Professional Documents
Culture Documents
NO. UKURAN BESI KANAL " L " BERAT / BATANG BERAT PER 1 M1
1 25 x 25 x 3 x 6 mm 6.72 kg 1.12
2 30 x 30 x 3 x 6 mm 8.16 kg 1.36
3 40 x 40 x 3 x 6 mm 11.00 kg 1.83
4 40 x 40 x 4 x 6 mm 14.50 kg 2.42
5 50 x 50 x 4 x 6 mm 18.50 kg 3.08
6 50 x 50 x 5 x 6 mm 22.60 kg 3.77
7 60 x 60 x 5 x 6 mm 27.30 kg 4.55
8 60 x 60 x 6 x 6 mm 32.52 kg 5.42
9 65 x 65 x 6 x 6 mm 35.46 kg 5.91
10 70 x 70 x 7 x 6 mm 44.28 kg 7.38
11 75 x 75 x 6 x 6 mm 41.22 kg 6.87
12 75 x 75 x 8 x 6 mm 54.18 kg 9.03
13 80 x 80 x 8 x 6 mm 57.96 kg 9.66
14 90 x 90 x 9 x 6 mm 73.20 kg 12.20
15 100 x 100 x 8 x 6 mm 73.20 kg 12.20
16 100 x 100 x 10 x 6 mm 90.60 kg 15.10
17 120 x 120 x 10 x 12 mm 218.40 kg 36.40
18 120 x 120 x 12 x 12 mm 260.00 kg 43.33
19 125 x 125 x 12 x 12 mm 280.00 kg 46.67
20 130 x 130 x 9 x 12 mm 214.20 kg 35.70
21 130 x 130 x 12 x 12 mm 280.00 kg 46.67
BERAT PER 1 M1
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
BERAT PER 1 M1
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
BERAT PER 1 M1
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
1 isi sheet harga bahan dan upah bedasarkan harga survey barang dilokasi masing masing
2 Isi sheet Persiapan
3 isi volume masing masing pekerjaan disesuaikan dengan jumlah bantuan, jenis dan bentuk konstruksi.
4 isi sheet furnt sesuai dengan bangunan yang dibangun
5 isi sheet adm
PROGRAM BANTUAN KINERJA DAN BANTUAN AFIRMASI
Dengan Mekanisme Partisipasi Masyarakat
NSM :
Nama Madrasah :
Desa :
Kecamatan :
Kabupaten :
Propinsi :
DAFTAR HARGA UPAH
HARGA
NO JENIS UPAH SATUAN
Rp.
I. Bahan Kaca
1 Kaca Polos 5 mm 185,000.00 M²
Kaca Polos 3 mm 140,000.00 M²
J. Bahan Paku
1 Paku Biasa 18,000.0 Kg
2 Paku Tripleks 25,000.0 Kg
3 Paku Seng + karet seal 30,000.0 Kg
4 Paku Ulir 1,000.00 bh
Q. Alat-alat Listrik
1 Kabel 1x2,5mm NYM 9,000.00 M1
2 Kabel 2x2,5mm NYM 12,000.00 M1
3 Kabel 3x2,5mm NYM 17,000.00 M1
4 Kabel 3x2,5mm NYM 20,000.00 M1
5 Kabel 3x4mm NYY 26,000.00 M1
6 Saklar Tunggal setara Broco 19,000.00 Bh
7 Saklar Ganda setara Broco 25,000.00 Bh
8 Stop Kontak setara Broco 16,000.00 Bh
9 Lampu TL 2 x 40 watt + armaturnya, setara Phillips 200,000.0 Set
10 Lampu Pijar 25 watt setara Phillips + fitting 20,000.00 Bh
11 Box Sekring 40,000.00 Bh
12 Inbowdoos 2,500.00 Bh
13 Isolasi/Seal Tape 15,000.00 Bh
14 Klem Kabel 100.00 Bh
15 MCB 20,000.00 Bh
16 Panel Box Utama 450,000.00 Bh
1 Air 4,000 m3
Alat
1 Stemper jam
2 Concrete Mixer jam
3 Concrete Vibrator jam
4 Manual Tool ls
5 Alat Semprot ls
Daftar Harga Furniture
NSM :
NAMA MADRASAH :
KABUPATEN :
PROVINSI :
Pekerjaan : ADMINISTRASI
NSM :
NAMA MADRASAH :
KABUPATEN :
PROVINSI :
Pekerjaan : PERSIAPAN
Total 1,650,000.00
Total 1,650,000.00
REKAPITULASI RAB
PEMBANGUNAN RUANG KELAS BARU
Dengan Mekanisme Partisipasi Masyarakat
NSM :
NAMA MADRASAH :
KABUPATEN :
PROVINSI :
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PEKERJAAN KONSTRUKSI 2,317,680.00
I. PEKERJAAN PENDAHULUAN -
II. PEK. TANAH -
III. PEK. PONDASI -
IV. PEKERJAAN BETON -
V. PEKERJAAN DINDING 2,317,680.00
VI. PEKERJAAN PINTU DAN JENDELA -
VII. PEKERJAAN KUDA-KUDA DAN ATAP -
VIII. PEKERJAAN PLAFOND -
IX. PEKERJAAN LANTAI / KERAMIK -
X. PEKERJAAN PENGECATAN -
XI. PEKERJAAN INSTALASI LISTRIK -
XII. PEKERJAAN PENGGANTUNG / PENGUNCI -
XIII. PEKERJAAN LAIN-LAIN -
XIV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 27,399,480.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 39,077,160.00
Dibulatkan 39,077,000.00
Terbilang :
NSM :
NAMA MADRASAH :
KABUPATEN :
PROVINSI :
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PEKERJAAN KONSTRUKSI 388,527,406.44
I. PEKERJAAN PENDAHULUAN 5,060,160.00
II. PEK. TANAH 802,502.16
III. PEK. PONDASI 4,070,838.18
IV. PEKERJAAN BETON 116,603,617.73
V. PEKERJAAN DINDING 65,142,563.80
VI. PEKERJAAN PINTU DAN JENDELA 18,968,810.40
VII. PEKERJAAN KUDA-KUDA DAN ATAP 58,785,504.84
VIII. PEKERJAAN PLAFOND 36,584,960.01
IX. PEKERJAAN LANTAI / KERAMIK 35,772,038.19
X. PEKERJAAN PENGECATAN 18,074,016.06
XI. PEKERJAAN INSTALASI LISTRIK 9,494,761.50
XII. PEKERJAAN PENGGANTUNG / PENGUNCI 4,055,660.00
XII. PEKERJAAN LAIN-LAIN 15,111,973.57
XIV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 44,616,800.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
JUMLAH TOTAL 442,504,206.44
Dibulatkan 442,504,000.00
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NSM :
NAMA MADRASAH :
KABUPATEN :
PROVINSI :
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PEKERJAAN KONSTRUKSI 392,730,875.08
I. PEKERJAAN PENDAHULUAN 5,421,600.00
II. PEK. TANAH 5,874,684.72
III. PEK. PONDASI 19,238,553.83
IV. PEKERJAAN BETON 57,578,097.11
V. PEKERJAAN DINDING 63,707,065.64
VI. PEKERJAAN PINTU DAN JENDELA 21,665,668.80
VII. PEKERJAAN KUDA-KUDA DAN ATAP 66,892,134.39
VIII. PEKERJAAN PLAFOND 38,254,213.87
IX. PEKERJAAN LANTAI / KERAMIK 47,336,708.40
X. PEKERJAAN PENGECATAN 34,106,366.16
XI. PEKERJAAN INSTALASI LISTRIK 9,790,702.00
XII. PEKERJAAN SANITASI 2,587,260.00
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI 4,607,960.00
XIV. PEKERJAAN LAIN-LAIN 15,669,860.17
XV. PEK. RAMPA + HAND RAILING -
2 FURNITURE 61,634,540.00
3 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 454,365,415.08
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000
NAMA SEKOLAH : 0.000
KABUPATEN : 0.000
PROVINSI : 0
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PEKERJAAN KONTRUKSI 382,361,360.63
I. PEKERJAAN PENDAHULUAN 5,421,600.00
II. PEK. TANAH 4,904,224.92
III. PEK. PONDASI 21,945,319.02
IV. PEKERJAAN BETON 52,196,425.44
V. PEKERJAAN DINDING 63,707,065.64
VI. PEKERJAAN PINTU DAN JENDELA 22,331,578.00
VII. PEKERJAAN KUDA-KUDA DAN ATAP 64,212,134.39
VIII. PEKERJAAN PLAFOND 39,339,271.59
IX. PEKERJAAN LANTAI / KERAMIK 44,835,450.00
X. PEKERJAAN PENGECATAN 34,131,857.84
XI. PEKERJAAN INSTALASI LISTRIK 9,224,754.00
XII. PEKERJAAN PENGGANTUNG / PENGUNCI 4,607,960.00
XIII. PEKERJAAN LAIN-LAIN 15,503,719.80
XIV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 30,915,250.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 422,636,610.63
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000
NAMA SEKOLAH : 0.000
KABUPATEN : 0.000
PROVINSI : 0
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PEKERJAAN KONSTRUKSI 382,361,360.63
I. PEKERJAAN PENDAHULUAN 5,421,600.00
II. PEK. TANAH 4,904,224.92
III. PEK. PONDASI 21,945,319.02
IV. PEKERJAAN BETON 52,196,425.44
V. PEKERJAAN DINDING 63,707,065.64
VI. PEKERJAAN PINTU DAN JENDELA 22,331,578.00
VII. PEKERJAAN KUDA-KUDA DAN ATAP 64,212,134.39
VIII. PEKERJAAN PLAFOND 39,339,271.59
IX. PEKERJAAN LANTAI / KERAMIK 44,835,450.00
X. PEKERJAAN PENGECATAN 34,131,857.84
XI. PEKERJAAN INSTALASI LISTRIK 9,224,754.00
XII. PEKERJAAN PENGGANTUNG / PENGUNCI 4,607,960.00
XIII. PEKERJAAN LAIN-LAIN 15,503,719.80
XIV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 61,634,540.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 453,355,900.63
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000
NAMA SEKOLAH : 0.000
KABUPATEN : 0.000
PROVINSI : 0
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PERKERJAAN KONSTRUKSI 382,098,846.56
I. PEKERJAAN PENDAHULUAN 5,421,600.00
II. PEK. TANAH 4,665,390.32
III. PEK. PONDASI 20,130,211.74
