You are on page 1of 6

Estimate of Raw Materials Use

A. Concrete Works
A.1.FOOTING F1
THICKNESS, m 0.50
LENGTH, m 2.00
WIDTH, m 2.00
NO. of pcs 24
VOLUME 48.00
V.TOTAL 48.00 m3

No. of CEMENT 432 bags


V.SAND 24.00 m3
V.GRAVEL 48.00 m3
V.H20 9824 L

A.2.COLUMN C1
HEIGHT, m 14.40
LENGTH, m 0.40
WIDTH, m 0.40
NO. of pcs 24
VOLUME 55.30
V.TOTAL 55.30 m3

No. of CEMENT 498 bags


V.SAND 27.65 m3
V.GRAVEL 55.30 m3
V.H20 11317 L

A.3.BEAMS B-1 B-2 B-3 B-4


HEIGHT, m 0.35 0.35 0.35 0.40
LENGTH, m 3.60 2.60 1.00 3.60
WIDTH, m 0.30 0.30 0.30 0.30
NO. 32.00 4.00 12.00 32.00
VOLUME 12.10 1.09 1.26 13.82
V.TOTAL 29.52 m3

No. of CEMENT 266 bags


V.SAND 14.76 m3
V.GRAVEL 29.52 m3
V.H20 6041 L

A.4.SLAB A1 A2
LENGTH, m 15.00 15.00
WIDTH, m 12.00 14.00
AREA 180.00 630.00
THICKNESS, m 0.15
VOLUME 27.00 94.50
V.TOTAL 121.50 m3

No. of CEMENT 1093.50 bags


V.SAND 60.75
V.GRAVEL 121.50
V.H20 24866.19

SUMMARY:
No. of CEMENT 2289 bags
V.SAND 127.16 m3
V.GRAVEL 294.82 m3
V.H20 52049 L
B. Masonry
• 6-inch CHB total area = 398.6 sq. m.
• 4-inch CHB total area = 775.36

*1 sq. m. CHB = 12.5 pieces


o 6-inch CHB quantity = 4983 pieces
o 4-inch CHB quantity = 9693 pieces

6"CHB 0.0068 4"CHB 0.0035


No. of CHB 4983 PCS No. of CHB 9693 PCS
MORTAR: MORTAR:
V 35.58 m3 V 33.93 m3
No. of No. of
CEMENT 320 bags CEMENT 305 bags
V.SAND 35.58 m3 V.SAND 33.93 m3
V.H20 7281.52 L V.H20 6943.19 L

PLASTER: ROUGH PLASTER: ROUGH


V 15.70 m3 V 30.53 m3
No. of No. of
CEMENT 141.27 bags CEMENT 274.80 bags
V.SAND 20.88 m3 V.SAND 40.61 m3
V.H20 3212.44 L V.H20 6248.87 L

FINE FINE
AREA 100.71 m2 AREA 45.26 m2
No. of No. of
CEMENT 25 bags CEMENT 11 bags
V.H20 572.51 L V.H20 257.33 L

SUMMARY:
6" CHB 4983 pcs
4" CHB 9693 pcs

No. of CEMENT 1079 pcs


V.SAND 130.99 m3
V.H20 24516 L
C. Steelworks
C.1. Footing
F1:
No of PC/Footing 28 pcs
No. of Footing 24 pcs
TOTAL PC 672 pcs
CUT/6M 3
PC OF 20mm Rebar 224

