You are on page 1of 63

ACTIVITY SCHEDULECONSTRUCTION OF A URBAN HEALTH AND BIRTHING CENTRE, NAHA.

HONIARASUMMARY Date 14/12/2018 Rev A

AOLA AHC TRADE ACTIVITY SCHEDULE SUMMARY


Item Description of Work Unit Qty Amount

1 Preliminaries & General $1,750,235.00

2 Demolition/Repair $321,882.00

3 Groundworks $62,471.00

4 Concrete Work $185,500.00

5 Formwork $20,650.00

6 Reinforcement $70,014.00

7 Concrete Masonry $77,600.00

8 Metal Work $50,234.00

9 Metal Roofing & Wall Cladding $100,460.00

10 Windows $170,990.00

11 Carpentry $1,400,532.00

12 Doors $240,654.00

13 Hardware $145,235.00

14 Fittings, Fixtures & Equipment $345,500.00

15 Applied Finishes, Render & Textured $20,500.00

16 Tiling $140,500.00

17 Resilient Flooring $150,850.00

18 Painting $400,725.00

19 Joinery $48,600.00

20 Hydraulics $370,250.00

21 Electrical Services $700,100.00

22 Fire Services $60,600.00

23 Exterior Elements $360,560.00

24 Septic Tank, Absorption Bed & Distribution Box $553,350.00

25 Manhole $32,000.00

26 Solar (Covered under Electrical Services)

Sub Total $7,779,992.00

Shipping costs $477,399.00

Amount of overhead costs & profit margin


$1,142,450.00

Amount of Contingency (10%) $969,701.00

TOTAL LUMP SUM (Tender Price)

All Rates and item prices must be included by the Tenderer. Check arithmetically all amounts and sums to avoid any
calculation errors. Editing or changing this Activity Schedule will disqualify the tenderer. Prices for each trade
are to be filled in by hand on this document as originally received with the Tender Instructions. The Tenderer must
add any extra items if required for the successful completion of the project as intended by the Ministry of Health and
Medical Service.

486389755.xlsx Summary Page 1 of 63


Date 14/12/2018 Rev A

PRELIMINARIES & GENERAL


Item Description of Work Unit Qty Rate Amount
SCOPE OF WORK
The site of the works is Aola, Guadalcanal in Solomon Islands.
The scope comprises the refurbishment single level AHC building
medical and administration facilities, a new staff residence, two toilet note no costing
blocks, drainage works together with perimeter security fence

CONDITIONS OF TENDERING
Tenderers are referred to the Conditions of Tendering for full details note no costing
CONDITIONS OF CONTRACT
Tenderers are referred to the WHO/MHMS Conditions of Contract for full
details note no costing

PRELIMINARY AND GENERAL


Tenderers are referred to and specific requirements
Ausenco Kramer for full Preliminary & General items note no costing

The Preliminary & General sections are tabulated hereunder in order


that tenderers may allow for them should they consider it necessary. It
is deemed that these sections shall include for all sub sections:
1.0 Introduction

2.0 Background Information note no costing


3.0 Scope of Works
4.0 Project & Site Requirements
5.0 Contractor's Responsibilities
6.0 Technical Requirements

TENDER DOCUMENTS
Tenderers are particularly referred to the following documents:
(a) Contract
Agreement Form
note no costing
(b) Standard Form of Guarantee
(c) Drawings and Specification
(d) Trade Activity Schedule
SITE ACCESS & TEMPORARY PROTECTION
Site Access and Site Limitations shall be agreed with the Owner at the
first site meeting note no costing

Allow to provide temporary roads, driveways, tracks, etc as required and


remove on completion item $25,500.00

Allow for fully protecting existing driveways from all damage and
ensure clear access at all times to all properties serviced from the
item $25,000.00
driveways

Allow to provide screens, fences, hoardings, barricades and any other


temporary protection as may be required for the protection of the
public and workforce to plant and works around the site. The Contractor
will be confined to the area of the site as agreed with the Owner item $15,000.00

deleted
Allow to provide, or make provision security of the building site, site
facilities and storage yards . item $15,500.00

Provide all necessary temporary bracing and propping item $105,000.00


PERMITS, NOTICES & FEES
Allow to obtain all other permits, authorisations and approvals related to
the works and pay all fees and levies as applicable item $4,500.00

deleted
Allow to obtain all necessary consents and approvals for temporary
works item $4,500.00

Allow to comply with the Health and Safety Act note no costing
INSURANCES
Ensure insurance premiums for the Contract Works are in place note no costing
Ensure Public Liability Insurance is in place note no costing
Ensure insurance premiums for Workers Compensation are in place
note no costing

Allow to effect and maintain marine insurance for all plant and materials
being shipped as part of the works.The marine insurance is to be in the item $12,500.00
joint names of the Principal and the Contractor.

Allow to effect and pay premiums for any additional Insurance the
Contractor deems necessary or is not adequately covered item $12,500.00

SETTING OUT
Allow for setting out the work including providing instruments and
labour and for checking same item $3,500.00

GUARANTEES & WARRANTIES


The Contractor is referred to the Specification for Guarantee Individual materials Guarantees and
requirements and shall allow for all costs associated with providing such note Warranties are costed under the relevant
documentation description of works sheet
SITE SIGN BOARD
Allow to provide, erect and maintain a site signboard as clause
2.1.10.4 and 2.1.10.5 note no costing

SUPERVISION
Allow for supervision of the work including the period of maintenance item $50,000.00
SITE STAFF RESOURCES
Allow to provide a site staff resources breakdown note no costing
ADMINISTRATION
Allow for contract programming, updating and reporting note no costing
Allow for Management and Administration of the Contract works
including maintaining site diaries, progress payments and associated
statements, the processing of variation price requests and variations to
contract, RFI systems, photographic records of progress and any note no costing
other charges to which the Contractor considers he is entitled. No
additional administration costs will be entertained

486389755.xlsx Preliminaries & General Page 2 of 63


Date 14/12/2018 Rev A

Allow for all costs in relation to obtaining all documentation in


respect of guarantees, warranties, samples, tests, shop drawings,
underground services lay out drawings, 'as built ' drawings,
'maintenance manuals' and the like as required to be provided by the
relevant trades persons and issuing such documentation to the item $400,000.00
Principal's representative. Documentation to be
provided is identified in the appropriate trades included elsewhere

Allow for costs associated with all meetings item $5,000.00


Allow for the identification of all Contract or Personnel working on site as
required including photo identification note no costing

deleted
SHEDS, OFFICES & CONVENIENCE
Allow for providing as necessary temporary sheds, offices,
messrooms, sanitary accommodation and other temporary buildings
required for storage, and remove from site and make good on item $350,000.00
completion

TEMPORARY SERVICES
Allow for all temporary services necessary for the carrying out of this
contract including water, plumbing, air,power, lighting, telephones,
facsimile mchines, fire protection, safety and directional signage and
other services, pay fees for the duration of the Contract and
remove on completion. These temporary services shall be made item $250,000.00
available free of charge to all Sub-Contractors, Nominated
Sub-Contractors, Separate Sub-Contractors and the Principal

The cost of electricity from a permanent power supply used for


commissioning and equipment shall be borne by the Principal item $150,000.00

TEMPORARY WORKS
All ow for all temporary works as required for the construction of the
works including propping and strengthening existing structures and the item $250,000.00
like as necessary

PLANT & TOOLS


Allow for the provision and maintenance of all plant and tools item $55,000.00
SCAFFOLDING
Allow to provide all internal and external scaffolding and afford free of
charge the use of all scaffolding to sub-contractors, nominated sub-
contractors, separate contractors and the Owner for the efficient item $123,000.00
carrying out of their work

CRANAGE & HOISTING


Allow to provide lifting facilities and provide same free of charge to
sub-contractors, nominated sub-contractors, separate contractors and item $150,500.00
the Principal for the efficient carrying out of their work

MAKING GOOD & PROTECTION


Allow to safeguard the site, the works, materials and plant item $56,250.00
Allow for fire protection item $30,000.00
Allow for the maintenance and protection from damage during the
carrying out of the contract all contiguous property, of water, electricity
and gas companies, drainage authorities and similar undertakings. item $150,000.00
Include for making good all damage thereto

Allow to protect work from damage due to inclement weather. Include for
drying out the building if required to allow the works to proceed note no costing

Allow to respect the rights and convenience of all persons occupying


the premises during building operations note no costing

Allow for all costs associated with minimising the noise nuisance during
the building operations item $15,000.00

At completion of the Contract reinstate any adjacent property, foot


paths, roads, kerbs or other work damaged during the progress of work
and leave in a neat and tidy condition.This shall include making good to
public foot paths disturbed due to excavations or building item $250,000.00
operations

CLEANING UP SITE
Allow for the periodic collection and removal of all trade debris from the
site and for generally keeping the works clean item $85,430.00

Allow to clean up at the completion of the contract and hand the


building over clean.This includes removing all rubbish, cleaning all
plumbing fittings, and the like, cleaning and polishing all glass both
sides, cleaning all gutters and downpipes, oiling all locks, etc., and item $75,000.00
generally leaving the site clean and tidy

Al low for final cleaning of the building by a commercial cleaning


contractor prior to handing over to the Employer.This shall include
polishing all internal glass, cleaning toilet areas, cleaning and polishing item $860,000.00
floors and removing dust generally

Allow for periodic cleaning of the offices of site administration staff,


foreman, workmen's sheds, and sanitary conveniences note no costing

OTHER COSTS
Allow for all other costs incurred in site establishment item $17,000.00
Allow for all cost associated with provision of suitable accommodation
on for staff as required during the period of the Contract Works item $17,500.00

Allow for all cost associated with shipping and handling of goods,
materials and planti ncluding but not limited to payment of all port fees item $100,000.00
and transport related costs

Allow for Area Health Centre Signage - at front of building.Allow for


graphic design to be approved by Architect and Client item $15,000.00

DEFECTS LIABILITY
Allow to maintain the work for the Defects Liability period and in
accordance with the General Conditions of Contract item $25,300.00

QUALITY ASSURANCE
Allow for Quality Assurance including systems, plans, etc as required
note no costing

ATTENDANCE
Allow to attend upon all Sub-Contractors and Nominated Sub-
Contractors including cutting away for and making good after, allowing
use of plant, storage, messing, power, artificial light, etc and unloading item $250,000.00
and placing in position, as required

Allow for all costs incurred to attend upon any Separate Contractors
and the Principal in allowing them access to the site during the Contract note no costing

COSTS INCLUDED IN UNIT RATES


Allowances for the following are deemed included for within unit rates
within the Schedules unless separatetly identified and priced here under
:
( a) Travelling time, fares and board
( b) Additional overtime as may be required to complete the contract
( c ) Lost and wet time note no costing
( d) Cartage
( e) Duty on imported material
( f ) Government and Local taxes and levies

486389755.xlsx Preliminaries & General Page 3 of 63


Date 14/12/2018 Rev A

PROVISIONAL SUMS
There is no Provisional Sums secti ons of these schedules of quantities note no costing

ADDITIONAL PRELIMINARY & GENERAL


Allow for all other Preliminary and General items deemed necessary to note no costing
complete the contract works not covered else where by this trade
section