IV. PEKERJAAN BETON 54,213,911.76
V. PEKERJAAN DINDING 60,751,618.40
VI. PEKERJAAN PINTU DAN JENDELA 20,111,378.80
VII. PEKERJAAN KUDA-KUDA DAN ATAP 66,892,134.39
VIII. PEKERJAAN PLAFOND 39,366,120.09
IX. PEKERJAAN LANTAI / KERAMIK 46,790,072.43
X. PEKERJAAN PENGECATAN 32,972,526.96
XI. PEKERJAAN INSTALASI LISTRIK 9,398,411.50
XII. PEKERJAAN SANITASI 1,479,430.00
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI 4,236,180.00
XIV. PEKERJAAN LAIN-LAIN 15,669,860.17
XV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 59,093,130.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 450,551,976.56
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000
NAMA SEKOLAH : 0.000
KABUPATEN : 0.000
PROVINSI : 0
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PERKERJAAN KONSTRUKSI 382,098,846.56
I. PEKERJAAN PENDAHULUAN 5,421,600.00
II. PEK. TANAH 4,665,390.32
III. PEK. PONDASI 20,130,211.74
IV. PEKERJAAN BETON 54,213,911.76
V. PEKERJAAN DINDING 60,751,618.40
VI. PEKERJAAN PINTU DAN JENDELA 20,111,378.80
VII. PEKERJAAN KUDA-KUDA DAN ATAP 66,892,134.39
VIII. PEKERJAAN PLAFOND 39,366,120.09
IX. PEKERJAAN LANTAI / KERAMIK 46,790,072.43
X. PEKERJAAN PENGECATAN 32,972,526.96
XI. PEKERJAAN INSTALASI LISTRIK 9,398,411.50
XII. PEKERJAAN SANITASI 1,479,430.00
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI 4,236,180.00
XIV. PEKERJAAN LAIN-LAIN 15,669,860.17
XV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 59,093,130.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 450,551,976.56
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000
NAMA SEKOLAH : 0.000
KABUPATEN : 0.000
PROVINSI : 0
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PERKERJAAN KONSTRUKSI 382,098,846.56
I. PEKERJAAN PENDAHULUAN 4,608,360.00
II. PEK. TANAH 4,195,071.77
III. PEK. PONDASI 17,059,758.57
IV. PEKERJAAN BETON 46,705,660.63
V. PEKERJAAN DINDING 27,161,251.80
VI. PEKERJAAN PINTU DAN JENDELA 35,558,762.08
VII. PEKERJAAN KUDA-KUDA DAN ATAP 53,007,529.33
VIII. PEKERJAAN PLAFOND 30,762,392.61
IX. PEKERJAAN LANTAI / KERAMIK 30,368,372.42
X. PEKERJAAN PENGECATAN 23,128,868.27
XI. PEKERJAAN INSTALASI LISTRIK 7,510,168.70
XII. PEKERJAAN SANITASI 1,415,330.00
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI 3,018,400.00
XIV. PEKERJAAN LAIN-LAIN 12,232,483.36
XV. PEK. RAMPA + HAND RAILING -
3 FURNITURE
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 391,458,846.56
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000
NAMA SEKOLAH : 0.000
KABUPATEN : 0.000
PROVINSI : 0
Jumlah Harga
No Uraian Pekerjaan
( Rp )
1 PEK. PERSIAPAN 1,650,000.00
2 PERKERJAAN KONSTRUKSI 393,386,696.52
I. PEKERJAAN PENDAHULUAN 4,879,440.00
II. PEK. TANAH 4,994,655.54
III. PEK. PONDASI 22,350,167.45
IV. PEKERJAAN BETON 58,950,119.73
V. PEKERJAAN DINDING 76,041,528.84
VI. PEKERJAAN PINTU DAN JENDELA 31,245,991.50
VII. PEKERJAAN KUDA-KUDA DAN ATAP 54,422,799.39
VIII. PEKERJAAN PLAFOND 29,285,084.01
IX. PEKERJAAN LANTAI / KERAMIK 39,489,350.65
X. PEKERJAAN PENGECATAN 32,422,607.76
XI. PEKERJAAN INSTALASI LISTRIK 11,986,161.50
XII. PEKERJAAN SANITASI 5,578,690.00
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI 6,419,280.00
XIV. PEKERJAAN LAIN-LAIN 15,320,820.15
XV. PEK. RAMPA + HAND RAILING -
3 FURNITURE 27,917,780.00
4 BIAYA OPERASIONAL DAN ADMINISTRASI KOMITE 7,710,000.00
Jumlah Total 430,664,476.52
Dibulatkan
Terbilang :
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
Pekerjaan : GEDUNG TU -
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
Pekerjaan : UKS
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
NPSN : 111000.000
Nama Sekolah : 0.000
Kabupaten : 0.000
Propinsi : 0
Pekerjaan 1 2 3 4 5 6=(3x5)
A.01.06 1 M1 PENGUKURAN DAN PASANGAN BOUWPLANK
BAHAN :
Kayu Kelas III Balok 0.0100 m3 3,500,000.00 35,000.00
Paku Biasa 0.0200 Kg 18,000.00 360.00
Kayu Kayu Kelas III Papan 3/20 0.0070 m3 4,000,000.00 28,000.00
Jumlah Bahan 63,360.00
UPAH :
Pekerja 0.1000 Oh 110,000.00 11,000.00
P PK05 Tukang Kayu 0.1000 Oh 135,000.00 13,500.00
P PK03 Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
LL01 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 27,000.00
Jumlah Bahan + Pekerja 90,360.00
A001 Dibulatkan 90,360.00
A.02.01 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 0.4000 Oh 110,000.00 44,000.00
P PK05 Mandor 0.0400 Oh 180,000.00 7,200.00
Jumlah Pekerja 51,200.00
Jumlah Bahan + Pekerja 51,200.00
A001 Dibulatkan 51,200.00
A.02.02 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 2 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 0.5260 Oh 110,000.00 57,860.00
P PK05 Mandor 0.0520 Oh 180,000.00 9,360.00
Jumlah Pekerja 67,220.00
Jumlah Bahan + Pekerja 67,220.00
A001 Dibulatkan 67,220.00
A.02.03 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 3 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 0.7350 Oh 110,000.00 80,850.00
P PK05 Mandor 0.0730 Oh 180,000.00 13,140.00
Jumlah Pekerja 93,990.00
Jumlah Bahan + Pekerja 93,990.00
A001 Dibulatkan 93,990.00
A.02.11 1 M3 URUGAN TANAH KEMBALI
BAHAN :
Tanah Urug 1.2000 m³ 125,000.00 150,000.00
Jumlah Bahan 150,000.00
UPAH :
Pekerja 0.1920 Oh 110,000.00 21,120.00
P PK05 Mandor 0.0190 Oh 180,000.00 3,420.00
Jumlah Pekerja 24,540.00
Jumlah Bahan + Pekerja 174,540.00
A001 Dibulatkan 174,540.00
A.02.12 1 M3 URUGAN TANAH DIPADATKAN
BAHAN :
Tanah Urug 1.2000 m³ 125,000.00 150,000.00
Jumlah Bahan 150,000.00
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
P PK05 Mandor 0.0300 Oh 180,000.00 5,400.00
Jumlah Pekerja 38,400.00
Jumlah Bahan + Pekerja 188,400.00
A001 Dibulatkan 188,400.00
A.02.13 1 M3 URUGAN PASIR
BAHAN :
Pasir Urug 1.2000 m³ 135,000.00 162,000.00
Jumlah Bahan 162,000.00
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
P PK05 Mandor 0.0100 Oh 180,000.00 1,800.00
Jumlah Pekerja 34,800.00
Jumlah Bahan + Pekerja 196,800.00
A001 Dibulatkan 196,800.00
A.02.22 1 M3 PENIMBUNAN TANAH DIPADATKAN (TANAH DARI LUAR)
BAHAN :
Tanah Urug (didatangkan) 1.2000 m³ 125,000.00 150,000.00
Page 92 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
A001 Dibulatkan 207,600.00
A.03.02 1 M3 PASANG PONDASI BATU KALI 1 Pc : 2 Ps
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ 200,000.00 220,000.00
Semen PC (50 kg) 267.0000 Kg 1,160.00 309,720.00
Pasir Pasang 0.4270 m³ 200,000.00 85,400.00
Jumlah Bahan 615,120.00
UPAH :
Pekerja 1.5000 Oh 110,000.00 165,000.00
Tukang Batu 0.6000 Oh 135,000.00 81,000.00
Kepala Tukang 0.0600 Oh 160,000.00 9,600.00
P PK05 Mandor 0.0350 Oh 180,000.00 6,300.00
Jumlah Pekerja 261,900.00
Jumlah Bahan + Pekerja 877,020.00
A001 Dibulatkan 877,020.00
A.03.03 1 M3 PASANG PONDASI BATU KALI 1 Pc : 3 Ps
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ 200,000.00 220,000.00
Semen PC (50 kg) 202.0000 Kg 1,160.00 234,320.00
Pasir Pasang 0.4850 m³ 200,000.00 97,000.00
Jumlah Bahan 551,320.00
UPAH :
Pekerja 1.5000 Oh 110,000.00 165,000.00
Tukang Batu 0.6000 Oh 135,000.00 81,000.00
Kepala Tukang 0.0600 Oh 160,000.00 9,600.00
P PK05 Mandor 0.0350 Oh 180,000.00 6,300.00
Jumlah Pekerja 261,900.00
Jumlah Bahan + Pekerja 813,220.00
A001 Dibulatkan 813,220.00
A.03.04 1 M3 PASANG PONDASI BATU KALI 1 Pc : 4 Ps
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ 200,000.00 220,000.00
