You are on page 1of 1

Project Name

Project Number

Date

100 SQUARE FEET

DIV DESCRIPTION COST / UNIT TOTAL

DIRECT EXPENSE

DIV 01 GENERAL REQUIREMENTS $ 50.00 $ 5,000.00

DIV 02 SITE WORKS $ 60.00 $ 6,000.00

DIV 03 CONCRETE $ 70.00 $ 7,000.00

DIV 04 MASONRY $ 80.00 $ 8,000.00

DIV 05 METALS $ 90.00 $ 9,000.00

DIV 06 WOOD AND PLASTICS $ 100.00 $ 10,000.00

DIV 07 THERMAL AND MOISTURE $ 110.00 $ 11,000.00

DIV 08 DOORS AND WINDOWS $ 120.00 $ 12,000.00

DIV 09 FINISHES $ 130.00 $ 13,000.00

DIV 10 SPECIALTIES $ 140.00 $ 14,000.00

DIV 11 EQUIPMENT $ 150.00 $ 15,000.00

DIV 12 FURNISHINGS $ 160.00 $ 16,000.00

DIV 13 SPECIAL CONSTRUCTION $ 170.00 $ 17,000.00

DIV 14 CONVEYING $ 180.00 $ 18,000.00

DIV 15 MECHANICAL $ 190.00 $ 19,000.00

DIV 16 ELECTRICAL $ 200.00 $ 20,000.00

TOTAL DIRECT EXPENSE $ 2,000.00 $ 200,000.00

GENERAL EXPENSE

GE-1 PROJECT STAFF $ 210.00 $ 21,000.00

GE-2 EQUIPMENT $ 210.00 $ 21,000.00

GE-3 OVERHEAD $ 210.00 $ 21,000.00

GE-4 TEMPORARY FACILITIES $ 210.00 $ 21,000.00

TOTAL GENERAL EXPENSE $ 840.00 $ 84,000.00

FEE 4% $ 11,360.00

TOTAL PROJECT COST $ 2,953.60 $ 295,360.00

** DOES NOT INCLUDE TAXES

Template created by Construction Repository (https://www.constructionrepository.com) in partnership with cnstrctr (https://www.cnstrctr.com)

You might also like