BILL OF QUANTITIES
The Bills of Quantities have generally been measured in accordance note no costing
with the Australian Standard Method of Measurement of Building
Works, Sixth Edition.
Tenderers are required to fully acquaint themselves with this method
and to allow in their pricing for the implementation of this met hod. Not
withstanding the Conditions of Contract no claims for method of
measurement issues will be entertained

All items are measured net as fixed in place, exclusive of laps .Unless note no costing
stated otherwise the description of each item shall include for supply,
conveyance, deliver y, unloading, storing, hoisting, all labour in setting
out , fittings and fixing in position, square cutting and waste, return of
packagings, use of plant and tools, over head charges and profit

The basic unit of length used in the Bill of Quantities is the millimetre note no costing
unless stated otherwise
Items marked (PROVISIONAL) are subject to note no costing
remeasurement and shall be adjusted according to the quantity
incoporated into the Works
The Contractor is required to price each individual item separately note no costing
within the Bills of Quantities when presenting the priced Schedules to be
used for the administration of the Contract
If items of work in the Bills of Quantities do not have a cost allowance note no costing
allocated to them by the Contractor then it will be deemed that eit er all
relevant costs associated with such items have been included
elsewhere within costs for other items of wor k; or that no remuneration
is required for such items

The following abbreviations have been used throughout these schedules


: m3 cubic
metres m2 square
metres m metres
mm millimetres
t tonnes
kg kilograms
No number (fin)
finished size
approx approximately RL
reduced level
B. S. British Standard CHS
cirular hollow section
RHS rectangular hollow section
SHS square hollow section UB
universal beam
UC universal column note no costing
EA equal angle
p. v . c . poly vinyl chloride
s . s . stainless steel
s . s . s . satin stainless steel
c . i . cast iron
m. s . mild steel
g. m. s . galvanised mild steel
galv . galvanised
c . p. chromium plated
s . c . p. satin chromium plated
d. p. c . dampproof course
I . D. internal diameter
O. D. outside diameter
r ad. radius
c . o. p. circular on plan
max . maximum
mi n. OF
USE minimum
SCHEDULE OF QUANTI TI ES F OR ORDERI NG
ave. average
PURPOSES
nom. nomi nal
Quantities, sizes or dimensions ass cheduled are as accurate as note
possible and net fixed insitu, but on no account should this document
be used as a basis for ordering any material or particular items as this
is not the intent of the document

Total Preliminaries & General Carried to Summary $1,850,235.00

486389755.xlsx Preliminaries & General Page 4 of 63


DEMOLITION & REPAIR
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for full note no costing
details of materials and work manship

Refer to the Preliminary and General section of this Bill


of Quantities and liaise with the Main Contractor in
respect of the responsibilities in note no costing
allowing costs for each item scheduled there in

METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured
inaccordance with the rules identified in Australian
Standard Method of Measurement of Building Works,
Sixth Edition subject to provisions identified
below.Tenderers are required to fully acquaint thems
elves with this method of measurement and allow in
their pricing for the implementation of this method. Not note no costing
withstanding the Conditions of Contract, no claims for
method of measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Bill of Quantities are deemed to
include the plural note no costing

deleted
Give all notices at start and completion of Demolition
works note no costing

Allow to comply with Demolished material classes table


as specified 5. 2. 1. 1 item $4,500.00
Allow for all temporary supports as specified 5. 3. 2. 1
item $4,500.00

Allow for weather, dust, and security


protection as specified clauses 5. 3. 3. 2,
5. 3. 3. 3, 5. 3. 3. 4,
item $4,500.00

DEMOLITION
Demolish old that ched roof house and foundations item $35,000.00
Demolish and remove reinforced concretes even flight
external stairs item $35,000.00
Make good ground surface where concrete
stairs and ramps removed m2 14 $1,500.00 $21,000.00
Demolish and remove reinforced concrete
ramp, stairs and suppots each 1 $2,500.00 $2,500.00
Demolish and remove verandah timber rails and posts,
make good m 4 $2,500.00 $10,000.00
Remove complete external wall and linings, include
for propping roof structure m 2 $1,500.00 $3,000.00
Remove existing window, infill opening with new timber
framing cladding, insulation and linings and trim each 7 $1,500.00 $10,500.00

Remove existing interior window, infill opening with new


timber framing cladding, insulation and linings and trim each 4 $1,500.00 $6,000.00

Form new opening in external wall for window, trim


and make good each 2 $1,500.00 $3,000.00

Form opening in external wall for new single door, trim


and make good each 1 $1,600.00 $1,600.00
Form opening in internal wall for new door, trim and
make good each 5 $1,050.00 $5,250.00
Completely remove internal wall including frames,
cladding and doors and windows, make good to floor
m2 32 $1,050.00 $33,600.00
and ceiling.( in 8 no)

Completely remove external door, frame and trim,infill


with timber framing and linings and trim each 2 $2,500.00 $5,000.00

Completely remove internal door, frame and trim, infill


with timber framing and linings and trim each 3 $2,500.00 $7,500.00

Remove external door and archi traves, adjust opening


to suit new door size,new archi traves each 1 $1,500.00 $1,500.00

Remove internal door and archi traves, adjust opening


to suit new door size, new archi traves each 4 $350.00 $1,400.00

486389755.xlsx Demolition & Repair Page 5 of 63


Item Description of Work Unit Qty Rate Amount
Dis connect pipe work and remove existing
sinks and timber benches with frames,make good each 3 $350.00 $1,050.00
damaged walls and floor

Disconnect and remove existing WC sanitary fittings each 3 $300.00 $900.00


Disconnect and remove existing wash hand basin,
complete each 3 $300.00 $900.00

Completely remove existing roofing including sheeting,


timber rafter sand purlins to Ablutions block m2 39 $500.00 $19,500.00

Cut roof over hand including sheeting and


framing for new extension wall and box gutter m2 5 $450.00 $2,250.00

Cut and remove existing roof, including rafters and


purlins for new roof extension m2 17 $450.00 $7,650.00

Remove existing internal wall linings m2 531 $95.00 $5,035.00


Remove existing ceiling linings and scotia m2 303 $150.00 $45,450.00
Remove existing floor coverings m2 292 $150.00 $43,800.00

Total Demoliton & Repair Carried to Summary $221,882.00

486389755.xlsx Demolition & Repair Page 6 of 63


TRADE ACTIVITY SCHEDULECONSTRUCTION OF A BIRTHING AND URBAN HEALTH CENTRE, NAHA. Rev A
Date 14/12/2018
HONIARACONCRETE WORKS

Item Description of Work Unit Qty Rate Amount


PREAMBLES
GENERAL
A Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for
full details of materials and work manship note no costing

Refer to the Preliminary and General section of this


Bill of Quantities and laise with the Main Contractor
in respect of the responsibilities in note no costing
allowing costs for each item scheduled there in

METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured
in accordance with the rules identified in the
Australian Standard Method of Measurement of
Building Works, Sixth Edition" subject to
provisos identified below.Tenderers are required to
fully acquaint themselves with this method of note no costing
measurement and allow in their pricing for the
implementation of this method. Not withstanding the
Conditions of Contract , no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES

All descriptions in this Bill of Quantities are deemed note no costing


to include the plural

All excavation has been measured net and no


allowance has been made for increase in bulk of
excavated materials and similarly all filling has
been measured as the net compacted volume in note no costing
place

Excavation for pipe work, drains, cables, has been


included under their respective trade sections note no costing

486389755.xlsx Ground Works Page 7 of 63


TRADE ACTIVITY SCHEDULECONSTRUCTION OF A BIRTHING AND URBAN HEALTH CENTRE, NAHA. Rev A
Date 14/12/2018
HONIARACONCRETE WORKS

Prices shall include for : Establishment expenses,


Excavating in all material encountered other than
solid rock Excavating inclose proximity to existing
buildings Trimming sides and for ming batters to
excavated faces Over break to excavations and
subsequent additional backfill Temporary stock piling
Dewatering and keeping excavations free from
water at all levels of excavaton Planking and strutting
to excavations not exceeding 1.5 metre deep
Levelling to grades,trimming and compacting
Forming batter stoboth excavated and filled areas
Filling and excavating building plat form irregularities note no costing
Forming rebates and sinkings in excavated face and
hardfill Back filling in layers and compacting,
Protection
Rock is defined as material which cannot
be ripped using an excavat or less than 20
tonnes

GENERAL
Allow for the cost of all Preliminary and General
items required after liais on with the Main Contractor item $5,000.00

Allow for giving notices, submittals and carrying out


inspections item $1,500.00

Allow for testing item $1,500.00


deleted
Allow for set out, locate and protect existing under
ground services & dust control item $3,500.00
Allow to protect existing buildings and
adjoinng properties note no costing

EXCAVATION
Excavation commencing at ground or reduced levels
and stock pile on site where directed note no costing

SITE WORKS
Clear Site of surface vegetation m2 222.8 54.00 $11,989.00
Surface Excavation
Strip ave. 100mm top soil and remove from site m2 222.8 54.00 $11,989.00
Excavation over Site
Cut and fill over site to give correct levels and profiles
m2 222.8 59.00 $11,989.00

Excavate for Piers & Footings


Excavate for piers m3 103 125.00 $6,500.00

486389755.xlsx Ground Works Page 8 of 63


TRADE ACTIVITY SCHEDULECONSTRUCTION OF A BIRTHING AND URBAN HEALTH CENTRE, NAHA. Rev A
Date 14/12/2018
HONIARACONCRETE WORKS

Excavate for slabs m3 21 $125.00 $2,625.00


BACKFILL

486389755.xlsx Ground Works Page 9 of 63


TRADE ACTIVITY SCHEDULECONSTRUCTION OF A BIRTHING AND URBAN HEALTH CENTRE, NAHA. Rev A
Date 14/12/2018
HONIARACONCRETE WORKS

Selected backfill
To pads and footings m3 68 135.00 $9,180.00
To slabs and ramps m3 20 135.00 $2,700.00
FILLING & HARDCORE
Bulk fill to site
Under slab m3 56 250.00 $14,000.00
50mm sand blinding
To pads and footings m2 1 250.00 $250.00
To slab m2 91 230.00 $7,500.00
PAPER & PLASTIC MEMBRANES
0. 2mm Polythened pc under slab
Ground slab and footings m2 132 250.00 $3,250.00
UNDERPINNING
Under pin existing wall for 50mm x 350mm
deep concrete footing each 1 $2,500.00

TERMITE PROTECTION
Provide installation certificate as specified note no costing
Buildings - Hand spray Binfenthrin as specified item $1,500.00

Buildings - Install trith or collars to slab penetrations item $1,500.00


Buildings - Apply Spectrum 2000SDC around
perimeter of Buildings item $2,500.00

Total Ground Works Carried to Summary $72,471.00

486389755.xlsx Ground Works Page 10 of 63


Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for full
note no costing
details of materials and work manship

Refer to the Preliminary and General section of this Bill


of Quantities and liaise with the Main Contractor in
respect of the responsibilities in allowing costs for each note no costing
item scheduled there in

METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the rules identified
in the Australian Standard Method of Measurement of
Building Works, Sixth Edition subject to provisos
identified below.Tenderers are
required to fully acquaint themselves with this method
of measurement and allow in their pricing for the note no costing
implementation of this method.Not with standing the
Conditions of Contract, no claims for
method of measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Bill of Quantities are deemed to
include the plural note no costing

