GODREJ PROPERTIES LIMITED

Incident Investigation Report


(Category 6 to 7)

Ref.No. GPL F HS 21 Date: 20-10-2020

Rev.No.: 00 Page no.: 01 of 04


Tower D 1st floor Lobby
Site GODREJ 24 Location Date 16.06.2022
area
A. Event Time & Date :-
Incident Date : 27 6 2022
Incident Time : 4 30 PM

B. Event Type :-
a. First Aid
: c. Minor incident :

non-reportable but
b. Near Miss d. medical treatment injury :
:

C. Injured Person Details :- (NA in case of Near miss & Minor incident )
Name :- first name last name middle name
Employee Number/ID :- Job Title :-
No.
Employment Type :- Temporary : Permanent :
Designation :-
Date of Joining :- Date of Induction :-
NA :-

D. Incident Description :- ( add separate sheet if require )


It was reported that a piece of glass used for uPVC window was left after work at tower D 1st floor & the same was found
damaged/broken.

E. Cause of Incident :-
a. Fall from Height : b. Machinery / Plant :
c. Hot Substances : d. Objects Falling :
e. Transport : f. Hazardous Substances :
g. Handling goods : h. Electricity :
i. Slips/ trips / falls : j. Fire Explosion :
k. Stricking against objects : l. Hand tools :
m. Dust / mud in eyes : n. other, :
2
Site GODREJ 24 Location Tower D 1st floor Lobby Date 16.06.2022
area
F. Actual Activity Leading To Incident
a. Using portable plants / equipments : b. Driving :
c. Handling hazardous materials : d. Operating plant / machinery :
e. Grinding : f. Breaking connections :
g. Assembling / dismantling : h. welding / burning :
i. Scaffolding : j. loading / unloading :
k. Draining / flushing : l. Cleaning :
m. Climbing / descending : n. Painting :
o. Working at height : p. Mechanical lifting :
q. Working at depth : r. manual handling :
s. Digging : t other, :

G. Possible Immediate Cause


a. Failure in communication : b. Poor Housekeeping :
c. Inadequate PPE's : d. Failure to follow procedures :
e. Failure to use safety devices : f. Improper Manual Handling :
g. Faulty tools / equipemnts : h. Insufficient time for task :
i. Work environment : j. Misuse of tools / equipments :
k. Fatigue / illness : l. Poor lighting :
m. No supervision : n. Improper maintenace :
3
Site GODREJ 24 Location Tower D 1st floor Lobby Date 16.06.2022
area
H. Medical Details :- (NA in case of Near miss & Minor incident )
Part of body affected ( X for the main injury and √ for the other injuries)

a. N/A : b. feets & toes :


c. Chest & Abdomen : d. Lungs :
e. Shoulder, arms, elbow, forearm : f. Multiple Injuries :
g. Eyes : h. Pelvis :
i. Neck & spine : j. Hand, fingures & thumb :
k. Knees, ankle,legs : l. Ears :
m. Head : n. None :
NA :
Comments : -
…………………………………………………………………………………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………………………………..

I. Nature Of Injury :- (NA in case of Near miss & Minor incident )

a. Fatal : b. None :
c. Foreign bodies : d. Sprain / strain :
e. Amoutation : f. Burns :
g. Irradation : h. Crushing Injuries :
i. Asphyxiation : j. Fainting :
k. Fractures : l. Electrical shock :
m. Puncture : n. Exposure to hazardous substances :
o. Drowning : p. Ingestion :
q. Dislocations : r. Bruising with intact skin :
s. Other, Specify : NA :
4
Site GODREJ 24 Location Tower D 1st floor Lobby Date 16.06.2022
area
J. Root Cause :-
a. Inadequate Knowledge / skill : b. Inadequate physical / mental capability :
c. Inadequate Equipment : d. Stress :
e. Inadequate planning / procedures : f. Negligence :
g. Inadequate maintenance : h. Inadequate supervision :
i. Inadequate management support : j. Inadequate PPE's :
1 St Root Cause/s (Detail):

1. Workmen installing the glass piece to uPvc window had left the glass piece at floor after completion of work

K. Correction/s & Corrective action/s :-

1. Store keeper/site engineer will track the loose glasses issued, installed & returned on daily basis.
2. Workman carrying glass installation workmen has been educated on manual handling safety
3. The incident has been discussed in next day TBT

L. Learning From Incident :-


Necessary control measures shall be followed during storing & handling of loose glass materials

Date : 16 : 6 : 2022

Project Manager (Contractor) Project Manager PMC

MR.YRS Yeshwanth MR. Bopiah Sannu


Project safety incharge Project Manager (GPL)