PURPOSE
This is to streamline all the procedures and processes for the Method Statement for Cuplock System Erection &
Dismantling in order to ensure safe working conditions and practices. This also enable planning, controlling the
execution and documentation in compliance with ADNOC Specifications and procedures.
SCOPE
The scope of this document is the erection and dismantling process of Cuplock systems which covers the material,
safety and regulatory requirements.
REFERENCES
• Contract agreement no. 1157609
• UAE Federal Law No. 8 Industrial Safety, Preventive Measures, Health and Social Care of workers.
• ADNOC Guidelines and procedures
• Material Safety Data Sheet (MSDS)
• Technical Data Sheet (TDS)
• Material Standards and Specifications
• Operation and Maintenance Manuals
• Training Manuals
• Approved Drawings if Any
• SR - Service Request
• SP - Service Provider (SCAFFCO)
• PPM - Planned preventive maintenance works
• HSE - Health Safety & Environment
• PPE - Personal protective equipment
• PTW - Permit to Work
• RA - Risk Assessment
• SOP - Standard Operating Procedure
• MS - Method Statement
User Method Statement – SFP-50 SYSTEM General Guideline
RESPONSIBILITIES
SP Site Supervisor
• Ensure that the works are carried out with approved materials and specification.
• Ensure that all works are carried out as per approved method statement and risk assessment.
• All equipment and materials to be used according to the procedure and specification and ADNOC safety rule and
regulation.
• Ensure and monitor that the work progress is in accordance with the required program and report this activity to
Project Engineer.
• Coordinate with Project Engineer for sequence of works at site
• Provide all necessary information and distribute the responsibilities to his execution team.
• Co-ordinate with the safety engineer to ensure that the works are carried out in a safe working practice.
• Carrying out the work and the proper distribution of all the available resources in coordination with the project
Engineer on a daily basis.
• Continuous coordination and following instructions to meet quality requirement during the job execution.
• Ensure that the proper equipment’s and tools are using for execution.
• All materials and equipment stored properly at allocate area.
• Carry out proper housekeeping and dumped into waste skip
• Monitoring the house keeping & site safety of the work on daily basis.
• Elaborating inspection and test programs.
• Assure all technical documents relative to site quality control are current status.
User Method Statement – SFP-50 SYSTEM Introduction
Dismantling Formwork
• Do not strike the formwork until the concrete has reached sufficient strength and the person in charge has given
the order for the formwork to be struck.
• Observe all regulations applying to the handling of formwork and scaffolding.
• All components must be stacked and stored safely, Remove any loose parts or fix them in place so that they can
not fall free.
Note:
• We reserve the right to make modifications in the interest of technical progress.
User Method Statement – SFP-50 SYSTEM Technical Details
System Description
The most important aspect of a successful structural construction is the formwork system. SPF System offers the
most trustful, secure, efficient and cutting edge of formwork technology for various structures. The SPF System is an
ingenious small-panel formwork system that was specially designed for cost-effective forming of concrete elements.
All of the panels belonging to this system are relatively light and handy that they can be handled and fitted by a
maximum of two people
SCAFFCO light weight SPF 50 Frame system, with its 5 mm Aluminum steel angle profile, is the ideal solution for
quick & economical forming, with or without the use of cranes.
System Features:
• SPF system panels are made from steel frames which makes the
panels more rigid, more robust and lighter than competitor panels.
SPF system enables huge saving in timber elements at site.
• SPF system can be used without requiring a crane, which dramatically reduces construction costs.
• The quality 18mm plywood sheet overlay on the face provides long life and a high quality finish for the concrete.
• SPF system has a wide range of panel sizes, allowing virtually any configuration to be erected.
• The erection and striking of SPF system is fast and straight forward and only needs a team of two, thereby saving
time and money.
• Panels are attached together using Key Bolt, which improves erection time.
• SPF system’s comprehensive range of accessories enable it to be used in an extensive range of construction
projects.
• SPF system panels can be used with steel soldiers or steel walers to create large crane handled
formwork shutters.
User Method Statement – SFP-50 SYSTEM Technical Details
User Method Statement – SFP-50 SYSTEM Instruction for SPF-50 Assembly and Use
B
A
User Method Statement – SFP-50 SYSTEM Instruction for SPF-50 Assembly and Use
➢ Insert the SPF Steel Waler at the endpoint of the attached steel panel connector
4 5
➢ Insert the SPF Steel Waler at the endpoint of the attached steel panel connector
4 5
HSE REQUIREMENTS
Safety Precautions
• Ensure users understand that any unauthorized modification to the scaffold or removal of components could cause a
safety hazard. Alterations or extensions should be carried out under the direction of a competent person.
• Carry out regular inspections to check that the components have not been removed or damaged, or that
components have not been removed and replaced incorrectly. Provide barriers and warning notices to prevent
access to incomplete sections of scaffolding.
• When the scaffolding configuration has been completed, it shall be checked by qualified scaffolding supervisor and
Scaff tag/ Hand over certificate shall be issued. This certificate shall be signed as an acceptance of completed work.
• No part of the scaffolding shall be modified/Changed by anyone other than qualified scaffold person.
• Fall protection must be used in accordance with the procedure.
• Maximum load on anchor point when fall is arrested will be up to 6KN.
• Anchor Points for a fall arrest system shall be installed in such a matter as to minimize “Swing Fall”.
• The operatives must use full body harness with double lanyard.
• Rescue kit should be in place of working.
• Personal fall protection equipment shall be worn whenever working.
• All the materials are tested and fit for use.
PTW
• Relevant permit needs to be obtained before starting the work
• Risk Assessment .
• Hazard analysis to be done.
• Safety personnel & designated responsible person will ensure that all above is carried out & any other statutory
requirements are completed with before any work takes.
PPE Requirements
As a minimum the following PPE should be used by staff/labors
•
Hard hat
• Safety shoe
• Safety goggles
• Face Shield
• Ear Plugs
• Hand gloves
• High visibilities
• Dust mask
• Safety harness