2 Demolition/Repair $321,882.00
3 Groundworks $62,471.00
5 Formwork $20,650.00
6 Reinforcement $70,014.00
10 Windows $170,990.00
11 Carpentry $1,400,532.00
12 Doors $240,654.00
13 Hardware $145,235.00
16 Tiling $140,500.00
18 Painting $400,725.00
19 Joinery $48,600.00
20 Hydraulics $370,250.00
25 Manhole $32,000.00
All Rates and item prices must be included by the Tenderer. Check arithmetically all amounts and sums to avoid any
calculation errors. Editing or changing this Activity Schedule will disqualify the tenderer. Prices for each trade
are to be filled in by hand on this document as originally received with the Tender Instructions. The Tenderer must
add any extra items if required for the successful completion of the project as intended by the Ministry of Health and
Medical Service.
CONDITIONS OF TENDERING
Tenderers are referred to the Conditions of Tendering for full details note no costing
CONDITIONS OF CONTRACT
Tenderers are referred to the WHO/MHMS Conditions of Contract for full
details note no costing
TENDER DOCUMENTS
Tenderers are particularly referred to the following documents:
(a) Contract
Agreement Form
note no costing
(b) Standard Form of Guarantee
(c) Drawings and Specification
(d) Trade Activity Schedule
SITE ACCESS & TEMPORARY PROTECTION
Site Access and Site Limitations shall be agreed with the Owner at the
first site meeting note no costing
Allow for fully protecting existing driveways from all damage and
ensure clear access at all times to all properties serviced from the
item $25,000.00
driveways
deleted
Allow to provide, or make provision security of the building site, site
facilities and storage yards . item $15,500.00
deleted
Allow to obtain all necessary consents and approvals for temporary
works item $4,500.00
Allow to comply with the Health and Safety Act note no costing
INSURANCES
Ensure insurance premiums for the Contract Works are in place note no costing
Ensure Public Liability Insurance is in place note no costing
Ensure insurance premiums for Workers Compensation are in place
note no costing
Allow to effect and maintain marine insurance for all plant and materials
being shipped as part of the works.The marine insurance is to be in the item $12,500.00
joint names of the Principal and the Contractor.
Allow to effect and pay premiums for any additional Insurance the
Contractor deems necessary or is not adequately covered item $12,500.00
SETTING OUT
Allow for setting out the work including providing instruments and
labour and for checking same item $3,500.00
SUPERVISION
Allow for supervision of the work including the period of maintenance item $50,000.00
SITE STAFF RESOURCES
Allow to provide a site staff resources breakdown note no costing
ADMINISTRATION
Allow for contract programming, updating and reporting note no costing
Allow for Management and Administration of the Contract works
including maintaining site diaries, progress payments and associated
statements, the processing of variation price requests and variations to
contract, RFI systems, photographic records of progress and any note no costing
other charges to which the Contractor considers he is entitled. No
additional administration costs will be entertained
deleted
SHEDS, OFFICES & CONVENIENCE
Allow for providing as necessary temporary sheds, offices,
messrooms, sanitary accommodation and other temporary buildings
required for storage, and remove from site and make good on item $350,000.00
completion
TEMPORARY SERVICES
Allow for all temporary services necessary for the carrying out of this
contract including water, plumbing, air,power, lighting, telephones,
facsimile mchines, fire protection, safety and directional signage and
other services, pay fees for the duration of the Contract and
remove on completion. These temporary services shall be made item $250,000.00
available free of charge to all Sub-Contractors, Nominated
Sub-Contractors, Separate Sub-Contractors and the Principal
TEMPORARY WORKS
All ow for all temporary works as required for the construction of the
works including propping and strengthening existing structures and the item $250,000.00
like as necessary
Allow to protect work from damage due to inclement weather. Include for
drying out the building if required to allow the works to proceed note no costing
Allow for all costs associated with minimising the noise nuisance during
the building operations item $15,000.00
CLEANING UP SITE
Allow for the periodic collection and removal of all trade debris from the
site and for generally keeping the works clean item $85,430.00
OTHER COSTS
Allow for all other costs incurred in site establishment item $17,000.00
Allow for all cost associated with provision of suitable accommodation
on for staff as required during the period of the Contract Works item $17,500.00
Allow for all cost associated with shipping and handling of goods,
materials and planti ncluding but not limited to payment of all port fees item $100,000.00
and transport related costs
DEFECTS LIABILITY
Allow to maintain the work for the Defects Liability period and in
accordance with the General Conditions of Contract item $25,300.00
QUALITY ASSURANCE
Allow for Quality Assurance including systems, plans, etc as required
note no costing
ATTENDANCE
Allow to attend upon all Sub-Contractors and Nominated Sub-
Contractors including cutting away for and making good after, allowing
use of plant, storage, messing, power, artificial light, etc and unloading item $250,000.00
and placing in position, as required
Allow for all costs incurred to attend upon any Separate Contractors
and the Principal in allowing them access to the site during the Contract note no costing
PROVISIONAL SUMS
There is no Provisional Sums secti ons of these schedules of quantities note no costing
BILL OF QUANTITIES
The Bills of Quantities have generally been measured in accordance note no costing
with the Australian Standard Method of Measurement of Building
Works, Sixth Edition.