Sizes and dimensions given are approximate only


and prices shall include for slight variances note no costing

486389755.xlsx Concrete Works Page 11 of 63


Prices shall include for : Establishment expenses
Stop end construction joints Castingin sleeves, bolts
etc Cutting away for and casting in traps,
floor outlets, sleeves, floor ducting, conduits ( other
than where specifically measured), pipes, ducts and
the like Mixing on or off site Hoisting or delivery to all
levels and all locations
Pumping including the cost of pump mix concrete
Placing, compacting and packing around bar
and fabric reinforcement, conduits and the like
F-Vibrating
G-Pouring breaks
H-Scabbling
J-Staging
K-Forming rebates, grooves, chases and the like for
dressing in flashings, roofing membranes and the like
L-Construction joints, isolation joints, sawcuts and the note no costing
like other than those specifically measured
M-Hydrophilic strips as required
N-Water stops other than those specifically measured
elsewhere
P-Secondary pours for infills and the like
Q-Blocking off proprietary flooring system voids as
requi r ed
R-Laying to falls and/or cross falls
S-Screeds and screeding of
T-Curing

Vibrating,Pouring breaks, Scabbli g, Staging,


Forming rebates, grooves, chases and the like for
dressing in flashings, roofing membranes and the like
Construction joints, isolation joints, sawcuts and the
like other than those specifically measured
Hydrophilic strips as required Water stops
other than those specifically measured elsewhere note no costing
Secondary pours for infills and the like Blocking off
proprietary flooring system voids as required
Laying to falls and/ or cross falls Screeds and
screeding Curing & Protection

Prices for proprietary flooring shall include for :


Shop drawings note no costing
Supply of all components, taking delivery, storing as note no costing
necessary, hoisting and placing in position

Temporary lifting eyes - Edge hangers note no costing


Seating including packers, wedges, plank edge
bearing strips, mortar bed and the like note no costing

Packers and formwork closers as necessary between


flooring units and concrete / structural steel beams note no costing

486389755.xlsx Concrete Works Page 12 of 63


Straight, raking and circular cutting as required,
including cutting components to suit site conditions note no costing

486389755.xlsx Concrete Works Page 13 of 63


Supply and removal of all temporary supports note no costing
Forming penetrations note no costing
GENERAL
Allow for giving notice and inspections item $500.00
Allow for samples and testing item $500.00
Allow for guarantees item $500.00
CONCRETE

15Mpa concrete in 50mm thick blinding m3 3 2,500.00 $7,500.00


25Mpa concrete in pads, tie beams & footings m3 16 2,500.00 $40,000.00
25Mpa concrete in 190mm thick foundation wall m3 1 3,000.00 $3,000.00
25Mpa concrete in stub columns m3 2 2,500.00 $5,000.00
25Mpa concrete in circular columns m3 3 2,500.00 $7,500.00
25Mpa concrete in beams m3 23 2,500.00 $57,500.00
32Mpa concrete in 125mm thick path & thickening m3 5 3,000.00 $15,000.00
32Mpa concrete in 150mm thick ramp & thickening m3 7 2,500.00 $17,500.00
32Mpa concrete in suspended stairs & attached beams
m3 2 3,500.00 $7,000.00
32Mpa concrete in 150mm slab & thickening m3 13 500.00 $6,500.00
32Mpa concrete in beam m3 1 3,500.00 $3,500.00
SURFACE FINISHES
Power float finish m2 25 1,500.00 $37,500.00
Broom finish to slabs / paths m2 90 500.00 $45,000.00
Finish to 300mm wide stair treads m 21 1,500.00 $31,500.00

Total Concrete Works Carried to Summary $285,500.00

486389755.xlsx Concrete Works Page 14 of 63


Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for full
note no costing
details of materials and workmanship

Refer to the Preliminary and General section of this Bill


of Quantities and liaise with the Main Contractor in
respect of the responsibilities in allowing costs for each note no costing
item scheduled there in

METHOD OF MEASUREMENT

This Bill of Quantities has generally


been measured in accordance with the
rules identified in the Australian
Standard Method of Measurement of
Building Works, Sixth Edition subject to
provisos identified below. Tenderers are
required to fully acquaint themselves
note no costing
with this method of measurement and allow
in their pricing for the implementation
of this method. Not withstanding the
Conditions of Contract, no claims for
method of measurement issues will be
accepted

MEASUREMENT & PRICES


All descriptions in this Bill of
Quantities are deemed to include the note no costing
plural

486389755.xlsx Formwork Page 15 of 63


Item Description of Work Unit Qty Rate Amount
PREAMBLES
Prices for formwork shall include for :
Fabricating, setting in position and
stripping
Propping and supporting to all
heights, centering, bracing, battens, and
any other supports
Propping and supporting in confined
situations
Fillets to form chamfers in columns,
beams, etc
Forming rebates and sinkings unless
otherwise measured note no costing
Straight and raking cutting
Cutting around projecting
reinforcement, pipes, bolt set c
Temporary inspection or clean out
openings, Release agents, Cleaning and treating,
Cutting backties and generally
making good after removal with cement
mortar

FORMWORK
Sides of pads, tie beams and footings m2 60 360.00 $21,600.00
Side of stub column m2 60.7 360.00 $21,600.00
CLASS 2 FORMWORK
175mm slab edge formwork m 29 360.00 $5,400.00
240mm high slab sides m 10 56.00 $560.00
275mm slab edge formwork m 40 62.00 $2,480.00
300mm high slab edge formwork m 75 56.00 $4,200.00
Sloping Soffit of stair m 20 62.00 $1,240.00
Profiled stair side m 5.1 56.00 $280.00
160mm high stair tread m 11 56.00 $616.00
Column sides, circular m 20 360.00 $360.00
Side of beam m 1.8 360.00 $360.00
SUNDRY
Form dowelled construction joint m 1.7 56.00 $56.00
Form 20 x 10mm slab rebate, fill with
approved sealant m 27 56.00 $1,512.00

Total Formwork Carried to Summary $25,650.00

486389755.xlsx Formwork Page 16 of 63


REINFORCEMENT
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to the
Specifications and Drawings for full note no costing
details of materials and workmanship
Refer to the Preliminary and General
section of this Bill of Quantities and
liaise with the Main Contractor in
respect of the responsibilities in note no costing
allowing costs for each item scheduled
therein

METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in the Australian
Standard Method of Measurement of
Building Works, Sixth Edition subject to provisos
identified below. Tenderers are required to fully
acquaint themselves with this method of
measurement and allow in their pricng for the note no costing
implementation of this method. Not withstanding
the Conditions of Contract, no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Bill of
Quantities are deemed to include the plural

All reinforcing steel herein has been


measured from the structural drawings
issued for tender and prices shall include for all note no costing
and any subsequent additional cost resulting from
alternative methods of measurement
including bar bending schedules. Any remeasures
resulting from variations will
only be assessed from contract drawings

486389755.xlsx Reinforcement Page 17 of 63


All reinforcing steel herein has been
measured from the structural drawings
issued for tender and prices shall
include for all and any subsequent
additional cost resulting from
alternative methods of measurement note no costing
including bar bending schedules. Any
remeasures resulting from variations will only be
assessed from contract drawings

All bars are measured net length with


allowance for hooks and laps as required note no costing

All bars have been measured together


irrespective of length and where actual
lengths have not been shown laps have note no costing
been allowed at 8000 intervals

Bars described as stirrups include stirrups, binders,


links, ties or any bar with multiple bends in a short
length linking bars at right angles to the stirrups note no costing

Mesh has been measured net - no allowance


made for laps note no costing

Weights have been calculated from the


standard weights as given by the
manufacturers and price rates shall note no costing
include for any v ariances considered
necessary

Prices shall include for :


Est ablishment expenses
Preparing bending schedules
Rolling margins
Cutting, hooking, bending and fixing
Bars of special length
Hoisting and delivering to all levels
in all locations
Welded joints, welding to steel work
Tie wires, chairs and saddles, spacers and
formers note no costing
Cutting bars or mesh at construction or sawcut
joints
Raking and circular cutting of mesh
Cranking and bending mesh
Cutting holes through or not ching mesh
Protection

GENERAL
Allow for inspections item $500.00
Allow for samples and testing item $500.00
Allow for Quality Assurance item $1,500.00
FOUNDATION ON PADS/FOOTINGS
HD16mm dia bar kg 661 30.00 $19,830.00
D 16mm dia bar kg 373 30.00 $11,290.00
D12mm dia bar kg 45 30.00 $1,350.00
D12 starter bar kg 99.1 30.00 $2,970.00
D12mm dia stirrup kg 139.7 30.00 $4,170.00
D10mm ties kg 45 10.00 $450.00
GROUND SLABS, RAMPS & THICKENINGS
SL 92 mesh m2 48 56.00 $2,688.00
SL 82 mesh m2 46 56.00 $2,576.00
D12mm dia bar kg 461 30.00 $13,830.00
D10 ties kg 130 10.00 $1,300.00

486389755.xlsx Reinforcement Page 18 of 63


D10 trimmer bar kg 74 10.00 $740.00
BEAM
D16mm dia bar kg 13 30.00 $3,900.00
D12mm dia stirrups kg 15 30.00 $450.00
COLUMNS
N16mm dia bar kg 229 30.00 $6,870.00
R10mm dia ties kg 29 10.00 $290.00
STAIRS
D12mm dia bar kg 113 30.00 $3,390.00
D10mm dia ties
kg 14 30.00 $420.00

Total Reinforcement Carried to Summary $79,014.00

486389755.xlsx Reinforcement Page 19 of 63


CONCRETE MASONRY
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to the
Specifications and Drawings for full details of materials note no costing
and workmanship

Refer to the Preliminary and General


section of this Bill of Quantities and
liaise with the Main Contractor in
respect of the responsibilities in note no costing
allowing costs for each item scheduled
therein

METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in the Australian
Standard Method of Measurement of
Building Works, Sixth Edition subject to
provisos identified below. Tenderers are
required to fully acquaint themselves with this method note no costing
of measurement and allow in their pricing for the
implementation of this method. Not withstanding the
Conditions of Contract, no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Bill of
Quantities are deemed to include the note no costing
plural
Prices shall include for :
Establishment expenses
Lintel, open end, bond beam, end, half height and other
standard blocks unless otherwise measured
Control and expansion joints
Seismic movement joints
Forming openings for vents and the like
Temporary bracing and propping
Square cutting
Forming all angles and intersctions
note no costing
Closing cavities
Fair ends
Laying and cutting to bond
Jointing and pointing as specified
Fair face finish
Damp proof courses
Bonding mesh

486389755.xlsx Concrete Masonry Page 20 of 63


Clean- out ports, weep and vent holes
Wedging and pinning to soffits
including head restraints
Sealants and sealing strips
Forming chases, chamfers and the like
Cutting or leaving holes, rebates, recesses or openings
note no costing
and for building- in pipes, conduits, sleeves, ducts,
gratings, grilles, steel work, bolts and the like
Protection

Prices for reinforcing steel shall


include for :
Preparing bending schedules
Rolling margins
Supplying, cutting, hooking, bending
and fixing complete note no costing
Bars of special length Tie
wires, chairs and saddles
Protection

