You are on page 1of 14

www.ietdl.

org

Published in IET Generation, Transmission & Distribution


Received on 23rd August 2007
Revised on 3rd December 2007
doi: 10.1049/iet-gtd:20070370

ISSN 1751-8687

Towards reactive power markets


Part 2: differentiated market reactive power requirements
K.L. Lo Y.A. Alturki
Department of Electronic & Electrical Engineering, University of Strathclyde, Glasgow, UK
E-mail: cnas0l@eee.strath.ac.uk

Abstract: Two major contributions are discussed in this part of a two-part set. First, it presents a new concept of
market reactive power requirement (Qreq) for every participant in both bilateral and pool markets. This Qreq is
defined as the reactive power loss allocation to each bilateral transaction using current adjustment factor (CAF)
method that has been proposed in Part 1. When a transaction is allowed to provide reactive power more than
its Qreq , it contributes to system reactive power needs and it is considered a reactive power provider. On the
other hand, if it cannot produce its Qreq , it relies on other reactive power sources to ship its contracted
power and it is considered a reactive power consumer even though it may generate some reactive power.
The concept then is extended to participants in a pool market. Secondly, this paper proposes a new general
concept of differentiated reactive power requirements for every participant in electricity markets. It assumes
that Qreq of a participant depends on its allocated losses using any appropriate loss allocation method.
The proposals help system operators and market participants to trade reactive power as well as real power
effectively and fairly. The simulation results show validity and consistency of the proposals.

1 Introduction classify these costs into explicit and implicit costs. The
explicit costs include fixed costs and maintenance and
Reactive power plays an important role in power system operating costs. The implicit costs include any
reliability and security. It maintains voltage profile and opportunity costs of lost profits of real power in order to
improves real power transfer capability. Since the produce reactive power instead. Some proposals divide
deregulation of energy markets has started, pricing of cost of reactive power into two major components; the
reactive power as an ancillary service has become an active first one is incurred from generators and the second one
area of research. In a vertically integrated power system, is incurred from transmission. Generator costs include
the utility calculates the whole cost of 1 MW to be explicit (capital) and implicit (opportunity) costs. The
transferred from sources to end users. This cost includes second incurred cost is that of transmission which is
the cost of reactive power as embedded cost. In deregulated explicit cost only consisting of losses, cost of capacitors,
energy market environments, ancillary services such as transformers and compensators [4, 5]. While fixed costs
reactive power and reserves are open for competition. This of equipments that only manages reactive power are easy
paper contributes to developing reactive power markets by to determine, it is not straightforward for generators.
proposing a new concept of Market Reactive Power Alvarado et al. [2] listed several proposed methods in the
Requirement (Q req) for every market participant. The literature to quantify the portion of fixed cost that was
proposal is built on Current Adjustment Factor (CAF) allocated to reactive power.
method proposed in Part 1 of this two-part set [1].
Many methods for reactive power pricing are based on
Most reactive power pricing proposals are based on locational marginal pricing scheme either neglecting
reactive power costs which might be determined directly production cost or taking into consideration the
or through market processes [2]. The authors in [3] production cost and/or other transmission equipments

