SUNWAY CONSTRUCTION SDN BHD

PROJEK KLCC P1

HAZARD & EFFECT REGISTER (HER)


DESCRIPTION OF ACTIVITY : DEEP EXCAVATION –
DIV/DEPT : SUNWAY CONSTRUCTION PREPARED BY :
STORM WATER DRAINAGE
LOCATION : KLCC HER NO : 01 REV NO : 00 REVIEWED BY :

TYPE OF ACTIVITIES : ROUTINE/ NON ROUTINE/EMERGENCY DATE : 20 / 02 / 2014 Page : 1 of 2 APPROVED BY :


Hazard (1) Threat (6) Barrier (7) Top Event (2) Control / Recover Consequences (3) Risk Rating (4) Initial Risk Final Risk Level Remedial Action
Measure (8) P A E R Level (5) (9) Plan (10)
1. Sub-activity : - Excavation
Unstable of soil Raining, Safety work Soil collapse Emergency Recovery Fatality H - H H H M Nil
Weather instruction Team
Training Special toolbox by
Tool Box treat
ERP Cover soil with plastic
sheet
Deep Raining, Safety work Fall from height Emergency Recovery Fatality H - H H H M Nil
Excavation Weather instruction Buried by soil Team
Soil failure Hard Special toolbox by
Barricade treat
Training Cover soil with plastic
Tool Box sheet
ERP Strengthen the slope
2. Sub-activity : - Level check by surveyor
Uneven surface Slippery surface Housekeepin Falling from Emergency Recovery Major Injury H - - H H M Nil
Poor g height Team
Housekeeping Toolbox Trip and Fall Special toolbox by
treat

3. Sub-activity : - Mobilization & Demobilization of Machinery


Machinery Negligence of Safety work Machine Topple Emergency Recovery Fatality H H M H H M Nil
operator instruction Team
Training Special toolbox by
Competent & machinery
Certified
Operator
ERP

Revision No.: 02, Date : 20/02/2014 Issues No.: 01 Effective Date: 01/03/2009
Page 1 of 2
SUNWAY CONSTRUCTION SDN BHD
PROJEK KLCC P1

HAZARD & EFFECT REGISTER (HER)


DESCRIPTION OF ACTIVITY : DEEP EXCAVATION –
DIV/DEPT : SUNWAY CONSTRUCTION PREPARED BY :
STORM WATER DRAINAGE
LOCATION : KLCC HER NO : 01 REV NO : 00 REVIEWED BY :

TYPE OF ACTIVITIES : ROUTINE/ NON ROUTINE/EMERGENCY DATE : 20 / 02 / 2014 Page : 2 of 2 APPROVED BY :


Hazard (1) Threat (6) Barrier (7) Top Event (2) Control / Recover Consequences (3) Risk Rating (4) Initial Risk Final Risk Level Remedial Action
Measure (8) P A E R Level (5) (9) Plan (10)

PREPARED BY : ……………………………………… APPROVED BY : …………………………………..(PIC) SUPERVISOR : ……………………………………..

NAME: ZAHRUL HUZAIRI HUSSIN NAME: NIRMALENDU KUMAR DAS NAME:______________________________

Revision No.: 02, Date : 20/02/2014 Issues No.: 01 Effective Date: 01/03/2009
Page 2 of 2