Professional Documents
Culture Documents
Important Point
Grillage Foundation
Types of Grillage Foundation
o 1. Steel Grillage Foundation
o 2. Timber Grillage Foundation
o Grillage Foundation Project
o Features of Grillage Foundation
o Installation of the Grillage Foundation
Advantages of Grillage Foundation
Disadvantages of Grillage Foundation
o Grillage Foundation
o What is a Grillage foundation?
o Is Grillage Foundation a deep foundation?
o Is Grillage a code for foundation?
o What is timber Grillage foundation?
o How do you make a Grillage foundation?
o What is a Grillage beam?
o What is a steel Grillage?
o What is Grillage in engineering?
Grillage Foundation
A foundation consisting of one, two or more layers of beams (typically steel)
superimposed on a concrete layer to disperse the load over a large area is a
foundation for grilling.
Although the foundation and the grid look the same, they are different. Where
the foundation transfers the load from the structure to the ground, the grid
disperses heavy loads over large areas.
The depth of the concrete must be at least 15 cm. After leveling the base and
pouring the concrete, we must check that the compaction is done properly and
that an impermeable layer of a thickness of not less than 15 cm is formed.
It protects steel beams from groundwater, which can lead to corrosion. Then,
we place the first layer of beams on the concrete bed at a distance of 100 to
300 mm, with the help of tube separators.
Then, we pour concrete between and around the beams of the first layer. After
that, we place the second beam level at right angles to the first levels with the
help of the separator.
Then again, we pour concrete between and around the steel beams. In doing
so, we connect the steel supports to the top layer with the help of a base
plate, side angles, and a reinforcement plate.
These connecting elements are also embedded in the concrete to make the
joint rigid.
Timber planks and Timber beams are used instead of steel beams. there is no
concrete enclosed between the Timber joints.
However, the lower concrete supplied in the steel grid is replaced by a Timber
platform built with Timber planks.
The excavation of the base is level. The bottom layer of Timber boards of size
20 to 30 cm and width of 5 to 7.5 cm thick is placed side by side, with no
space between them.
Above this layer, a Timber beam of the same section as that of the Timber
post is placed at a right angle.
Then, another layer of planks is placed again at right angles to the direction of
the beams. The top layer of boards maybe 7.5-10 cm. Thick, extending the
entire width of the base of the wall, on which the masonry wall is built.
Also, read: What Is Raft Foundation | Type of Footing | Detail of Raft
Footing
From this, we need to determine the base area required for an adequate
allowable ground bearing pressure of the condition.
Dividing this area, we will find the numbers and the size of each grid layer.
Next, we have to design the layer so that it slopes from the edge of the layer
above.
It will determine the beam sizes needed to withstand bending moments and
shear forces.
The grid cannot be enclosed in concrete and in order, as the composite action
of the beam and concrete will be demoralized. The method of construction
and loading must be compatible with the needs of the project
1. First, for the solid monolithic grid, we need to produce and install
the structure. We prefer this barbecue because it is more reliable.
2. The formwork is made of edge boards in the form of rectangular
gutters. Its height is 1 foot and width is equal to the minimum
thickness of the house wall. A space of about 15 to 30 cm should
be defined between each grid.
3. Within the formwork, we have to define a reinforcement connection
structure using the connecting wire. The shortest distance from the
structure next to the formwork must be the same.
4. Then, the reinforcement is connected to the same connecting wire
used previously.
5. Then, the concrete must be prepared with the cement mixer. It is
poured into the formwork in a continuous cycle. The connections
must be placed at a height of about 25 to 30 mm so that they are
completely immersed in the concrete. Concrete must be poured
with care to avoid unwanted cavities. 6. After filling the surface, it
should be leveled and left to dry. When dry, the formwork can be
removed. The foundation is ready now.