Multiplying factors
FOR SOFT SOIL OR SAND
Daily output to be multiplied by 1.O
FOR HEAVY SOIL OR STIFF CLAY
Daily out put multiplied by O.5
FOR WET EXCAVATION
With all other equipment
Daily output to be multiplied by O.6
1.7 Loading
1.7.1 Hand loading trucks from stock pile, sandy soil m3 1 lab 8.1
Hand loading trucks from stock pile, heavy soil or
1.7.2 clay m3 2 lab 5.4
1.7.3 For wet or muck hand loading m3 3 lab O.6
1.8 hauling Earth
1.1 Grading
Rough grading in ordinary soil upto 100mm cut
1.10.1 With a grader of 150 Hp m2 G-5 215.O
1.10.2 With a grader of 200 Hp m2 G-6 435.O
1.10.3 With a grader of 300 Hp m2 G-7 615.O
1.11 Others
2 FORMWORK
2.9.4 Box out for wall openings, upto 400mm thick yo 1.00m2 No FW - 2 18.O
2.9.5 Box out for wall openings,over, 1.00m2 (use perimeter) m FW - 2 49.5
Form works in soft wood, sub-structure in normal finish
2.1O to:
2.10.1 Footing m2 FW - 3 4.4
2.10.2 Subgrade column m2 FW - 3 4.7
2.10.3 Grade beam m2 FW - 3 4.6
2.10.4 Suspended slab m2 FW - 3 4.7
2.10.5 Concrete wall m2 FW - 3 4.3
2.10.6 Lift shaft m2 FW - 3 4.3
2.10.7 Mat foundation m2 FW - 3 4.4
3 Reinforcement
4 Concrete
4.2.2 Columns
4.2.2.1 300mm x 300mm, minimum reinforcing m3 C - F4 2.6
4.2.2.2 300mm x 300mm, averagereinforcing m3 C - F4 2.3
4.2.2.3 300mm x 300mm, maximum reinforcing m3 C - F7 2.O
4.2.2.4 400mm x 400mm, minimum reinforcing m3 C - F4 3.5
4.2.2.5 400mm x 400mm, average reinforcing m3 C - F4 2.9
4.2.2.6 400mm x 400mm, maximum reinforcing m3 C - F7 2.4
5.1.1 Mortar
5.1.1.1 With mortar mixer m3 BW - 3 4.O
5.1.1.2 With hand tools m3 2 Lab 2.7
5.4
5.4.1 General
including excavation, concrete footing and stone
1000mm below grade
6.12 Fasica
Aluminium, reverse board & batter, 0.8mm thick,
6.12.1 coloured, no furring included m2 1 Shee 8.9
STANDARD STANDARD OUT
ITEM No ACTIVITY DESCRIPTION UNIT CREW PUT NORMS
6.12.2 Steel, galv and enamelled, no furring included m2 1 Shee 8.9
6.12.2.1 long panels m2 1 Shee 8.9
6.12.3 Short panels m2 1 Shee 7.1
6.13 Downpipes
7 Waterproofing
9.3.2 Medium
9.3.2.1 Connectiomn plate kg SS - 4 3OO.O
9.3.2.2 Base plate kg SS - 4 3OO.O
9.3.2.3 Angle ties kg SS - 4 3OO.O
9.3.2.4 Brackets kg SS - 4 3OO.O
9.3.3 Heavy
9.3.3.1 Connectiomn plate kg SS - 2 4OO.O
9.3.3.2 Base plate kg SS - 2 4OO.O
9.3.3.3 Angle ties kg SS - 2 4OO.O
9.3.3.4 Brackets kg SS - 2 4OO.O
10 Metal Work
11.12 Chiselling
11.12.1 Surface
11.12.1.1 Concrete floor slab m2 1 Chisler 15.O
11.12.1.2 Concrete vertical surface m2 1 Chisler 1O.O
11.12.1.3 Concrete soffit m2 1 Chisler 5.O
12.4 Skirting
12.4.1 Size 70mm x 15mm "Harrer Dalecha" m FWF - 2 17.O
12.4.2 Size 70mm x 15mm "Gojam Grey" m FWF - 2 17.O
12.4.3 Size 70mm x 15mm "Wollega Grey" Daleti m FWF - 2 17.O
12.4.4 Size 70mm x 15mm "Wollega Grey" Bokea m FWF - 2 17.O
13 Painting
14 Glazing
15 Sanitary installation