Tenderers are required to fully acquaint themselves with this method
and to allow in their pricing for the implementation of this met hod. Not
withstanding the Conditions of Contract no claims for method of
measurement issues will be entertained
All items are measured net as fixed in place, exclusive of laps .Unless note no costing
stated otherwise the description of each item shall include for supply,
conveyance, deliver y, unloading, storing, hoisting, all labour in setting
out , fittings and fixing in position, square cutting and waste, return of
packagings, use of plant and tools, over head charges and profit
The basic unit of length used in the Bill of Quantities is the millimetre note no costing
unless stated otherwise
Items marked (PROVISIONAL) are subject to note no costing
remeasurement and shall be adjusted according to the quantity
incoporated into the Works
The Contractor is required to price each individual item separately note no costing
within the Bills of Quantities when presenting the priced Schedules to be
used for the administration of the Contract
If items of work in the Bills of Quantities do not have a cost allowance note no costing
allocated to them by the Contractor then it will be deemed that eit er all
relevant costs associated with such items have been included
elsewhere within costs for other items of wor k; or that no remuneration
is required for such items
METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured
inaccordance with the rules identified in Australian
Standard Method of Measurement of Building Works,
Sixth Edition subject to provisions identified
below.Tenderers are required to fully acquaint thems
elves with this method of measurement and allow in
their pricing for the implementation of this method. Not note no costing
withstanding the Conditions of Contract, no claims for
method of measurement issues will be accepted
deleted
Give all notices at start and completion of Demolition
works note no costing
DEMOLITION
Demolish old that ched roof house and foundations item $35,000.00
Demolish and remove reinforced concretes even flight
external stairs item $35,000.00
Make good ground surface where concrete
stairs and ramps removed m2 14 $1,500.00 $21,000.00
Demolish and remove reinforced concrete
ramp, stairs and suppots each 1 $2,500.00 $2,500.00
Demolish and remove verandah timber rails and posts,
make good m 4 $2,500.00 $10,000.00
Remove complete external wall and linings, include
for propping roof structure m 2 $1,500.00 $3,000.00
Remove existing window, infill opening with new timber
framing cladding, insulation and linings and trim each 7 $1,500.00 $10,500.00
METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured
in accordance with the rules identified in the
Australian Standard Method of Measurement of
Building Works, Sixth Edition" subject to
provisos identified below.Tenderers are required to
fully acquaint themselves with this method of note no costing
measurement and allow in their pricing for the
implementation of this method. Not withstanding the
Conditions of Contract , no claims for method of
measurement issues will be accepted
GENERAL
Allow for the cost of all Preliminary and General
items required after liais on with the Main Contractor item $5,000.00
EXCAVATION
Excavation commencing at ground or reduced levels
and stock pile on site where directed note no costing
SITE WORKS
Clear Site of surface vegetation m2 222.8 54.00 $11,989.00
Surface Excavation
Strip ave. 100mm top soil and remove from site m2 222.8 54.00 $11,989.00
Excavation over Site
Cut and fill over site to give correct levels and profiles
m2 222.8 59.00 $11,989.00
Selected backfill
To pads and footings m3 68 135.00 $9,180.00
To slabs and ramps m3 20 135.00 $2,700.00
FILLING & HARDCORE
Bulk fill to site
Under slab m3 56 250.00 $14,000.00
50mm sand blinding
To pads and footings m2 1 250.00 $250.00
To slab m2 91 230.00 $7,500.00
PAPER & PLASTIC MEMBRANES
0. 2mm Polythened pc under slab
Ground slab and footings m2 132 250.00 $3,250.00
UNDERPINNING
Under pin existing wall for 50mm x 350mm
