Date Effective: 08-07-11 Documentation No. Rev.

00-01
SSPI-SMM-05-07
Approved by: Managing Director

JOB RISK ASSESSMENT FORM Prepared by: ODPA


Revised Date 14/05/2015

VESSEL: M/V GEMINI 2

Work Area of Job Activity UNDER WATER HULL SURVEY (TRANSDUCER) Plan your work safely
Your life may depend on it
JRA No.: DISPLAY ON WORKSITE Date:
Page: 1 of 1 11 NOV.2020
Safety PPE, Tagline, Watch man standby w/
portable VHF Radio.
NO. WORK ACTIVITY HAZARD POTENTIAL EFFECT SEVERITY LIKELIHOOD RISK RATING MITIGATION RESIDUAL
(S) (L) FACTOR (SXL) RISK

Under water hull inspection Machineries running in the Complete PPE, provide Operation
tagline,1 compressor set for must be
1 and repair. E.R possible it caused of continued
2 2 2 diving and watchman
danger for the diver.
standby w/ VHF radio.

Legend:
Severity: LIKELIHHOD: Risk Rating Factor: Mitigation:
1 – Slightly Harmful 1 – Highly Unlikely 1- Trivial Trivial & Tolerable . Engineering
2 – Harmful 2 – Unlikely 2 & 3 - Tolerable . No Action Required . System of Work
3 – Very Harmful 3 – Likely 4 & 6 - Moderate . Warning Signs . PPE
4 – Extremely Harmful 4 – Very Likely 8 & 9 - Substantial Moderate & Substantial Intolerable
12 & 16 – Intolerable . Removal . Urgent and Positive Action, Work must be stopped
. Substitution . Operation must be continued
Risk Rating level should reduce at least 1 step downward after mitigation = (residual Risk).