You are on page 1of 19

As per MSBTE Curriculum of “I” Scheme

A Micro Project on

Prepare Approximate estimate of School, Auditorium hall, Hostel,


Hospital
Submitted by

Enrollment no. Name


2009910007 Deshmukh Sandesh Sachin
2009910008 Mohite Prashant Tanaji
2009910009 Mandale swapnil Abaso

Under the Guidance of


Miss. C.B.Rajput

Loknete Hon. Hanmantrao Patil Charitable Trust’s


Adarsh Institute of Technology And Research Centre ,
Vita
______________________________________________________________________________

Department of Civil Engineering


2022-2023
Loknete Hon. Hanmantrao Patil Charitable Trust’s
Adarsh Institute of Technology And Research Centre,

Vita

CERTIFICATE
This is to certify that the Micro Project entitled
Prepare Approximate estimate of School, Auditorium hall, Hostel,
Hospital
has been submitted by
Enrollment no. Name
2009910007 Deshmukh Sandesh Sachin
2009910008 Mohite Prashant Tanaji
2009910009 Mandale Swapnil Abaso

For Sixth Semester of Diploma in Civil Engineering of course Estimating And


Costing (22503) for academic year 2022-2023 as per MSBTE, Mumbai
curriculum of ‘I’ scheme.

Project Guide Head, Civil Engineering, Principal,


AITRC, Vita AITRC, Vita

Date:
Place:
Acknowledgement
I feel happiness in forwarding this Micro Project report as an image of sincere efforts. The
successful Micro Project Report reflects my work, effort of my guide in giving me good
information.

My sincere thanks to my guide respected Miss. C.B.Rajput


who has been a constant source of inspiration and guiding star in achieving my goal. I give
my special thanks to respected Mrs.N.P. Thorat (Head, Civil Engineering) for his constant
interest and encouragement throughout the completion of my Micro Project.
I express my deep gratitude to all staff members who lend me their valuable support and
cooperation to enable me to complete my Micro Project.
I am also equally indebted to our principal Prof. Mr.Dr.P.R.Badadapure. for his valuable
help whenever needed.

Name of Student Sign of Student

Deshmukh Sandesh Sachin

Mohite Prashant Tanaji

Mandale Swapnil Abaso


Index

Sr. No. Content Page No.

1.0 Rationale

2.0 Course Outcomes Addressed

3.0 Literature Review

4.0 Actual Methodology Followed

5.0 Actual Resources Used

6.0 Outputs of the Micro Project

7.0 Skill Developed / learning out of this Micro Project

8.0 Applications of this Micro Project

9.0 Area of Future Improvement


A. Micro Project Proposal

Title of Micro Project:- Prepare Approximate estimate of School, Auditorium


hall, Hostel, Hospital

1.0 Brief Introduction: The approximate estimate is done in order to find out an
approximate cost in very shorttime before starting the project. The estimation is made
before selecting the finalspecification and design of the project. This method is also
known as preliminary or roughestimate.

1.1 Purpose of approximate estimate:


1. To evaluate the cost of a project in short time.
2. To evaluate the difference between several options.
3. To check the final cost of the project that is calculated by detailed estimation.

2.0 Aim of the Micro Project:


Feasibility Investigation.
• To Save Time and Money.
• To Investigate Benefit and Comparison of Cost with Utility.
• To Make Planning Adjustments.
• Obtain Administrative Approval.
• For Insurance and Tax Schedule.

3.0 Intended Course Outcomes:


1.Select the modes of measurements for different items of works.
2.Prepare approximate estimate of a civil engineering works.
3.Prepare detailed estimate of a civil engineering works.
4.Justify the rate for given items of work using rate analysis techniques.
5.Use relevant software for estimating the quantities and cost of items of works.

4.0 Literature Review


Review: Approximate estimate of commercial and Industrial buildings.