deep concrete footing each 1 $2,500.00
TERMITE PROTECTION
Provide installation certificate as specified note no costing
Buildings - Hand spray Binfenthrin as specified item $1,500.00
METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the rules identified
in the Australian Standard Method of Measurement of
Building Works, Sixth Edition subject to provisos
identified below.Tenderers are
required to fully acquaint themselves with this method
of measurement and allow in their pricing for the note no costing
implementation of this method.Not with standing the
Conditions of Contract, no claims for
method of measurement issues will be accepted
METHOD OF MEASUREMENT
FORMWORK
Sides of pads, tie beams and footings m2 60 360.00 $21,600.00
Side of stub column m2 60.7 360.00 $21,600.00
CLASS 2 FORMWORK
175mm slab edge formwork m 29 360.00 $5,400.00
240mm high slab sides m 10 56.00 $560.00
275mm slab edge formwork m 40 62.00 $2,480.00
300mm high slab edge formwork m 75 56.00 $4,200.00
Sloping Soffit of stair m 20 62.00 $1,240.00
Profiled stair side m 5.1 56.00 $280.00
160mm high stair tread m 11 56.00 $616.00
Column sides, circular m 20 360.00 $360.00
Side of beam m 1.8 360.00 $360.00
SUNDRY
Form dowelled construction joint m 1.7 56.00 $56.00
Form 20 x 10mm slab rebate, fill with
approved sealant m 27 56.00 $1,512.00
METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in the Australian
Standard Method of Measurement of
Building Works, Sixth Edition subject to provisos
identified below. Tenderers are required to fully
acquaint themselves with this method of
measurement and allow in their pricng for the note no costing
implementation of this method. Not withstanding
the Conditions of Contract, no claims for method of
measurement issues will be accepted
GENERAL
Allow for inspections item $500.00
Allow for samples and testing item $500.00
Allow for Quality Assurance item $1,500.00
FOUNDATION ON PADS/FOOTINGS
HD16mm dia bar kg 661 30.00 $19,830.00
D 16mm dia bar kg 373 30.00 $11,290.00
D12mm dia bar kg 45 30.00 $1,350.00
D12 starter bar kg 99.1 30.00 $2,970.00
D12mm dia stirrup kg 139.7 30.00 $4,170.00
D10mm ties kg 45 10.00 $450.00
GROUND SLABS, RAMPS & THICKENINGS
SL 92 mesh m2 48 56.00 $2,688.00
SL 82 mesh m2 46 56.00 $2,576.00
D12mm dia bar kg 461 30.00 $13,830.00
D10 ties kg 130 10.00 $1,300.00
METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in the Australian
Standard Method of Measurement of
Building Works, Sixth Edition subject to
provisos identified below. Tenderers are
required to fully acquaint themselves with this method note no costing
of measurement and allow in their pricing for the
implementation of this method. Not withstanding the
Conditions of Contract, no claims for method of
measurement issues will be accepted
METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in Australian Standard
Method of Measurement of Building Works, Sixth
Edition subject to provisos
identified below. Tenderers are required
to fully acquaint themselves with this
note no costing
method of measurement and allow in their pricing
for the implementation of this method. Not
withstanding the Conditions of Contract, no claims
for method of measurement issues will be
accepted
GENERAL
Allow for the cost of all Preliminary and
General items after liaison with the Main item $1,500.00
Contractor
BALUSTRADE
50mm dia galvanised handrail, with paint
finish, on and including 40mm square
balustrade posts, complete with 100 x m 49 450.00 $45,300.00
50mm galvanised RHS kerb rail
Form 300 x 330mm end to 50mm dia handrail each 10 500.00 $5,000.00
1000mm high 20mm dia galvanised steel
tube top, middle and bottom rail balustrade with
20mm dia vertical rails and 40 x 40mm galvanised
m 13 500.00 $12,500.00
posts to sloping stair/ramp and 50mm dia
galvanised handrail
METHOD OF MEASUREMENT
This Schedule of Quantities has generally been measured in
accordance with the rules identified in Australian Standard
Method of Measurement of Building Works, Sixth Edition NZS
4202:1995 `Standard
Method of Measurement of Building Works' subject to provisos
identified below.