All bars are measured net length with


allowance for hooks and laps as required note no costing

486389755.xlsx Concrete Masonry Page 21 of 63


All bars have been measured together
irrespective of length and where actual
lengths have not been shown laps and note no costing
hooks have been allowed at 8000 intervals

Weights have been calculated from the


standard weights as given by the note no costing
manufacturers
GENERAL
Allow for inspections item $500.00
Allow for construction joints item $3,500.00
Allow for test and testing and keeping records item $2,500.00
Allow for Quality Assurance item $2,500.00
BLOCKWORK
Class1 concrete blocks laid in staggered
pattern with 12.5 MPa mortar
150mm thick blockwork to foundations m2 10 $260.00 $2,600.00
150mm thick blockwork to external wall m2 27.5 $260.00 $7,020.00
200mm thick blockwork to external wall m2 27.5 $260.00 $7,020.00
150mm thick blockwork to internal wall m2 57 $260.00 $14,820.00
20Mpa grout filling to 150mm block wall m2 7.8 $260.00 $1,820.00
20Mpa grout filling to 200mm block wall m2 57 $260.00 $14,820.00
REINFORCING STEEL
D12 Reinforcing steel to blockwork kg 1350 $30.00 $40,500.00

Total Concrete Masonry Carried to Summary $87,600.00

486389755.xlsx Concrete Masonry Page 22 of 63


METAL WORK
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to the
Specific ations and Drawings for full note no costing
details of materials and workmanship

Refer to the Preliminary and General


section of this Bill of Quantities and
liaise with the Main Contractor in
respect of the responsibilities in allowing costs for note no costing
each item scheduled
therein

METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in Australian Standard
Method of Measurement of Building Works, Sixth
Edition subject to provisos
identified below. Tenderers are required
to fully acquaint themselves with this
note no costing
method of measurement and allow in their pricing
for the implementation of this method. Not
withstanding the Conditions of Contract, no claims
for method of measurement issues will be
accepted

MEASUREMENT & PRICES


All descriptions in this Bill of Quantities are
deemed to include the note no costing
plural
All structural steel work including
rectangular and square hollow sections
has been measured n `tonnes ' unless note no costing
otherwise stated
All connections/plates including base
plates, cap plates, splices, stiffeners, purlin cleats,
gussets and the like have note no costing
been grouped together and described as
attached connections '

Weights have been calculated from the


standard weights given by the
manufacturers and prices shall include note no costing
for any adjustment considered necessary

486389755.xlsx Metal Work Page 23 of 63


Prices shall include for :
Establishment expenses
Fabrication, supply and delivery to site
Storing on site, hoisting and erection in position
complete
Preparation, cutting, notching,
machining, grinding, drilling, etc
Splice joints as required
Shop welding, Site welding
Holes and slotted holes
Connection bolts including flat or note no costing
tapered washers
Temporary bracing or strutting, temporary erection
bolts, steel wedges
under baseplates, etc
-Touching up shop priming, galvanising
or other finish where damaged after
installation, Protection

Prices shall include for fabricating in


convenient lengths for ease of note no costing
transportation and erection

Prices for Trubolts, Dynabolts and the


like shall include for drilling note no costing
structural elements

GENERAL
Allow for the cost of all Preliminary and
General items after liaison with the Main item $1,500.00
Contractor

486389755.xlsx Metal Work Page 24 of 63


Allow for inspections item $1,500.00
Allow for Quality Assurance item $1,500.00
Allow for shop drawings item $1,500.00
BRACKETS
440 x 100 x 12mm thick galvanised plate
cast into pier each 19 $150.00 $2,850.00
M16- G8. 8/ S galvanised bolt 190mm long each 38 $50.00 $1,900.00
BRACING
16mm dia galvanised threaded cross
bracing ( BR1) m 1 $50.00 $50.00
M16 - G4. 6/ S bolt x 125mm long each 18 $50.00 $900.00
Pryda cyclone strap MPQH56, 450mm long no 38 $60.00 $2,280.00
Pry da knuckle nail plate MP10R10 each 49 $65.00 $3,185.00
125 x 125 x 10mm thick x 100mm long
galvanised equal agle each 32 $65.00 $2,080.00
125 x 125 x 10mm thick x 150mm long
galvanised equal angle each 8 75.00 $600.00

400 x 100 x 10mm galvanised plate, splay


cut one end each 22 75.00 $1,650.00

275mm l ong x 150 x 150mm x 10mm


galvanised angle, splay cut one end each 14 65.00 $910.00

275mm long x 51 x 51mm x 5mm galvanised


angle, splay cut one end each 14 65.00 $910.00

M12 - G4. 6/ S x 75mm long bolt each 134 30.00 $4,020.00


M12 - G4. 6/ S x 100mm long bolt each 78 30.00 $2,340.00
M12 - G4. 6/ S x 125mm long bolt each 59 30.00 $1,770.00
ANT CAPS
Stainless steel ant caps to 250 x 250mm piers,
include for edge fold down each 19 450.00 $8,550.00

BALUSTRADE
50mm dia galvanised handrail, with paint
finish, on and including 40mm square
balustrade posts, complete with 100 x m 49 450.00 $45,300.00
50mm galvanised RHS kerb rail

Form 300 x 330mm end to 50mm dia handrail each 10 500.00 $5,000.00
1000mm high 20mm dia galvanised steel
tube top, middle and bottom rail balustrade with
20mm dia vertical rails and 40 x 40mm galvanised
m 13 500.00 $12,500.00
posts to sloping stair/ramp and 50mm dia
galvanised handrail

1000mm high 20mm square galvanised steel


balustrade, with 40 x 40mm galvanised
posts to landing and 50mm dia galvanised
m 48 500.00 $24,000.00
steel handrail and 100 x 50mm galvanised
RHS kerb rail

0.55mm BMT x 200mm high colorbond Z flashing


m 1 500.00 $3,500.00

Total Metal Work Carried to Summary $650,234.00

486389755.xlsx Metal Work Page 25 of 63


METAL ROOFING & WALL CLADDING
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to the Specifications and Drawings for
full details of materials and workmanship
Refer to the Preliminary and General section of this Schedule of
Quantities and liaise with the Main Contractor in respect of the note no costing
responsibilities in allowing costs for each item scheduled therein

Refer to the Preliminary and General section of this Schedule of


Quantities and liaise with the Main Contractor in respect of the
responsibilities in allowing costs for each item scheduled therein note no costing

METHOD OF MEASUREMENT
This Schedule of Quantities has generally been measured in
accordance with the rules identified in Australian Standard
Method of Measurement of Building Works, Sixth Edition NZS
4202:1995 `Standard
Method of Measurement of Building Works' subject to provisos
identified below.
Tenderers are required to fully acquaint themselves with this note no costing
method of measurement and allow in their pricing for the
implementation of this method.
Not withstanding the Conditions of Contract, no claims for method
of measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are deemed to
include the plural note no costing

Sizes given are approximate only and


prices shall include for slight variances note no costing

The pitch and height of roofing above


ground floor level has not been stated
and prices shall include for working at note no costing
all heights and levels

486389755.xlsx Metal Roofing & Wall Cladding Page 26 of 63


Prices shall include for: Establishment
expenses
Fixing in accordance with manufacturers instructions
All fixing clips, screws, button punching, etc
Laps, turn -ups, turn- downs, lipping, folding, capping, stopping
ribs or seams
Penetrations, flashings, sealants, etc all services pipework, ducts
and the like
Expansion joints, Colour matched fasteners and / or touching up note no costing
exposed fixings
Protective treatment to laps and cut edges, Sealants and seals,
Separation strips
Sheets of all lengths, Straight and raking cutting
Cleaning down on completion
Protection

Prices for gutters, rainwater heads, downpipes and the like shall
include for all fixing brackets, fixing clips, ends, jointing, sealants, note no costing
connections including connections to drains, etc
GENERAL
Allow to supply maintenance data item $500.00
Allow for tests and testing item $500.00
Allow for guarantees and warranties item $500.00
Allow to liaise with the Electrical Contractor and provide facilities
for a roof earthing system item $2,500.00

ROOF CLADDING
COLORBOND ULTRA Steel Roofing
17 degree roof cladding fixed to timber purlins m2 120 145.00 $17,400.00
7 degree roof cladding fixed to timber purlins m2 51 145.00 $7,395.00
Reflective thermal insulation membrane, blanket type thermal
insulation and wire safety mesh m2 171 145.00 $24,795.00

ROOF UNDERLAYS
0.48BMT COLORBOND ULTRA Steel Flashing
500mm girth twice bent on fascia flashing m 36 120.00 $4,320.00
430mm girth thrice bent colorbond ridge flashing m 10 120.00 $1,200.00
180mm girth underflashing twice bent including seal into timber
chase m 10 120.00 $1,200.00

486389755.xlsx Metal Roofing & Wall Cladding Page 27 of 63


DOWNPIPES
100 dia. PVC downpipe m 54 450.00 $24,300.00
100mm dia bend each 18 450.00 $2,700.00
150 dia. PVC downpipe fixed to concrete m 108 150.00 $16,200.00
150mm dia bends each 36 150.00 $5,400.00
COLORBOND ULTRA STEEL GUTTER
200 x 100mm eaves Gutter m 87 150.00 $13,050.00
Forms top end to gutter each 20 150.00 $3,000.00
Form 100mm dia downpipe outlet each 9 150.00 $1,350.00
Form 150mm dia downpipe outlet each 18 150.00 $2,700.00
BOX GUTTER
460mm girth thrice bent 0. 55 BMT zinc alume gutter lining, one
edge sealed into timber chase m 27 400.00 $10,800.00

Forms top end to box gutter each 4 400.00 $1,600.00


SUNDRIES
Allow for pre- moulded closure to roofing iron m 35 $450.00 $15,750.00
Form opening through roofing for 80mm dia pipe no 2 450.00 $900.00
ROOF ACCESS SYSTEM
Safety link anchor points no 2 450.00 $900.00
Safety link Handrail Header kit item 1 $4,500.00

Total Metal Roofing & Wall Cladding Carried to Summary $163,460.00

486389755.xlsx Metal Roofing & Wall Cladding Page 28 of 63


WINDOWS
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings
for full details of materials and workmanship note no costing

Refer to the Preliminary and General


section of this Bill of Quantities and
liaise with the Main Contractor in
respect of the responsibilities in note no costing
allowing costs for each item scheduled
therein

METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in Australian Standard
Method of Measurement of Building Works,Sixth
Edition subject to provisos identified below.
Tenderers are required to fully acquaint
themselves with this
method of measurement and allow in their note no costing
pricing for the implementation of this
method. Not withstanding the Conditions of
Contract, no claims for method of
measur ement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are
deemed to include the plural note no costing

Sizes given are approximate only and


prices shall include for slight variances note no costing

Prices for automatic sliding doors shall include for


all running gear, door activation equipment and
note no costing
connections to power supply

Prices shall include for :


Establishment expenses, Fabrication, delivery to
site, storing, assembling and fixing into position,
Fixing to all backgrounds, Separator strips
between dissimilar metals, Marking and note no costing
labelling,Surface finish or coating to all
components including touching up on completion

