A-B-C-E-F-G
A-D-F-G
A-C-D-E-F-G
A-B-D-F-G
Feedback
The correct answer is: A-B-C-E-F-G
Considering the following information, what is the critical path?
Task A has a duration of 3 days and is a starting activity;
Task B has a duration of 6 days and has Task A as a predecessor;
Task C has a duration of 5 days and has Tasks A and B as predecessors.;
Task D has a duration of 4 days and has Task B as a predecessor;
Task E has a duration of 1 day and has Task C as the predecessor;
Task F has a duration of 6 days and has Tasks D and E as predecessors;
Task G has a duration of 4 days and has Tasks E and F as predecessors.
A-B-C-E-F-G
A-D-F-G
A-C-D-E-F-G
A-B-D-F-G
Feedback
The correct answer is: A-B-C-E-F-G
Product Owner
Share
Tweet
Share
The engine of the car is those who define the value. The wheels are those
who implement value.
The Product Owner connects the engine to the wheels by answering the
development team’s questions about the value they will implement. The
Product Owner is the team’s main source for insights into customer and
stakeholder motivation. The Product Owner helps the team know just what
the end customer or the enterprise is expecting of their products.
The Product Owner connects the wheels to the engine by feeding back
implementation issues to those who define the value. The definers of value
may be able to redefine it in a way that is simpler or less expensive or
even simply possible to implement. This also lets the definers of value
know when something is going to be delivered later or at higher cost due to
technical difficulties.