*TIE WIRE
No. of TIE 294
LENGTH 88.2 m
WEIGHT 1.66 KG

C.2. Column
C1: MAIN 20mm C2: MAIN 20mm C3: MAIN 20mm
BEND 0.2 BEND 0.2 BEND 0.2

LENGTH 3 LENGTH 3 LENGTH 3.2

SPLICE 0.3 SPLICE 0.3 SPLICE 0.3

LENGTH OF BAR 3.5 LENGTH OF 3.5 LENGTH OF


BAR BAR 3.7

BAR/COLUMN 8 BAR/COLUMN 8 BAR/COLUMN 8

No.COLUMN 24 No.COLUMN 72 No.COLUMN 24

TOTAL LENGTH 672 TOTAL 2016 TOTAL


LENGTH LENGTH 710.4

CUT/6M 1 CUT/6M 1 CUT/6M 1

PC OF 16mm 112 PC OF 20mm 336 PC OF 16mm 119

LATERAL TIES 12mm LATERAL TIES 10mm LATERAL TIES 10mm

TIE/COLUMN 21 TIE/COLUMN 21 TIE/COLUMN 27

TOTAL PCS 504 TOTAL PCS 1512 TOTAL PCS 648

LENGTH/TIE 0.848 LENGTH/TIE 1.048 LENGTH/TIE 1.048

No.TIE/6m 7 No.TIE/6m 5 No.TIE/6m 5

PC OF 12mm 71.232 PC OF 12mm 302 PC OF 10mm 130

TIE WIRE TIE WIRE TIRE WIRE

No. TIE 4032 No. TIE 12096 No. TIE 5184

LENGTH 1209.6 LENGTH 3628.8 LENGTH 1555.2

WEIGTH 23 WEIGTH 68 WEIGTH 29

SUMMARY:
20mm REBAR 903 pcs
12mm REBAR 503 pcs
No. of 16 GI WIRE 121 KG
C.3. Beams
B1: MAIN 16mm B2: MAIN 20mm

BEND 0.30 BEND 0.30

LENGTH 3.60 LENGTH 2.60

SPLICE 0.20 SPLICE 0.20

LENGTH OF BAR 3.60 LENGTH OF BAR 3.10

BAR/BEAM 7.00 BAR/BEAM 7.00

No.BEAM 34.00 No.BEAM 136.00

TOTAL LENGTH 856.80 TOTAL LENGTH 2951.20

CUT/6M 1.00 CUT/6M 1.00

PC OF 16mm 142.80 PC OF 16mm 491.87

STIRRUPS 12mm STIRRUPS 12mm

STEEL/BEAM 27.00 STEEL/BEAM 23.00

TOTAL PCS 918.00 TOTAL PCS 3128.00

L/STEEL 0.75 LENGTH/TIE 0.75

No.STEEL/6m 8.00 No.STEEL/6m 8.00

PC OF 12mm 114.75 PC OF 10mm 391.00

TIRE WIRE TIRE WIRE

No. TIE 6426.00 No. TIE 21896.00

LENGTH 1927.80 LENGTH 6568.80

WEIGTH 36.37 WEIGTH 123.94

SUMMARY:
16mm REBAR 143 pcs
20mm REBAR 491 pcs
12mm REBAR 518 pcs
No. of 16 GI WIRE 161 KG

C.4. Slabs
MAIN: MAIN: MAIN:

As1 423.36 As2 384.00 As3 284.00

STEEL/1SQ.M 8.00 STEEL/1SQ.M 8.00 STEEL/1SQ.M 8.00

No. 3386.88 No. 3072.00 No. 2272.00

0.00

TIRE WIRE TIRE WIRE TIRE WIRE 0.00

TIE/1SQ.M 16.00 TIE/1SQ.M 16.00 TIE/1SQ.M 16.00

No. TIE 6773.76 No. TIE 6144.00 No. TIE 4544.00

LENGTH 2032.13 LENGTH 1843.20 LENGTH 1363.20

WEIGTH 38.34 WEIGTH 34.78 WEIGTH 25.72


SUMMARY:
12mm REBAR 8731 pcs
No.16 GI WIRE 99 KG

C.5. CHB Walls

AREA STEEL/1SQ.M No. of STEEL TIE/1SQ.M No. ofTIE LENGTH WEIGTH


TOTAL WALL 1174 4 4696.00 4 4696 1408.8 26.58

SUMMARY:
10mm REBAR 4696 pcs
No. of 16 GI WIRE 27 KG
SUMMARY OF ALL MATERIALS USE
1. Concrete Works and Masonry

▪ No. of cement bags (40kg per piece) = 2289+1079 = 3368 bags


▪ Volume of sand = 127.16 + 130.99 = 258.15 ~ 259 m3
▪ Volume of gravel = 294.82 ~ 295 m3
▪ Volume of water = 52049 + 24516 = 76565 L
▪ No. of 6” CHB = 4983 pieces
▪ No. of 4” CHB = 9693 pieces

2. Steelworks

▪ No. of 20mm Rebar = 224 + 903 + 491 = 1618 pieces


▪ No. of 16mm Rebar = 143 pcs
▪ No. of 12mm (stirrups/column ties) = 294 + 503 +518 + 8731 = 10046 pieces
▪ No. of 10mm (wall rebar) = 4696 pieces
▪ No. 16 G.I. Tie wire = 1.66 + 121 + 161 + 99 + 27 = 409 KG

3. Roofing

MARK DESCRIPTION SIZE QUANTITY


▪ W-1 TOP & BOTTOM CHORDS 2"x2"x1/4" 27 pieces
▪ W-2 WEB MEMBERS 2"x2"x3/16" 31 pieces
▪ C-Purlins 150x50x15x2.0 47 pieces
▪ Pre-Painted Roof 6mx0.6mm 50 pieces

You might also like