Abstract: An approximate estimate gives a basic or starting point estimate for any
project. It is very important to have an accurate estimate though approximate. An
approximate estimate helps the takers of the project to make a decision as to take up the
project or not. If the approximate estimate is too high, then the project manager would
leave the project without preparing the detailed estimate. Work with detailed surveys,
soil investigations, designs and drawings of a project start only when the approximate
estimate is low. And when it is found that the detailed estimate is much higher than the
approximate estimate then the project may be cancelled. This would result in loss of the
entire labor, time, and expenses.In conclusion, it is important for government or public
bodies or even private owners to know the approximate estimate of the intended
project for approval to undertake the project

4.0 Actual Methodology Followed.


1) Select the micro project subject.
2) To collect the literature review and information role of estimating and costing
engineering in sustainable and resilient cities.
3) Then study all details of the role of estimating and costing in sustainable and resilient
cities.
4) Study the different between role of estimating and costing in sustainable and resilient
cities in detail.

5) Layout design.

6) Implementing.

7) Compiling project.

8) Analysis.

9) Report making.
Name of Resource/
Specifications Quantity Remark
Sr. Material
No.
For collect project
1 Wikipedia 1
information
Project Cost
2 Management.
Books 1
(Saikumar sela)

3 Website https://theconstructor.org 1

Planned
Sr. Planned Name of Responsible Team
Details of activity Finish
No. start date Members
date
1 Project Proposal
2 Data Collection & Analysis Deshmukh Sandesh sachin
3 Preparation of Prototype/ Model Mohite Prashant tanhaji
4 Preparation of Report Mandale Swapnil abaso
5 Presentation & Submission
B – Micro Project Report

Title of Micro Project: Prepare Approximate estimate of School, Auditorium hall,


Hostel, Hospital

1.0 Rational: In the construction of any civil structure, specifications of the civil work are the
significant parameters in deciding the cost of the project. In construction, it is often required to
use the local material for which the rates are varying in greater extent across the country. The
rate analysis justifies the rates to be finalized for various items of works based on local market
survey for budget provision. Therefore there emerges the need of a discipline to suggest a
specific scientific technique to determine the quantities and cost of the materials along with its
justification. Thus, this course provides the necessary knowledge and skills in developing the
competency in the areas mentioned above in professional manner. Today being the era of
technology, a provision has also been made to use the various software’s for more accuracy
and speedy determination of quantities.

2.0 Course Outcomes Addressed :-


1.Select the modes of measurements for different items of works.
2.Prepare approximate estimate of a civil engineering works.
3.Prepare detailed estimate of a civil engineering works.
4.Justify the rate for given items of work using rate analysis techniques.
5.Use relevant software for estimating the quantities and cost of items of works.

3.0 Literature Review :-


Review: Approximate estimate of commercial and Industrial buildings.
Abstract: An approximate estimate gives a basic or starting point estimate for any project.
It is very important to have an accurate estimate though approximate. An approximate
estimate helps the takers of the project to make a decision as to take up the project or not.
If the approximate estimate is too high, then the project manager would leave the project
without preparing the detailed estimate. Work with detailed surveys, soil investigations,
designs and drawings of a project start only when the approximate estimate is low. And
when it is found that the detailed estimate is much higher than the approximate estimate
then the project may be cancelled. This would result in loss of the entire labor, time, and
expenses.In conclusion, it is important for government or public bodies or even private
owners to know the approximate estimate of the intended project for approval to
undertake the project

4.0 Actual Methodology Followed.


1) Select the micro project subject.
2) To collect the literature review and information role of estimating and costing engineering
in sustainable and resilient cities.
3) Then study all details of the role of estimating and costing in sustainable and resilient
cities.

4) Study the different between role of estimating and costing in sustainable and resilient cities
in detail.

5) Layout design.

6) Implementing.

7) Compiling project.

8) Analysis.

9) Report making.

5.0 Actual Resources Used

Sr. Name of Resource/ Qua


Specifications Remark
No. Material ntity
For collect project
1 Wikipedia 1
information
Project Cost
Management. (Saikumar
2 Books 1
sela)

3 Website https://theconstructor.org 1

6.0 Outputs of the Micro Project:-

➢ Methods of Approximate Estimate:

A. Plinth Area Method:

This estimation is done by selecting the price of 1 square meter area of a building. It ismainly
adopted for calculating the cost of following buildings:

❖ Office Buildings.
❖ Residential Buildings.
❖ School Buildings.
❖ Apartment/Flat Buildings.
❖ Hospitals.