Semen PC (50 kg) 163.0000 Kg 1,160.00 189,080.00
Pasir Pasang 0.5200 m³ 200,000.00 104,000.00
Jumlah Bahan 513,080.00
UPAH :
Pekerja 1.5000 Oh 110,000.00 165,000.00
Tukang Batu 0.6000 Oh 135,000.00 81,000.00
Kepala Tukang 0.0600 Oh 160,000.00 9,600.00
P PK05 Mandor 0.0350 Oh 180,000.00 6,300.00
Jumlah Pekerja 261,900.00
Jumlah Bahan + Pekerja 774,980.00
A001 Dibulatkan 774,980.00
A.03.05 1 M3 PASANG PONDASI BATU KARANG MATI 1 Pc : 4 Ps
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ 200,000.00 220,000.00
Semen PC (50 kg) 136.0000 Kg 1,160.00 157,760.00
Pasir Pasang 0.5440 m³ 200,000.00 108,800.00
Jumlah Bahan 486,560.00
UPAH :
Pekerja 1.5000 Oh 110,000.00 165,000.00
Tukang Batu 0.6000 Oh 135,000.00 81,000.00
Kepala Tukang 0.0600 Oh 160,000.00 9,600.00
P PK05 Mandor 0.0350 Oh 180,000.00 6,300.00
Jumlah Pekerja 261,900.00
Jumlah Bahan + Pekerja 748,460.00
A001 Dibulatkan 748,460.00
A.03.13 1 M3 PASANG BATU KOSONG ( AANSTAMPING ), JENIS BATU KALI
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ 200,000.00 220,000.00
Pasir Urug 0.3000 m³ 135,000.00 40,500.00
Jumlah Bahan 260,500.00
UPAH :
Pekerja 0.7800 Oh 110,000.00 85,800.00
Tukang Batu 0.3900 Oh 135,000.00 52,650.00
Kepala Tukang 0.0390 Oh 160,000.00 6,240.00
P PK05 Mandor 0.0200 Oh 180,000.00 3,600.00
Jumlah Pekerja 148,290.00
Jumlah Bahan + Pekerja 408,790.00
A001 Dibulatkan 408,790.00
A.03.13.a 1 M3 PASANG BATU KOSONG ( AANSTAMPING ), JENIS BATU KARANG MATI
BAHAN :
Batu Karang Mati 1.2000 m³ - -
Pasir Urug 0.3000 m³ 135,000.00 40,500.00
Jumlah Bahan 40,500.00
UPAH :
Pekerja 0.7800 Oh 110,000.00 85,800.00
Tukang Batu 0.3900 Oh 135,000.00 52,650.00
Kepala Tukang 0.0390 Oh 160,000.00 6,240.00
P PK05 Mandor 0.0200 Oh 180,000.00 3,600.00
Jumlah Pekerja 148,290.00
Jumlah Bahan + Pekerja 188,790.00
A001 Dibulatkan 188,790.00
A.04.09 1 M2 PASANGAN DINDING BATA MERAH TEBAL 1/2 BATA, 1 Pc : 2 Ps
BAHAN :
Bata Merah Bakar Kelas I 70.0000 bh 1,000.00 70,000.00
Semen PC (50 kg) 18.9500 Kg 1,160.00 21,982.00
Pasir Pasang 0.0380 m³ 200,000.00 7,600.00
Jumlah Bahan 99,582.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Batu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Page 93 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Pekerja 51,200.00
Jumlah Bahan + Pekerja 150,782.00
A001 Dibulatkan 150,780.00
A.04.10 1 M2 PASANGAN DINDING BATAKO 1/2 BATA, 1 Pc : 2 Ps
BAHAN :
Batako 35.0000 bh 2,500.00 87,500.00
Semen PC (50 kg) 9.4750 Kg 1,160.00 10,991.00
Pasir Pasang 0.0380 m³ 200,000.00 7,600.00
Jumlah Bahan 106,091.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Batu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 51,200.00
Jumlah Bahan + Pekerja 157,291.00
A001 Dibulatkan 157,290.00
A.04.11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc : 4 Ps
BAHAN :
Bata Merah Bakar Kelas I 70.0000 bh 1,000.00 70,000.00
Semen PC (50 kg) 11.5000 Kg 1,160.00 13,340.00
Pasir Pasang 0.0430 m³ 200,000.00 8,600.00
Jumlah Bahan 91,940.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Batu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 51,200.00
Jumlah Bahan + Pekerja 143,140.00
A001 Dibulatkan 143,140.00
A.04.12 1 M2 PASANGAN DINDING BATAKO 1/2 BATA, 1 Pc : 4 Ps
BAHAN :
Batako 35.0000 bh 2,500.00 87,500.00
Semen PC (50 kg) 5.7500 Kg 1,160.00 6,670.00
Pasir Pasang 0.0430 m³ 200,000.00 8,600.00
Jumlah Bahan 102,770.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Batu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0150 Oh 180,000.00 2,700.00
Jumlah Pekerja 53,000.00
Jumlah Bahan + Pekerja 155,770.00
A001 Dibulatkan 155,770.00
A.05.19 1 M2 PASANGAN PLESTERAN 1 Pc : 2 Ps, TEBAL 25 MM
BAHAN :
Semen PC (50 kg) 15.5000 Kg 1,160.00 17,980.00
Pasir Pasang 0.0130 m³ 200,000.00 2,600.00
Jumlah Bahan 20,580.00
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
Tukang Batu 0.2000 Oh 135,000.00 27,000.00
Kepala Tukang 0.0200 Oh 160,000.00 3,200.00
P PK05 Mandor 0.0130 Oh 180,000.00 2,340.00
Jumlah Pekerja 65,540.00
Jumlah Bahan + Pekerja 86,120.00
A001 Dibulatkan 86,120.00
A.05.21 1 M2 PASANGAN PLESTERAN 1 Pc : 4 Ps, TEBAL 25 MM + ACIAN
BAHAN :
Semen PC (50 kg) 9.4800 Kg 1,160.00 10,996.80
Pasir Pasang 0.0380 m³ 200,000.00 7,600.00
Jumlah Bahan 18,596.80
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
Tukang Batu 0.2000 Oh 135,000.00 27,000.00
Kepala Tukang 0.0200 Oh 160,000.00 3,200.00
P PK05 Mandor 0.0130 Oh 180,000.00 2,340.00
Jumlah Pekerja 65,540.00
Jumlah Bahan + Pekerja 84,136.80
A001 Dibulatkan 84,130.00
A.05.36 1 M2 ACIAN PC
BAHAN :
BA34 Semen PC (50 kg) 0.0800 zak 58,000.00 4,640.00
Jumlah Bahan 4,640.00
UPAH :
P PK02 Pekerja 0.1430 org 110,000.00 15,730.00
P PK04 Tukang Batu 0.1070 org 135,000.00 14,445.00
P PK06 Kepala Tukang batu 0.0105 org 160,000.00 1,680.00
P PK19 Mandor 0.0053 org 180,000.00 945.00
Jumlah Pekerja 32,800.00
Jumlah Bahan + Pekerja 37,440.00
Jumlah 37,440.00
A077 Dibulatkan 37,440.00
A.06.01 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KAYU KLS II
BAHAN :
Kayu Kelas II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Paku Biasa 1.2500 Kg 18,000.00 22,500.00
Lem kayu 0.0500 Kg 17,000.00 850.00
Jumlah Bahan 4,400,000.00
UPAH :
Pekerja 6.0000 Oh 110,000.00 660,000.00
Tukang Kayu 15.0000 Oh 135,000.00 2,025,000.00
Kepala Tukang 3.0000 Oh 160,000.00 480,000.00
Page 94 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
P PK05 Mandor 0.5000 Oh 180,000.00 90,000.00
Jumlah Pekerja 3,255,000.00
Jumlah Bahan + Pekerja 7,655,000.00
A001 Dibulatkan 7,655,000.00
A.06.02 1 UNIT PEK. KUSEN PINTU P1 (L=170 cm) + JALUZI
BAHAN :
Pek. Kusen pintu P1 + Jaluzi 0.06760 m³ 7,655,000.00 517,478.00
Jumlah Bahan 517,478.00
A001 Dibulatkan 517,470.00
A.06.03 1 UNIT PEK. KUSEN PINTU P2 (L=90 cm) + JALUZI
BAHAN :
Pek. Kusen pintu P2 + Jaluzi 0.0500 m³ 7,655,000.00 382,750.00
Jumlah Bahan 382,750.00
A001 Dibulatkan 382,750.00
A.06.04 1 UNIT PEK. KUSEN PINTU P3 (L=70 cm)
BAHAN :
Pek. Kusen pintu P3 0.0290 m³ 7,655,000.00 221,995.00
Jumlah Bahan + Pekerja 221,995.00
A001 Dibulatkan 221,990.00
A.06.05 1 UNIT PEK. KUSEN PINTU P5 (L=100 cm)
BAHAN :
Pek. Kusen pintu P5 0.0510 m³ 7,655,000.00 390,405.00
Jumlah Bahan 390,405.00
A001 Dibulatkan 390,400.00
A.06.06 1 UNIT PEK. KUSEN PINTU JENDELA PJ1/PJ1A + JALUZI
BAHAN :
Kusen Pintu Jendela PJ1 + Jaluzi 0.1010 m³ 7,655,000.00 773,155.00
Jumlah Bahan 773,155.00
A001 Dibulatkan 773,150.00
A.06.07 1 UNIT PEK. KUSEN PINTU JENDELA PJ2 + JALUZI
BAHAN :
Kusen Pintu Jendela PJ2 + Jaluzi 0.1010 m³ 7,655,000.00 773,155.00
Jumlah Bahan 773,155.00
A001 Dibulatkan 773,150.00
A.06.08 1 UNIT PEK. KUSEN PINTU JENDELA PJ3 + JALUZI
BAHAN :
Kusen Pintu Jendela PJ3 + Jaluzi 0.1630 m³ 7,655,000.00 1,247,765.00
Jumlah Bahan 1,247,765.00
A001 Dibulatkan 1,247,760.00
A.06.09 1 UNIT PEK. KUSEN JENDELA J2 + JALUZI
BAHAN :
Kusen Jendela J2 + Jaluzi 0.0690 m³ 7,655,000.00 528,195.00
Jumlah Bahan 528,195.00
A001 Dibulatkan 528,190.00
A.06.10 1 UNIT PEK. KUSEN JENDELA J3 + JALUZI
BAHAN :
Kusen Jendela J3 + Jaluzi 0.0950 m³ 7,655,000.00 727,225.00
Jumlah Bahan 727,225.00
A001 Dibulatkan 727,220.00
A.06.11 1 UNIT PEK. KUSEN JENDELA J4 + JALUZI
BAHAN :
Kusen Jendela J4 + Jaluzi 0.1470 m³ 7,655,000.00 1,125,285.00
Jumlah Bahan 1,125,285.00