516 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

costs [6, 7]. Optimisation theories are the main proportional sharing or operating guides. For a given
techniques used to determine spot prices for real real power output from the test generator, Q min is the
power and reactive power by modifying optimal power generator reactive power output that brings back the
flow (OPF) to include reactive power costs. These voltage stability margin to the reference margin. Since
schemes use the modified OPF to price reactive power it is possible that certain generators can not supply their
at each node. minimum required reactive power, due to system
constraints or the capability curve limits of the
Some proposed methods are based on reactive power generator, these generators actually draw some reactive
valuation [8, 9]. These methods propose to base power from the system to be able to transmit their own
reactive power in a different way trying to value its active power. In such circumstances, these generators
effect on system security and reliability which are the cannot support the system even though they
main functions of reactive power in a power system in are generating some reactive power. This method
addition to load reactive power requirements. Among proposes that reactive power compensation should be
reactive power valuation proposals are equivalent paid only for the amount of reactive power
reactive compensation (ERC), back-up generation, PV produced that is above the minimum required reactive
curves and voltage sensitivities (VS) methods. ERC and power.
back-up generation methods look at other
reactive power sources’ response to a particular source, This paper is Part 2 of a two-paper set. Part 1 proposed
which can be viewed as a measure of the value of that current adjustment factor (CAF) method to allocate every
source’s output. PV curves and VS methods look at the transaction in bilateral markets its share of the real and
reactive power sources response to load changes. A reactive power losses [1]. Different power transmissions
monetary model of reactive power compensation can cause different real and reactive power losses on the
be based on the reactive power value of each source. network depending on system operating conditions and
network topology. Remote generators from load center
Other literatures propose to base reactive power are expected to cause more reactive power losses and
pricing on power flow tracing [10– 12]. These schemes thus are expected to need more reactive power help,
start from a solved power flow. They determine the than closer ones. CAF method effectively and fairly
power that can reach each bus by each generator. Buses allocates each transaction its share of the losses as
that are fed by the same generator are determined. illustrated in detail in [1, 14]. Since CAF method starts
Using proportionality assumption, which is neither from a solved load flow (base case) where all
provable nor disprovable, each generator is assigned its transactions declare their shares of the market and all
share of loads and branch flows. Under these proposed system conditions are satisfied, the resulted allocated
methods, the consumers and generators do not have losses covers all system needs of reactive power. Every
any control on the price they would be charged because bilateral transaction Ti is responsible for its allocated
the method outputs determine exactly every load that reactive power losses (Q Tiloss). So, Q Tiloss is the required
can be reached by a generator and by how much. In reactive power participation from each transaction,
other words, output of a generator is delivered to respecting all system constraints, in order to compensate
certain loads and each load obtains its power from its allocated losses. If a transaction can not fulfill its
certain generators according to the calculated results required reactive power participation, due to either the
based on power-flow tracing. capability limits of its generator or the system
constraints, it relies on other reactive power sources to
A minimum amount of reactive power (Q min) required make up its allocated losses for which it should be
from every generator in a pool system in order to ship its responsible. This introduces the proposed concept of
active power is proposed in [13]. Q min is defined as the market reactive power requirement (Q req). For a
minimum amount of reactive power needed from each transaction, Q req is defined as the minimum reactive
generator in order to transmit its own real power power output required from a generator (or a group of
without the help of other reactive power sources in the generators) that is involved in the transaction in order to
system. In other words, it is the amount of reactive compensate its allocated losses. So, Q req from a
power when produced by a generator, it neither transaction is equal to its allocated reactive power losses
enhances nor reduces the voltage stability margin of the resulted from CAF method. The system operator is
base case, which can be measured by PV or QV curve responsible for maintaining system voltage profile which
margin. The base case is defined as the case when the is the main function of reactive power support. Each
generator under consideration outputs zero real and generator produces an amount of reactive power
reactive power. The corresponding voltage stability according to the instructions of the system operator. If a
margin is the reference margin. The power mismatch transaction generator (the generator that is involved in
caused by setting the output of the test generator to the transaction) is instructed to produce reactive power
zero is produced by re-dispatching other generators that is less than its Q req , it would need to depend on
using different re-dispatching schemes such as OPF, other reactive power sources in the system to

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 517
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

compensate for the losses it caused and the transaction is reactive power sources available in the system actually
considered as a net reactive power consumer, that is, it produce the remaining allocated reactive power and the
actually draws some reactive power support from the transaction is considered a net reactive power consumer.
system. On the contrary, if a transaction generator is So, it is possible that some generators are considered as
allowed to produce more than its Q req , it supports the reactive power consumers even if they are producing
system and it is considered as a net reactive power some reactive power as their productions are less than
provider. their Q req . It should be noticed here that the reactive
power outputs of generators are determined by the
The concept of Q req is extended to pool markets by independent system operator to maintain voltages within
which every participant, including loads and generators, limits and to respect all system constraints.
is assigned its requirement of reactive power
participation. So, a transaction reactive power support can be
defined as follows
This paper also introduces a new general concept that
assigns each participant in electricity markets its own T T T Ti
reactive power obligation which can differ from other i
Q Support ¼ Q Inji  Q Alloc
i
losses  Q cont (1)
obligations of other participants. The concept assumes
that the reactive power requirements of participants where
depend on their reactive power loss allocations using
any appropriate loss allocation method. Q TInji ¼ the reactive power provided by generators
involved in transaction Ti
The rest of the paper is divided into four sections.
Market reactive power requirement concept in bilateral Q TAlloc
i
losses ¼ the allocated losses to transaction Ti
markets is introduced in Section 2, the application of using CAF method
the proposed concept in pool markets is presented in
Section 3, case studies of both bilateral and pool Q Tcont
i
¼ the contracted reactive power traded by Ti
markets are presented in Sections 4 and 5 respectively,
generalisation of the proposed concept is introduced in A transaction should expect payments for its reactive
Section 6 and finally the conclusion is in Section 7. power support if its Q Support is greater than zero. On
the other hand, a system operator should charge a
transaction if its Q Support is negative. It is assumed here
2 Market reactive power that the system is operating under heavy loading
requirement (Qreq) in bilateral conditions, that is, the system needs reactive power
markets production to maintain bus voltages. It is worth noting
here that for equipments that are dedicated for reactive
CAF method allocates each transaction its share of the power support such as synchronous condensers have
system reactive power losses. This paper introduces the always positive Q Support as they are allocated zero
concept of market reactive power requirement (Q req) losses and they have no contracts for reactive power
which is defined as a portion of the whole system demands (i.e. their reactive power outputs are solely
reactive power losses for which each bilateral transaction for system reactive power support.)
is responsible. Q req for a transaction Ti is equal to its
allocated reactive power loss, that is, Q req and the Q req concept has important features, as it will be
allocated reactive power loss to a participant are equal. illustrated in case studies, such as: (1) it takes into
A transaction generator should produce an amount of consideration the locality nature of reactive power; (2) it
reactive power that equals to Q req in order to sends clear signals to transaction parties about the
compensate the losses that it causes without relying on impact of their contracts on the system; (3) it sends
the help of other reactive power sources in the system. correct signals about where reactive power support is
Because of the locality nature of reactive power and the needed more and where there is excess of it; (4) it
capability limits of each generator, it is possible that provides a basis of competitive environment for reactive
some generators can not fulfil all their allocated reactive power procurement; (5) it provides opportunity for
power losses whereas others are instructed by the generators to optimise their real and reactive power
system operator to participate in reactive power more outputs to maximise their profits; (6) it creates
than their allocated losses in order to maintain system incentives for reactive power participation and for new
security and voltage profile. If a generator is instructed participants to enter the market at the right location.
to produce more reactive power than its Q req , it
supports the system and and it is considered a net Market reactive power requirement (Q req) concept
reactive power provider. On the other hand, if it in bilateral markets is illustrated first on a simple two
produces less reactive power than its Q req , other bus system. Then it is verified on IEEE-14 bus system.

