The document outlines a 4-week timeline for drilling 450mm diameter boreholes starting on October 10th, 2022. During the first week, pre-mobilization preparation will take place. In the second week, site visits, mobilization, and camp setup are scheduled. Drilling of 17 boreholes will occur during the third week, along with casing and gravel packing. Testing and development of the boreholes is scheduled for the fourth week before demobilization. The timeline is subject to change based on site conditions.
The document outlines a 4-week timeline for drilling 450mm diameter boreholes starting on October 10th, 2022. During the first week, pre-mobilization preparation will take place. In the second week, site visits, mobilization, and camp setup are scheduled. Drilling of 17 boreholes will occur during the third week, along with casing and gravel packing. Testing and development of the boreholes is scheduled for the fourth week before demobilization. The timeline is subject to change based on site conditions.
The document outlines a 4-week timeline for drilling 450mm diameter boreholes starting on October 10th, 2022. During the first week, pre-mobilization preparation will take place. In the second week, site visits, mobilization, and camp setup are scheduled. Drilling of 17 boreholes will occur during the third week, along with casing and gravel packing. Testing and development of the boreholes is scheduled for the fourth week before demobilization. The timeline is subject to change based on site conditions.
TIMELINE OF PROJECT- DRILLING OF 450MM DIAMETER BOREHOLES
Start Date: 10/10/2022
week 1 week 2 week 3 week 4
oct oct oct oct nov mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
assigned to: status:
Workshop PRE-MOBILIZATION PREP Pending
REPORTING OF G&G Team SITE VISIT Pending TESTING AND SITE MOBILIZATION / HOUSEKEEPING / Drilling Team EP 1-3 DRILLING OF 450mm BOREHOLE NOS 1-17 Pending CAMP SETUP DEMOBILIZATION Drilling Team EP 1-3 CASING AND GRAVEL PACKING OF BOREHOLE NOS 1-17 Pending
G&G - Mech Team TESTING AND DEVELOPMENT OF BOREHOLE NOS 1-17 Pending
! foot notes Final timeline may vary based on site conditions