A001 Dibulatkan 1,125,280.00
A.06.12 1 UNIT PEK. KUSEN JENDELA J
BAHAN :
Kusen Jendela J 0.0300 m³ 7,655,000.00 229,650.00
Jumlah Bahan 229,650.00
A001 Dibulatkan 229,650.00
A.06.13 1 UNIT PEK. KUSEN BOUVENLICH BV1
BAHAN :
Kusen Bouvenlich BV1 0.0240 m³ 7,655,000.00 183,720.00
Jumlah Bahan 183,720.00
A001 Dibulatkan 183,720.00
A.06.14 1 UNIT PEK. KUSEN BOUVENLICH BV2
BAHAN :
Kusen Bouvenlich BV2 0.0430 m³ 7,655,000.00 329,165.00
Jumlah Bahan 329,165.00
A001 Dibulatkan 329,160.00
A.06.15 1 UNIT PEK. KUSEN BOUVENLICH BV3
BAHAN :
Kusen Bouvenlich BV3 0.0610 m³ 7,655,000.00 466,955.00
Jumlah Bahan 466,955.00
A001 Dibulatkan 466,950.00
A.06.16 1 UNIT PEK. KUSEN ANGIN-ANGIN LA-LB + JALUZI
BAHAN :
Kusen Angin-Angin LA-LB + Jaluzi 0.0340 m³ 7,655,000.00 260,270.00
Jumlah Bahan 260,270.00
A001 Dibulatkan 260,270.00
A.06.17 1 M2 PEKERJAAN DAUN PINTU PANEL KAYU LOKAL KLS II
BAHAN :
Kayu Kelas II Papan 0.0400 m³ 5,000,000.00 200,000.00
Lem Kayu 0.0500 kg 17,000.00 850.00
Jumlah Bahan 200,850.00
UPAH :
Pekerja 1.0000 Oh 110,000.00 110,000.00
Tukang Kayu 2.5000 Oh 135,000.00 337,500.00
Kepala Tukang 0.2500 Oh 160,000.00 40,000.00
P PK05 Mandor 0.0500 Oh 180,000.00 9,000.00
Jumlah Pekerja 496,500.00
Jumlah Bahan + Pekerja 697,350.00
A001 Dibulatkan 697,350.00
A.06.18 1 BH PASANGAN DAUN PINTU PANIL
BAHAN :
Page 95 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
Pintu Panil 1.6800 m2 697,350.00 1,171,548.00
Jumlah Bahan 1,171,548.00
A001 Dibulatkan 1,171,540.00
A.06.19 1 BH PASANGAN DAUN PINTU PANIL P5
BAHAN :
Pintu Panil 1.8900 m2 697,350.00 1,317,991.50
Jumlah Bahan 1,317,991.50
A001 Dibulatkan 1,317,990.00
A.06.20 1 M2 PEKERJAAN DAUN PINTU TRIPLEKS RANGKAP, RANGKA KAYU KLS II
BAHAN :
Kayu Kls. II Balok 0.0196 m³ 4,000,000.00 78,400.00
Paku Biasa Tripleks 0.0300 kg 25,000.00 750.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Tripleks 6 mm 1.0000 lbr 80,000.00 80,000.00
Jumlah Bahan 164,250.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Kayu 2.0000 Oh 135,000.00 270,000.00
Kepala Tukang 0.2000 Oh 160,000.00 32,000.00
P PK05 Mandor 0.0300 Oh 180,000.00 5,400.00
Jumlah Pekerja 373,400.00
Jumlah Bahan + Pekerja 537,650.00
A001 Dibulatkan 537,650.00
A.06.21 1 BH PASANGAN DAUN PINTU TRIPLEKS P3
BAHAN :
Pintu Tripleks P3 1.2600 m2 537,650.00 677,439.00
Jumlah Bahan 677,439.00
A001 Dibulatkan 677,430.00
A.06.22 1 M2 PEKERJAAN DAUN JENDELA + KACA
BAHAN :
Kayu Kelas II Papan 0.1000 m³ 5,000,000.00 500,000.00
Kaca Polos 5 mm 1.1000 m2 185,000.00 203,500.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Jumlah Bahan 708,600.00
UPAH :
Pekerja 0.8000 Oh 110,000.00 88,000.00
Tukang Kayu 2.0000 Oh 135,000.00 270,000.00
Kepala Tukang 0.2000 Oh 160,000.00 32,000.00
P PK05 Mandor 0.0300 Oh 180,000.00 5,400.00
Jumlah Pekerja 395,400.00
Jumlah Bahan + Pekerja 1,104,000.00
A001 Dibulatkan 1,104,000.00
A.06.23 1 BH PASANGAN DAUN JENDELA + KACA (PJ1 dan PJ2)
BAHAN :
Daun Jendela + Kaca (PJ1 dan PJ2) 0.5070 m2 1,104,000.00 559,728.00
Jumlah Bahan 559,728.00
A001 Dibulatkan 559,720.00
A.06.24 1 BH PASANGAN DAUN JENDELA + KACA PJ3
BAHAN :
Daun Jendela + Kaca PJ3 1.2480 m2 1,104,000.00 1,377,792.00
Jumlah Bahan 1,377,792.00
A001 Dibulatkan 1,377,790.00
A.06.25 1 BH PASANGAN DAUN PINTU + KACA PJ3
BAHAN :
Daun Pintu + Kaca PJ3 1.6800 m2 1,104,000.00 1,854,720.00
Jumlah Bahan 1,854,720.00
A001 Dibulatkan 1,854,720.00
A.06.26 1 BH PASANGAN DAUN JENDELA + KACA J2
BAHAN :
Daun Jendela + Kaca J2 0.5070 m2 1,104,000.00 559,728.00
Jumlah Bahan 559,728.00
A001 Dibulatkan 559,720.00
A.06.27 1 BH PASANGAN DAUN JENDELA + KACA J3
BAHAN :
Daun Jendela + Kaca J3 0.5915 m2 1,104,000.00 653,016.00
Jumlah Bahan 653,016.00
Dibulatkan 653,010.00
A.06.28 1 BH PASANGAN DAUN JENDELA + KACA J4
BAHAN :
Daun Jendela + Kaca J4 1.2480 m2 1,104,000.00 1,377,792.00
Jumlah Bahan 1,377,792.00
Dibulatkan 1,377,790.00
A.06.29 1 BH PASANGAN DAUN JENDELA + KACA J5
BAHAN :
Daun Jendela + Kaca J5 0.8050 m2 1,104,000.00 888,720.00
Jumlah Bahan 888,720.00
Dibulatkan 888,720.00
A.06.30 1 BH PASANGAN DAUN JENDELA + KACA J6
BAHAN :
Daun Jendela + Kaca J6 0.5980 m2 1,104,000.00 660,192.00
Jumlah Bahan 660,192.00
Dibulatkan 660,190.00
A.06.31 1 UNIT PEK. KUSEN JENDELA J5
BAHAN :
Kusen Jendela J5 0.0310 m³ 7,655,000.00 237,305.00
Jumlah Bahan 237,305.00
Dibulatkan 237,300.00
A.06.32 1 UNIT PEK. KUSEN JENDELA J6
BAHAN :
Kusen Jendela J6 0.0490 m³ 7,655,000.00 375,095.00
Jumlah Bahan 375,095.00
Dibulatkan 375,090.00
A.06.32.a 1 M2 PASANG KACA TEBAL 5 MM
BAHAN :
Page 96 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
- m³ 5,000,000.00 -
Kaca Polos 5 mm 1.1000 m2 185,000.00 203,500.00
Paku Biasa Tripleks 0.0300 kg 25,000.00 750.00
Jumlah Bahan 204,250.00
UPAH :
Pekerja 0.0150 Oh 110,000.00 1,650.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
P PK05 - Oh 180,000.00 -
Jumlah Pekerja 24,300.00
Jumlah Bahan + Pekerja 228,550.00
A001 Dibulatkan 228,550.00
A.06.33 1 M1 PASANG KONSTRUKSI NOK BUBUNGAN 6/12 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Paku Biasa 0.0500 kg 18,000.00 900.00
Jumlah Bahan 4,400,900.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
P PK05 Mandor 0.0130 Oh 180,000.00 2,340.00
Jumlah Pekerja 52,490.00
Jumlah Bahan + Pekerja 4,453,390.00
A001 Dibulatkan 4,453,390.00
A.06.34 1 M3 PASANG KONSTRUKSI SKOOR ANGIN 6/12 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Paku Biasa 5.8000 kg 18,000.00 104,400.00
Jumlah Bahan 4,504,400.00
UPAH :
Pekerja 4.0000 Oh 110,000.00 440,000.00
Tukang Kayu 12.0000 Oh 135,000.00 1,620,000.00
Kepala Tukang 1.2000 Oh 160,000.00 192,000.00
P PK05 Mandor 0.2000 Oh 180,000.00 36,000.00
Jumlah Pekerja 2,288,000.00
Jumlah Bahan + Pekerja 6,792,400.00
A001 Dibulatkan 6,792,400.00
A.06.35 1 M3 PASANGAN KONSTRUKSI KUDA - KUDA 8/12 KAYU KAYU LOKAL KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Paku Biasa 5.8000 kg 18,000.00 104,400.00
Jumlah Bahan 4,504,400.00
UPAH :
Pekerja 4.0000 Oh 110,000.00 440,000.00
Tukang Kayu 12.0000 Oh 135,000.00 1,620,000.00
Kepala Tukang 1.2000 Oh 160,000.00 192,000.00
P PK05 Mandor 0.2000 Oh 180,000.00 36,000.00
Jumlah Pekerja 2,288,000.00
Jumlah Bahan + Pekerja 6,792,400.00
A001 Dibulatkan 6,792,400.00
A.06.36 1 M3 PASANG KONSTRUKSI GORDING 5/10 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Paku Biasa 5.8000 kg 18,000.00 104,400.00
Jumlah Bahan 4,504,400.00
UPAH :
Pekerja 4.0000 Oh 110,000.00 440,000.00
Tukang Kayu 12.0000 Oh 135,000.00 1,620,000.00
Kepala Tukang 1.2000 Oh 160,000.00 192,000.00
P PK05 Mandor 0.2000 Oh 180,000.00 36,000.00
Jumlah Pekerja 2,288,000.00
Jumlah Bahan + Pekerja 6,792,400.00
A001 Dibulatkan 6,792,400.00
A.06.37 1 M3 PASANG KASO 5/7 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 0.0120 m³ 4,000,000.00 48,000.00
Paku Biasa 0.1500 kg 18,000.00 2,700.00
Jumlah Bahan 50,700.00
UPAH :
Pekerja 0.1000 Oh 110,000.00 11,000.00
Tukang Kayu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 27,000.00
Jumlah Bahan + Pekerja 77,700.00
A001 Dibulatkan 77,700.00
A.06.38 1 M3 PASANG RENG 3/4 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 0.0120 m³ 4,000,000.00 48,000.00
Paku Biasa 0.1500 kg 18,000.00 2,700.00
Jumlah Bahan 50,700.00
UPAH :
Pekerja 0.1000 Oh 110,000.00 11,000.00