Tenderers are required to fully acquaint themselves with this note no costing
method of measurement and allow in their pricing for the
implementation of this method.
Not withstanding the Conditions of Contract, no claims for method
of measurement issues will be accepted
Prices for gutters, rainwater heads, downpipes and the like shall
include for all fixing brackets, fixing clips, ends, jointing, sealants, note no costing
connections including connections to drains, etc
GENERAL
Allow to supply maintenance data item $500.00
Allow for tests and testing item $500.00
Allow for guarantees and warranties item $500.00
Allow to liaise with the Electrical Contractor and provide facilities
for a roof earthing system item $2,500.00
ROOF CLADDING
COLORBOND ULTRA Steel Roofing
17 degree roof cladding fixed to timber purlins m2 120 145.00 $17,400.00
7 degree roof cladding fixed to timber purlins m2 51 145.00 $7,395.00
Reflective thermal insulation membrane, blanket type thermal
insulation and wire safety mesh m2 171 145.00 $24,795.00
ROOF UNDERLAYS
0.48BMT COLORBOND ULTRA Steel Flashing
500mm girth twice bent on fascia flashing m 36 120.00 $4,320.00
430mm girth thrice bent colorbond ridge flashing m 10 120.00 $1,200.00
180mm girth underflashing twice bent including seal into timber
chase m 10 120.00 $1,200.00
METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the
rules identified in Australian Standard
Method of Measurement of Building Works,Sixth
Edition subject to provisos identified below.
Tenderers are required to fully acquaint
themselves with this
method of measurement and allow in their note no costing
pricing for the implementation of this
method. Not withstanding the Conditions of
Contract, no claims for method of
measur ement issues will be accepted
GENERAL
B METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured in
accordance with the rules identified in Australian
Standard
Method of Measurement of Building Works,Sixth Editi
on subj ect to provisos identified below. Tenderers are
required to fully acquaint themselves with this method
of measurement and allow in their pricing for the note no costing
implementation of this method. Not withstanding the
Conditions of Contract, no claims for method of
measurement issues will be accepted
GENERAL
Allow for the cost of all Preliminary and
General items after liais on with Main Contractor
item $1,500.00
Allow for two 400 x 400mm samples item $2,500.00
All ow for shop drawings item $1,500.00
Allow for nail plates, joist hangers, strapping, brackets,
etc item $25,000.00
EXTERNAL TRIMS
250 x 50mm H3. 2 timber Fascia m 236 45.00 $10,620.00
45mm halfs played Akwa timber architrave m 65 30.00 $1,950.00
Soffit quadrant m 77 30.00 $2,310.00
GUTTER FRAMING & LINING
METHOD OF MEASUREMENT
This Schedule of Quantities has generally
been measured in accordance with the rules identified
in Australian Standard Method of Measurement of
Building Works, Sixth Edition NZS 4202:1995
`Standard Method of Measurement of Building Works
'subject to provisos identified below.
Tenderers are required to fully acquaint
themselves with this method of measurement and note no costing
allow in their pricing for the implementation of this
method.