518 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

3 Market reactive power It is worth noting that, in addition to the advantages


mentioned in the previous section, the proposed concept
requirement (Qreq) in pool markets assigns both loads and generators their Q req according to
To apply CAF method in pool markets, the method is their utilisation of the system by which there is no need
modified by using an economic despatch technique for an arbitrary sharing percentage such as 30% for
instead of load flow calculations. It allocates every user, generators and 70% for loads.
generator or load, its share of real and reactive
power losses. Every participant Ti , whether a load or Market reactive power requirement (Q req) concept
a generator, is responsible for its allocated reactive in pool markets is illustrated first on a simple two bus
power losses (Q Tiloss). So, Q Tiloss is the required reactive system. Then it is verified on IEEE-14 bus system.
power participation from each participant, while
respecting all system constraints, in order to fully
compensate its allocated losses. If a participant can not 4 Determination of (Qreq) in
fulfill its required reactive power participation, which is bilateral markets: case studies
possible due to its capability limits or due to system
constraints, it relies on other reactive power sources 4.1 Simple two bus system for illustration
available in the system to make up its allocated losses Consider the system in Fig. 1 where the system voltage
for which it should be responsible. This introduces the is fixed at 1.0 pu at all buses. Within the system, all
concept of market reactive power requirement (Q req) generators and loads are represented by G (System)
in pool markets. (Q Treq i
) is equal to the allocated and Load (System), respectively. Generator 2 has a
reactive power loss to participant Ti using CAF method. transaction with load 2 that is located within the
system. All other transactions are represented by
A participant Ti should produce an amount of reactive transaction one (fixed at 100 MW) which is between
power equal to Q Treq
i
in order to compensate the losses it G (System) and Load (System). It should be noticed
causes on the network without relying on the other that the transmission line solely serves generator 2
reactive power sources in the system. Because of the (carrying its contracted real power to load 2) implying
locality nature of reactive power and the capability that all the transmission losses are caused by generator
limits of each participant, it is possible that some 2 for which it should be solely responsible. Notice
participants can not fulfil all their Q req whereas others also that there is no contracted reactive power, so,
are instructed by the system operator to participate in Q Tcontracted
i
in (1) is zero in this case study simulations.
reactive power needs more than their Q req in order to
maintain system security and voltage profile. If Q Treq
i
is Three scenarios are conducted to illustrate the proposed
less than what participant Ti produces, the participant concept. Scenarios one and two assume that the traded real
supports the system and is considered a net reactive power of transaction 2 is 200 and 300 MW, respectively.
power provider. On the other hand, if it produces less Scenario three assumes that generator 2 is farther away,
reactive power than its Q Treq i
, the system actually that is, Z ¼ 0.02 þ j 0.3 pu instead of Z ¼ 0.01 þ j
produces the remaining allocated reactive power and 0.1 pu. In all scenarios, the setpoint voltage of generator
the participant is considered a net reactive power 2 changes from 0.9 to 1.1 pu in 0.01 steps.
consumer even if it is producing some reactive power.
So, Q Support of each participant in a pool market is 4.1.1 Scenario 1: Transaction 1 and 2 are fixed at 100
determined as follows and 200 MW, respectively. The simulation results are
shown in Figs. 2 and 3. Point A in Fig. 2a deserves
T T T attention. When the setpoint voltage of generator 2 is
i
Q Support ¼ Q Inji  Q Alloc
i
losses (2) less than A (about 1.04 pu), G(System) injects reactive
power which flows from System towards Bus 2. This
where Q TInji is the reactive power provided by participant Ti . means that G(System) participates in reactive power loss
If a load Ti consumes lagging power factor demand, Q TInji will compensation on the line. As the setpoint voltage of
be negative whereas if it consumes leading power factor
demand, Q TInji will be positive. On the other hand, Q TInji
for a generator is positive if it injects reactive power and
it is negative if it absorbs reactive power. Q TSupport
i
defined
in (2) assumes heavy loaded conditions, that is, the
system needs reactive power production to maintain
voltage profile. A participant Ti is considered a reactive
power provider only if Q TSupport
i
is greater than zero. On
the other hand, a system operator considers a participant Figure 1 Simple two bus system for illustration (case study
a reactive power consumer if its Q TSupport
i
is negative. in Section 4.1)