Glass and glazing to windows, doors and vision


panels including all cleats, beads, gaskets, seals,
wedges, silicone joints, back painting, raking and
circular cutting, Manifestations and other safety
markings as required unless measured herein, All
associated sub- frames, support brackets, angles,
etc including staining where required
Preparation of adjoining surfaces
Reveal sub- linings, All associated flashings,
cilltrays, facings, rainshields, weather bars and note no costing
seals, mouldings, etc. including cutting or notching
adjoining surfaces as required, All seal ants,
caulking and pointing with backing rods as
necessary, All fire and acoustic seals as required

All trim angles as detailed, All hardware required


including special locking with card key operation,
door seals and master keying, Allowance for
seismic, wind and thermal movement, Cleaning note no costing
down on completion, Protection

GENERAL

486389755.xlsx Windows Page 29 of 63


Allow for shop drawings item $500.00
Allow for guarantees item $500.00
EXTERNAL WINDOWS
All windows shall have insect netting and
amplimesh anti crime screen and frame
Glass to Louvres shall be 152mm high 6mm thick
toughened safety clear Glass
Rates for louvres shall include for all necessary note no costing
F17 local hardwood "Akwa" timber frame and trim,
Breezway Easy screen "Altair " Louvre
Window - Multi Bay

511mm high x 2090mm window louvre Single


Bay window ( W. 05, W. 16, W. 50) no 4 600.00 $2,400.00

651mm high x 750mm window louv re Single Bay


window ( W. 21, W. 24) no 2 550.00 $1,100.00

651mm high x 1395mm window louvre Single


Bay window ( W. 05, W. 16, W. 22, W. 38, W. no 7 650.00 $4,550.00
42, W. 48, W. 49)

651mm high x 2090mm window louvre Single


Bay window ( W. 46) no 1 1,200.00 $1,200.00

1491mm high x 800mm wide Breezeway


Ëasi clean " Alt air " Louvre window - single no 2 1,200.00 $2,400.00
bay ( W. 31, W. 33)
1491mm high x 1395mm wide Breezeway
Ëasi clean " Altair " Louvre window - multi bay
(W. 39, W. 40, W. 41, W. 43, W. 44, no 7 1,250.00 $8,750.00
W. 45, W.47)

1491mm high x 2090mm wide Breezeway


Ëasi clean "Altair " Louvre window - multi bay
no 1 2,500.00 $2,500.00
(W.35)

1100mm high x 660mm wide Aluminium frame


sliding glass dispensing window (W. 37) each 1 3,500.00 $3,500.00

1100mm high x1500mm wide Aluminium frame


sliding glass dispensing window (W. 36) each 1 4,500.00 $4,500.00

EXTERIOR WINDOWS MAINTENANCE


Clean and make good frames, replace any
missing glass louvres, install new insect screen note no costing
and Amplimesh security mesh

651mm high x 750mm wide Breezeway


Ëasi clean "Altair " Louvre window - single no 4 7,500.00 $30,000.00
bay (W. 17, W. 18, W. 19, W. 20, )

651mm high x 995mm wide Breezeway


Ëasi clean " Alt air " Louvre window -multi bay ( W. no 1 7,200.00 $7,200.00
25)
651mm high x 1395mm wide Breezeway
Ëasi clean " Alt air " Louvre window -
no 5 6,500.00 $32,500.00
multi bay ( W. 03, W. 04, W. 12, W. 13, W. 27)

1491mm high x 1395mm wide Breeze way


Ëasi clean " Altair " Louvre window -
multi bay ( W. 01, W. 02, W. 06, W. 07, W. 08,
W.09, W. 10, W. 11, W. 14, W. 15, W. 28, W. no 15 3,500.00 $52,500.00
29,W. 30, W. 32, W. 34)

1491mm high x 2090mm wide Breezeway


Ëasi clean " Altair " Louvre window -multi bay
no 1 12,000.00 $1,200.00
( W. 23)

Total Windows Carried to Summary $190,990.00

486389755.xlsx Windows Page 30 of 63


CARPENTRY
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for full note no costing
details of materials and workmanship

Refer to the Preliminary and General section of this Bill


of Quantities and liaise with the Main Contractor in
respect of the responsibilities in allowing costs for each note no costing
item scheduled therein

B METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured in
accordance with the rules identified in Australian
Standard
Method of Measurement of Building Works,Sixth Editi
on subj ect to provisos identified below. Tenderers are
required to fully acquaint themselves with this method
of measurement and allow in their pricing for the note no costing
implementation of this method. Not withstanding the
Conditions of Contract, no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of
Quantities are deemed to include the plural note no costing

Sizes given are approximate only and


prices shall include for slight variances note no costing

Timber sizes stated are 'nominal sizes '.


The descriptions do not differentiate between rough
sawn and gauged sizes and the Contract or shall allow note no costing
for all costs associated with this

Passings in timber framing have not been


deducted note no costing

486389755.xlsx Carpentry Page 31 of 63


Items are fixed to timber unless otherwise stated
note no costing

Timber partitions have been measured in square


metres with no deduction for openings unless such note no costing
openings are full height

Metal stud partitions have been measured


in linear metres stating the height over all note no costing

Prices for members fixed to concrete, steel, etc . , shall


include for d. p. c . and specialised fixings as required
including note no costing
drilling the base element

Prices shall include for :


Establishment expenses,Nails, Z- nails, adhesive,
screws, bolts, etc
Priming, galvanising or other finishes
where required and touching up after installation

Waste, Labours forming rebates,


splays, notches, grooves, throats, rounded
edges and the like note no costing
Boring holes, drilling concrete and steel, counter
sinking and the like
Wedges, packings, blocks and the like
Mitres, bends, angl es scribing,
returned ends, tongues, grooves, laps,
and all joints as required
Protection

Prices for timber partitions shall


include for : All
framing as required including plates, studs, noggings,
packers, lintels and the like,Trimming to openings,
recesses and the like, Cutting and fitting into adjacent
surfaces, Fixing to all backgrounds encountered note no costing
including concrete, masonry and steel work, Dpc and
specialised fixings as required including drilling
structural elements

Prices for metal stud partitions shall include for :


All necessary plates, starters , end
studs, corner studs, junction studs, intermediate studs,
boxed studs, noggings, beams, brackets, angles,
cleats, top hat sections, etc., to form a
note no costing
rigid partition Control joints, bracings, deflection
heads, etc, Positioning of framing to suit sheet sizes,
Painting welds with approved zinc rich paint

486389755.xlsx Carpentry Page 32 of 63


Forming penetrations or openings as
necessary for light fittings, sanitary fittings, service
pipes, fittings, wiring, etc, Fixings complete with all
necessary bolts, screws, etc. to all back grounds note no costing
All waste, boring holes, cutting, notching, wedging,
packing and the like, Protection

Prices for linings and sarking shall include for:


Flush stopping unless
otherwise stated Stopping to fixings, joints edges and
external corners Stopping for paint finish unless
otherwise stated Sealants, sealing strips, backing tape
and rods, etc. including fire and acoustic ratings
Flashings, sealants, etc .to ensure water tightness note no costing
Cutting and fitting into adjacent surfaces Cutting, fitting
and not ching around brackets, ducts, pipes and other
items
and sealing on completion including fire
and acoustic ratings

Laying to falls and crossfalls Narrow widths, Straight


and raking cutting Forming angles, stop ends and the
like J moulds and other trim unless other wise note no costing
measured Control / expansion joints "

Prices for flashings shall include for folding to required


profile, laps , angl es , ends, jointing, dressing,
sealants and sealing in to rebates, chases, etc . and note no costing
fixing to all backgrounds

GENERAL
Allow for the cost of all Preliminary and
General items after liais on with Main Contractor
item $1,500.00
Allow for two 400 x 400mm samples item $2,500.00
All ow for shop drawings item $1,500.00
Allow for nail plates, joist hangers, strapping, brackets,
etc item $25,000.00

Allow for bolt fixings including


Dynabolts, Trubolt sand the like item $12,000.00

All w for bracing as required item $13,000.00


Allow for additional noggings, framing and the like as
required for installing fixtures, fittings, services and item $25,000.00
equipment, etc .

486389755.xlsx Carpentry Page 33 of 63


Allow for guarantees and warranties item $1,500.00
Allow for builders work for services item $1,500.00
SUB FLOOR FRAMING
200 x 75mm F17 HWD bearer ( BR) m 41 105.00 $4,305.00
150 x 50mm F17 HWD floor joist ( FJ 1) m 181 $50.00 $9,050.00
150 x 50mm F17 HWD blocking m 11 50.00 $550.00
150 x 50mm F17 HWD wall plate m 2 $50.00 $100.00
M10 - 4. 6/ s bolt each 20 $52.00 $1,040.00
M12 galvanised bolts 100mm long each 20 $52.00 $1,040.00
M12 - G4. 6/ S bolts 175mm long each 8 $30.00 $240.00
5mm dia stainless steel Z nails, 100mm each 162 $55.00 $8,910.00
Pryda Steel strap Knuckle nail plate MP4R5 no 16 $55.00 $880.00
ROOF FRAMING

125 x 50mm F17 rafter ( RF1) m 141 $48.00 $6,768.00


175 x 75mm F17 roof beam ( RB) m 9 $55.00 $495.00
175 x 75mm cross beam ( CB3) m 27 $55.00 $1,485.00
150 x 75mm F17 knee brace ( KB) m 15 $48.00 $720.00
70 x 50mm F 17 Purlins ( P1) m 293 $48.00 $14,064.00
175 75mm under purlin beam m 18 $55.00 $990.00
200 x 75mm cross beam m 5 $55.00 $275.00
Pryda HXB1 roof cross brace m 114 46.00 $5,244.00
Pryda HXB1 roof cross brace each 246 46.00 $11,316.00
Pryda rafter Cyclone strap MPQHS6, 550mm long each 24 46.00 $1,104.00
EXTERNAL WALL FRAMING
100 x 50mm hard wood timber framing m2 66 45.00 $2,970.00
100 x 100mm timber post m 45 45.00 $2,025.00
220mm long M12- G4. 6/ S bolts each 8 45.00 $360.00
Pryda VXB1 wall bracing m 65 45.00 $2,925.00
Steel Z nails each 15 45.00 $675.00
EXTERNAL LININGS
150 x 25mm rusticated profile weather boards to walls
m2 70.6 52.00 $3,640.00

246mm wide 16mm thick marine plywood


substrate m2 70.6 52.00 $3,640.00

6mm fibre cement sheeting, flush jointed,sand and


paint finish ( 051. FC1) m2 46.6 79.00 $3,496.00

EXTERNAL TRIMS
250 x 50mm H3. 2 timber Fascia m 236 45.00 $10,620.00
45mm halfs played Akwa timber architrave m 65 30.00 $1,950.00
Soffit quadrant m 77 30.00 $2,310.00
GUTTER FRAMING & LINING

486389755.xlsx Carpentry Page 34 of 63


180mm high 16mm thick marine plywood substrate
m 23 50.00 $1,150.00
246mm wide 16mm thick marine plywood substrate
246mm wide 16mm thick marine plywood substrate m 23 50.00 $1,150.00
740mm high 16mm thick marine plywood gutter lining
m 23 51.00 $1,173.00

50 x 50mm framing m 23 25.00 $575.00


25 x 25mm chamfer blocks m 189 25.00 $4,725.00
INTERNAL WALL FRAMING
100 x 50mm hardwood timber framing m2 47 35.00 $1,645.00
INTERNAL LININGS
Pack top of joists to suit floor level m2 160 35.00 $5,600.00
9mm thick fibre cement flooring m2 20 45.00 $900.00
9mm thick wall lining, flush jointed, tape,stop and sand
m2 306 45.00 $13,770.00