Tukang Kayu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 27,000.00
Jumlah Bahan + Pekerja 77,700.00
A001 Dibulatkan 77,700.00
A.06.39 1 M1 PASANG KONSTRUKSI NOK TEPI PAPAN 6/12 KAYU KLS II
BAHAN :
Kayu Kelas II Papan 1.0000 m³ 5,000,000.00 5,000,000.00
Paku Biasa 0.0450 kg 18,000.00 810.00
Page 97 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Bahan 5,000,810.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
P PK05 Mandor 0.0130 Oh 180,000.00 2,340.00
Jumlah Pekerja 52,490.00
Jumlah Bahan + Pekerja 5,053,300.00
A001 Dibulatkan 5,053,300.00
A.06.44 1 M2 PASANG RANGKA PLAFOND BALOK 5/7 KAYU LOKAL KLS II
BAHAN :
Kayu Kls II, Kaso 5/7 Rangka Plafon 0.0154 m³ 4,000,000.00 61,600.00
Paku Biasa 0.2000 kg 18,000.00 3,600.00
Jumlah Bahan 61,600.00
UPAH :
Pekerja 0.1500 Oh 110,000.00 16,500.00
Tukang Kayu 0.3000 Oh 135,000.00 40,500.00
Kepala Tukang 0.0300 Oh 160,000.00 4,800.00
P PK05 Mandor 0.0100 Oh 180,000.00 1,800.00
Jumlah Pekerja 63,600.00
Jumlah Bahan + Pekerja 125,200.00
A001 Dibulatkan 125,200.00
A.06.50 1 M2 PASANG LISPLANG UKURAN (3 x 25) cm, KAYU LOKAL KLS II
BAHAN :
Kayu Kelas II Papan 0.0110 m³ 5,000,000.00 55,000.00
Paku Biasa 0.0500 kg 18,000.00 900.00
Jumlah Bahan 55,900.00
UPAH :
Pekerja 0.1100 Oh 110,000.00 12,100.00
Tukang Kayu 0.2200 Oh 135,000.00 29,700.00
Kepala Tukang 0.0220 Oh 160,000.00 3,520.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 46,220.00
Jumlah Bahan + Pekerja 102,120.00
A001 Dibulatkan 102,120.00
A.06.60 1 M1 PASANG LIST PLAFOND PROFIL KAYU LOKAL KLS II 3/3
BAHAN :
List Plafond 3/3 1.0500 m' 8,750.00 9,187.50
Paku Biasa 0.0100 kg 18,000.00 180.00
Jumlah Bahan 9,367.50
UPAH :
Pekerja 0.0500 Oh 110,000.00 5,500.00
Tukang Kayu 0.0500 Oh 135,000.00 6,750.00
Kepala Tukang 0.0050 Oh 160,000.00 800.00
P PK05 Mandor Oh 180,000.00 -
Jumlah Pekerja 13,050.00
Jumlah Bahan + Pekerja 22,417.50
A001 Dibulatkan 22,410.00
A.07.01 1 M3 MEMBUAT BETON TUMBUK, 1 Pc : 3 Ps : 5 Kr
BAHAN :
Semen PC (50 kg) 218.0000 kg 1,160.00 252,880.00
Pasir Beton 0.5200 M3 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.8700 m³ 220,000.00 191,400.00
Jumlah Bahan 561,280.00
UPAH :
Pekerja 1.6500 Oh 110,000.00 181,500.00
Tukang Batu 0.2500 Oh 135,000.00 33,750.00
Kepala Tukang 0.0250 Oh 160,000.00 4,000.00
P PK05 Mandor 0.0800 Oh 180,000.00 14,400.00
Jumlah Pekerja 233,650.00
Jumlah Bahan + Pekerja 794,930.00
A001 Dibulatkan 794,930.00
A.07.13 1 M3 MEMBUAT BETON BERTULANG 1 Pc : 2 Ps : 3 Kr
BAHAN :
Semen PC (50 kg) 336.0000 kg 1,160.00 389,760.00
Pasir Beton 0.5400 m3 225,000.00 121,500.00
Batu Kerikil / Split 2/3 cm 0.8100 m³ 220,000.00 178,200.00
Jumlah Bahan 689,460.00
UPAH :
Pekerja 2.0000 Oh 110,000.00 220,000.00
Tukang Batu 0.3500 Oh 135,000.00 47,250.00
Kepala Tukang 0.0350 Oh 160,000.00 5,600.00
P PK05 Mandor 1.0000 Oh 180,000.00 180,000.00
Jumlah Pekerja 452,850.00
Jumlah Bahan + Pekerja 1,142,310.00
A001 Dibulatkan 1,142,310.00
A.07.25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR
BAHAN :
Besi Beton Polos 1.0500 kg 13,000.00 13,650.00
Kawat Beton 0.0150 kg 15,000.00 225.00
Jumlah Bahan 13,875.00
UPAH :
Pekerja 0.0070 Oh 110,000.00 770.00
Tukang Besi 0.0070 Oh 135,000.00 945.00
P PK05 Kepala Tukang 0.0007 Oh 160,000.00 112.00
P PK05 Mandor 0.0003 Oh 180,000.00 54.00
Jumlah Pekerja 1,881.00
Jumlah Bahan + Pekerja 15,756.00
A001 Dibulatkan 15,750.00
A.07.28 1 m2 PASANG BEKISTING UNTUK PONDASI
BAHAN :
Kayu Kelas III Papan 0.0400 m³ 4,000,000.00 160,000.00
Paku Biasa 0.3000 m³ 18,000.00 5,400.00
Minyak Bekisting 0.1000 ltr 7,000.00 700.00
Page 98 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Bahan 166,100.00
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
Tukang Kayu 0.2600 Oh 135,000.00 35,100.00
P PK05 Kepala Tukang 0.0260 Oh 160,000.00 4,160.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 73,160.00
Jumlah Bahan + Pekerja 239,260.00
A001 Dibulatkan 239,260.00
A.07.29 1 m2 PASANG BEKISTING UNTUK SLOOF
BAHAN :
Kayu Kelas III Papan 0.0044 m³ 4,000,000.00 17,600.00
Paku Biasa 0.3000 m³ 18,000.00 5,400.00
Minyak Bekisting 0.1000 m³ 7,000.00 700.00
Jumlah Bahan 23,700.00
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
Tukang Kayu 0.2600 Oh 135,000.00 35,100.00
P PK05 Kepala Tukang 0.0260 Oh 160,000.00 4,160.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 73,160.00
Jumlah Bahan + Pekerja 96,860.00
A001 Dibulatkan 96,860.00
A.07.30 1 m2 PASANG BEKISTING UNTUK KOLOM
BAHAN :
Kayu Kelas III Papan 0.0040 m³ 4,000,000.00 16,000.00
Paku Biasa 0.4000 kg 18,000.00 7,200.00
Minyak Bekisting 0.2000 ltr 7,000.00 1,400.00
Kayu Kelas III Balok 0.0015 m³ 3,500,000.00 5,250.00
Jumlah Bahan 29,850.00
UPAH :
Pekerja 0.3000 Oh 110,000.00 33,000.00
Tukang Kayu 0.3300 Oh 135,000.00 44,550.00
P PK05 Kepala Tukang 0.0330 Oh 160,000.00 5,280.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 83,910.00
Jumlah Bahan + Pekerja 113,760.00
A001 Dibulatkan 113,760.00
A.07.31 1 m2 PASANG BEKISTING UNTUK BALOK
BAHAN :
Kayu Kelas III Papan 0.0040 m³ 4,000,000.00 16,000.00
Paku Biasa 0.4000 kg 18,000.00 7,200.00
Minyak Bekisting 0.2000 ltr 7,000.00 1,400.00
Kayu Kelas III Balok 0.0018 m³ 3,500,000.00 6,300.00
Kayu Dolken 2.0000 btg 40,000.00 80,000.00
Jumlah Bahan 110,900.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Kayu 0.3300 Oh 135,000.00 44,550.00
P PK05 Kepala Tukang 0.0330 Oh 160,000.00 5,280.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 86,110.00
Jumlah Bahan + Pekerja 197,010.00
A001 Dibulatkan 197,010.00
A.07.32 1 m2 PASANG BEKISTING UNTUK LANTAI
BAHAN :
Kayu Kelas III Papan 0.0020 m³ 4,000,000.00 8,000.00
Paku Biasa 0.4000 kg 18,000.00 7,200.00
Minyak Bekisting 0.2000 ltr 7,000.00 1,400.00
Kayu Kelas III Balok 0.0015 m³ 3,500,000.00 5,250.00
Polywood tebal 9 mm 0.3500 lbr 100,000.00 35,000.00
Kayu Dolken 4.0000 btg 40,000.00 160,000.00
Jumlah Bahan 216,850.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Kayu 0.3300 Oh 135,000.00 44,550.00
P PK05 Kepala Tukang 0.0330 Oh 160,000.00 5,280.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 86,110.00
Jumlah Bahan + Pekerja 302,960.00
A001 Dibulatkan 302,960.00
A.07.33 1 m2 PASANG BEKISTING UNTUK DINDING
BAHAN :
Kayu Kelas III Papan 0.0300 m³ 4,000,000.00 120,000.00
Paku Biasa 0.4000 kg 18,000.00 7,200.00
Minyak Bekisting 0.2000 ltr 7,000.00 1,400.00
Kayu Kelas III Balok 0.0200 m³ 4,000,000.00 80,000.00
Polywood tebal 9 mm 0.3500 lbr 100,000.00 35,000.00
Kayu Dolken 3.0000 btg 40,000.00 120,000.00
Formtie / Penjaga Jarak Berkisar / Spacer 4.0000 bh -
Jumlah Bahan 363,600.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Kayu 0.3300 Oh 135,000.00 44,550.00
P PK05 Kepala Tukang 0.0330 Oh 160,000.00 5,280.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 86,110.00
Jumlah Bahan + Pekerja 449,710.00
A001 Dibulatkan 449,710.00
A.07.47 1 M3 MEMBUAT SOFI-SOFI 12/15 (220,80 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM 190.1393
BAHAN :
Kayu Kelas III Papan 0.3700 m³ 4,000,000.00 1,480,000.00
Paku Biasa 1.5000 kg 18,000.00 27,000.00
Page 99 of 156
Analisa Satuan Pekerjaan
Kode1K Kode3 NO. URAIAN KOEF SAT. Harga Satuan JUMLAH
Pekerjaan 1 2 3 4 5 6=(3x5)
Pelumas Bekesting 0.4000 lt 7,000.00 2,800.00