Not withstanding the Conditions of Contract, no claims
for method of measurement issues will be accepted
METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured in
accordance with the rules identified in Australian Standard
Method of Measurement of Building Works, Sixth Edition subject
to proviso identified below. Tenderers are required
to fully acquaint themselves with this method of measurement
and allow in their pricing for the implementation of this method. note no costing
Not withstanding the Conditions of Contract , no claims for
method of
measurement issues will be accepted
Brayco Stainless steel bench with splash back, 1800 wide x 700
deep x 900 high. With under shelf (J 06) each 1 150.00 150
Brayco Stainless steel bench with splash back, 1000 wide x
700 deep x 900 high. With under shelf ( J 09) each 1 140.00 140
Brayco 1525 wide x 450 deep x 2000 high Stainless steel
shelving with 4 racks (J 10, J 13, J 14, J 17) each 4 140.00 560
Brayco 925 wide x 450 deep x 2000 high
Stainless steel shelving with 4 racks (J 11, J 15, J 16) each 3 250.00 750
METHOD OF MEASUREMENT
This Bill of Quantities has generally been measured in
accordance with the rules identified in Australian Standard
Method of Measurement of Building Works, Sixth Edition subject
to provisos identified bel ow. Tenderers are required
to fully acquaint themselves with this method of measurement
and allow in their pricing for the implementation of this method. note no costing
Not withstanding the Conditions of Contract , no claims for
method of
measurement issues will be accepted
GENERAL
Allow for the cost of all Preliminary and General items after liais
on with the Main Contractor item 500.00
Allow for inspections item 500.00
Allow for samples item 1,500.00
Allow for guarantees and warranties item 1,500.00
SOLID PLASTER
EXTERNAL
10mm plaster to concrete block wall m2 57 150.00 12,000.00
INTERNAL
10mm plaster to concrete block wall m2 140 95.00 4,500.00
METHOD OF MEASUREMENT
This Schedule of Quantities has generally
been measured in accordance with the rules
identified in Australian Standard Method of
Measurement of Buil ding Works, Sixth Edition
NZS 4202: 1995 `Standard Method of
Measurement of Building Works subject to provisos
identified below.Tenderers are required to fully
acquaint themselves with this method of note no costing
measurement and allow in their pricing for the
implementation of this method. Not withstanding
the Conditions of Contract, no claims for method of
measurement issues will be accepted
GENERAL
Allow for the cost of all Preliminary and General
items required after liais on with the Main item 1,500.00
Contractor
WALL TILING
200 x 200mm Ceramic tiles laid in adhesive to
plaster / fibre cement wall lining m2 140 350 49,000.00
FLOOR TILING
600 x 300mm " Timeless " ceramic tile with
R12 slip resistance to Fibre cement / concrete floor m2 34 350 11,900.00
200mm high x 300mm long cut skirting tile m 348 150 52,200.00
TILE SPARES
Provide all spare tiles as specified item 15,000.00
METHOD OF MEASUREMENT
This Schedule of Quantities has generally been
measured in accordance with the rules identified in
Australian Standard
Method of Measurement of Building Works, Sixth
Edition NZS 4202:1995 `Standard
Method of Measurement of Building Works subject
to provisos identified below.
Tenderers are required to fully acquaint themselves
with this method of measurement and allow in their note no costing
pricing for the implementation of this method.
Not wit hstanding the Conditions of Contract, no
claims for method of measurement issues will be
accepted
WEATHER BAR
Metal weather bar m 11 250 2,750.00
FLOOR FINISH DIVIDER
Aluminium trim divider strip m 3 250 750
METHOD OF MEASUREMENT
This Schedule of Quantities has generally been
measured in accordance with the rules identified in
Australian Standard Method of Measurement of
Building Works, Sixth Edition NZS 4202: 1995
`Standard Method of Measurement of Building
Works subject t o provisos identified below.
Tenderers are required to fully acquaint
note no costing
themselves with this method of measurement and
allow in their pricing for the implementation of this
method. Not withstanding the Conditions of
Contract, no claims for method of
measurement issues will be accepted
GENERAL
Allow for the cost of all Preliminary and General
items required after liais on with the Main item 1,500.00
Contractor
Allow for inspections item 1,500.00
METHOD OF MEASUREMENT
This Schedule of Quantities has generally been
measured in accordance with the rules identified
in Australian Standard Method of Measurement of
Building Works, Sixth Edition NZS 4202: 1995
`Standard Method of Measurement of Building
Works subject to provisos identified below.