75mm Sounds creen 2.0 insulation to walls m2 620 35.00 $21,700.00


6mm fibre cement sheeting to raking
ceiling, flush jointed, taped, stop and
m2 414 45.00 $18,630.00
sand ( 051. FC1)

90 x 20mm T & G flooring m2 408 200.00 $81,600.00


INTERNAL TRIMS
60 x 10mm skirting m 82 35.00 $2,870.00
45mm half splayed Akwa timber archi trave m 290 35.00 $10,150.00
Standard timber scotia m 208 45.00 $9,360.00
SUNDRY
Timber boarded seating to waiting area
comprising three 50mm x 140mm hardwood
slats fixed with 10mm carriage bolts to 30mm square
galvanised tube frame 10mm dia dynabolt through m 607 50.00 $30,350.00
8mm galvanised steel plate to slab, as detailed J 25- A

Proprietary Curtain and rail to rooms m 18 45.00 $810.00


240mm high galvanised birdwire m 53 45.00 $2,385.00
1000mm high timber balus trade comprising
50 x 75mm top and bottom rails, 50 x 25mm
vertical mambers , 145 40mm dressed m 81 56.00 $4,536.00
handrail

Total Carpentry Carried to Summary $1,800,532.00

486389755.xlsx Carpentry Page 35 of 63


DOORS
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for
note no costing
full details of materials and workmanship

Refer to the Preliminary and General section of this


Bill of Quantities and liaise with the Main Contractor in
respect of the responsibilities in allowing costs for note no costing
each item scheduled there in

METHOD OF MEASUREMENT
This Schedule of Quantities has generally
been measured in accordance with the rules identified
in Australian Standard Method of Measurement of
Building Works, Sixth Edition NZS 4202:1995
`Standard Method of Measurement of Building Works
'subject to provisos identified below.
Tenderers are required to fully acquaint
themselves with this method of measurement and note no costing
allow in their pricing for the implementation of this
method.
Not withstanding the Conditions of Contract, no claims
for method of measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are note
deemed to include the plural no costing

Rates for doors shall include for frames . note no costing


Door frames shall be H3. 2 treated timber unless note
nominated as local timber, all as specified no costing

Visual panels shall be 600mm high x 200mm note


wide 6mm clear glass no costing

486389755.xlsx Doors Page 36 of 63


Refer to specification clause note no costing
EXTERNAL DOORS & FRAMES
1650mm wide x 2040mm high solid core
double doors, vision panel and frame (D.01) no 1 3,500.00 $35,600.00

INTERNAL DOORS & FRAMES


820mm wide x 2040 mm high solid core door
local timber frame (D.04, D.05, D.06 D.07, D.28) no 5 1,600.00 $24,500.00
920mm wide x 2040mm high solid core door
and local timber frame (D.24, D.25) no 2 1,200.00 $25,320.00

1000mm wide x 2040mm high solid core door


and local timber frame (D.18, D.20, D.22) no 3 1,500.00 $21,300.00

1000mm wide x 2040mm high solid core


door, vision panel and local timber frame
- (D.02, D.03, D.08, D.09, D.10, D.11, D.12, D.13, no 14 2,600.00 $35,650.00
D.14, D.15, D.16, D.23, D.26, D.27)
1000mm wide x 2040mm high solid core door
with vision panel and timber frame , - / 60/ 30 fire door no 2 2,600.00 $13,650.00
( D.17, D.19)
1650mm wide x 2040mm high solid core
double door swith vision panel and timber no 1 3,500.00 $5,450.00
frame, - / 60/ 30 fire door (D.21)

Total Doors Carried to Summary $240,654.00

486389755.xlsx Doors Page 37 of 63


FITTINGS FIXTURES & EQUIPMENT
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of Contract and to
the Specifications and Drawings for full details of materials and note no costing
workmanship
Refer to the Preliminary and General section of this Bill of
Quantities and liaise with the Main Contractor in respect of the
responsibilities in allowing costs for each item scheduled note no costing
there in

METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured in
accordance with the rules identified in Australian Standard
Method of Measurement of Building Works, Sixth Edition subject
to proviso identified below. Tenderers are required
to fully acquaint themselves with this method of measurement
and allow in their pricing for the implementation of this method. note no costing
Not withstanding the Conditions of Contract , no claims for
method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are deemed to
include the plural note no costing

SUPPLY & FIX


All fittings shall be 304 Grade Stainless Steel note no costing
Caroma Care 500 Wall Hung Basin and Shroud with Strap
( 081. BA1) no 6 500.00 3,000.00
Brayco Wall mounted Hand Basin (081. BA2) no 9 500.00 4,500.00
Caroma Sovereign Trident connect or suite with Strap ( 081.
WC1) no 4 450 1,800.00
Caroma Cosmo Sovereign Care Toilet Suite with Back rest with
Strp (081. WC2) no 2 450.00 900
Enware- Delabie tempo stop Time Flow Pillar leveraction
(081. TP1) no 15 450 6,750.00

486389755.xlsx Fittings Fixtures & Equipment Page 38 of 63


Enware - Or as Vega Series Sink mixer - aerated ( 081. TP2)
no 1 500.00 500

Enware - Key Operated Hosetap (081. TP3) no 2 350.00 700


Enware - Or as Vega Series Shower mixer
aerated (081. TP4) no 3 350.00 1,050.00
Enware Comlab Dual Mixer Swivel Outlet (081. TP5) no 6 250.00 1,500.00
Enware Hob Mounted Ultra Rinse Unit with Dual Mixed
Assembly (081. TP6) no 1 150.00 150
Lever 80 Recessed Hand Held shower set with SGR023 900mm
s / s grab rail with no 2 150.00 300
white hand helds hower and hose white (081. SR1)
Enware - Anti Vandal shower rose ( 081. SR2) no 3 95.00 285
Caroma Cosmo metal soap dish ( 081. SP) no 5 95.00 475
Bobrick Channel frame mirror ( 081. M1) each 6 150.00 900
Bobrick surface mounted dispenser for
anti - bacterial soaps ( 081. SD) each 6 150.00 900
Bobrick Toilet Issue Dispenser for two rolls ( 081. TR1) each 6 150.00 900
Metlam MLR Grab Rail Set (081. GR) no 2 95.00 190
Surface Mount folding shower seat B- 8196871 (081. SS) no 2 120.00 240
Brayco Stainless steel bench with splash back, 1500 wide x 700
deep x 900 high.With under shelf (J 02, J 04) each 2 150.00 300

Brayco Stainless steel bench with splash back, 1800 wide x 700
deep x 900 high. With under shelf (J 06) each 1 150.00 150
Brayco Stainless steel bench with splash back, 1000 wide x
700 deep x 900 high. With under shelf ( J 09) each 1 140.00 140
Brayco 1525 wide x 450 deep x 2000 high Stainless steel
shelving with 4 racks (J 10, J 13, J 14, J 17) each 4 140.00 560
Brayco 925 wide x 450 deep x 2000 high
Stainless steel shelving with 4 racks (J 11, J 15, J 16) each 3 250.00 750

Brayco 1225 wide x 450 deep x 2000 high


Stainless steel shelving with 4 racks (J 12) each 1 250.00 250

Brayco 300mm deep x 1800 wide wall mounted stainless steel


shelf (J19, J20, J21, J22) each 4 250.00 1,000.00
Brayco 300mm deep x 1200 wide wall
mounted stainless steel shelf ( J 23) each 4 250.00 1,000.00

Total Fittings Fixtures & Equipment Carried to Summary


$345,500.00

486389755.xlsx Fittings Fixtures & Equipment Page 39 of 63


APPLIED FINISHES, RENDER & TEXTURED FINISHES
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of Contract and to
the Specifications and Drawings for full details of materials and note no costing
workmanship

Refer to the Preliminary and General section of this Bill of


Quantities and liaise with the Main Contractor in respect of the
responsibilities in allowing costs for each item scheduled note no costing
there in

METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured in
accordance with the rules identified in Australian Standard
Method of Measurement of Building Works, Sixth Edition subject
to provisos identified bel ow. Tenderers are required
to fully acquaint themselves with this method of measurement
and allow in their pricing for the implementation of this method. note no costing
Not withstanding the Conditions of Contract , no claims for
method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are deemed to
include the plural note no costing

Glazed doors, timber boarding and slats, balus trades, weather


boarding, linings with recessed joints or grooves and other non-
flat surfaces are measured flat face area overall and prices shall note no costing
include for the additional work involved

486389755.xlsx Applied Finishes, Render & Text Page 40 of 63


Prices shall include for :
Establishment expenses All preparatory work to provide a first
class finish to both new and exis ting surfaces, Masking as
required Varying colours, matt, gloss, semi - gloss, etc
Temporarily removing and refixing hardware, fixtures and
fittings where required, Flashings behind expressed joints,
Jointing and sealant stolinings, Supporting brackets, Working note no costing
from ladders , scaffolding, swinging stages etc Working to all
heights, Cutting into other surfaces or colours, Work in confined
spaces, inside ducts, joinery fittings and the like, Protection

GENERAL
Allow for the cost of all Preliminary and General items after liais
on with the Main Contractor item 500.00
Allow for inspections item 500.00
Allow for samples item 1,500.00
Allow for guarantees and warranties item 1,500.00
SOLID PLASTER
EXTERNAL
10mm plaster to concrete block wall m2 57 150.00 12,000.00
INTERNAL
10mm plaster to concrete block wall m2 140 95.00 4,500.00

Total Applied Finishes, Render & Textured Finishes


Carried to Summary $20,500.00

486389755.xlsx Applied Finishes, Render & Text Page 41 of 63


TILING
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specific ations and Drawings
for full details of materials and work manship note no costing

Refer to the Preliminary and General section of this


Bill of Quantities and liaise with the Main Contractor
in respect of the responsibilities in
allowing costs for each item scheduled note no costing
there in

METHOD OF MEASUREMENT
This Schedule of Quantities has generally
been measured in accordance with the rules
identified in Australian Standard Method of
Measurement of Buil ding Works, Sixth Edition
NZS 4202: 1995 `Standard Method of
Measurement of Building Works subject to provisos
identified below.Tenderers are required to fully
acquaint themselves with this method of note no costing
measurement and allow in their pricing for the
implementation of this method. Not withstanding
the Conditions of Contract, no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of
Quantities are deemed to include the
plural note no costing

486389755.xlsx Tiling Page 42 of 63


Prices shall include for :
Establishment expenses Preparation of the
surface to be tiled including hacking to form key
Levelling or dubbing- out of surface to be tiled as
specified, Reinforcing mesh Work in narrow widhs
and in isolated areas unless other wise described
All straight cutting, All fair edge tiles
Stop ends , mitres , internal and external angles ,
returned ends and the like( t o al l l i neal i t ems)
Cutting and laying to form patterns Sealant to
internal corners Cutting and fitting around floor note no costing
springs, mat frames and the like Cutting and
working around pipes, waste outlets , sleeves and
th like unless otherwise measured
Forming holes and building in items Laying flat and
to falls and/ or cross falls Levelling screeds,
Sealant and sealing Grouting

