68 Kalayaan VCP Building EDG & ATS Testing Checklist

I. Preparation (Prior Shutting down of Normal Power)

Item Test Description Yes No Remarks


1 All tenants and Offices are well informed.
2 Availability of Security personnel at UG w/ Radio & Flashlight.
3 Availability of Security personnel at LG w/ Radio & Flashlight.
4 Availability of Maintenance personnel at LG w/ Radio &
Flashlight, and inspect EDG parameters such as Oil, Battery,
Diesel, temperature, etc.
5 Availability of Maintenance personnel at 6th, 8th, & 9th Flr w/
Radio & Flashlight.
5.1 (Optional) Availability of IT personnel at 8th Flr w/ Radio &
Flashlight on the Server room.
6 All personnel w/ Radio acknowledges that Test is ready to
commence.
7 Safety Officer having Radio to monitor all activity and to
confirm Start of activity.
Time Commenced: __________ HRS

II. Test Proper for Loss of Main Normal Incomer (Meralco)

Item Test Description Yes No Remarks


1 Maintenance Personnel at LG ensures EDG & ATS are both in Device ID: ECB 2000A
Auto Mode, then shuts down Meralco Main Incomer MCCB.
2 All personnel w/ Radio confirms loss of Normal Power.
3 (Optional) If EDG runs but ATS did proceed to Transfer, Item III. ATS Calibration
proceed to Calibration Checklist.
4 Maintenance Personnel at LG confirms EDG runs and build up
Emergency Power.
Record time MCCB OFF: __________ HRS
Record time EDG Starts (in seconds from MCCB was switched
off): __________ seconds
Record time ATS acts (in seconds from MCCB was switched
off): __________ seconds
5 Maintenance Personnel at LG confirms ATS senses the
Emergency DG Power.
6 Maintenance Personnel at LG confirms ATS commence
switching from Normal Power source to Emergency Power
source.
7 Security personnel at UG w/ Radio confirms availability of
Emergency power within area of responsibility.
8 Maintenance personnel at 6th, 8th, & 9th Flr w/ Radio confirms
ATS switching & the availability of Emergency power within
area of responsibility.
8.1 (Optional) IT personnel at 8th Flr w/ Radio at Server room no
loss of server power due to UPS activity.
9 Maintenance Personnel at 6th, 8th, & 9th Flr w/ Radio starts
HVAC units in area of responsibility to add up on EDG load and
build up to 35kW load (10% EDG Capacity).

1|R e v i s i o n 0 2 JAS-2022.09.14
68 Kalayaan VCP Building EDG & ATS Testing Checklist
10 Maintenance personnel at LG w/ Radio confirms EDG load
measurements in kW.
Record reading:
L1: __________ kW
L2: __________ kW
L3: __________ kW
Average Power: __________ kW (__________% RC)
11 Safety Officer monitors time of from when EDG measures at
least minimum of 35kW load.
Time starts: __________ HRS
12 Maintenance Personnel at LG ensures all EDG parameters are
normal such as Voltage, Speed, Sound
13 Safety Officer monitors time of activity and continue until 10
minutes duration starting from when EDG measures at least
10kW load, then declare to return electrical source to Normal
Power.
Time after 10 minutes: _________ HRS
14 Last record reading prior to unloading the EDG:
L1: __________ kW
L2: __________ kW
L3: __________ kW
Average Power: __________ kW (__________% RC)
15 Maintenance Personnel at 6th, 8th, & 9th Flr w/ Radio stops
HVAC units in area of responsibility to reduce EDG load. Then
confirm all HVAC are already Off.
16 Maintenance Personnel at LG confirms EDG load was reduced
and measures EDG load on the HMI.
Record reading:
L1: __________ kW
L2: __________ kW
L3: __________ kW
Average Power: __________ kW (__________% RC)
17 Maintenance Personnel at LG normalizes Meralco power by Device ID: ECB 2000A
switching ON the main MCCB.
18 Maintenance Personnel at LG confirms transfer of loads to Note:
Normal Power Source. Expects 3 minutes or 180
Record time MCCB ON: __________ HRS seconds EDG cooldown
Record time ATS action (from after ECB-200A MCCB was time before shutdown
switched ON): __________ seconds
Record time EDG cools down & Stop (in seconds from MCCB
was switched ON): __________ seconds; __________ HRS
19 Security personnel at UG w/ Radio confirms availability of
Normal power within area of responsibility.
20 Maintenance personnel at 6th, 8th, & 9th Flr w/ Radio confirms
ATS switching & the availability of Normal power within area
of responsibility.
20.1 (Optional) IT personnel at 8th Flr w/ Radio at Server room
confirms no loss of server power due to UPS activity and
Normal power was resumed.

