RA No.
ACTIVITY: BLOCK WORKS
DATE
POTENTIAL HAZARDS / CONDITIONS CONSIDERED (TICK BOX) PERSONS AT RISK (TICK BOX)
SAFE WORK PLACE PROPER BARRICADE AND WARNING SIGN IN THE AFFECTED AREA
H (HIGH-Potential to cause death or permanent injury) M (MEDIUM – Potential to cause loss time injury) L (LOW – An injury treatable with First Aid)
1. IMPROBABLE. 1. NEGLIGIBLE.
HIGH = 15 – 25 4 4 8 12 16 20
2. REMOTE. 2. MINOR.
3 3 6 9 12 15
3. PROBABLE 3. REPORTABLE. MEDIUM = 07 – 14
2 2 4 6 8 10
4. OCCASIONAL. 4. SERIOUS. LOW = 01 - 06
1 1 2 3 4 5
5. FREQUENT 5. CATASTROPHIC.
1 2 3 4 5
SEVERITY (S)
NOTE: 1. Risk assessment must be addressed to workers by work in charge before starting job.
2. Risk assessment is a continuous process hence to be reviewed depending on activity and risk
involved
Logo RISK ASSESSMENT Document number
Ensure unloading area is leveled and barricaded for material storage. Site Manager/
Serious Crush
Site Engineer
Injury, Flagman required for guiding trailers to the agreed location.
01. Site Traffic. 3X5 Site L
Property Damage, Always follow the traffic management signs on the site.
Supervisor/
Ensure all drivers are having valid driving license Site Security.
Check & calculate SWL of the materials before lifting with crane, ensure
crane has capacity to lift.
Ensure certified banks man unload any heavy items required by crane.
Use proper block lifting methods to lift the block pallet. Never lift the block
Site Engineer
in wooden pallet with webbing slings. (Use block lifting cage, or material
Serious Injury, Site
02. Lifting Operation. 3X5 shifting skips) L
Property damage. Supervisor/
All lifting gear for offloading materials to be certified and submitted to BM
Banks man
HSE Dept. prior to use.
Ensure materials elevated from ground with timber bearers or similar and
separated with timber blocks to ensure safe slinging prior to lifting.
Ensure appropriate PPE used (hand gloves etc)
Permanent
Disability, Ensure only lighter items are unloaded by hand. Use manual lifting
Sprain, procedures.
Spinal defect, Use Mechanical lifting equipment to Lift where possible.
Property Do not allow anyone to carry loads above his capacity (25 kg / person per
Damages, lift) and also allocate enough people to handle the load. Site Engineer
03. Manual Handling Lacerations 3X4 Ensure all materials are to be moved by hands, the size of material should Site L
Crushing of not be above the size and the employee can be easily to move. Supervisor.
Hands or The bulky materials which are restricting visibility should not be moved by
Fingers, hand.
Bruised or Use handling aids to lift / move the load.
Broken Toes or Allocate sufficient number of people for heavy items shifting by manual.
Feet
04. Fall from height - Working Serious Injury, 3X5 Site Manager/ L
Ensure all labour is aware of approved Method Statement and block
at height Disability, Site Engineer
installation sequences.
Fatality Site Supervisor
Safe and secured working platform to be provided for the installation.
Property Damage, Operatives.
Working platform to be inspected by competent person and scafftag to be
provided.
Never over load the platforms with materials and blocks pallet to be
stacked on slab away from the slab edge or openings as appropriate.
Ensure all people are equipped with full body harness and hook it on rigid
place.
Logo RISK ASSESSMENT Document number
Ensure that all the operatives exposed to leading edge during block work
shall use fall restraints or proper fall arrest systems.
Ensure full time supervision.
Always follow work permit system to work in shaft area and to remove or
alter permanent edge protection.
Ensure all power tools are inspected and tagged by BM HSE Dept prior to
Permanent use.
Disability, Noise, Ensure grinders are secured with safety guard and leads/cables are safe.
Environment Always use correct cutting disk for the task. Only experienced persons are
impact (Dust). allowed to use grinders.
Property Only authorized and trained persons are allowed to use any cartridge to fix
Damages, block tie on rigid structure.
Lacerations,
All the cartridge tools operators are fully aware of the safe installation and Site Engineer
Incorrect use of Power Crushing of Hands
operations of the tools as per manufactures instructions. Site
06. Tools, Cartridge Tools and or Fingers. 3X5 L
Ensure that only authorized personals are deployed to work with wet Supervisor,
Hand tools. Permanent
cutting machines. Store Keeper
Disability, Noise,
Environment Ensure that all the wet cutter operators are fully aware of the risk related
Impact Property with the block cutter.
Damage, Block and concrete cuttings are only allowed in properly ventilated area.
Laceration Pedestal fan/Water to be used to control heavy dust during the cutting.
Crushing of Hands Keep all hand tools and power tools in good condition.
or Fingers Ensure appropriate PPE used (hand gloves and goggles, mask and ear
muff/plug for grinding as required etc).
Logo RISK ASSESSMENT Document number