Mortar bedding, Mechanical fixing systems and


fixing same to all back grounds Control and
expansion joints including all necessary brass or
stailess steel strips, filling, sealants and backing
rods ( other than those measured here i n)
Polished, honed and A12 lamed surface finishes,
Finishing/ polishing to exposed edges, ends and note no costing
the like,Support angles where required, Cleaning
down and polishing on completion,Sealing coatings
to finished surfaces, Protection

GENERAL
Allow for the cost of all Preliminary and General
items required after liais on with the Main item 1,500.00
Contractor

Allow for samples item 1,500.00


Allow for certification item 1,400.00

486389755.xlsx Tiling Page 43 of 63


Allow for guarantees and warranties item 3,500.00
Allow to provide sparetiles item 3,500.00
WATER PROOFING
Approved Ardex WPM368 water proof membrane
system to Fibre cement / concrete floor m2 34 250 8,500

Approved Ardex WPM368 water proof membrane


system to Fibre cement plaster wall linings m2 141 500 70,500.00

WALL TILING
200 x 200mm Ceramic tiles laid in adhesive to
plaster / fibre cement wall lining m2 140 350 49,000.00
FLOOR TILING
600 x 300mm " Timeless " ceramic tile with
R12 slip resistance to Fibre cement / concrete floor m2 34 350 11,900.00

200mm high x 300mm long cut skirting tile m 348 150 52,200.00
TILE SPARES
Provide all spare tiles as specified item 15,000.00

Total Tiling Carried to Summary


$140,500.00

486389755.xlsx Tiling Page 44 of 63


RESILIENT FLOORING
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to the
Specifications and Drawings for full note no costing
details of materials and work manship
Refer to the Preliminary and General
section of this Bill of Quantities and liaise with the
Main Contractor in respect of the responsibilities in
note no costing
allowing costs for each item scheduled therein

METHOD OF MEASUREMENT
This Schedule of Quantities has generally been
measured in accordance with the rules identified in
Australian Standard
Method of Measurement of Building Works, Sixth
Edition NZS 4202:1995 `Standard
Method of Measurement of Building Works subject
to provisos identified below.
Tenderers are required to fully acquaint themselves
with this method of measurement and allow in their note no costing
pricing for the implementation of this method.
Not wit hstanding the Conditions of Contract, no
claims for method of measurement issues will be
accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of
Quantities are deemed to include the plural note no costing

Prices shall include for : Establishment expenses,


Preparation of the surfaces to be covered including
all necessary levelling, grinding, sanding, filling,
priming or sealing, Work in isolated areas, Narrow
widths, Raking cutting Laying to falls and cross falls
Scribing to abutting surfaces Working and finishing
around pipes, sleeves, brackets , pedestals, floor
outlets , accesslids, and the like Seals to metal
junction bars and the like, Stopends, mitres, note no costing
internal and external angles and the like ( to all
lineal items), Coved fillets and the like Jointing and
fixing tapes, Gripper bars Varying colours and
patterns Cleaning down and polishing on
completion, Protection

486389755.xlsx Resilient Flooring Page 45 of 63


GENERAL
delete
Allow for samples item 500

486389755.xlsx Resilient Flooring Page 46 of 63


Allow for guarantees and warranties item 500
Allow to provide maintenance and cleaning
instructions item 3,500.00
Allow for Hard underlay as specified item 5,500.00
Allow for Soft underlay as specified item 5,600.00
Allow to provide spares as specified item 5,000.00
VINYL SHEETING
2.0mm thick Armstrong Accolade homogeneous
sheet vinyl laid over fibre cement sheeting to Floor m2 283 250 70,750.00

WEATHER BAR
Metal weather bar m 11 250 2,750.00
FLOOR FINISH DIVIDER
Aluminium trim divider strip m 3 250 750

Total Resilient Flooring Carried to Summary


$150,850.00

486389755.xlsx Resilient Flooring Page 47 of 63


PAINTING
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for note no costing
full details of materials and work manship
Refer to the Preliminary and General section of this
Bill of Quantities and liaise with the Main Contractor
in respect of the responsibilities in
allowing costs for each item scheduled note no costing
there in

METHOD OF MEASUREMENT
This Schedule of Quantities has generally been
measured in accordance with the rules identified in
Australian Standard Method of Measurement of
Building Works, Sixth Edition NZS 4202: 1995
`Standard Method of Measurement of Building
Works subject t o provisos identified below.
Tenderers are required to fully acquaint
note no costing
themselves with this method of measurement and
allow in their pricing for the implementation of this
method. Not withstanding the Conditions of
Contract, no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are
deemed to include the plural note no costing

Glazed doors, timber boarding and slats,


balustrades, weather boarding, linings
with recessed joints or grooves and other
non- flat surfaces are measured flat face note no costing
area overall and prices shall include for
the additional work involved

Prices shall include f or : Establishment expenses,


All preparatory work to provide a first
class finish to both new and existing surfaces,
Masking as required Varying colours, matt , gloss,
semi - gloss, etc Temporarily removing and refixing
hardware, fixtures and fittings where required,
Flashings behind expressed joints, Jointing and
sealant stolinings note no costing
Supporting brackets, Working from ladders,
scaffolding, swinging stages etc Working to all
heights, Cutting in to other surfaces or colours,
Work in confined spaces, inside ducts, joinery
fittings and the like, Protection

GENERAL
Allow for the cost of all Preliminary and General
items required after liais on with the Main item 1,500.00
Contractor
Allow for inspections item 1,500.00

486389755.xlsx Painting Page 48 of 63


Allow for samples item 1,500.00

486389755.xlsx Painting Page 49 of 63


Allow for guarantees and warranties item 1,500.00
EXTERNAL
Berger Jet Dry Non- slip to paving m2 97 95 9,215.00
Low Sheen Dulux paint
Galvanised steel members, girthed m2 22 95 2,090.00
Galvanised steel balustrade, measured
flat overall m2 16 95 1,520.00
Low gloss latex to timber, members girthed. m2 122 75 9,150.00
Low gloss latex to timber doors and frame
(measured flat overal l) m2 97 75 7,275.00
Low gloss latex to Fibrements of fit linings m2 14 75 1,050.00
Low gloss latex to PVC downpipe ( girthed) m2 47 75 3,525.00
Low gloss latex to Timber balustrade ( measured flat
overall ) m2 68 75 5,100.00
Low gloss latex to Timber weather boards m2 28 75 2,100.00
Low gloss latex to Timber windows ( measured flat
overall )
m2 71 75 5,325.00
Clean down and repaint timber windows (measured
flat overall ) m2 33 75 2,475
INTERNAL
Stain to Rosewood strips (measured flat overall) m2 42 85 3,570.00
Semi gloss latex to fibre cement wall infills m2 4 85 340
Semi gloss latex to fibre cement plaster board walls
m2 32 95 3,040.00
Semi gloss latex to doors and frames (members
girthed) m2 620 95 5,890.00
Semi gloss latex to timber trim, 0 - 100mm girth m2 129 75 9,675.00
Semi gloss latex to fibre cement raked ceilings m2 1105 75 8,250.00
Semi gloss latex to timber windows ( measured flat
over all)
m2 408 95 38,760.00
Clean down and repaint timber windows (measured
flat overall)
m2 33 85 2,805.00
To sand T&G flooring and apply sealer m2 42 85 3,570

Total Painting Carried to Summary


$400,725.00

486389755.xlsx Painting Page 50 of 63


JOINERY
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for note no costing
full details of materials and work manship

Refer to the Preliminary and General section of


this Bill of Quantities and liaise with the Main
Contractor in respect of the responsibilities in note no costing
allowing costs for each item scheduled therein

METHOD OF MEASUREMENT
This Schedule of Quantities has generally been
measured in accordance with the rules identified
in Australian Standard Method of Measurement of
Building Works, Sixth Edition NZS 4202: 1995
`Standard Method of Measurement of Building
Works subject to provisos identified below.
Tenderers are required to fully acquaint
themselves with this method of measurement and note no costing
allow in their pricing for the implementation of this
method. Not withstanding the Conditions of
Contract , no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of Quantities are
deemed to include the plural note no costing

Brief descriptions only have been given together


with room/ drawing references appropriate, prices
shall include for laminate/ veneered finishes and
components necessary to complete the unit as note no costing
detailed and as specified

Sizes and di mensions given are approximate only


and prices shall include for slight variances note no costing

Prices shall include for fabricating in sections for


ease of transportation and installation note no costing

Prices for integral sink bowls , basins the likes hall


include for cp brass waste outlet, plug, stay and
chain where required and connections to water note no costing
supply waste pipes

486389755.xlsx Joinery Page 51 of 63


Prices shall include f or : Establishment expenses,
Manufacturing, delivery to site, storing and
assembling as necessary, Not ching and cutting
around columns, corners and the like
Forming all rebates, grooves, clashed edges,
rounded and free form, and the like All hardware,
Drawer runners, All fixing cleats, support brackets,
support angles, bearers, but tons, blocks, back
panels, etc as required, Closer panels as required,
Metal / timber support brackets, frames and sub-
frames etc, Pre finishing including touching up after note no costing
installation, Surface finish to metal brackets, frames
, etc
Scribers and other trim, Sealants as required,
Fixing in position including all fixings, wall plates,
brackets, etc . as required, Finishing against
adjoining surfaces with closing beads where
required, Skirting strips, Protection

GENERAL
Allow for the cost of all Preliminary and
General items required after liais on with the Main item 1,500
Contractor
Allow for inspections item 2,500.00
Allow for samples item 2,500.00
Allow for shop drawings item 2,500.00
Allow for guarantees and warranties item 2,500.00
FITTINGS
Rates for fittings shall include for
painting, staining or laquering as specified note

2770 x 3450mm girth x 750mm deep x 750mm


high, complete with top and four sets of drawers, each 1 25,100.00
reception counter (J 24) as drawing A700 A
1840mm high x 1340mm wide x 600mm wide
Radio cupboard unit ( J 26) , as drawing each 1 12,000.00
A702

Total Joinery Carried to Summary


$48,600.00

486389755.xlsx Joinery Page 52 of 63


HYDRAULICS
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings
for full details of materials and workmanship note no costing

Refer to the Preliminary and General section of


this Bill of Quantities and liaise with the Main
Contractor in respect of the responsibilities in
note no costing
allowing costs for each item scheduled
therein

GENERAL
Allow for all secondary steel, supports, brackets,
etc . item 1,500
Allow for height access and lifting and
positioning of equipment as required note no costing

Allow for tools, plant and equipment as required note covered under preliminaries
Allow to provide Spares item 1,500.00
Allow for all Testing and Commissioning item 1,500.00
Allow for all Insurance, fees and charges item 3,500.00
Allow for Shop drawings,Test and Commissioning
Reports, Operation Maintenance Manuals, As Built
Drawings and Health and Safety etc item 3,500.00

Allow for warranty and preventative


maintenance during defects liability period of 12 item 4,300.00
months from the date of practical completion