This method is considered as the best method for calculating the cost of new buildings.
In case of multi-storeyed buildings, the following assumptions are to be considered for
the estimation.
1. For 1 square meter area, the cost of all the floors with basement and roof are in equal costs.
2. The cost of the basement is 60% of the floor.
3. The cost of the roof is 40% of the floors.

B. Cubic Meter Method:-

This method gives more exact result comparatively than the square meter method.
1. For 1 meter cube area the costs of all floors are equal in costs.
2. The cost of the basement is 60% of the cost of different floors.

The volume of the floor is determined as,

Volume = Area x Height of one floor

The height of one floor is found out by the following guidelines:

➢ Ground Floor:
The height of ground floor is calculated from the top of the footing tothe middle of the
parapet.
➢ First Floor:
The height of the first floor is calculated from the ground rooftop to themiddle of the
parapet.
➢ Other Floors:
The heights of other floors are calculated from floor to floor.Besides these methods,
there are some other approximate methods such as1. Cost comparison method.2. Unit rate
method.3. Approximate quantities with bill method.4. Bay method.5. The cost of materials
and labour method.

B. Typical Bay Method

This method is useful for application to framed structures consisting of a number of


similar bays, as for example, industrial buildings. A typical interior bay (between two
successive columns) is selected and its total cost worked out.

Then, the approximate cost of building = Number of bays in the building x cost of one bay.

Suitable correction factors may have to be used to take into account the dissimilarities inend-
bay (and in different floors, if applied to multi storey construction).

C. Approximate Quantity Method Cost Estimate

In approximate quantity method cost estimate, Total wall length of the structure is measured
and this length is multiplied by the rate per running meter which gives the cost of
the building. Rate per running meter is calculated separately for foundation
and superstructure.

In case of foundation, the rate per running meter is decided by considering quantities such as
excavation cost, brickwork cost up to plinth. While in case of superstructure quantitieslike
brickwork for the wall, wood works, floor finishing etc. are considered for decidingrate per
running meter.
D. The Service Unit Method

Buildings are constructed to serve a specific purpose. For example hospitals are designed
to accommodate certain number of beds. Each bed is then considered a service unit. Hotels
are designed to accommodate certain number of guest rooms. Each guest room is considered
a service unit. Same applies to offices, residential houses etc. Whenever a building
is constructed the Engineer or the architect keeps the record of the place, actualcost, number
of service units, and the year of construction. From this record, it is possible to work out the
cost per service unit. This cost is then adjusted to account for inflation, and peculiarities
of the project under consideration. Then the adjusted cost per service unit is simply
multiplied by the number of service units in the proposed project to get an approximate cost
estimate.

7.0Actual Procedure followed

1. Estimate for School building:-

1) The cost of construction of school building is 2.50 crores for a capacity of 600students and
area of construction is 1600 m^2. Prepare approximate estimate of newly proposed school
building for 1500 students with the area of 5000 m^2. Use Plinth Area method

Solution:

Rate of Plinth Area of existing school building = 25000000÷1600


= 15625Rs/m^2
Then,
The approximate cost of newly proposed school building Plinth
= Total plinth Area of proposed building X Cost per area of similar existing building.
= 15625 X 50000 = 7.8125 crores

2) The cost of construction of school building is 4 crores for a capacity of 1200 studentsand
area of construction is 3200 m^2. Prepare approximate estimate of newly proposedschool
building for 3000 students with the area of 1000m^2. Use Plinth Area method
Solution:
Rate of Plinth Area of existing school building = 40000000÷3200

= 12500Rs/m^2
Then,
The approximate cost of newly proposed school building Plinth
= Total plinth Area of proposed building X Cost per area of similar existing building
= 12500 X 10000
= 125000000 crores

.
2. Approximate Estimate for Auditorium Hall -

1) Prepare approximate of Auditorium Hall building having Plinth Area 1500 m^2
➢ Plinth Area rate - 4000Rs per m^2
➢ Water supply and sanitary installation -5% of cost of building
➢ Electric installation - 10% of cost of building
➢ Other services - 5% of cost of building
➢ Contingencies-3% of overall cost of building
➢ Super vision charges - 8% of overall cost of building
Solution:

Cost of Auditorium Hall = plinth Area X Rate


= 1500m^2 X 4000 Rs
= 6000000
Cost of water supply and sanitation installation = (5÷100) X 6000000= 300000
Electric installation = (10÷100) X 6000000= 600000
Other services = (5÷100) X 6000000= 300000
Contingencies = (3÷100) X [60 lakh+ 3 lakh + 6 lakh + 3 lakh]
= 0.03 X 72 lakh= 216000 (2 lakh 16 thousand)
Supervision charge = (8÷100) X 72 lakh= 576000
Approximate estimate of town hall
= 72 lakh + 2 lakh 16 thousand + 5 lakh 76 thousand
= 79.92 lakh
2) Prepare approximate of Auditorium Hall building having Plinth Area 2200 m^2.
Plinth Area rate - 3500Rs per m^2
➢ Water supply and sanitary installation -3% of cost of building.
➢ Electric installation - 8% of cost of buildingOther services - 5% of cost of building.
➢ Contingencies - 2% of overall cost of building.
➢ Super vision charges - 4% of overall cost of building.
Solution:
Cost of Auditorium Hall = plinth Area X Rate
= 2200 m^2 X 3500Rs
= 7700000
Cost of water supply and sanitation installation = (3÷100) X 7700000= 231000
Electric installation = (8÷100) X 7700000= 616000
Other services = (5÷100) X 7700000= 385000
Contingencies = (2÷100) X [7700000+231000+616000 + 385000]
= 178640
Supervision charge = (4÷100) X 178640= 71456
Approximate estimate of Auditorium Hall = 8932000 +178640+ 71456
= 9182096 Lakh

3. Approximate Estimate for Hospital building

1) A hospital building of 150 beds is constructed in Talegoan the cost of construction of RS 5


crore. Find the approximate Estimate of a small hospital of 35 beds in the similar locality by
using service unit method

Solution:

Rate per service unit = (cost of construction÷ number of beds)= 50000000 ÷ 150

= Rs 333333.33/ bed

Approximate cost of newly proposed hospital of 35 beds

= Number of beds X Rate per bed

= 35 X 333333.33

= RS.11666666.662
2. A hospital building of 200 beds is constructed in Pune the cost of construction of RS
7crore. Find the approximate Estimate of a small hospital of 45 beds in the similar locality by
using service unit method

Solution:

Rate per service unit = (cost of construction= number of beds)

= 70000000 ÷ 200= Rs.350000 /bed

Approximate cost of newly proposed hospital of 35 beds

= Number of beds X Rate per bed= 45 X 350000

= Rs.15750000

4. Approximate Estimate for hostel building

1) A hostel building for 150 students is constructed in Pune the cost of construction is RS6
crore. Find the approximate estimate of a newly proposed hostel building of 250 students in
the similar locality by using service unit method

Solution:

Rate per service unit = (cost of construction number of students)

= 60000000 ÷ 150

= RS.400000

Approximate cost of newly proposed hostel building for 250 students

= Number of students X Rate per student

= 250 X 400000= RS.1000000002


2. A hostel building for 200 students is constructed in Pune the cost of construction is Rs. 8
crore. Find the approximate estimate of a newly proposed hostel building of 300 studentsin
the similar locality by using service unit method.

Solution:

Rate per service unit = (cost of construction÷ number of students)

= 80000000÷200 = 400000

Approximate cost of newly proposed hostel building for 300 students

= Number of students X Rate per student

= 300 X 400000 = RS.120000000

7.0 Skill Developed / learning out of this Micro-Project


1) Self-learning attitude.
2) Presentation and Report writing skills.

8.0 Applications of this Micro-Project


1. In commercial and industrial building planning and management.
2 .for any construction related to civil engineering.

9.0 Area of Future Improvement


1) Goals of Construction Planners: Time, Cost, Quality, and Safety. The objectives of
construction approximate estimation are the same for all projects: Builders and owners strive
to meet cost, schedule, quality, and safety requirements.
Teachers Evaluation Sheet

Name of Student: Enrollment No:


Deshmukh Sandesh Sachin
2009910007
Mohite Prashant Tanaji
Mandale Swapnil Abaso 2009910008
2009910009

Academic Year: 2022-23 Semester: V


Name of Programme: Civil Engineering Course: Estimating And Costing
Course Code: 22503 Course Coordinator: Miss. C.B. Rajput

Title of the Micro Project: Prepare Approximate estimate of School,


Auditorium hall, Hostel, Hospital

Course Outcomes Addressed:

The theory, practical experiences and relevant soft skills associated with this course are to be
taught and implemented, so that the student demonstrates the following industry oriented COs
associated with the above mentioned competency:

1) Select the modes of measurements for different items of works.