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 519
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Figure 2 Reactive power flow and injections results of scenario 1


a Reactive power injection at bus 1
b Reactive power injections from generator 2 and System

generator 2 increases, its reactive output increases and the At point C, generator 2 outputs zero reactive power and
reactive injection from System decreases. At point A, depends fully on reactive power help of other sources
G(System) injects zero reactive power to the line within the system to compensate the transmission
which means that generator 2 compensates all the reactive loss.
losses created on the line. This also means that the
setpoint voltage of generator 2 has to be at least 1.04 pu Fig. 3 shows the results of applying (1) to calculate
to transmit its 200 MW without any help reactive power support of transaction 2. These results
from G(System). The corresponding reactive power are consistent with Figs 2a and 2b with identical ‘A’
injection of generator 2 in Fig. 2b is the minimum point value. When generator 2 is operating at a
required reactive power participation (Q req) in order to setpoint voltage larger than A, it generates reactive
transmit its 200 MW real output. If the generator power more than its allocated reactive power losses
produces less than this amount, the transaction requires (i.e. line reactive losses) and thus reactive power flows
help from other reactive power sources within the into System. This can be seen as negative flow in
system whereas if it generates more than Q req , Fig. 2a (where reactive power flow is negative when
it provides excess reactive power to support the system. System bus receives reactive power from Bus 2) and
At point B, both generator 2 and G(System) provide System negative injection in Fig. 2b ( where a reactive
half of the reactive power needed on the line. power injection is negative when it is absorbed by a
generator).

4.1.2 Scenario 2: Scenario one is repeated when


generator 2 trades 300 MW instead of 200 MW. As
the results show in Figs. 4 and 5, generator 2 now
needs more help from other reactive power sources to
transmit its real power output. In other words,
generator 2 has to inject more reactive power (higher
setpoint voltage) to be able to ship its contracted real
power without any help from other sources within the
system. When compared with the results of scenario
1, it is noticed that point A has moved to the right
(i.e. higher setpoint voltage), Q req has increased and
the amount of reactive power with which generator 2
can support System is reduced. This is consistent with
engineering expectation and locality nature of reactive
power.

4.1.3 Scenario 3: Scenario one is repeated


Figure 3 Reactive power support from generator 2 and when generator 2 now is farther away, that is,
System Z ¼ 0.02 þ j 0.3 pu instead of Z ¼ 0.01 þ j 0.1 pu.

520 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Figure 4 Reactive power flow and injections results of scenario 2


a Reactive power flow from System to bus 2
b Reactive power injections from generator 2 and System

phenomenon is taken into consideration in reactive


power procurements and payments, some generators
actually subsidise others which could be seen as
imperfect competition.

4.2 IEEE-14 bus system


The market reactive power requirement concept
proposed in this paper is tested on a slightly modified
IEEE-14 bus system shown in Fig. 8 [15]. Since line
charging susceptance plays an important role in power
systems, two scenarios have been conducted in this
case study to show that the proposal takes into
consideration the effect of line charging.

4.2.1 Scenario 1: This scenario considers line charging


Figure 5 Reactive power support from generator 2 and susceptance as a part of the network, that is system losses
System equal the losses created on transmission lines
(Losses ¼ I 2  Zline) lines. The data and results
summary of this scenario are shown in Tables 1 and 2,
The results shown in Figs. 6 and 7 are consistent with respectively.
previous results emphasising the locality nature of
reactive power. Generator 2 now can neither transmit It is found that Q req is consistent with intuitive
its real power output without the help of other expectation. Both generators 1 and 2 receive reactive
reactive power sources in the system nor support the power support from other reactive power sources
system with any reactive power as the setpoint voltage available in the system as both of them have contracted
of generator 2 has to be higher than the maximum loads (115 þ j 31.7) and (211 þ j 41.8) MVA,
limit of 1.1 pu in order to reach point ‘A’. respectively, and their allocated reactive power losses are
15.77 and 65.09 MVAr, respectively, whereas they are
It should be emphasised that a generator could producing 15.99 and 5.68 MVAr, respectively. Since the
depend on reactive power support of other sources to synchronous condensers have no contracted reactive
transmit its own real power output even if the power with loads, their outputs solely support the
generator is producing some reactive power as it can network with its need of reactive power. Thus
be seen in the results. This happens when Q req of the synchronous condensers at buses 3, 6 and 8 are net
generator is larger than its actual reactive power reactive power providers with 32.59 MVAr, 35.03 MVAr
injection. This phenomenon is crucial in deregulated and 20.74 MVAr, respectively as their outputs solely
energy markets even though it was not of interest in serve the network needs of reactive power. Results also
vertically integrated utility environments. Unless this show that transaction 2 relies more than transaction 1 on