Bell & spigot (with oakum & leaded joint for metal
15.18.5 pipes)
15.18.5.1 Diameter, 2" No. SI - 1 2.6
15.18.5.2 Diameter, 3" No. SI - 1 2.6
15.18.5.3 Diameter, 4" No. SI - 1 1.6
15.18.5.4 Diameter, 5" No. SI - 2 2.1
15.18.5.5 Diameter, 6" No. SI - 2 2.1
15.18.5.6 Diameter, 8" No. SI - 4 1.6
15.18.5.7 Diameter, 10" No. SI - 4 1.6
15.18.5.8 Diameter, 12" No. SI - 4 1.O
16 Electrical Installation
16.1 Raceways
16.2.1 Wire
16.2.1.1 600 V type THW copper solid
16.2.1.1.1 # 14 (2.5mm2) m 1 Electrican 275.O
16.2.1.1.2 # 12 (4mm2) m 1 Electrican 235.O
16.2.1.1.3 # 10 (6mm2) m 1 Electrican 21O.O
16.2.1.2 600 V type THW copper stranded
16.2.1.2.1 # 14 (2.5mm2) m 1 Electrican 275.O
16.2.1.2.2 # 12 (4mm2) m 1 Electrican 235.O
16.2.1.2.3 # 10 (4mm2) m 1 Electrican 21O.O
16.2.1.2.4 # 8 (10mm2) m 1 Electrican 17O.O
16.2.1.2.5 # 6 (16mm2) m 1 Electrican 135.O
16.2.1.2.6 # 4 (25mm2) m 1 Electrican 11O.O
16.2.1.2.7 # 3 (35mm2) m 1 Electrican 1O5.O
16.2.1.2.8 # 1/0 (50mm2) m 1 Electrican 7O.O
16.2.1.2.9 # 2/0 (70mm2) m 1 Electrican 61.O
16.2.1.2.10 # 250mcm (120mm2) m 1 Electrican 42.O
16.2.1.2.11 # 500mcm (240mm2) m 1 Electrican 34.O
16.4.2.1 Flexible conduit & fittings 240v 1HP motor No 1 Electrican 4.6
16.4.2.2 Flexible conduit & fittings 240v 25HP motor No 1 Electrican 2.0
16.4.2.3 Flexible conduit & fittings 240v 50HP motor No 1 Electrican 1.7
16.4.2.4 Flexible conduit & fittings 240v 100HP motor No 1 Electrican 1.1
16.5 Lighting
Interior lighting Fixtures including 1As,
mounting hardware and connection
16.9 Lamps
16.11.5 Cables
16.11.5.1 Less than or equal to 4 X 16mm2 m ELI - 8 8.O
16.11.5.2 Between 3 X 25/16mm2 - 3 X 95/50mm2 m ELI - 7 8.O
16.11.5.3 Greater than or equal to 3 X 120/70mm2 m ELI - 6 8.O
17.13 Fencing
17.14.2 Gates
EX - A1
1 Equipment Operator III
1 Grease boy 1 Hydraulic Excavator C.Y 1 m3 0.765
EX - A2
1 Equipment Operator III
1 Grease boy 1 Hydraulic Excavator C.Y 1.5 m3 1.15
EX - A3
1 Equipment Operator III
1 Grease boy 1 Hydraulic Excavator C.Y 2 m3 1.53
EX - A4
1 Equipment Operator III
1 Grease boy 1 Hydraulic Excavator C.Y 3.5 m3 2.7
EX - A5
1 Equipment Operator III
1 Grease boy 1 Hydraulic Excavator C.Y ½ m3 0.38
EX - A6
1 Equipment Operator III
1 Grease boy 1 Hydraulic Excavator C.Y ¾ m3 0.57
EX - A7
1 Equipment Operator III 1 Crawler Crane ton. 15
1 Grease boy 1 Clamshell Bucket C.Y 5 m3 3.8
EX - A8
1 Equipment Operator III 1 Crawler Crane ton. 25
1 Grease boy 1 Clamshell Bucket C.Y 1 m3 0.765
EX - A9
1 Equipment Operator II
½ Labouer II
1 Dozer H.P 75
EX - A9A
1 Equipment Operator II
½ Labouer II
1 Dozer H.P 140
EX - A9B
1 Equipment Operator II
½ Labouer II
1 Dozer H.P 200
STANDARD CREWS UNIT CAPACITY UNIT CAPACITY
EX - A10
1 Equipment Operator II
½ Labouer II
1 Dozer H.P 300
EX - A11
1 Equipment Operator III
