TWO WEEK PLAN (From 11-Sep-22 to 24-sep-22)
Project Diversion pf existing railway line near Hofuf
OWNER SAUDI RAILWAYS ORGANIZATION
CONSULTANT SAUDI CONSULTING SERVICES
MAIN CONTRACTOR AL MOBTY COMPANY
SUB CONTRACTOR CHINA RAILWAY ENGINEERING GROUP NO.2
Water tanker
Skilled Labor
Compactor
Dam truck
Steel fixer
Carpenter
Excavator
UnSkilled
Vibrator
Trailler
Loader
Planned
Crane
Labor
S.No Activity Name Activity Duration Unit Qty %
A Mobilization
1 Mobilization 14 100%
B Bridge NO.1
1 Re-excavation of temporary backfilling at abutment 2, backwall area 2 CUM 175 100%
32 7
2 Surface preparation (Cleaning), abutment 2, backwall area 1 Sq.M 64 100%
3 Water proofing with two coal tar, abutment 2, backwall area 2 Sq.M 64 100%
4 Supply and installation of water proof membrane,abutment 2, backwall area 5 Sq.M 64 100%
5 Abutment wall backfilling 6 CUM 319.64 20%
B · Bridge NO.2
1 Subcontractor Agreement signing (Jeddah Foundation) 2 100%
2 Purchasing steel for bored piling & delivery to site 14 ton 280 100%
B · Bridge NO.3
1 Dilivery of material for gridder 100%
1.1.B Trumpet for three gridder 1 pic 21 100%
1.2.B Saddle (Duct Grout pipe connection), for three gridder 1 pic 15 100%
2 Repainting of steel rebair (small portion), all three gridder 1 100%
3 Fixing of Trumpit & Saddle, only one gridder 3 100%
27 5
Consultant inspection, for steel, only one gridder 1 100%
4 Form work installation, one girdder 5 100%
27 5