Besi Beton Polos Dia. 10 mm 152.6578 kg 13,000.00 1,984,551.11
Besi Beton Polos Dia. 8 mm 37.4815 kg 12,000.00 449,777.78
Kawat Beton 2.2500 kg 15,000.00 33,750.00
Semen PC (50 kg) 6.4600 zak 58,000.00 374,680.00
Pasir Beton 0.5200 m³ 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Jumlah Bahan 4,641,158.89
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 5,361,808.89
Dibulatkan 5,361,800.00
A.07.48 1 M3 MEMBUAT RING BALOK 15/20 (145,92 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Papan 0.3700 m³ 4,000,000.00 1,480,000.00
Paku Biasa 1.5000 kg 18,000.00 27,000.00
Pelumas Bekesting 0.4000 lt 7,000.00 2,800.00
Besi Beton Polos Dia. 10 mm 92.5867 kg 13,000.00 1,203,626.67
Besi Beton Polos Dia. 8 mm 53.3333 kg 12,000.00 640,000.00
Kawat Beton 2.2500 kg 15,000.00 33,750.00
Semen PC (50 kg) 6.4600 zak 58,000.00 374,680.00
Pasir Beton 0.5200 m³ 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Jumlah Bahan 4,050,456.67
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 4,771,106.67
Dibulatkan 4,771,100.00
A.07.48'' 1 M3 MEMBUAT RING BALOK 12/20 (177,9556 Kg Besi + Bekesting) 177.9556
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Papan 0.3700 m³ 4000000 1,480,000.00
Paku Biasa 1.5000 kg 18000 27,000.00
Pelumas Bekesting 0.4000 lt 7000 2,800.00
Besi Beton Polos Dia. 10 mm 115.7333 kg 13000 1,504,533.33
Besi Beton Polos Dia. 8 mm 62.2222 kg 12000 746,666.67
Kawat Beton 2.2500 kg 15000 33,750.00
Semen PC (50 kg) 6.4600 zak 58000 374,680.00
Pasir Beton 0.5200 m³ 225000 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220000 171,600.00
Jumlah Bahan 4,458,030.00
UPAH :
Tukang Batu 0.3500 org 135000 47,250.00
Tukang Kayu 1.0400 org 135000 140,400.00
Tukang Besi 1.0500 org 135000 141,750.00
Kepala Tukang 0.2450 org 160000 39,200.00
Pekerja 3.0000 org 110000 330,000.00
Mandor 0.1225 org 180000 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 5,178,680.00
Dibulatkan 5,178,680.00
A.07.49 1 M3 MEMBUAT KOLOM 20/25 (169,67 Kg Besi + Bekesting)
DENGAN TULANGAN 6 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Bekesting 0.3700 m³ 4,000,000.00 1,480,000.00
Paku Biasa 1.5000 kg 18,000.00 27,000.00
Pelumas Bekesting 0.4000 lt 7,000.00 2,800.00
5.88 Besi Beton Polos Dia. 12 mm 122.8200 kg 13,000.00 1,596,660.00
4.19 Besi Beton Polos Dia. 8 mm 42.6667 kg 12,000.00 512,000.00
Kawat Beton 2.2500 kg 15,000.00 33,750.00
Semen PC (50 kg) 6.4600 zak 58,000.00 374,680.00
Pasir Beton 0.5200 m³ 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Jumlah Bahan 4,315,490.00
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 5,036,140.00
Dibulatkan 5,036,140.00
A.07.50 1 M3 MEMBUAT SLOOF SELASAR 15/20 (188,88 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Bekesting 0.2900 m³ 4,000,000.00 1,160,000.00
Paku Biasa 1.5000 kg 18,000.00 27,000.00
Pelumas Bekesting 0.4000 lt 7,000.00 2,800.00
3.70 Besi Beton Polos Dia. 12 mm 132.9067 kg 13,000.00 1,727,786.67
Pekerjaan 1 2 3 4 5 6=(3x5)
2.64 Besi Beton Polos Dia. 8 mm 53.3333 kg 12,000.00 640,000.00
Kawat Beton 2.2500 kg 15,000.00 33,750.00
Semen PC (50 kg) 6.4600 zak 58,000.00 374,680.00
Pasir Beton 0.5200 m³ 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Jumlah Bahan 4,254,616.67
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 4,975,266.67
Jumlah 4,975,266.67
Dibulatkan 4,975,260.00
A.07.51 1 M3 PEK. BETON BERTULANG PLAT MEJA, adukan 1 : 2 : 3
BAHAN :
Kayu Kelas III Bekesting 0.3300 m3 4,000,000.00 1,320,000.00
Paku Biasa 3.0000 kg 18,000.00 54,000.00
Besi Beton Polos Dia. 10 mm 110.0000 kg 13,000.00 1,430,000.00
Kawat Beton 3.0000 kg 15,000.00 45,000.00
Semen PC (50 kg) 6.4600 Zak 58,000.00 374,680.00
Pasir Beton 0.5200 m3 225,000.00 117,000.00
Kerikil beton 0.7800 m3 225,000.00 175,500.00
Jumlah Bahan 3,516,180.00
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 4,236,830.00
Jumlah 4,236,830.00
Dibulatkan 4,236,830.00
A.07.52 1 M3 MEMBUAT KOLOM 12/15 (197 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM 190.1393
BAHAN :
Kayu Kelas III Bekesting 0.4000 m³ 4,000,000.00 1,600,000.00
Paku Biasa 1.5000 kg 18,000.00 27,000.00
Pelumas Bekesting 0.4000 lt 7,000.00 2,800.00
20.42 Besi Beton Polos Dia. 10 mm 152.6578 kg 13,000.00 1,984,551.11
10.13 Besi Beton Polos Dia. 6 mm 37.4815 kg 12,000.00 449,777.78
Kawat Beton 2.2500 kg 15,000.00 33,750.00
Semen PC (50 kg) 6.4600 zak 58,000.00 374,680.00
Pasir Beton 0.5200 m³ 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Jumlah Bahan 4,761,158.89
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 5,481,808.89
Dibulatkan 5,481,800.00
A.07.60 1 M3 MEMBUAT KOLOM SELASAR 15/15 (181,88 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Bekesting 0.4400 m³ 4,000,000.00 1,760,000.00
Paku Biasa 1.5000 kg 18,000.00 27,000.00
Pelumas Bekesting 0.4000 lt 7,000.00 2,800.00
8.33 Besi Beton Polos Dia. 10 mm 122.6222 kg 13,000.00 1,594,088.89
4.13 Besi Beton Polos Dia. 8 mm 59.2593 kg 12,000.00 711,111.11
Kawat Beton 2.2500 kg 15,000.00 33,750.00
Semen PC (50 kg) 6.4600 zak 58,000.00 374,680.00
Pasir Beton 0.5200 m³ 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Jumlah Bahan 4,792,030.00
UPAH :
Tukang Batu 0.3500 org 135,000.00 47,250.00
Tukang Kayu 1.0400 org 135,000.00 140,400.00
Tukang Besi 1.0500 org 135,000.00 141,750.00
Kepala Tukang 0.2450 org 160,000.00 39,200.00
Pekerja 3.0000 org 110,000.00 330,000.00
Mandor 0.1225 org 180,000.00 22,050.00
Jumlah Pekerja 720,650.00
Jumlah Bahan + Pekerja 5,512,680.00
Dibulatkan 5,512,680.00
A.07.75 1 M3 PEK. PLAT BETON BERTULANG, TULANGAN 1 LAPIS DIA.10 JARAK 10 cm TEBAL 10 cm
BAHAN :
Semen PC (50 kg) 232.0000 kg 1,160.00 269,120.00
Pasir Beton 0.5200 lbr 225,000.00 117,000.00
Batu Kerikil / Split 2/3 cm 0.7800 m³ 220,000.00 171,600.00
Besi Beton Polos Dia. 10 mm 137.3610 Kg 13,000.00 1,785,693.00
Kawat Beton 1.9623 Kg 15,000.00 29,434.50
Kayu Kelas III Bekesting 0.2450 m³ 4,000,000.00 980,000.00
Paku Biasa 0.1500 kg 18,000.00 2,700.00
Minyak Bekisting 1.4000 Ltr 7,000.00 9,800.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Kayu Kelas III Balok 0.0700 m³ 3,500,000.00 245,000.00
Jumlah Bahan 3,610,347.50
UPAH :
Pekerja 6.4697 Oh 110,000.00 711,671.40
Tukang Batu 0.2500 Oh 135,000.00 33,750.00
Tukang Kayu 4.0260 Oh 135,000.00 543,510.00
Tukang Besi 1.0073 Oh 135,000.00 135,987.39
Kepala Tukang 0.5192 Oh 160,000.00 83,067.84
Mandor 0.1924 Oh 180,000.00 34,640.28
Jumlah Pekerja 1,542,626.91
Jumlah Bahan + Pekerja 5,152,974.41
Dibulatkan 5,152,970.00
A.08.02 1 M2 PASANG ATAP GENTENG TANAH
BAHAN :
Genteng Tanah 25.0000 buah 3,000.00 75,000.00
Jumlah Bahan 75,000.00
UPAH :
Pekerja 0.1500 Oh 110,000.00 16,500.00
Tukang Kayu 0.0750 Oh 135,000.00 10,125.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0080 Oh 180,000.00 1,440.00
Jumlah Pekerja 29,345.00
Jumlah Bahan + Pekerja 104,345.00
A001 Dibulatkan 104,340.00
A.08.03 1 M2 PASANG ATAP SPANDEK / GALVALYUM 0,3mm
BAHAN :
Atap Spandek/Galvalyum 1.0200 Lbr 125,000.00 127,500.00
Paku Seng +seal 0.2000 Kg 30,000.00 6,000.00
Jumlah Bahan 133,500.00
UPAH :
Pekerja 0.1200 Oh 110,000.00 13,200.00
Tukang Kayu 0.0600 Oh 135,000.00 8,100.00
P PK05 Kepala Tukang 0.0060 Oh 160,000.00 960.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 23,340.00
