BILL OF QUANTITY

Bill Of Quantity For


Bpk. Yohanes Date 19 November 2021
CCTV 21 ONLINE INDONESIA No BoQ BD-BOQ.1.S/088/TRJ-HO/XI/2021
Revision 00

Material Price Labour Cost

No. Description Qty Vol Unit Price Total Price Unit Price Total Price

A MAIN EQUIPMENT FIRE ALARM SYSTEM


A.1 HOOSEKI MCFA HS-10L 1 Unit 9.120.000 9.120.000 1.368.000 1.368.000
A.2 HOOSEKI Announciator HS-ANN 20L 1 Unit 5.776.000 5.776.000 866.400 866.400
A.3 HOOSEKI Junction Box 24 Pairs complit set 8 Unit 950.000 7.600.000 142.500 1.140.000
A.4 HOOSEKI Indicator Lamp HS-FL3 8 Unit 98.800 790.400 14.820 118.560
A.5 HOOSEKI Manual Call Point HS-FP1 c/w jack phone 8 Unit 296.400 2.371.200 44.460 355.680
A.6 HOOSEKI Alarm Bell, type: HS-FB6 8 Unit 334.400 2.675.200 50.160 401.280
A.7 HOOSEKI Smoke Detector, type: HS-WT30L 20 Unit 380.000 7.600.000 57.000 1.140.000
A.8 HOOSEKI FIX Heat Detector, type: HS-Wk100L 223 Unit 129.200 28.811.600 19.380 4.321.740
64.744.400 9.711.660

B DISTRIBUTION SYSTEM
Instalasi MCFA HS-10L NYA 2x1.5mm dalam Conduit c/w
B.1 1 Titik 2.000.000 2.000.000 350.000 350.000
accessories
B.2 Instalasi Announciator AWG18 dalam Conduit c/w 1 Titik 2.000.000 2.000.000 350.000 350.000
Instalasi Junction Box NYMHY 2x1,5mm dalam Conduit c/w
B.3 8 Titik 750.000 6.000.000 350.000 2.800.000
accessories
Instalasi Indicator Lamp HS-FL3 NYA 2x1,5mm dalam
B.4 8 Titik 500.000 4.000.000 350.000 2.800.000
Conduit c/w accessories
B.5 Instalasi Manual Call Point HS-FP1 c/w jack phone NYA 8 Titik 500.000 4.000.000 350.000 2.800.000
Instalasi Alarm Bell, type: HS-FB6 2x1,5mm dalam Conduit
B.6 8 Titik 500.000 4.000.000 350.000 2.800.000
c/w accessories
Instalasi Smoke Detector, type: HS-WT30L NYA 2x1,5mm
B.7 20 Titik 500.000 10.000.000 350.000 7.000.000
dalam Conduit c/w accessories
Instalasi FIX Heat Detector, type: HS-Wk100L NYA
B.8 223 Titik 500.000 111.500.000 350.000 78.050.000
2x1,5mm Conduit c/w accessories
B.9 Instalasi jack phone Conduit kabel ITC 2x0.6mm c/w 1 Lot 2.000.000 2.000.000 350.000 350.000
SUB TOTAL B 145.500.000 97.300.000

C. OTHER
C.1 Mob / Demob / Transportation 15.000.000 15.000.000
C.2 Design Engineering Drawing 1.500.000 1.500.000
C.3 Testing & Comissioning 3.000.000 3.000.000

SUB TOTAL C 19.500.000


SUB TOTAL ( A + B + C ) 210.244.400 126.511.660

If you have any questions concerning this Bill Of Quantity, TOTAL HARGA PENAWARAN MATERIAL & LABOUR 336.756.060
Please contact : TOTAL HARGA SETELAH PEMBULATAN 336.700.000
Email : info@triargha.co.id TAX PPN 10%
Thank you for your business! GRAND TOTAL 336.700.000