2|R e v i s i o n 0 2 JAS-2022.09.14
68 Kalayaan VCP Building EDG & ATS Testing Checklist
21 Safety Officer confirms everything is back to normal, declares
END OF TEST, & records time of activity.
Time Completed: __________ HRS

III. ATS Calibration (reference from item II.3.)

Item Test Description Yes No Remarks


1 Set EDG to Manual mode
2 Operate the EDG until it build up voltage of 220V.
3 Set ATS to Auto mode
4 Long press ‘’OFF’’ button until ‘’-LS-‘’ appears on the HMI.
5 Press ‘’↓’’ button until ‘’-CS-‘’ appears on the HMI.
6 Press ‘’↓’’ & ‘’↑’’ button simultaneously until ‘’220‘’ appears
on the HMI.
7 Press ‘’↑’’ button continuously until ‘’230‘’ appears on the (Optional)
HMI.
8 Press ‘’OFF’’ button to acknowledge saving of settings.
9 Pres ‘’Auto/Man’’ to escape from settings menu and go back
to main menu.
10 Observe ATS LEDs:
 ensure that the LED on the Emergency Power
Direction of the ATS is lit, this proves that the ATS
already acknowledged the EDG power input.
 If LED is not lit, repeat steps III.1 up to III.5.
11 Manually stop the EDG then set to Auto mode.
12 Test ATS operation: Expectation:
 Switch OFF the Normal Power Sensing MCB (3P), to  EDG runs, ATS
simulate loss of Meralco or Normal Power. switches to Emergency
 Switch ON the Normal Power Sensing MCB (3P), to  ATS switches to
simulate restoration of Meralco or Normal Power. Normal
13 If all conditions are met, proceed back to step II.1.;
If not, repeat ATS Calibration (step III.)
Notes:

Westco Building Building Technician Engineering Security Officer Safety Officer


Management Team Personnel
Name

Signature

Date

3|R e v i s i o n 0 2 JAS-2022.09.14
68 Kalayaan VCP Building EDG & ATS Testing Checklist
Annex A:

ATS Schematic Diagram

Normal Power Emergency Power


Sensing MCB (3P) Sensing MCB (3P)

Battery MCB (1P)


Battery Charger EDG Remote
MCB (2P) & Start Command
Auxiliary Relay

4|R e v i s i o n 0 2 JAS-2022.09.14
68 Kalayaan VCP Building EDG & ATS Testing Checklist
Annex B:

ATS Control Panel


Auto Mode LED Manual Mode LED HMI

Emergency Power
Emergency Power Direction LED
Direction LED

Emergency Power
Emergency Power
Transfer LED
Transfer LED

Auto-Manual Scroll-Up,
Mode Transfer Scroll-Down, &
Button OFF buttons

Manual Transfer Switch


Using Switching Lever

Work = for
Automatic Transfer
Switch Controller
Operation

Test = for Manual


Transfer Switch
Operation

5|R e v i s i o n 0 2 JAS-2022.09.14
68 Kalayaan VCP Building EDG & ATS Testing Checklist
Annex C:

ATS Control Auxiliary Circuit

Battery Auxiliary Relay


MCB (1P)

Battery Charger Normal Power Emergency Power EDG Remote Start


MCB (2P) Sensing MCB (3P) Sensing MCB (3P) Command & Control
Grounding Terminal Block

6|R e v i s i o n 0 2 JAS-2022.09.14