Jumlah Bahan + Pekerja 156,840.00
A001 Dibulatkan 156,840.00
A.08.05 1 M2 PASANG NOK BUBUNGAN GENTENG TANAH
BAHAN :
Bubungan Genteng Tanah 5.0000 Bh 8,000.00 40,000.00
Semen PC (50 kg) 0.1600 zak 58,000.00 9,280.00
Pasir Pasang 0.0320 m3 200,000.00 6,400.00
Jumlah Bahan 55,680.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
P PK05 Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
P PK05 Mandor 0.0130 Oh 180,000.00 2,340.00
Jumlah Pekerja 52,490.00
Jumlah Bahan + Pekerja 108,170.00
A001 Dibulatkan 108,170.00
A.08.06 1 M2 PASANG NOK BUBUNGAN GENTENG METAL
BAHAN :
Nok Genteng Metal 1.1000 buah 50,000.00 55,000.00
Paku Seng + karet seal 0.0500 kg 30,000.00 1,500.00
Jumlah Bahan 56,500.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
P PK05 Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
P PK05 Mandor 0.0130 Oh 180,000.00 2,340.00
Jumlah Pekerja 52,490.00
Jumlah Bahan + Pekerja 108,990.00
A001 Dibulatkan 108,990.00
A.08.11 1 M2 PASANG ATAP SENG GELOMBANG BJLS 0,3 mm
BAHAN :
Seng Gelombang BJLS 0,3 0.7000 lbr 68,000.00 47,600.00
Paku Seng 0.0200 kg 30,000.00 600.00
Jumlah Bahan 48,200.00
UPAH :
Pekerja 0.1200 Oh 110,000.00 13,200.00
Tukang Kayu 0.0600 Oh 135,000.00 8,100.00
P PK05 Kepala Tukang 0.0060 Oh 160,000.00 960.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 23,340.00
Jumlah Bahan + Pekerja 71,540.00
A001 Dibulatkan 71,540.00
A.08.12 1 M2 PASANG ATAP ZYNCALUM 0,3 mm
BAHAN :
Atap Spandex Zyncalum 1.0200 lbr 125,000.00 127,500.00
Paku Seng + karet seal 0.2000 kg 30,000.00 6,000.00
Jumlah Bahan 133,500.00
UPAH :
Pekerja 0.1200 Oh 110,000.00 13,200.00
Tukang Kayu 0.0600 Oh 135,000.00 8,100.00
P PK05 Kepala Tukang 0.0060 Oh 160,000.00 960.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 23,340.00
Jumlah Bahan + Pekerja 156,840.00
A001 Dibulatkan 156,840.00
A.08.13 1 M2 PASANG ATAP GENTENG METAL 0,3 mm
BAHAN :
Genteng Metal/metal roof 1.6200 lbr 40,000.00 64,800.00
Paku Seng + karet seal 0.2000 kg 30,000.00 6,000.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Bahan 70,800.00
UPAH :
Pekerja 0.1200 Oh 110,000.00 13,200.00
Tukang Kayu 0.0600 Oh 135,000.00 8,100.00
P PK05 Kepala Tukang 0.0060 Oh 160,000.00 960.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 23,340.00
Jumlah Bahan + Pekerja 94,140.00
A001 Dibulatkan 94,140.00
A.08.14 1 M' PASANG NOK SENG POLOS 0,3 mm
BAHAN :
Seng Plat Polos 0.3000 lbr 50,000.00 15,000.00
Paku Seng + karet seal 0.0400 kg 30,000.00 1,200.00
Jumlah Bahan 16,200.00
UPAH :
Pekerja 0.0150 Oh 110,000.00 1,650.00
Tukang Kayu 0.0700 Oh 135,000.00 9,450.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 13,460.00
Jumlah Bahan + Pekerja 29,660.00
A001 Dibulatkan 29,660.00
A.08.30 1 M1 PASANG NOK TEPI SENG GELOMBANG
BAHAN :
Nok Tepi Seng Gelombang 1.0000 m¹ 40,000.00 40,000.00
Paku Seng + karet seal 0.0450 kg 30,000.00 1,350.00
Jumlah Bahan 41,350.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.0750 Oh 135,000.00 10,125.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0080 Oh 180,000.00 1,440.00
Jumlah Pekerja 40,345.00
Jumlah Bahan + Pekerja 81,695.00
A001 Dibulatkan 81,690.00
A.08.31 1 M1 PASANG NOK TEPI ZYNCALUM
BAHAN :
Nok Tepi Zyncalum 1.0000 Bh 40,000.00 40,000.00
Paku Seng + karet seal 0.0450 kg 30,000.00 1,350.00
Jumlah Bahan 41,350.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.0750 Oh 135,000.00 10,125.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0080 Oh 180,000.00 1,440.00
Jumlah Pekerja 40,345.00
Jumlah Bahan + Pekerja 81,695.00
A001 Dibulatkan 81,690.00
A.08.32 1 M1 PASANG NOK TEPI GENTENG METAL
BAHAN :
Nok Tepi Genteng Metal 1.0000 Bh 40,000.00 40,000.00
Paku Seng + karet seal 0.0450 kg 30,000.00 1,350.00
Jumlah Bahan 41,350.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.0750 Oh 135,000.00 10,125.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0080 Oh 180,000.00 1,440.00
Jumlah Pekerja 40,345.00
Jumlah Bahan + Pekerja 81,695.00
A001 Dibulatkan 81,690.00
A.08.33 1 M1 PASANG NOK TEPI GENTENG TANAH
BAHAN :
Nok Tepi Genteng Metal 1.0000 Bh 40,000.00 40,000.00
Semen PC (50 kg) 0.1600 zak 58,000.00 9,280.00
Pasir Pasang 0.0320 m3 200,000.00 6,400.00
Jumlah Bahan 55,680.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.0750 Oh 135,000.00 10,125.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0080 Oh 180,000.00 1,440.00
Jumlah Pekerja 40,345.00
Jumlah Bahan + Pekerja 96,025.00
A001 Dibulatkan 96,020.00
A.08.34 1 M1 PASANG NOK TEPI ATAP SPANDEK/GALVALYUM
BAHAN :
Nok Tepi Atap Spandek 1.0000 Bh 40,000.00 40,000.00
Paku Seng 0.0450 kg 30,000.00 1,350.00
Jumlah Bahan 41,350.00
UPAH :
Pekerja 0.2500 Oh 110,000.00 27,500.00
Tukang Kayu 0.0750 Oh 135,000.00 10,125.00
P PK05 Kepala Tukang 0.0080 Oh 160,000.00 1,280.00
P PK05 Mandor 0.0080 Oh 180,000.00 1,440.00
Jumlah Pekerja 40,345.00
Jumlah Bahan + Pekerja 81,695.00
A001 Dibulatkan 81,690.00
A.09.02 1 M2 PASANG PLAFOND TRIPLEKS , TEBAL 4 mm
BAHAN :
Tripleks 4 mm 0.3750 lbr 70,000.00 26,250.00
Paku Biasa 0.0300 kg 18,000.00 540.00
Jumlah Bahan 26,790.00
UPAH :
Pekerjaan 1 2 3 4 5 6=(3x5)
Pekerja 0.1000 Oh 110,000.00 11,000.00
Tukang Kayu 0.1000 Oh 135,000.00 13,500.00
P PK05 Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
P PK05 Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 27,000.00
Jumlah Bahan + Pekerja 53,790.00
A001 Dibulatkan 53,790.00
A.10.01 MEMASANG 1 BUAH KLOSET DUDUK
BAHAN :
Kloset Duduk 1.0000 bh 1,000,000.00 1,000,000.00
Perlengkapan 0.0600 harga kloset 1,000,000.00 60,000.00
Jumlah Bahan 1,060,000.00
UPAH :
P PK05 Pekerja 2.1000 Oh 110,000.00 231,000.00
P PK05 Tukang Batu 0.9600 Oh 135,000.00 129,600.00
Kepala Tukang 0.0010 Oh 160,000.00 160.00
Mandor 0.1600 Oh 180,000.00 28,800.00
Jumlah Pekerja 389,560.00
Jumlah Bahan + Pekerja 1,449,560.00
Dibulatkan 1,449,560.00
A.10.02 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN
BAHAN :
Kloset Jongkok 1.0000 bh 450,000.00 450,000.00
Semen PC (50 kg) 6.0000 kg 1,160.00 6,960.00
Pasir Pasang 0.0100 m³ 200,000.00 2,000.00
Jumlah Bahan 458,960.00
P PK05 UPAH :
P PK05 Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.3000 Oh 135,000.00 40,500.00
Kepala Tukang 0.1500 Oh 160,000.00 24,000.00
Mandor 0.0800 Oh 180,000.00 14,400.00
Jumlah Pekerja 144,900.00
A001 Jumlah Bahan + Pekerja 603,860.00
Dibulatkan 603,860.00
A.10.04 MEMASANG 1 BUAH URINOIR
BAHAN :
Urinoir 1.0000 bh 700,000.00 700,000.00
P PK05 Perlengkapan 0.3000 hrg urinoir 700,000.00 210,000.00
P PK05 Semen PC (50 kg) 6.0000 kg 1,160.00 6,960.00
Pasir Pasang 0.0100 m³ 200,000.00 2,000.00
Jumlah Bahan 918,960.00
UPAH :
Pekerja 1.0000 Oh 110,000.00 110,000.00
A001 Tukang Batu 0.9000 Oh 135,000.00 121,500.00
Kepala Tukang 0.1000 Oh 160,000.00 16,000.00
Mandor 0.1000 Oh 180,000.00 18,000.00
Jumlah Pekerja 265,500.00
Jumlah Bahan + Pekerja 1,184,460.00
Dibulatkan 1,184,460.00
A.10.05 MEMASANG 1 BUAH WASTAFEL
P PK05 BAHAN :
P PK05 Wastafel 1.0000 bh 300,000.00 300,000.00
Perlengkapan 0.1200 hrg kloset 300,000.00 36,000.00
Semen PC (50 kg) 6.0000 kg 1,160.00 6,960.00
Pasir Pasang 0.0100 m³ 200,000.00 2,000.00
Jumlah Bahan 344,960.00
A001 UPAH :
Pekerja 1.2000 Oh 110,000.00 132,000.00
Tukang Batu 1.4500 Oh 135,000.00 195,750.00