1 Grease boy 1 Crawler Crane ton. 20
1 Bucket H.P 0.75 m3 0.57
EX - A12
1 Equipment Operator III
1 Grease boy 1 Crawler Crane ton. 40
1 Bucket H.P 1.5 m3 1.15
EX - A13
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 2.25 m3 1.15
EX - A15
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 2.25 m3 1.72
EX - A16
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 3.5 m3 2.7
EX - A17
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 5 m3 3.8
EX - A18
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 1 m3 0.765
EX - A19
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 1.5 m3 1.15
STANDARD CREWS UNIT CAPACITY UNIT CAPACITY
EX - A20
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 2.5 m3 1.9
EX - A21
1 Equipment Operator II
½ Labouer II 1 Front end Loader,
Track Nounted H.P 5.5 m3 4.2
EX - A22
1 Equipment Operator III
1 Grease boy 1 Gradall ton. 3
H.P 5 m3 3.8
EX - A23
1 Equipment Operator III
1 Grease boy 1 Gradall
H.P 1 m3 0.77
EX - A25
1 Equipment Operator III
½ Labouer II
1/4 Equipment Operator III
1 Scraper towed C.Y. 12 m3 9.18
1 Dozer H.P 300
1/4 Dozer H.P 300
EX - A26
1 Equipment Operator II
½ Labouer II 1 Scraper towed C.Y. 15 m3 11.48
1/4 Dozer H.P 300
EX - A27
1 Equipment Operator III
½ Labouer II
1/4 Equipment Operator III
1 Self propelled
Scraper C.Y. 14 m3 10.71
1/4 Dozer H.P 300
STANDARD CREWS UNIT CAPACITY UNIT CAPACITY
EX - A28
1 Equipment Operator III
½ Labouer II
1/4 Equipment Operator III
1 Self propelled
Scraper C.Y. 14 m3 18.36
1/4 Dozer H.P 300
EX - A29
1 Equipment Operator III
½ Labouer II
1/4 Equipment Operator III
EX - A30
1 Equipment Operator III
½ Labouer II
1/4 Equipment Operator III
EX - A31
1 Equipment Operator III
1 Grease boy
1 Power Shovel
1 Front End Attachment C.Y. 0.5 m3 0.38
EX - A32
1 Equipment Operator III
1 Grease boy
1 Power Shovel m3 0.57
1 Front End Attachment C.Y. 0.75 m3 0.57
EX - A33
1 Equipment Operator III
1 Grease boy
1 Power Shovel
1 Front End Attachment C.Y. 1 m3 0.77
STANDARD CREWS UNIT CAPACITY UNIT CAPACITY
EX - A34
1 Equipment Operator III
1 Grease boy
1 Power Shovel
1 Front End Attachment 1½ m3 1.15
EX - A35
1 Equipment Operator III
1 Grease boy
1 Backhoe C.Y. m3 0.29
EX - A36
1 Equipment Operator III
1 Grease boy
1 Backhoe C.Y. 0.5 m3 0.38
EX - A37
1 Equipment Operator III
1 Grease boy
1 Hydraulic Excavator C.Y. m3 0.48
EX - A38
1 Equipment Operator III
1 Grease boy
1 Hydraulic Excavator C.Y. 1 1/4 m3 0.96
EX - A39
1 Equipment Operator III
1 Grease boy
1 Hydraulic Excavator C.Y. 2½ m3 1.9
EX - A40
1 Equipment Operator III
1 Chain Trencher H.P. 12
EX - A41
1 Equipment Operator II
1 Chain Trencher H.P. 40
EX - A42
½ Gang Chief
2 Labourers II
EX - A43
1/4 Gang Chief
3 Labourers II Sledge Hammer Pcs 1 Pcs 1
EX - A44
1 Equipment Operator III
1 Equipment Operator III
1 Dozer H.P. 300
1 Excavator m3 3.5