2) Prepare approximate estimate of a civil enginccring works.
3) Prepare detailed estimate of a civil engineering works.
4) Justify the rate for given items of work using rate analysis techniques.
5) Use relevant software for estimating the quantities and cost of items of works.

c) Outcomes in Affective Domain

➢ Demonstrate working as a leader or a team member.

Report of work carried out:

Sr. Planned Completed Sign of


Details of activity
No. schedule Schedule Guide
1 Project Proposal
2 Data Collection & Analysis
3 Preparation of Prototype/ Model
4 Preparation of Report
5 Presentation & Submission
Evaluation as per Suggested Rubric for Assessment of Micro Project

Sr. Characteristicto be Poor Average Good Excellent


No assessed ( Marks 1-3 ) ( Marks 4 - 5 ) ( Marks 6 - 8 ) ( Marks 9- 10 )
Relate to very fewLos Related to some Los Take care of at-leastone CO Take care of morethan
1 Relevance tothe
one CO
course

Not more than two sources At-least 5 relevantsources, At –least 7 relevantsources, About 10 relevant sources,
Literature (primary andsecondary), very at least 2 latest most latest most latest
2 Survey / old
information reference
collection
Completed less than50% Completed 50 to Completed 60 to Completed morethan 80
Completion ofthe
60% 80% %
Target as per
3
project proposal
Sample Size small,data Sufficient and appropriate Sufficient and appropriate Enough data collected by
neither organized nor sample,enough data sample,enough data sufficient and appropriate
presented well generated but not organized generated which is sample size. Proper
and not presented well. No organized and presented inferences drawn by
or poor inferences drawn well but poor inferences organizing and presenting
Analysis of Data and drawn data through tables,
4 representation charts and graphs.

Incomplete Just Well Well


fabrication/assembly. assembled/fabricatedand parts assembled/fabricatedwith assembled/fabricatedwith
are not functioning well. proper functioning parts. In proper functioning parts. In
Not in proper shape, proper shape, within proper shape, within tolerance
Quality of Prototype/ dimensions beyond tolerance tolerance dimensions and dimensions and good
Model limit. good finish/appearance. finish/appearance.
5 Appearance/finish isshabby. But no creativity in Creativity in designand use of
design and use ofmaterial material
Sr. Characteristicto Poor Average Good Excellent
No be assessed
( Marks 1-3 ) ( Marks 4 - 5 ) ( Marks 6 - 8 ) ( Marks 9- 10 )
Very short, poor quality Nearly sufficient and Detailed, correct andclear Very detailed, correct,
sketches, Details about correct details about description of methods, clear description of
methods, material, methods, material, materials, precautions methods, materials,
precaution and precautions and and Conclusions. precautions and
6 Report conclusions omitted, conclusion, but clarity is Sufficient Graphic conclusions. Enough
Preparation some details are wrong not there inpresentation. Description. tables, charts and
But not sketches
enough graphic
description.

Major information isnot Includes major Includes major Well organized,


7 Presentation included, information is information but notwell information and well includes major
not organized and organized but not information ,well
well organized . not presented well presented well presented

Any other
(depending upon
nature ofproject:
8 pleasewrite
indicators by
pen)
Could not reply to Replied to considerable Replied properly to Replied most of the
considerable numberof number considerable numberof questions properly
question. of questions but notvery question.
9 Defense
properly
Micro Project Evaluation Sheet

Process Assessment Product Assessment


Part B - Project Total
Part A - Project individual
Project Report/Workin Mark
Proposal Presentation/Viv
Methodology g Model s 10
(2 marks) a(4 marks)
(2 marks) (2 marks)

Comments/Suggestions about team work/leadership/inter-


personal communication(if any)

Any Other Comment:

Name and designation of the Faculty Member

Dated Signature

You might also like