JADWAL PELAKSANAAN

Bobot 24 Des- 31 Des - 7 Jan - 14 Jan - 21 Jan - 28 Jan - 4 Feb - 11 Feb - 18 Feb - 25 Feb - 4 Mar - 11 Mar - 18 Mar - 25 Mar - 1 Apr - 8 Apr - 15 Apr - 22 Apr - 29 Apr - 6 Mei - 13 Mei - 20 Mei - 27 Mei - 3 Jun - 10 Jun - 17 Jun - 24 Jun - 1 Jul - 7 8 Jul - 15 Jul - 22 Jul - 29 Jul - 4
No. Jenis barang/jasa 5 Agu
(%) 30 Des 6 Jan 13 Jan 20 Jan 27 Jan 3 Feb 10 Feb 17 Feb 24 Feb 3 Mar 10 Mar 17 Mar 24 Mar 31 Mar 7 Apr 14 Apr 21 Apr 28 apr 5 Mei 12 Mei 19 Mei 26 Mei 2 Jun 9 Jun 16 Jun 23 Jun 30 Jun Jul 14 Jul 21 Jul 28 Jul Agu
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35 M-36
II MTSN 1 MAMUJU

REKONSTRUKSI MASSA 1
PEKERJAAN TANAH DAN STUKTUR 0.33 0.08 0.08 0.08 0.08
Pek. Sloof, uk. 15X20 cm 0.13 0.04 0.04 0.04
Pek. Plat Lantai Beton t. 8 cm 0.76 0.19 0.19 0.19 0.19
Pek. Kolom K1, uk. 20x25 cm 0.20 0.07 0.07 0.07
Pek. Kolom K2, uk. 20x20 cm 0.05 0.03 0.03
Pek. Kolom KP, uk 15x15 cm 0.06 0.03 0.03
- Balok B1, uk. 15x20 cm 0.31 0.10 0.10 0.10
- Balok B2, uk. 15x20 cm 1.00 0.14 0.14 0.14 0.14 0.14 0.14 0.14

PEKERJAAN ARSITEKTUR 1.53 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
Pek. Pintu Type P1 termasuk Assesories 0.21 0.04 0.04 0.04 0.04 0.04
Pek. Jendela Type J1 termasuk Assesories 0.27 0.07 0.07 0.07 0.07
Pek. Jendela Type J2 termasuk Assesories 0.17 0.04 0.04 0.04 0.04

PEKERJAAN KELISTRIKAN 0.09 0.02 0.02 0.02 0.02

PEKERJAAN LAIN-LAIN 0.40 0.06 0.06 0.06 0.06 0.06 0.06 0.06