Project ‐ 118 PENTHOUSE ‐ LEVEL 33 & 34

FITOUT CIVIL & MEP WORKS

BILL NO. 2.6


BILL OF QUANTITIES LEVEL‐33 FF&E

ITEM DESCRIPTION UNIT QUANTITY RATE AED


ART WORK
Entrance, Foyer and lift lobby ‐33 & 34 Floor
Supply and installation of Artwork to wall as per Drawings and
Specification
Powder room ‐33 Floor
Supply and installation of Artwork to wall as per Drawings and
Specification
A Formal Living & Dining ‐33 Floor No
Supply & Installation of Art work by Employer complete in all
aspects in accordance with the drawings and specification and
B Engineer's Approval No
Framed Artwork in green tones
Family Living ‐33 Floor
Supply & Installation of Art work by Employer complete in all
aspects in accordance with the drawings and specification and
Engineer's Approval
Framed Artwork Picture Frames
Staircase
Supply & Installation of Art work by Employer complete in all
aspects in accordance with the drawings and specification and
Engineer's Approval
C Custom 3D Artwork Item
Artwork mounted in black frame
Library ‐33 Floor
Supply & Installation of Art work by Employer complete in all
aspects in accordance with the drawings and specification and
Engineer's Approval
Set of 4 painted artworks
Master Bedroom ‐2 ‐34 Floor
Supply and installation of Artwork to wall as per Drawings and
Specification
D Item
E Item

F Item
G Item

H Item

J No
CARRIED TO COLLECTION
NO. 2.6
‐33 FF&E

AMOUNT AED
Page 11 of 14 Bill 2.6 FF&E