EX - A45
1 Blasting forman
1Driller
1Equipment operator
1 Crawller type drill 4"
1 Air Compressor hose
EX - A46
1 Forman
1Helper
1Equipment operator
1 Dozer H.P 300
1Agg. Spreader
EX - A47
1 Forman
1Helper
1Equipment operator
1 Paving machine
1Roller ton 1O
EX - A48
1 Forman
1Helper
1Equipment operator
1Roller ton 3
EX - A49
1 Forman
1Helper
2 Equipment operator
1 Bar bender
Plasterer
1 Grader H.P 200
1 Paving machine
EX - A50
1 Forman
1Helper
1Equipment operator
1 Berm machine
EX - A51
1 Forman
1Helper
1Equipment operator
1 Oiler
1 machine ton 3
EX - A52
1Equipment operator
1 Helper
2 Truck driver
2 Truck m3 12
1Dozer H.P 200
EX - A53
1Equipment operator
1 Helper
1Backhoe loader H.P 75
EX - A54
1 Forman
1 plumber
1 Helper
EX - A55
1 Forman
1 plumber
1 Equipment Operator
1 Helper 1 Self-propelled crane ton 5
EX - A56
1 Forman
2 Helper
EX - A57
1 Forman
1 Equipment Operator
1 Helper
1 Oiler
1 Crane ton 20
FILL
F - B1
1 Labourer II
1 Gas Engine power Tool
F - B2
1 Equipment Operator III
½ Labourer II
1 Dozer H.P 200
F - B3
1 Foreman (outside)
4 Laboureres II
1 Equipment Operator II
Earthwork Equipment
F - B4
1 Equipment Operator III
Labourer
1 Sheepfoot roller H.P 130
F - B5
1 Equipment Operator III
1 Labourer
1 Roller Compactor ton 10
F - B6
1 Foreman
4 Labourer
Air compressor cfm 250
Air tools & Accessories
F - B7
1 Equipment Operator III
1Labourer
1 Dozer H.P 200
Air compressor cfm 250
Air tools & Accessories
F - B5
1 Equipment Operator III
1 Labourer 1 Dozer H.P 200
1 Towed vibratory roller
Grading
G - C1
1 Equipment Operator III
½ Laboureer II
1 Scaper, towed C.Y 7 m3 5.36
1/4 Dozer H.P 300
G - C2
1 Equipment Operator III
1 Laboureer II
1 Dozer H.P 200
G - C3
1 Equipment Operator III
1 Laboureer II
1 Grader Ib 30,000 ton 13.6
G - C4
2 Equipment Operator II
1 Self propelled Grader 1 Self Prolled Grader
1 Roller ton 10
G - C5
1 Equipment Operator III
1 Labourer 1 Self Prolled Grader H.P 150
G - C6
1 Equipment Operator III
1 Labourer 1 Self Prolled Grader H.P 200
G - C7
1 Equipment Operator III
2 Labourer 1 Self Prolled Grader H.P 300
Disposal
D - D1
1 Truck Driver IV
1 Dump Truck C.Y 6 m3 4.59
D - D2
Drive IV
1 Truck 1 Dump Truck C.Y 12 m3 9.18
D - D3
1 Truck Driver IV
1 Truck Tractor ton 40
1 Dump Trailer C.Y 16.5 m3 12.62
D - D4
1 Truck Driver IV
1 Truck Tractor ton 40
1 Dump Trailer C.Y 20 m3 15.3
D - D5
1 Equipment Operator II
½ Labourer II
1 Dozer H.P 200
Hard Core
1 Mason II HC - E1
4 Labouers II
HC - E2
1 Mason II
4 Labourers II
Concrete
C - F1
1 Labourer Forman
5 Labourers II
1 Plasterer II
1 Equipment Operator II
2 Gas engine vibrator
1 Pump 4" Diameter
(102mm) F 80 m 24.4
C - F2
1 Labourer Forman
5 Labourers II
1 Plasterer II
1 Equipment Operator II
2 Gas engine vibrator
1 Concrete Bucket C.Y. 1 m3 0.765
1 Crane or Pump
C - F3
1 Forman