486389755.xlsx Hydraulics Page 53 of 63


Allow for all items not specifically detailed or
specified but required for the proper functioning of item 3,500.00
the system
HYDRAULICS
deleted
5 No. 5,000 liters rainwater storage tanks and all
other associated works item 45,200.00
Water booster pumps and all other associated
works item 45,000.00
Water Pump House and all other associated works
item 35,100.00
UV filter and Water filters ( coarse and fine) and all
other associated works item 36,200.00
Cold water system and all other associated works
item 26,300.00
Boiling Hot Water Units and all other associated
works item 34,200
Solar/Electric Hot Water Units and all other
associated works item 35,450.00
deleted
BUILDERS WORK IN CONNECTION
Allow for builders work other than that
specifically measured including forming
penetrations, building in sleeves and sealing
penetrations including flashings as required and
item 50,000.00
achieving fire and acoustic ratings as required

Total Hydraulics Carried to Summary


$370,250.00

486389755.xlsx Hydraulics Page 54 of 63


ELECTRICAL SERVICES
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special Conditions of
Contract and to the Specifications and Drawings for note no costing
full details of materials and workmanship

All descriptions in this Bill of Quantities are deemed


to include the plural note no costing

Prices shall include for: Establishment expenses


and setting out Surface run or concealed cabling
Fixing to all backgrounds and making good on
completion Provision of spare space and capacity,
Installation of all solar array, photocells and battery
bank, All conduits, trunking, cable trays, (except
where routes and sizes have been
specifically shown and measured)
including bends, junctions and other fittings,
Catenary wires, battens, fixing clips, cables, wiring,
connections, terminations of wiring and every thing
else necessary to complete the installation note no costing
Excavation for cabling where necessary in
materialas found, including bedding,
ducting, back filling and making good Supplying and
building in sleeves or forming penetrations
Sealing penetrations, including fire
and acoustic ratings Seismic restraint, Rates for
light circuits shall include for switches, Protection

Prices for cable trays where measured shall include


for all bends, jointers, angles, tees, covers,
brackets , fixings, support systems and all other note no costing
accessories required

GENERAL
Allow to comply with all statutory and other
requirements relating to the works item 3,500
Allow to give all notices, obtain all permits and
consents and pay all costs incurred item 3,500.00

Allow for all secondary steel, supports,


brackets, etc item 5,300.00
Allow for height access and lifting and positioning of
equipment as required item

Allow for tools, plant and equipment as required note covered under preliminaries
Allow to provide Spares item 2,500.00

486389755.xlsx Electrical Services Page 55 of 63


Allow for all Testing and Commissioning item 3,500.00
deleted
Allow for Shop drawings, Test and Commissioning
Reports, Operation and
Maintenance Manuals, As Built Drawings and item 3,500.00
Health and Safety etc

Allow for warranty and preventative maintenance


during defects liability period of 12 months from the item 4,500.00
date of practical completion
Allow for any items not listed above (please specify)
item 3,500.00

WORKS
deleted
HD under ground conduits from the stand by
generators to the generator synchronising panel and item 95,200.00
supports and associated accessories
Complete Main Switch board ( MSB)
including Automatic Transfer Switch, switch gears, item 75,000.00
busbar and all other associated works

Consumer mains cabling, generator mains cabling


and all other associated works item 55,100.00

All sub- mains cabling to respective


distribution boards and all other associated works item 55,100.00

Complete Stand- by Enclosed Diesel Generator Sets


including control panels and all other associated item 85,450.00
accessories
Complete indoor lighting system including cabling
and all other associated works . item 150,000.00
Complete exterior lighting system including cabling
and all other associated works item 150,000.00

Complete emergency and exit lighting system


including cabling and all other associated works 95,000.00

Complete General Power outlets including cabling


and all other associated works . item 23,100.00

Complete cable management system and all other


associated works item 18,000.00
Complete building earthing system including all
specialised equipment and protected areas and all item 12,300.00
other associated works

deleted
SOLAR OFF GRID WORKS
Supply and install Solar Panels, poles and required
brackets, Batteries DC cabling inverters, controllers,
isolators, Battery Inverter, String fuse, Multi-cluster
box, PV distribution board, Surge Protector,
Supports and all other associated works (refer to
item 250,000.00
relevant drawings and specifications)

486389755.xlsx Electrical Services Page 56 of 63


Solar data cabling to the standby generators and to
the PV Board and supports with all other associated item 96,230.00
accessories

PHOTO CELL
Photo cell shall be 345W 1650mm x 990mm as
documented in the electrical drawings and Item 65,250.00
specifications
Provide and mount Photo cell on roof and within
solar panel array area, pole mounted, and connect each 25,000.00
to circuits
SOLAR BATTERY BANK
Provide complete battery storage system, Allow for
PV contractor to determine battery sizing, fuse sizing
and battery inverter sizing to meet the documented each 95,000.00
performance

STRUCTURAL SUPPORT
Supply and install structural support for Solar panels
including 1000mm deep reinforced concrete pier,
galvanised pipe cast insert, mounting sleeve,
support bars and frame, module rail and support item 54,320.00
angle (refer to relevant drawings and specifications)

BUILDERS WORK IN CONNECTION


Allow for builders work other than that specifically
measured including support framing, building in
sleeves and sealing penetrations including fire and item 56,000.00
acoustic ratings, etc .

Total Electrical Services Carried to Summary


$700,100.00

486389755.xlsx Electrical Services Page 57 of 63


FIRE SERVICES
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to the Specifications and
Drawings for full details of materials and note no costing
workmanship
Refer to the Preliminary and section of this Pricing
Schedule liaise with the Main Contractor
respect of the responsibilities allowing costs for each note no costing
item scheduled therein

GENERAL
Allow for all secondary steel, supports,
brackets, et c . item 3,500.00
Allow for height access and lifting and positioning of
equipment as required note no costing

Allow for tools, plant and equipment as required note covered under preliminaries
Allow to provide Spares item 1,500.00
Allow for all Testing and Commissioning item 1,500.00
deleted
Allow for Shop drawings, Test and
Commissioning Reports, Operation and
Maintenance Manuals, As Built Drawings item 3,500.00
and Health and Safety etc

486389755.xlsx Fire Services Page 58 of 63


Allow for warranty and preventative
maintenance during defects liability
period of 12 months from the date of item 3,500.00
practical completion

Allow for all items not specifically detailed or


specified but required for the proper functioning of item 3,500.00
the system

FIRE SERVICES
deleted
Fire hose reel system and all other associated works
item 4,300.00
Portable fire extinguishers and fire
blankets and all other associated item 4,300.00
works
Fire alarm system and all other associated works item 3,500.00
Provide all necessary signage item 3,500.00
deleted
BUILDERS WORK IN CONNECTION
Allow for builders work other than that
specifically measured including forming
penetrations, building in sleeves and
sealing penetrations including flashings item 5,500.00
as required and achieving fire and
acoustic ratings as required

Total Fire Services Carried to Summary


$60,600.00

486389755.xlsx Fire Services Page 59 of 63


EXTERIOR ELEMENTS
Item Description of Work Unit Qty Rate Amount
PREAMBLES
GENERAL
Refer to the General and Special
Conditions of Contract and to he
Specifications and Drawings for full details of note no costing
materials and workmanship
Refer to the Preliminary and section of this Pricing
Schedule liaise with the Main Contractor
respect of the responsibilities note no costing
allowing costs for each item scheduled therein

METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the rules
identified in Australian Standard
Method of Measurement of Building Works,
Sixth Edition subject to provisos identified below.
Tenderers are required to fully acquaint themselves
with this method of measurement and allow in their note no costing
pricing for the implementation of this method. Not
withstanding the Conditions of
Contract, no claims for method of
measurement issues will be accepted

MEASUREMENT & PRICES


All descriptions in this Schedule of
Quantities are deemed to include the plural note no costing

SIGNAGE note no costing


Allow for Entry Sign item 500
Allow for Directory Signs item 500
EXTERIOR WORKS

486389755.xlsx Exterior Elements Page 60 of 63


Allow to reform road construct compact gravelfill m2 730 200.00 146,000.00
Allow for drainage to road item 120,000.00
Allow for excavation, 150mm thick
concrete, mesh reinforcement, edge and
stair riser formwork, and broom finish m2 40 200.00 8,000.00
for pedestrian access as drawing A002

Grassed Area/Planting m2 200 150.00 30,000.00


BOUNDARY FENCE
Refer drawing C06 A note no costing
Design and construction shall comply with 1725
Fence Type 1- R- L/ P- T, security fencing fabric
type shall be 2100mm wire coating for the chain link
shall be galvanised or zinc alloy heavy duty 3.15mm note no costing
wire chain link fabric and also comply with AS 2423
and AS/ NZ 4680

All tubular members shall be Grade C250LO to


AS1163 note no costing

Barbed wire shall be 2 strands of 1. 6mm dia high


tensile barbing grade wire twisted together, barbs
shall be 4 point type Ä " at 75 to 100mm cts' secured note no costing
to post with tie wire.

Grub out stumps and roots of removed


trees or shrubs and trim grass within 1 metre of m 181 150 27,150.00
fence alignment

New perimeter chainwire fence complete with posts,


concrete footings, bracing and barbed top selvedge m 181 150 27,150.00

6000mm wide x 2100mm high double gates


complete two pair of hinge clamps and with 20mm
dia lockable bolts with DN25 x set 1 50,000.00
100mm keeper set into and including
concrete footings( 3 no)

1000mm wide x 3210mm high single gate


complete with pair of hinge clamps and lockable each 1 50,000.00
shoot bolt

Total Exterior Elements Carried to Summary


$360,560.00

486389755.xlsx Exterior Elements Page 61 of 63


SEPTIC TANK, ABSORPTION BED & DISTRIBUTION BOX
Item Description of Work Unit Qty Rate Amount
Excavate and construct 5300mm long x 2000mm wide
x 2000mm deep two chamber septic tank, including
200mm thick reinforced concrete slab, 200mm thick
concrete block walls, solid filled, and 200mm thick no 150,000.00
concrete slab roof with two 500 x 500mm access lids,
all as drawing C04 A

1500mm wide Absorption bed including


excavation, geotextile, 20 - 30mm aggregate 300mm
deep fill, 200mm deep sandy loam backfill/ coarses m 220 $500.00 110,000.00
and, 150mm AGI preforated pipe and 50mm inspection
port

150mm dia pipe, include for excavation


and trench m 19 $1,500.00 28,500.00
Connect 150mm dia pipe connected to
distribution box/manhole each 3 1,500.00 4,500.00
150mm dia bend each 2 2,500.00 5,000.00
150m dia junction each 8 5,000.00 40,000.00
Connect 150mm dia pipe to 150mm dia
perforated pipe each 10 6,500.00 65,000.00
Excavate and construct 1500mm x 1500mm x
1300mm deep Distribution Box, complete
150mm thick reinforced concrete base,
200mm thick blockworkwalls, all cells fikked,150mm
thick reinforced concrete roof, Gatic cover with Class no 1 150,350.00
Bloading, concrete baffle and 150mm dia inlet and
outlet pipes l, all as detailed on drawing C04 A

Total Septic Tank, Absorption Bed & Distribution


Box Carried to Summary $553,350.00

486389755.xlsx Septic Tank, Absorption Bed & D Page 62 of 63


MANHOLE
Item Description of Work Unit Qty Rate Amount
Excavate and construct 1050mm dia concrete manhole,
complete with removable lid, 2mm hoop iron pipe
fixings bolted to wall, channel base on 100mm thick no 32,000
slab, all as drawing C05 A

Total Manhole Carried to Summary


$32,000.00

486389755.xlsx Manhole Page 63 of 63