Professional Documents
Culture Documents
Overhead Design Manual: © ENERGEX 2007 BMS 01613 2.0 Last Update: 15/01/2007
Overhead Design Manual: © ENERGEX 2007 BMS 01613 2.0 Last Update: 15/01/2007
OVERHEAD DESIGN
MANUAL
This policy applies whenever evaluating the establishment of isolation points In general, management of ABS’s in existing circuits should be aimed at
on the 11kV overhead distribution network. having ABS’s located in accordance with the policy for new 11kV circuits as
described above. Whenever additional transformer capacity is installed,
This policy provides a uniform approach to the installation of 11kV isolators ensure there is a maximum of 750kVA between ABS’s. Whenever
that will optimise the design of the 11kV overhead network as to the number transformer capacity between existing ABS’s is reduced, excess ABS’s may
of switching points created. be recovered. However, the costs of recovery may exceed any costs
associated with leaving the items in place. Such costs may include:
• Ongoing inspection and maintenance costs
POLICY GUIDELINES • Costs of maintaining data associated with the ABS’s.
The overhead 11kV sectionalising proposed below allows considerable Exemptions from 11kV Sectionalising Policy
flexibility to Network and Distribution Planners in determining locations for
installation, modification and/or removal of 11kV ABS’s. This allows decisions There may be situations in which ABS’s additional to those allowed above
to be made on a total life cycle cost basis. The policy is described below may be required. Some examples are described below:
• Commercial/industrial areas
• Transformers supplying ‘sensitive’ loads
• Feeders having greater than 80% utilisation.
• Feeders with a history of poor reliability performance
• Extremities of feeders near paralleling points.
• Transformers supplied by underground cables, which may be at risk of
ferroresonance.
SUMMARY
These shall be marked with markers of alternating colours, one of which shall
be White, while the other colour shall be chosen to achieve maximum contrast
with the background.
Diameter Interval
less than 600mm 25 – 30m
600mm to 800mm 30 – 35m
greater than 800mm 35 – 40m
Note: LV ABC can be damaged by overloads, either due to load growth or during load
transfers. Consideration must always be given to avoiding overload conditions,
particularly during transfers or when opening fuses.
Table 1: Fuses for XLPE Insulated Single 95mm2 Al LV ABC Mains
Reduced expense to customer. Each phase shall be protected by a single fuse matched to the
Avoids trenching associated with underground cable installation, maximum continuous load or one available fuse size larger.
(e.g concrete cutting for driveway/carpark area or tunnelling). Maximum fuse size to be 400 A.
Source Transformer Adjacent at Customer Load If the open wire mains from transformer to the service pole is
considerably less than 60 metres, parallel 95 mm² LV ABC service
Maximum load is 400 A per phase supplied by 300 kVA transformer length may be increased by approximately the same amount.
immediately outside customer premises.
At 400 A per phase, voltage drop for a parallel 95 mm² ABC is not of Note:
major concern. (For a service length of 60 metres at 400 A, the These guidelines assume no other large load on the immediate
voltage drop is approximately 5 volts). network. Designers should carry out actual voltage drop
calculations for each individual case, to determine suitability of
existing network mains.
Source Transformer not Adjacent to Customer Load
Rules for Use Minimum Sags For Xlpe Insulated Aluminium Service Cables
Using Dulmison IBTH / IBTC Strain Clamps
The following information is to be used when using 2/3/4B25 or
35mm2 XLPE as Low Voltage Conductors. The following sags and tensions were calculated with the
Rules for service cables limitation being that the maximum working tension (MWT) at 15o
The first choice in running service cables is to install an individual C and 500Pa wind will not exceed 2.25kN; ie. 50% of the
service cable to an individual house. Even if there are three minimum failing load of the strap on the clamp.
houses fed via a x-street pole. This means that your first choice in
this instance is three separate services. Stock code for 2B25 clamp - 17793
If for some reason we cannot install individual services to Stock code for 3B25 – 4B35 clamp - 17794
these houses via the x-street pole we can do the following:
Erect 95mm ABC cable. String cable as per the IDM and
have pole inspected if required
If we erect the Al service cable using the attached tables and the
Dulmison IBTH bolted strain clamps, you will need to do a tip load
calculation on the pole (EDT and MWT). You will notice that the
MWT tensions are fairly significant.