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 521
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Figure 6 Reactive power flow and injections results of scenario 3


a Reactive power flow from bus 1 to bus 2
b Reactive power injections from generator 2 and System

Figure 7 Reactive power support from generator 2 and


System

reactive power help of others (generator 2 produces only Figure 8 IEEE-14-bus system
5.68 MVAr even though it trades larger amount of active
and reactive power) because transaction 2 has much
longer electrical distance to reach its destinations than participants, that is, every participant is allocated its
transaction 1 does. Therefore it requires more reactive share of the losses of transmission lines taking
power help to ship its output. To further illustrate this explicitly into consideration the effect of the reactive
point, the simulation is repeated with all reactive power power production of line charging susceptance.
being supplied only by generators 1 and 2 (assuming no
voltage violation occurs). The results in Table 3 show
that generator 2 now produces almost all its Q req as Table 1 Data of IEEE-14-bus system case study
both generators have similar relative locations in terms Generations Bus (contracted load in MVA)
of the electrical distance from the load center where all
contracted loads of transaction 2 are located. 1 2(21 þ j12.7), 3(94 þ j19)
2 4(47 2 j3.9), 5(10 þ j1.6), 6(15 þ j7.5),
9(30 þ j16.6), 10(9 þ j5.8), 11(15 þ j1.8),
4.2.2 Scenario 2: In this scenario, the line charging
12(35 þ j1.6), 13(30 þ j5.8), 14(20 þ j5)
susceptance is included in the allocations of

522 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Table 2 Results of IEEE-14-bus system case study

Transacion Load value Base case Without synchronous Condensers


number
MW MVAr Qreq , Gen. output, Gen. support, Qreq , Gen. output, Gen. support,
MVAr MVAr MVAr MVAr MVAr MVAr
1 115 31.7 15.8 23.26 224.24 17.65 49.41 20.79
2 211 41.8 66.83 13.01 295.62 81.17 121.12 211.45

Table 3 Results of IEEE-14-bus system case study without synchronous condensers

Transacion Load value Qreq Generator output, Generator Support,


number mVAr MVAr MVAr
MW MVAr
1 115 31.7 17.65 49.41 20.79
2 211 41.8 81.17 121.12 211.45

Therefore it is expected that Q req of participants will be 7.74 MVAr whereas generator 2 is reactive power
smaller than the values in Scenario 1 as participants consumer of 7.74 MVAr.
benefit from the reactive power injection produced by
line charging susceptance. The reductions in Q req of
participants are different as their benefits differ due to
their relative locations within the network and system 5 Determination of (Qreq) in pool
conditions. The results are shown in Table 4. It is markets: case studies
shown that the Q req of transaction 1 has decreased
significantly compared to transaction 2. This is 5.1 Simple two bus system for illustration
because transaction 1 benefits from the line charging Consider the system in Fig. 9 where System voltage is fixed
more than transaction 2 due to its relative location at 1.0 pu. All System generators and System loads are
with respect to the charging susceptance. The total represented by G (System) and Load (System),
reactive power produced by these lines is 13.11 MVAr respectively. Four scenarios are conducted to illustrate
(15.86% of the losses on transmission lines and 9.17% the proposed concept. Scenarios 1 and 2 assume that bus
of the total MVAr outputs of generators and 2 is a load bus as shown in Fig. 9a while the load at bus
synchronous condensers.). 2 is replaced with a generator in Scenarios 3 and 4 in
Fig. 9b. It should be noticed that the transmission line
The simulation is repeated without the synchronous solely serves the load or the generator at bus 2.
condensers (assuming no voltage violations occur) giving
the results shown in Table 5. Generator 1 produces
some excess reactive power more than its Q req which 5.1.1 Scenario 1: In this scenario, the load at bus 2
helps transaction 2 ship its contracted loads. This is changes from 1 to 100 MW in 1 MW steps while
expected as all the destinations of transaction 2 are in System load is fixed at 200 MW. The voltage of bus 2
the load center with electrical distance longer than that has a lower limit of 0.9 pu. The impedance of the
between generator 1 and its demands. As a result, transmission line is 0.015 þ j 0.2 pu. The simulation
generator 1 is considered a reactive power provider of results are shown in Fig. 10.