5 Labourers II
1 Plasterer
2 Gas engine vibrator
C - F4
2 Forman
8 Skilled Workers
1/8 Crane & tools ton 80
C - F5
1/8 Labouer Forman
1 Labourer II
1 Concrete Cart C.F. 10 m3 7.65
C - F6
1/8 Labouer Forman
1 Labourer II
1 Concrete Cart C.F. 18 m3 0.51
C - F7
2 Forman
8 Skilled workers
1/4 Crane, & Tools ton 80
C - F8
1 Forman
2 Carpenters
3 Laboourers II
2 Plasterers II
1 Steel Fixer (reinforcement)
Power tools
C - F9
1 Labourer Foremen
2 Skilled workers
3/8 Crane, & tools ton 80
C - F10
2 Foremen
3 Labourers II
2 Plasterers II
1 Equipment Operator II
1 Concrete pumps (small)
C - F11
½ Foreman
2 Plasterers
1 Carpenter
1 Steel Fixer (reinf)
18 Labourers II
C - F13
1 Foreman
1 Carpenter II
1 Carpenter helper
2 Mason helper
1 Steel fixer (reinf)
1 Steel fixer helper
2 Equipment Operator I
2 Vibrator Operators
1 Labourer Foreman 1 Mixer 1t 500
19 Labourers 1 Front End Dumper
2 Vibrators
C - F14
1 Foreman
1 Carpenter II
1 Carpenter helper
2 Mason helper
1 Steel fixer (reinf)
1 Steel fixer helper
1 Equipment Operator I
1 Equipment Operator Ill
2 Vibrator Operators
1 Labourer Foreman 1 Mixer 1t 500
23 Labourers 1 Fixed crane
2 Vibrators
Formwork
FW - G1
3 Carpenters ll
1 Labour ll Power tools
FW - G2
1 Foreman
4 Carpenters ll
1 Labour ll Power tools
FW - G4
1/4 Foreman
2 Carpenter II
2 Helpers
FW - G5
1/4 Foreman
1 Carpenter II
2 Helpers
FW - G6
1 Carpenter II
1 Helper
2 Labourers II
8) Steel Reinforcement
SR - H1
4 Steel fixer II
SR - H2
1/4 Foreman
1 Steel fixer II
1 Steel fixer I
2 Helpers
SR - H3
1 Steel fixer II
2 Helpers
Masonry
SM - 11
1/4 Foreman
1 Mason II
4 Helpers
SM - 12
1/4 Foreman
2 Mason II
4 Helpers
SM - 13
1/4 Foreman
2 Mason II
1 Chiseller
4 Helpers
STANDARD CREW UNIT CAPACITY UNIT CAPACITY
BW - J1
1 Mason II
1 Mason helper
BW J2
3 Masons II
2 Mason helpers
1/4 Carpenter (Scaffolding)
BW - J3
2 Daily
Mortar mixer It 250
Water Proofing
WP - L1
1/4 Foreman
1Roofer
2 Helper
WP - L2
1 Roof foreman
4 Roofer
2 Roofer Helpers
Application equipment
CJ - N2
1/4 Foreman
1 Carpenter II
1 Carpenter I
4 Helpers
CJ - N3
1/4 Foreman
1 Carpenter II
1 Carpenter I
4 Helpers
CJ - N5
2 Carpenter II
Power tools
Structural Steel
SS - P1
1 Foreman
1 Welder
2 Carpenters II
1 Welding Machine
14 Laboureres II
SS - P2
1 Foreman
1 Welder
2 Carpenters II
1 Welding Machine
14 Laboureres II
1 Welding Machine
1 Mobile Crane ton 20 to 45
SS -P3
1/4 Foreman
2 Carpenter II
2 Carpenter I
SS - P4
1 Foreman
2 Carpenters II
1 Welder
4 Laboureres II
1 Welding Machine
1 Mobile Crane ton 05 to 10
Metal Work
MW - Q1
1/4 Foreman
1 Carpenter II
2 Helpers
MW - Q2
1 Carpenter II
1 Helper
MW - Q3
2 Carpenter II
Power tools
PP - R2
1/4 Foreman
1 Plaster II
1 Helper
PP R3
1/4 Foreman
1 Plaster II
½ Chiseller
1 Helper
PP R4
3 plaster II
2Helper
1 Mixer It 250
FWF - S2
1 Foreman
1 Tiler
2 Helper
