the contractor, miscellaneous expenses and other overheads also influence the rate analysis. What are the Elements of Rate Analysis of Civil Works? Elements which constitute the rate analysis are: a) Material cost inclusive of wastage b) Labour cost c) Plant & machinery owning and operating charges d) Water charges e) Taxes f) Insurance/ risk coverage charges g) Contractor’s overheads and profit Why Analysis of Rates is Required in Construction Projects? The rate analysis may be required in construction projects for following purposes: o For the purpose of tendering. In the case of tendering, the contractor may calculate cost of unit work involved in each construction activity for justified quoting of rates. The client may also require rate analysis to calculate the cost of construction project. o To assess the requirements of quantities of labours, materials, machineries and capital to complete the project. o To optimise the use of labour, materials and machineries and to know the alternatives to optimize the resources. o To assess the rate of unit work from time to time for payment increase in material or labour costs or any deviations in work specifications, extra items of work to the contractor. o To compare the cost of project with the sanctioned capital of the project to take necessary action or regularization of excess or less cost. o To workout the budget of the construction project and control the cash flows at various stages of construction work. o To find out the irrational rates quoted by the contractors during tendering process. o To serve as the basic data in case of dispute among project owner and contractor.
ANALYSIS OF RATES :
Tools and plants : 2.5 to 3% of labour cost
Transportation cost more than 8 km is considered Water charges : 1.5 to 2% of total cost Contractor’s profit : 10%
This section includes examples of floor plans,
elevations, and details commonly used to estimate the cost of painting exterior masonry walls. Masonry Unit: natural or manufactured building units of burned clay, stone, glass, gypsum,
concrete, etc.
Rule-of- Thumb: a statement or formula that is not
exact but is close enough for practical work.
Split-Face Unit: concrete masonry units with one or
more faces produced by purposeful
fracturing of the unit to provide architectural
effects in masonry wall construction. Masking:
the temporary covering of areas adjacent to those
to which paint is to be applied.
Cutting-In: a painting technique used to paint around
the edges of an object or areas, such as
trim, light fixture, or an opening.
CONCLUSION
By making these micro project, We know the
All information about rate analysis of painting works containing internal wall, outer wall. And we understood how to calculate rate analysis of painting works using plastic emulsion, oil paint ,luster paint.