EDT Conditions
Note:
1. These string tables are not to be used for services to houses unless the raiser bracket is suitably rated – Standard raiser bracket rating is 1kN
under MWT conditions
2. These stringing tables are not to be used for services to steel street light columns irrespective of foundation type.
3. These stringing tables are not to be used for flying fox services.
4. The resultant tip load on the timber pole shall include these service loads if these stringing tables are used.
5. Current ratings as stated in sect 2 Page 43 of the OCM still apply when the conductor is strung to these stringing tables
This Section outlines the various options for servicing LOW All diagrams in this section refer to the servicing arrangement for
VOLTAGE customers in a number of different situations and how BLOCK ‘B’ (Except where indicated).
costs are apportioned in each instance.
It is up to the local designer to select the most appropriate option CUSTOMER EXTENSION POLICY
from these, normally one that will minimise costs to ENERGEX
with due regard to the customer’s cost and maintenance of
Reference to ‘Customer Extension Policy’ used throughout the
statutory clearances.
booklet relates to current ENERGEX policy detailed in – ‘SUPPLY
AGREEMENTS FOR RETICULATION OF NEW SUBDIVISIONS
The sequence in which the options are presented should not be
AND CUSTOMER EXTENSION’.
regarded as the order of preference.
According to this instruction in residential situations ‘ENERGEX
The approach detailed in this section is based upon the following
provides funds towards the capital costs of making supply
general principles:
available, up to a maximum of APR/0.225’. The customer
provides the remaining funds if applicable. A 45% return is
- Minimise the amount of ‘footpath hardware.
required for Commercial and Industrial customers.
- Property crossings by new services are undesirable and
should only be used where written permission is obtained.
For most situations covered in this Section, it is expected that no
- Wayleave Form 1146 to be used for any new crossings.
charge will result since the APR usually covers the cost, unless
- Overhead services to hatchet blocks are undesirable, even
guarantee/capital contribution conditions exist.
disallowed by some local authorities.
- Any arrangements beyond a standard service should be at full
cost to the customer. In an overhead area, an overhead
service is standard, regardless of whether the local authority
EXCESS CABLE POLICY
imposes underground conditions or otherwise.
ENERGEX’s existing ‘Excess Cable Policy’ is to apply to all
While customer preferences should be accommodated to the situations where a service is installed across private property.
extent possible, ENERGEX is ultimately responsible for This includes each of the examples where the expression
determining the type and location of each service. ‘ENERGEX provides the standard service free of charge’ is used.
PROPERTY CROSSINGS
Customer services to be divided into two categories. 3 Blocks in category ‘B’ in underground areas shall be serviced
underground. The subdivider shall meet 50% of all costs
A - Services to an existing block. incurred by ENERGEX for the electrical installation.
B - Services to subdivisions.
5 All work in excess of the Standard ENERGEX service within
- Side by side subdivisions. the property boundary is at the customer’s expense.
1.1 Blocks in category ‘A’ in overhead areas shall be serviced 7 ENERGEX shall determine the optimum overhead service and
overhead, under the consumer extension policy. the location and size of property poles with due consideration
to property crossings, clearances, trees etc.
Maximum standard service length is 50m.
1.2 Blocks in category ‘A’ in underground areas shall be serviced This may be extended to 80m under special circumstances.
underground, under the consumer extension policy.
In addition designers shall consider issues detailed in the following extract Any action that does or has the potential to result in environmental
from ENERGEX BMS Procedure 1682 – Environmental Management remediation works of $5000 or more (a basic definition of what
System: Environmental Assessment. constitutes environmental harm) must be reported to the ENERGEX
Environmental Management Department as a matter of urgency. The
ENERGEX AND ALLGAS FACILITIES ENERGEX Environmental Management Department reserves the right to
monitor or audit the works for compliance. Any Infringement Notices or
The Environmental Management Department must be advised in writing to environmental fines issued to ENERGEX must be referred to
conduct an environmental assessment if any of the following criteria are ENERGEX’s Environmental Management Department.
true.
