CONTROL (HIRADC)
COMPANY : BGMC CORPORATION SDN BHD WORK ACTIVITY : EXCAVATION MORE THAN 1.5METER
COMPANY : BGMC CORPORATION SDN BHD WORK ACTIVITY : EXCAVATION MORE THAN 1.5METER
COMPANY : BGMC CORPORATION SDN BHD WORK ACTIVITY : EXCAVATION MORE THAN 1.5METER
surface and firm ground and safe supervisor & engineer. Supervisor
inadequate access access route for - Provide hard barricade at
- Machine topple moving machinery. edges.
- Hand or leg - Traffic controller to - Site engineer and supervisor
injury assist the operator in shall instruct machine
excavating operator, banksman &
workers of any adverse for
precautions.
- Bad weather - Temporary hold work 3 3 9 - Toolbox talk 2 2 4 Engineer/
(Heavy rain and move to safe - Pre start briefing Supervisor
and lightning) shelter area. - PTW/JHA
- Lightning strike - (Lightning less than
10 km to the site)
- Knock by - Speed limit and traffic 3 3 9 - Pre start check. 2 2 4 Supervisor
machine control - Toolbox talk
- Property damage - Hard barricading and - JHA
or injury to person signage to display
- Falling into pit - Waterproofing sheet 3 3 9 - Display signage 2 2 4 Supervisor
- Leg, head or or geotextile to protect - Pre start talk
hand injury slope protection
Failure of -Nobody shall stand 3 3 9 -Increase supervision by 2 2 4 Supervisor
machinery under or near Supervisor
excavator boom - Highlight the setting out hazard
-Proper signage to on-site in toolbox meeting
be displayed at Provide refreshment training
strategic locations
so that unauthorized
person cannot enter
-Fire Extinguisher to
COMPANY : BGMC CORPORATION SDN BHD WORK ACTIVITY : EXCAVATION MORE THAN 1.5METER
be provided on the
machine
-Ensure inspection
stickers displayed at
machine
-Collapse of -Ensure to follow 1:1 3 3 9 -Increase supervision by 2 2 4
excavation slope during Supervisor
(Soil slippage) excavation when -Highlight the setting out hazard
depth exceeds 1m on-site in toolbox meeting
-Excavation / trench -Provide refreshment training
were safe slope is
not able to be
provided competent
person shall design
the excavation by
providing earth
retaining measures
-Excavation shall be
done as per
foundation
construction
drawings
-Excavation shall be
carried out according
to Method Statement.
7. Access / Egress - Limited space - Safe working access 3 3 9 - Safe access and egress to 2 4 Project
route - Unhealthy work to be provided. be maintain always in safe Manager
2
place (scaffolding ladder w condition. Supervisor
Engineer
COMPANY : BGMC CORPORATION SDN BHD WORK ACTIVITY : EXCAVATION MORE THAN 1.5METER
- Uneven ground - Provided firm and 3 3 9 - -To monitor access and 2 4 - Supervisor to
2
- Injury to a safe access egress. remind the
person. workers
repeating.
9. Temporary earth - Speeding - Speed limit 20 km/h. 3 3 9 - Proper maintenance on all 2 2 4 Supervisor
dumping area - Property - Pre-task briefing or moving machineries.
damage reminder continuously. - Close supervision by
supervisor.
COMPANY : BGMC CORPORATION SDN BHD WORK ACTIVITY : EXCAVATION MORE THAN 1.5METER
* Note: The description and level of severity and probability may vary, subjected to project, legal and other requirement. Loss on property damage can be incorporated and shall be in accordance
to project requirement.
RISK RANKING
LIKELIHOOD RATING SEVERITY DESCRIPTION
Level Score
Very Unlikely, Probably Will Not Happen, Minor injury or ill health requiring first aid only, no lost
1 First Aid Injury / Non-Lost Time Injury L LOW (1-3)
Yearly of work time.
Unlikely, Rarely, 6 months 2 Minor Injury / Minor Ill Health / No Lost Time Injury Moderate injury or ill health requiring treatment. M MEDIUM (4-8)
Major Injury / Major Ill Health / Permanent Disability / Lost
Likely, Occasionally, 3 Serious bodily injury or serious work caused ill health. H HIGH (9-12)
Time Injury / Occupational Diseases
Very Likely, Monthly 4 Fatality & Property damage Death. VH HIGH (16)