Table 4 Results of IEEE-14-bus system case study with explicit consideration of line charging susceptance

Transacion Load value Base case Without synchronous Condensers


number
MW MVAr Qreq , Gen. output, Gen. support, Qreq , Gen. output, Gen. support,
MVAr MVAr MVAr MVAr MVAr MVAr
1 115 31.7 6.48 23.26 214.93 9.97 49.41 7.74
2 211 41.8 63.03 13.01 291.82 87.06 121.12 27.74

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 523
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Table 5 Results of IEEE-14-bus system case study with explicit consideration of line charging susceptance while no reactive
power from synchronous condensers

Transacion number Load value Qreq , MVAr Generator output, Generator support,
MVAr MVAr
MW MVAr
1 115 31.7 9.97 49.41 7.74
2 211 41.8 87.06 121.12 27.74

Figure 9 One line diagrams of the two bus system for illustration (case study in Section 5.1)
a Scenarios 1 and 2
b Scenarios 3 and 4

Fig. 10b shows the results of applying (2) to calculate 5.1.2 Scenario 2: Scenario 1 is repeated here with the
reactive power support of each participant. These load at bus 2 is farther away. This is simulated by
results are consistent with expectation. The system increasing the line impedance to 0.015 þ j 0.3 pu.
load is supplied by the system generator at the same As the results show in Fig. 11, the traded power
bus without system losses, that is, without any line transferred from System to load 2 requires more reactive
flow on the transmission line, whereas load 2 is power help than that of Scenario 1. This is because the
supplied by the system generator through the transmission reactive power loss is higher than that of
transmission line. So, all the reactive power support Scenario 1 as a result of increasing the transmission line
that comes from the system generator is utilised to impedance. Again, the system load does not cause any
compensate the transmission losses caused by the reactive power needs due to the same reason explained
traded power transferred from System to load 2. Thus in Scenario 1.
the system generator and load 2 should be responsible
for this support cost. The total reactive power 5.1.3 Scenario 3: This scenario simulates the system in
support is fairly divided equally between the system Fig. 9b with a setpoint voltage of 1.0 pu at bus 2. The
generator and the load at bus 2. simulation results are shown in Fig. 12 where it can be

Figure 10 Reactive power flow and supports results of Scenario 1


a MVAr injection at bus 1
b MVAr supports

524 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Figure 11 Reactive power flow and supports results of Scenario 2


a MVAr injection at bus 1
b MVAr supports

seen that the system generator always injects reactive System for values of traded power less than 74 MW.
power, which increases as the traded power increases, to This means that the generator burdens the system
compensate the transmission line reactive power losses more than the load and receives some reactive power.
and maintain voltage profile. Since the transmission line This is also clear when applying (2) in which the
solely serves generator 2 by transferring its traded injected reactive power of the generator is negative
power, all the loss allocation and its need of reactive resulting in larger reactive support received by the
power help should be attributed to generator 2 and the generator. When the traded power is 74 MW, the
load it serves within the system. This can be seen from generator and the load receive the same reactive power
the figure where generator 2 and system load obtain support as the generator now does not generate nor
reactive power support from system generator. The absorb reactive power. This equal results are expected as
required reactive power (Q req) for generator 2 and that the reactive power support is dedicated to compensate
for the traded load are not equal. Even though this might the loss on the transmission line which serves solely the
appear contradictory to expectation and fair allocation, generator at bus 2 and the served load within the
the results are correct. This is easily explained when system. When the generator at bus 2 starts to provide
looking carefully to the simulation results of MVAr some reactive power satisfying part of its Q req, the
output of the generator at bus 2 shown in Fig. 13. remaining required reactive power is reduced compared
Generator 2 absorbs (draws) some reactive power from to that of the load.

Figure 12 Reactive power flow and supports results of Scenario 3


a MVAr injection at bus 1
b MVAr supports

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 525
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

than the value at point A, G (System) starts


participating in the transmission needs of reactive
power in which both generator 2 and G (System)
cooperate in providing the Q req of system load. So,
generator 2 and the system generator are considered
reactive power providers whereas system load is
considered a reactive power consumer.

