Masbate City
Engineering Department
AND LOCAL) “
A proposal presented to
Engineering Department
2022- 2023
Thru: Jury
Dear Sir/Madam:
proposal for the 4 storey building Central Office designed for the fulfillment of
Sincerely Yours,
Endorsed By:
Adviser
Dear Sir/Madam,
for the 4 storey building Central Office upon the approval of our project, we are
dedicated to continue and improve our research on our project until it is ready to
Sincerely yours,
Adviser
ABSTRACT
A four storey central office for public and private a project that the
people of masbate surely needs since The current time is bursting with
their time and energy to do things in one and by that, they want an easy access
However, the four storey central office for private and local faces the
following problems: space and ventilation, customer’s traffic flow space, entry
and exit ways/ space planning, the availability of a central office within
masbate city area, and the proper requirement in cutting down trees for
structural improvement of the area and the Existing structures inside the lot
area.
This project aims to build a 4 storey central office within Masbate city
area located at Rosero street Masbate city with allotted area of 100 to 150
square meters. This project aims to provide both public and private office in
one place or infrastructure where you can find all different variants of offices
gives several benefits to the city and especially, to the people of Masbate
provides full service intended for the people in the community. A central office
bursting with exceptionally depleted and active individuals, where people want
to conserve their time and energy to do things in one and by that, they want an
When central office is established, the need for travel will decrease.
Costumers take time travel and incur travel cost when they shuttle from one
location to another. Having a central office will allow them to do all of their
advanced and must be able to accommodate the specific space and equipment
needs of the customers. This proposal aims to help customers manage their
time and effort. It will also improve the quality of life for the community.
However, the four storey central office for private and local faces the
following problems: space and ventilation, customer’s traffic flow space, entry
and exit ways/ space planning, the availability of a central office within
masbate city area, and the proper requirement in cutting down trees for
structural improvement of the area and the Existing structures inside the lot
area.
As for the researcher these kinds of problems are to be solved by the
and the proper allocation of space. A Well-built and designed interior and
exterior , not to cause traffic inside and outside of the said central office. The
entry and exit ways must be also well planned must be available in all sides of
the building where it is convenient for the customers to get in and out of the
building.
area.
This project aims to build a 4 storey central office within Masbate city
area located at Rosero street Masbate city with allotted area of 100 to 150
square meters. This project aims to provide both public and private office in
one place or infrastructure where you can find all different variants of offices
general public, the project aims to provide a single infrastructure that consists
of different offices to reduce the fare expenses of the commuters, and as well
for the vehicle owners to reduce their gas expenses. The project also aims to
the workers of the offices to provide the best working environment and spaces
where people, not just workers but the general public can unwind and rest or
relax after a period of work and errands. On the other hand the project will
The main objective of this project is to build and provide a well built and
designed 4 storey central office building for private and local. That will
office.
STATEMENT OF THE PROBLEM
3. Traffic congestion problems and lack of parking spaces within the offices or
SOLUTIONS
1. Building a 4 storey building that composed of public and private offices, the
said project will provide the citizens the comfort and convenience to their
different errands.
2. The 4 storey building will be that one place that will provide the convenience
3. The centralized office will lessen the traffic congestions within the city and
2000 President Joseph Estrada signed Republic act 8807 converting the
municipality of masbate into a component of city. In a plebiscite held later that
year Masbatenos voted 7,800 to 3200 in favor of cityhood laid on September
30, 2000 the commission on elections regional office in component city.
The project is a 4 storey building for public and private, the given lot
area has a phasing in different streets within Masbate city. Ibingay street ,
Capitol road and Rosero street with a total allotted area of 383.20 sq.m and
with the actual size of 150 sq.m for the said building. The 4 storey central
office project will be divided into different public and private offices.
FOUNDATION PLAN
`
CROSS SECTION BEAM
DESIGN PROPOSAL OF THE FOUR-STOREY BUILDING
ELAVATIONS
ZONING MAP