FWF - S3
1/4 Foreman
1 Tiler
1 Helper
1 Grinder
1 Grinder Operation
FWF - S4
1/4 Foreman
2 Plaster II
2 Labourer II
FWF - S6
1 Tiler II
1 Helper
FWF - S7
1 Brick layer
1 Helper
Painting
P - T1
1/2 Foreman
1 Painter II
1 Helper
Glazing
G - U1
1/4 Foreman
2 Glazer II
1 Helper
Sanitary Installation
SI - V1
1 Plumber II
1 Helper
1 Chiseller II
SI - V2
2 Plumber
1 Helper
1 Chiseller II
2 Electrician
2 E.Helper
2 Helper
ELI - W3
1 Electrician
1 E. Helper
2 Helper
ELI - W5
1 Electrician
1 E. Helper
1 Helper
ELI - W6
.1 Electrician
.1 E. Helper
2 Helper
ELI - W7
.08 Electrician
.08 E. Helper
2 Helper
ELI - W8
.06 Electrician
.06 E. Helper
2 Helper
ELI - W9
1 Electrician
2 E. Helper
2 Helper
R3
1 Foreman
1 Electrician
½ Equip. Oper (crane)
1/4 Plasterer
½ Crane ton 5
D. Hollow block maonry for supper structure
a) 10 cm thick hollow concrete block wall bedded in cement mortar 1:4
A. Cement Mortar
1. Stone = 1.5 m3 / m3
2. mortar = 0.4 m3 / m3
2.1 cement = 150 kgs/ m3
2.2 sand = 0.42 m3 / m3
C. Brick masonary for super - structure
a) 1/2 Brick wall bedded in compo - mortar 1: 2 : 9 sides left for plastering.
1. Brick with 5% wastage = 115 pcs/m2
2. Compo- mortar ( 10mm joints) = 0.0353 m3 / m2
2.1 Cement = 5Kgs /m2
2.2 lime = 14 kgs / m2
2.3 Sand = 0.34 m3 / m2
b) One brick wall bedded in compo-mortar 1:2:9 both sides left for plastering.
1. Brick with 5% wastage = 115 pcs /m2
2. Compo- mortar with 15% wastage = 0.085 m3 / m2 ( 10mm joints)
2.1 Cement = 12.5 kgs/m2
2.2 lime = 34 kgs/ m2
2.3 Sand = 0.081 m3 / m2
c) 1 1/2 brick wall bedded in compo-mortar 1:2:9 both sides left for plastering
1. Brick with 5% wastage = 173 pcs / m2
2. Compo - mortar with 15% wastage = 0.113 m3 /m2
2.1 Cement = 17 kgs / m2
2.2 lime = 45 kgs/ m2
2.3 Sand = 0.11 m3 / m2
C. LIME - MORTAR PLASTERING ON WALLS PER 10 SQUARE METERS
nal of Cement Lime sand Cement Lime sand Cement Lime sand Cement Lime sand
compo -
mortar ( Kgs) ( Kgs) ( m3) ( Kgs) ( Kgs) ( m3) ( Kgs) ( Kgs) ( m3) ( Kgs) ( Kgs) ( m3)
1:1:6 31.75 43.09 0.14 37.93 51.47 0.16 49.39 67.03 0.21 55.13 74.81 0.24
1: 1 :8 25.4 34.47 0.15 30.34 41.18 0.17 39.51 53.63 0.23 44.1 59.85 0.25
1:2:9 21.17 57.46 0.14 25.28 68.63 0.16 32.93 89.38 0.21 36.75 99.75 0.24
1/2 : 2 : 6 14.94 81.13 0.13 17.85 96.89 0.15 23.24 126.18 0.2 25.94 140.82 0.22
A . CEMENT - MORTAR PLASTERING ON WALLS PER 10 SQUARE METERS
Portion of
cement 12 mm thick with 20% wastages 15 mm thick with 15 % wastage 20 mm thick with 12 % wastage 25 mm thick with 10 % wastage
mortar mortar = 0.144 m3 mortar = 0.172 m3 mortar = 0.224 m3 mortar = 0.25 m3
Cement sand Cement sand Cement sand Cement sand
( Kgs) ( m3) ( Kgs) ( m3) ( Kgs) ( m3) ( Kgs) ( m3)
Note :- Hand mix shall only be allowed for class II concrete and shall not be allowed for concrete
of class c-20 and above.