It should be emphasised that a generator could


depend on other reactive power sources in the system
to ship its own real power output even if the
generator is producing some reactive power as it can
be seen from the simulation results. This happens
when Q req of a generator is larger than its actual
reactive power injection. Similarly, a load could be
considered a reactive power consumer even if it is a
Figure 13 Reactive power outputs of system and the pure unity power factor demand. On the other side,
generator at bus 2 of Scenario 3 the only portion of a generator’s reactive power
output that is greater than its Q req should be
considered as a system support. This phenomenon is
5.1.4 Scenario 4: Scenario 3 is repeated when crucial in deregulated energy markets even though it
generator 2 has a setpoint voltage that equals 1.06 pu. was not of interest in vertically integrated utility
The results shown in Fig. 14 are consistent with environment. Unless this phenomenon is taken into
previous results. Generator 2 now is able to support consideration in reactive power procurements and
the system with reactive power over the whole range payments, some generators would actually subsidise
of traded power. Point A in Figs. 14a and 14b other participants on the system which can be seen as
deserves special attention. For the traded power imperfect competition.
quantities less than that at point A, generator 2, by
injecting reactive power more than its Q req , provides
all the needed reactive power on the transmission line 5.2 IEEE-14 bus system
as well as some extra reactive power to support The proposed concept of Q req is tested on the IEEE-14
System. When the traded power of generator 2 bus system. The results summary is shown in
reaches point A, System stops receiving reactive Tables 6 and 7.
power support from generator 2 and all the reactive
power needs of the transmission line is provided by It is found that Q req is consistent with intuitive
generator at bus 2, that is G (System) outputs zero expectation in which traded power quantity and relative
reactive power. For quantities of traded power higher locations within the network are reflected on the results.

Figure 14 Reactive power flow and supports results of Scenario 4


a MVAr injection at bus 1
b MVAr supports

526 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

Table 6 Results of IEEE-14-bus system case study (loads)

Bus Load Qreq , Load support,


number MVAr MVAr
MW MVAr
1 0 0 0 0
2 21.7 12.7 0.0481 20.0481
3 94.2 19 15.5040 215.504
4 47.8 23.9 4.3964 24.3964
5 7.6 1.6 0.1191 20.1191
6 11.2 7.5 1.2073 21.2073
7 0 0 0 0
8 0 0 0 0
9 29.5 16.6 5.7663 25.7663
10 9 5.8 0.6261 20.6261
11 3.5 1.8 0.1048 20.1048
12 6.1 1.6 0.4468 20.4468
13 13.5 5.8 1.9751 21.9751
14 14.9 5 1.9313 21.9313

Loads close to generators have small Q req compared to situation, generator 2 is a reactive power provider while
those far from generation sources. Load 2 has the generator 1 and all loads are considered reactive power
smallest Q req benefiting from the local generator at consumers.
bus~2 while load 3 has the highest one due to its large
demand which needs to travel from generator 1 Similar to bilateral markets, the line charging
and 2. The results show that all the outputs of the susceptance can be easily included in Q req of each
synchronous generators are considered as reactive power participant resulting in different reductions for different
support delivered to the system which is expected since participants according to their relative locations. To avoid
their only function is to support the system with reactive unduly long paper, the simulation results here are omitted.
needs in order to compensate reactive losses and to
maintain voltages within limits. As stressed earlier,
generator 1 is considered a reactive power consumer, 6 Generalisation
that is, it draws some reactive power from the system, The proposed concept of Q req using CAF method is
even though it is generating some reactive power generalised to be applied using any appropriate loss
whereas generator 2 provides some reactive power allocation method. Q req is defined as the minimum
support to the system. This is because the output of reactive power requirement, respecting all system
generator 1 is less than its Q req whereas generator 2 conditions, for a participant and it equals its allocated
produces reactive power more than its Q req . In this reactive power loss using any appropriate loss

Table 7 Results of IEEE-14-bus system case study (generators and synchronous condensers)

Bus number Qreq , MVAr Generator output, MW Generator output, MVAr Generator support, MVAr
1 2.2736 105.87 1.8772 20.3964
2 5.8012 162.28 7.7206 1.9194
3 0 0 40 40
6 0 0 7.9616 7.9616
8 0 0 6.7756 6.7756

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 527
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

allocation method. Then a participant reactive power operators about where reactive power is most needed. It
support, Q TSupport
i
, can be defined as follows also drives participants to optimise their contracts taking
8 T into consideration both real and reactive power. In
> Ti addition, it encourages new entrants of reactive power
< Q Inj  Q Alloc losses
i

Ti providers to enter the market at the right locations.


