The document reports on various production issues at a mining site over a period from December 2019 to March 2020. It lists the date, duration and frequency of events as well as details of the specific issues, which include crushers stopping due to overload or choke, conveyors becoming blocked, and the surge pile emptying due to wet material or presence of boulders. The issues affected primary, secondary and tertiary crushers as well as reclaim and feed systems on multiple dates.
The document reports on various production issues at a mining site over a period from December 2019 to March 2020. It lists the date, duration and frequency of events as well as details of the specific issues, which include crushers stopping due to overload or choke, conveyors becoming blocked, and the surge pile emptying due to wet material or presence of boulders. The issues affected primary, secondary and tertiary crushers as well as reclaim and feed systems on multiple dates.
The document reports on various production issues at a mining site over a period from December 2019 to March 2020. It lists the date, duration and frequency of events as well as details of the specific issues, which include crushers stopping due to overload or choke, conveyors becoming blocked, and the surge pile emptying due to wet material or presence of boulders. The issues affected primary, secondary and tertiary crushers as well as reclaim and feed systems on multiple dates.
01-Dec-19 0.42 2 Production Tetiary crusher stopped on overload 13-Dec-19 0.5 2 Production Tetiary crusher stopped on overload 15-Dec-19 0.33 1 Production Tetiary crusher stopped on overload 20-Dec-19 1 1 Production Stacker boom conveyor blocked chute 08-Jan-20 0.33 1 Production Reclaim failing to start- chock 09-Jan-20 1.08 2 Production Reclaim failing to start- chock 11-Jan-20 0.91 2 Production Reclaim failing to start- chock 22-Jan-20 7 1 Production Primary crusher not starting- Choke 23-Jan-20 18 1 Production Primary crusher not starting- Choke 24-Jan-20 2.33 1 Production Primary crusher not starting- Choke 30-Jan-20 0.4 1 Production Tetiary crusher stopped on overload 05-Feb-20 1 1 Production Reclaim vibro feeder chute chocked 06-Feb-20 3.65 1 Production Tertiary crusher choked 11-Feb-20 0.58 1 Production Slewing chute choked 11-Feb-20 0.41 1 Production Reclaim not starting - wet material 11-Feb-20 0.33 1 Production Tertiary tripped 12-Feb-20 1.75 4 Production Surge pile empty , boulders inside bowel 12-Feb-20 0.65 1 Production Surge pile empty due to wet material 13-Feb-20 0.41 1 Production Tertiary crusher choked 14-Feb-20 0.33 1 Production Tertiary crusher choked 21-Feb-20 0.92 1 Production Tertiary crusher tripped on overload 05-Mar-20 1.75 1 Production Boulders in the crusher 10-Mar-20 0.92 4 Production Surge pile empty 15-Mar-20 0.16 1 Production Secondary crusher tripped on overload Week Start Date Month Weekday Work Order Number Comments (Mon) December Sun #N/A December Fri #N/A December Sun #N/A December Fri #N/A January Wed #N/A January Thu #N/A January Sat #N/A January Wed #N/A January Thu #N/A January Fri #N/A January Thu #N/A February Wed #N/A February Thu #N/A February Tue #N/A February Tue #N/A February Tue #N/A February Wed #N/A February Wed #N/A February Thu #N/A February Fri #N/A February Fri #N/A March Thu #N/A March Tue #N/A March Sun #N/A