Tenderers are required to fully acquaint
themselves with this method of measurement and note no costing
allow in their pricing for the implementation of this
method. Not withstanding the Conditions of
Contract , no claims for method of
measurement issues will be accepted
GENERAL
Allow for the cost of all Preliminary and
General items required after liais on with the Main item 1,500
Contractor
Allow for inspections item 2,500.00
Allow for samples item 2,500.00
Allow for shop drawings item 2,500.00
Allow for guarantees and warranties item 2,500.00
FITTINGS
Rates for fittings shall include for
painting, staining or laquering as specified note
GENERAL
Allow for all secondary steel, supports, brackets,
etc . item 1,500
Allow for height access and lifting and
positioning of equipment as required note no costing
Allow for tools, plant and equipment as required note covered under preliminaries
Allow to provide Spares item 1,500.00
Allow for all Testing and Commissioning item 1,500.00
Allow for all Insurance, fees and charges item 3,500.00
Allow for Shop drawings,Test and Commissioning
Reports, Operation Maintenance Manuals, As Built
Drawings and Health and Safety etc item 3,500.00
GENERAL
Allow to comply with all statutory and other
requirements relating to the works item 3,500
Allow to give all notices, obtain all permits and
consents and pay all costs incurred item 3,500.00
Allow for tools, plant and equipment as required note covered under preliminaries
Allow to provide Spares item 2,500.00
WORKS
deleted
HD under ground conduits from the stand by
generators to the generator synchronising panel and item 95,200.00
supports and associated accessories
Complete Main Switch board ( MSB)
including Automatic Transfer Switch, switch gears, item 75,000.00
busbar and all other associated works
deleted
SOLAR OFF GRID WORKS
Supply and install Solar Panels, poles and required
brackets, Batteries DC cabling inverters, controllers,
isolators, Battery Inverter, String fuse, Multi-cluster
box, PV distribution board, Surge Protector,
Supports and all other associated works (refer to
item 250,000.00
relevant drawings and specifications)
PHOTO CELL
Photo cell shall be 345W 1650mm x 990mm as
documented in the electrical drawings and Item 65,250.00
specifications
Provide and mount Photo cell on roof and within
solar panel array area, pole mounted, and connect each 25,000.00
to circuits
SOLAR BATTERY BANK
Provide complete battery storage system, Allow for
PV contractor to determine battery sizing, fuse sizing
and battery inverter sizing to meet the documented each 95,000.00
performance
STRUCTURAL SUPPORT
Supply and install structural support for Solar panels
including 1000mm deep reinforced concrete pier,
galvanised pipe cast insert, mounting sleeve,
support bars and frame, module rail and support item 54,320.00
angle (refer to relevant drawings and specifications)
GENERAL
Allow for all secondary steel, supports,
brackets, et c . item 3,500.00
Allow for height access and lifting and positioning of
equipment as required note no costing
Allow for tools, plant and equipment as required note covered under preliminaries
Allow to provide Spares item 1,500.00
Allow for all Testing and Commissioning item 1,500.00
deleted
Allow for Shop drawings, Test and
Commissioning Reports, Operation and
Maintenance Manuals, As Built Drawings item 3,500.00
and Health and Safety etc
FIRE SERVICES
deleted
Fire hose reel system and all other associated works
item 4,300.00
Portable fire extinguishers and fire
blankets and all other associated item 4,300.00
works
Fire alarm system and all other associated works item 3,500.00
Provide all necessary signage item 3,500.00
deleted
BUILDERS WORK IN CONNECTION
Allow for builders work other than that
specifically measured including forming
penetrations, building in sleeves and
sealing penetrations including flashings item 5,500.00
as required and achieving fire and
acoustic ratings as required
METHOD OF MEASUREMENT
This Bill of Quantities has generally
been measured in accordance with the rules
identified in Australian Standard
Method of Measurement of Building Works,
Sixth Edition subject to provisos identified below.
Tenderers are required to fully acquaint themselves
with this method of measurement and allow in their note no costing
pricing for the implementation of this method. Not
withstanding the Conditions of
Contract, no claims for method of
measurement issues will be accepted