Q Support ¼
> Q Tcont
i
in bilateral markets However, since it is assumed in this paper that the
: Q Ti  Q Ti in pool markets system is operating on heavy loaded conditions where
Inj Alloc losses
reactive power production is needed, another paper is
(3) being prepared to extend the applicability of the
proposals to light loaded conditions in which ‘excess’
where Q TAlloc
i
losses is the allocated losses to participant Ti reactive power needs to be absorbed.
using any appropriate loss allocation method.
So, instead of having fixed reactive power requirements 8 References
from participants in electricity markets, which is the
current practice, the new general concept assigns each [1] LO K.L., ALTURKI Y.A.: ‘Towards reactive power markets.
participant its own obligation of reactive power part 1: Reactive power allocation’, IEE Proc. Gener.
participation based on its allocated reactive power loss Transm. Distrib., 2006, 153, (1), pp. 59– 70
using any appropriate loss allocation method. Choosing
the loss allocation method is a policy issue that is [2] ALVARADO F., KIRSCH L.D., CHRISTENSEN L.R.: ‘Reactive power as
determined by the energy market regulator. an identifiable ancillary service’. Technical Report, DEC-TR-
506, Christensen Associates, Inc, Madison, USA, 2003
7 Conclusion [3] LUIZ DA SILVA E., HEDGECOCK J., MELLO J., FERREIRA DA LUZ J.: ‘Practical
Reactive power has become increasingly a crucial issue in cost-based approach for the voltage ancillary service’, IEEE
deregulated energy markets. It has been recognised as Trans. Power Syst., 2001, 16, (4), pp. 806–812
one of the important ancillary services that should be
procured competitively and fairly charged for. This paper [4] DAI Y., NI N.Y., WEN F., HAN Z.: ‘Analysis of reactive power
has two main contributions. First, it has proposed a new pricing under deregulation’. Power Engineering Society
method to determine the actual reactive power Summer Meeting, Seattle,WA, USA, July 2000, pp. 2162– 2167
providers and consumers. It is based on the proposed
concept of market reactive power requirement (Q req) [5] LAMONT J.W., FU J. : ‘Cost analysis of reactive power
from each participant conducted on the network. Q req support’, IEEE Trans. Power Syst., 1999, 14, (3), pp. 890– 898
of a participant equals its allocated reactive power loss
using CAF method proposed in part 1 of this two-part [6] MUCHAYI E.-H.M., EL-HAWARY M.: ‘A summary of algorithms
set paper. Every participant is considered as a net in reactive power pricing’, IEEE Trans. Electr. Comput.
reactive power provider if it produces reactive power Eng., 1995, 2, pp. 692 – 696
more than its Q req while respecting SO instructions. On
the contrary, a participant that requires reactive power [7] BAUGHMAN M.L., SIDDIQI S.N.: ‘Real-time pricing of reactive
help from other sources as its production of reactive power: theory and case study’, IEEE Trans. Power Syst.,
power is less than its Q req is considered as a reactive 1991, 6, (1), pp. 23 – 29
power consumer. The proposed concept is applicable in
bilateral markets as well as pool markets. In bilateral [8] STANIULIS R.: ‘Reactive power valuation’, Master’s thesis,
markets, every transaction as a whole, including load Department of Industrial Electrical Engineering and
and generator parties, is assigned its own Q req while in Automation, Lund University, Lund, Sweden, 2001
pool markets, every participant, load or generator, is
assigned its own Q req . The second contribution is the [9] XU W., ZHANG Y., SILVA L., KUNDUR P., WARRACK A.: ‘Valuation of
generalisation of the concept by which the reactive dynamic reactive power support services for transmission
power requirement for participants differ according to access’, IEEE Trans. Power Syst., 2001, 16, (4), pp. 719– 728
their reactive power loss allocation using any appropriate
loss allocation method approved by the regulator. The [10] KIRSCHEN D., ALLAN R., STRBAC G. : ‘Contributions of
proposals have been tested extensively on many case individual generators to loads and flows’, IEEE Trans.
studies, but due to space limit, only selected results are Power Syst., 1997, 12, (1), pp. 52 – 60
presented in this paper. The results show validity of the
introduced proposals. The proposed method and concept [11] STRBAC G., KIRSCHEN D., AHMAD S.: ‘Allocating transmission
help to have a fair and sound technical basis for reactive system usage on the basis of traceable contributions of
power compensation in electricity markets. It sends generators and loads to flows’, IEEE Trans. Power Syst.,
indicative signals for both contractors and system 1998, 13, (2), pp. 527– 534

528 /IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516 – 529 & The Institution of Engineering and Technology 2008
doi: 10.1049/iet-gtd:20070370
www.ietdl.org

[12] KIRSCHEN D., STRBAC G.: ‘Tracing active and reactive power [14] ALTURKI Y.A.: ‘Real and reactive power allocations in
between generators and loads using real and imaginary electricity market’, PhD dissertation, University of
currents’, IEEE Trans. Power Syst., 1999, 14, (4), pp. 1312–1319 Strathclyde, Glasgow, UK, 2006

[13] WANG Y., XU W.: ‘An investigation on the reactive power [15] KODSI S. , CANIZARES C.A.: ‘Modeling and simulation of
support service needs of power producers’, IEEE Trans. ieee 14-bus system with facts controlers’. Technical Report,
Power Syst., 2004, 19, (1), pp. 586 – 593 E&CE, University of Waterloo, Waterloo, 2003

& The Institution of Engineering and Technology 2008 IET Gener. Transm. Distrib., 2008, Vol. 2, No. 4, pp. 516– 529/ 529
doi: 10.1049/iet-gtd:20070370

You might also like