To achieve the general environmental requirements, planned works
• The acquisition of property for a new depot. are to be designed and conducted in a manner which takes into account
• A planned new activity, or the planned extension of an existing activity the environment in which it is being conducted and the appropriate
has the potential to require licensing under environmental legislation. management strategies implemented. The following requirements as
• Planned changes at a facility have the potential to impact on an relevant, must be applied without compromising the health and safety of
existing environmental licence under environmental legislation. ENERGEX employees, customers or the community:
• It is the requirement of an ENERGEX Service Level Agreement.
• The development and implementation of a specific communication
• The local council or other statutory body or ENERGEX management
program to identify and inform stakeholders in advance of planned
require the conduct of an environmental evaluation on some or all of
works, may be warranted.
the activities of the facility.
• Adherence to the Environmental Management Plan which has been
• The disposal of an existing depot.
developed for the site and any specific environmental permit
requirements must be complied with.
• All staff have successfully undertaken the nominated environmental
ENVIRONMENTAL REQUIREMENTS
training competencies.
• A record of complaints and resulting actions taken, shall be
Environmental requirements are those conditions that must apply to
maintained. These complaints may be on a separate document or
provide a reasonable level of certainty that all works are conducted in a
part of another existing register or form.
manner consistent with the ENERGEX Environmental Management
System.
• Use existing poles rather than replacement Specific environmental requirements are identified in the Environmental
Least change means least risk of adverse community reaction. Management Plan for the project. They include, as a minimum, General
This may involve use of superseded network building blocks (e.g. flat Environmental Requirements listed above.
33kV construction to replace existing flat 11kV construction).
In the event that the Board carries out any work which will affect
such signs – such as replacement of a pole – contact:
FOREMAN – SIGNS
Brisbane City Council
Department of Works
Ph: (07) 34030186
AIR BREAK SWITCH CHAINAGE The distance from a datum along the centreline of a
3∅, ganged, pole mounted switching device utilising air as
roadway. This term and offset are used to make reference
an insulation medium. Capable of making, carrying and
to points on roadworks plans.
breaking currents to specified levels under normal
conditions. Capabilities are extended through use of arcing CIRCUIT BREAKER Mechanical switching device capable of making, carrying
horns or “Arcmasters” which respectively provide limited to and breaking currents under normal conditions.
full load break ability. Air breaks cannot interrupt fault Capable of making, carrying for a specified time and
currents. Refer Isolator Switch. breaking currents under specified abnormal conditions (eg.
AutoCAD A popular proprietary software Computer-Aided Drafting short circuits).
package suitable for use with Personal Computers. Primary control is via external protection relays and manual
Registered Trademark of AutoDesk, Inc. overrides.
Circuit breakers are normally ground mounted.
AUXILIARY BOARD Addition to a LV switchboard. In general it:
A circuit breaker (fitted with automatic reclose and external
• includes a GPO with fuse and link
protection relays) is operationally similar to a recloser.
• may have additional fused supplies Circuit breakers may occur in ring main units. Refer
• is connected between the LV switch (ie. isolator or Recloser.
switch fuse), and the most convenient LV fuse or A combination of links that, close the through circuit and
COMBINATION LINKS
switch fuse. then isolate the apparatus in one sequenced action, or vice
BAY See “Span”. versa (eg. Live bypass for single-phase regulators).
BLOWOUT The horizontal deviation from centre of powerline
conductors subjected to wind forces. COMMON MEN The LV MEN system extended to include the HV system
BOLLARD A pole specifically for supporting an aerial staywire. SYSTEM (CMEN) earthing with voltages up to subtransmission level. See
BRIDGING Short flexible leads providing electrical continuity across “Multiple Earth Neutral”.
points on the system which are structurally broken.