Kepala Tukang 0.1500 Oh 160,000.00 24,000.00
Mandor 0.1000 Oh 180,000.00 18,000.00
Jumlah Pekerja 369,750.00
Jumlah Bahan + Pekerja 714,710.00
P PK05 Dibulatkan 714,710.00
A.10.07 MEMASANG 1 BUAH BAK MANDI FIBREGLASS VOLUME 0,3 M3
BAHAN :
Bak Fibreglass 1.0000 bh 150,000.00 150,000.00
Perlengkapan 0.1800 hrg bak 150,000.00 27,000.00
A001 Jumlah Bahan 177,000.00
UPAH :
Pekerja 1.8000 Oh 110,000.00 198,000.00
Tukang Batu 0.6000 Oh 135,000.00 81,000.00
Kepala Tukang 0.5400 Oh 160,000.00 86,400.00
Mandor 0.1100 Oh 180,000.00 19,800.00
Jumlah Pekerja 385,200.00
Jumlah Bahan + Pekerja 562,200.00
P PK05 Dibulatkan 562,200.00
A.10.08 MEMASANG 1 BUAH BAK MANDI BATU BATA VOLUME 0,3 M3
BAHAN :
Bata Merah Bakar Kelas I 110.0000 bh 1,000.00 110,000.00
Semen PC (50 kg) 80.0000 kg 1,160.00 92,800.00
A001 Pasir Pasang 0.3000 m³ 200,000.00 60,000.00
Keramik 20 x 20 cm 216.0000 bh 2,400.00 518,400.00
Semen Warna 6.0000 kg 2,000.00 12,000.00
Jumlah Bahan 793,200.00
UPAH :
Pekerja 2.0000 Oh 110,000.00 220,000.00
Tukang Batu 1.0000 Oh 135,000.00 135,000.00
Kepala Tukang 0.3000 Oh 160,000.00 48,000.00
Mandor 0.1500 Oh 180,000.00 27,000.00
P PK05 Jumlah Pekerja 430,000.00
P PK05 Jumlah Bahan + Pekerja 1,223,200.00
Dibulatkan 1,223,200.00
A.10.16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (30X30) TINGGI 35 CM
Pekerjaan 1 2 3 4 5 6=(3x5)
BAHAN :
Bata Merah Bakar Kelas I 0.1450 bh 1,000.00 145.00
P PK05 Semen PC (50 kg) 44.0000 kg 1,160.00 51,040.00
P PK05 Pasir Pasang 0.0700 m3 200,000.00 14,000.00
Batu Kerikil / Split 2/3 cm 0.0700 m³ 220,000.00 15,400.00
Besi Beton Polos Dia. 10 mm 1.6000 kg 13,000.00 20,800.00
Pasir Beton 0.0600 m3 225,000.00 13,500.00
Jumlah Bahan 114,885.00
A001 UPAH :
Pekerja 3.2000 Oh 110,000.00 352,000.00
Tukang Batu 1.0150 Oh 135,000.00 137,025.00
Kepala Tukang 0.0015 Oh 160,000.00 240.00
Mandor 0.0160 Oh 180,000.00 2,880.00
Jumlah Pekerja 492,145.00
Jumlah Bahan + Pekerja 607,030.00
Dibulatkan 607,030.00
P PK05 A.10.17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (45X45) TINGGI 50 CM
P PK05 BAHAN :
Bata Merah Bakar Kelas I 0.2500 m3 1,000.00 250.00
Semen PC (50 kg) 77.0000 kg 1,160.00 89,320.00
Pasir Pasang 0.1300 m3 200,000.00 26,000.00
Batu Kerikil / Split 2/3 cm 0.0200 m³ 220,000.00 4,400.00
A001 Besi Beton Polos Dia. 10 mm 2.6000 kg 13,000.00 33,800.00
Pasir Beton 0.0900 m3 225,000.00 20,250.00
Jumlah Bahan 174,020.00
UPAH :
Pekerja 1.4200 Oh 110,000.00 156,200.00
Tukang Batu 0.4730 Oh 135,000.00 63,855.00
Kepala Tukang 0.0470 Oh 160,000.00 7,520.00
Mandor 0.0710 Oh 180,000.00 12,780.00
Jumlah Pekerja 240,355.00
Jumlah Bahan + Pekerja 414,375.00
Dibulatkan - 414,370.00
A.10.18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (60X60) TINGGI 65 CM
BAHAN :
Bata Merah Bakar Kelas I 0.3710 m3 1,000.00 371.00
A001 Semen PC (50 kg) 114.0000 kg 1,160.00 132,240.00
Pasir Pasang 0.1840 m3 200,000.00 36,800.00
Batu Kerikil / Split 2/3 cm 0.0330 m³ 220,000.00 7,260.00
Besi Beton Polos Dia. 10 mm 4.8500 kg 13,000.00 63,050.00
Pasir Beton 0.1200 m3 225,000.00 27,000.00
Jumlah Bahan 266,721.00
UPAH :
Pekerja 2.1600 Oh 110,000.00 237,600.00
Tukang 0.1000 Oh 135,000.00 13,500.00
Tukang Batu 0.7200 Oh 135,000.00 97,200.00
P PK05 Kepala Tukang 0.0720 Oh 160,000.00 11,520.00
P PK05 Mandor 0.1080 Oh 180,000.00 19,440.00
Jumlah Pekerja 379,260.00
Jumlah Bahan + Pekerja 645,981.00
A001 Dibulatkan 645,980.00
A.10.19 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,5"
BAHAN :
Pipa Galvanis 0,5" 1.0000 m' 165,000.00 165,000.00
Perlengkapan 0.3500 hrg pipa 165,000.00 57,750.00
Jumlah Bahan 222,750.00
UPAH :
Pekerja 0.0540 Oh 110,000.00 5,940.00
Tukang Batu 0.0900 Oh 135,000.00 12,150.00
P PK05 Kepala Tukang 0.0090 Oh 160,000.00 1,440.00
P PK05 Mandor 0.0270 Oh 180,000.00 4,860.00
Jumlah Pekerja 24,390.00
Jumlah Bahan + Pekerja 247,140.00
A001 Dibulatkan 247,140.00
A.10.20 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,75"
BAHAN :
Pipa Galvanis 0,75" 1.0000 m' 211,000.00 211,000.00
Perlengkapan 0.3500 hrg pipa 211,000.00 73,850.00
Jumlah Bahan 284,850.00
UPAH :
Pekerja 0.0540 Oh 110,000.00 5,940.00
Tukang Batu 0.0900 Oh 135,000.00 12,150.00
Kepala Tukang 0.0090 Oh 160,000.00 1,440.00
P PK05 Mandor 0.0270 Oh 180,000.00 4,860.00
Jumlah Pekerja 24,390.00
Jumlah Bahan + Pekerja 309,240.00
A001 Dibulatkan 309,240.00
A.10.21 MEMASANG 1 M' PIPA GALVANIS DIAMETER 1"
BAHAN :
Pipa Galvanis 1" 1.0000 1,2 m' 322,000.00 322,000.00
Perlengkapan 0.3500 hrg pipa 322,000.00 112,700.00
Jumlah Bahan 434,700.00
UPAH :
Pekerja 0.0540 Oh 110,000.00 5,940.00
Tukang Batu 0.0900 Oh 135,000.00 12,150.00
Kepala Tukang 0.0090 Oh 160,000.00 1,440.00
Mandor 0.0270 Oh 180,000.00 4,860.00
P PK05 Jumlah Pekerja 24,390.00
Jumlah Bahan + Pekerja 459,090.00
Dibulatkan 459,090.00
A001 A.10.22.a MEMASANG 1 M' PIPA GALVANIS DIAMETER 1,5"
BAHAN :
Pipa Galvanis 1,5" 1.0000 1,2 m' 489,000.00 489,000.00
Perlengkapan 0.3500 hrg pipa 489,000.00 171,150.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Bahan 660,150.00
UPAH :
Pekerja 0.1080 Oh 110,000.00 11,880.00
Tukang Batu 0.1800 Oh 135,000.00 24,300.00
Kepala Tukang 0.0180 Oh 160,000.00 2,880.00
Mandor 0.0054 Oh 180,000.00 972.00
Jumlah Pekerja 40,032.00
Jumlah Bahan + Pekerja 700,182.00
Dibulatkan 700,180.00
A001 A.10.22 MEMASANG 1 M' PIPA GALVANIS DIAMETER 2"
BAHAN :
Pipa Galvanis 2" 1.0000 1,2 m' 666,000.00 666,000.00
Perlengkapan 0.3500 hrg pipa 666,000.00 233,100.00
Jumlah Bahan 899,100.00
UPAH :
Pekerja 0.1080 Oh 110,000.00 11,880.00
Tukang Batu 0.1800 Oh 135,000.00 24,300.00
Kepala Tukang 0.0180 Oh 160,000.00 2,880.00
Mandor 0.0054 Oh 180,000.00 972.00
Jumlah Pekerja 40,032.00
Jumlah Bahan + Pekerja 939,132.00
Dibulatkan 939,130.00
A.10.23 MEMASANG 1 M' PIPA GALVANIS DIAMETER 3"
BAHAN :
A001 Pipa Galvanis 3" 1.0000 1,2 m' 156,000.00 156,000.00
Perlengkapan 0.3500 hrg pipa 156,000.00 54,600.00
Jumlah Bahan 210,600.00
UPAH :
Pekerja 0.1080 Oh 110,000.00 11,880.00
Tukang Batu 0.1800 Oh 135,000.00 24,300.00
Kepala Tukang 0.0180 Oh 160,000.00 2,880.00
Mandor 0.0054 Oh 180,000.00 972.00
Jumlah Pekerja 40,032.00
Jumlah Bahan + Pekerja 250,632.00
P PK05 Dibulatkan 250,630.00
A.10.24 MEMASANG 1 M' PIPA GALVANIS DIAMETER 4"
BAHAN :
Pipa Galvanis 4" 1.0000 1,2 m' 1,587,000.00 1,587,000.00
Perlengkapan 0.3500 hrg pipa 1,587,000.00 555,450.00
A001 Jumlah Bahan 2,142,450.00
UPAH :
Pekerja 0.1350 Oh 110,000.00 14,850.00
Tukang Batu 0.2250 Oh 135,000.00 30,375.00
Kepala Tukang 0.0225 Oh 160,000.00 3,600.00
Mandor 0.0068 Oh 180,000.00 1,224.00
Jumlah Pekerja 50,049.00
Jumlah Bahan + Pekerja 2,192,499.00
Dibulatkan 2,192,490.00
A.10.25 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 0,5"
P PK05 BAHAN :
Pipa PVC AW 0,5" 1.0000 m' 4,500.00 4,500.00
Perlengkapan 0.3500 hrg pipa 4,500.00 1,575.00
Jumlah Bahan 6,075.00
UPAH :
A001 Pekerja 0.0360 Oh 110,000.00 3,960.00
Tukang Batu 0.0600 Oh 135,000.00 8,100.00
Kepala Tukang 0.0060 Oh 160,000.00 960.00
Mandor 0.0018 Oh 180,000.00 324.00
Jumlah Pekerja 13,344.00
Jumlah Bahan + Pekerja 19,419.00
Dibulatkan 19,410.00
A.10.26 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 0,75"
BAHAN :
P PK05 Pipa PVC AW 0,75" 1.0000 m' 5,250.00 5,250.00
Perlengkapan 0.3500 hrg pipa 5,250.00 1,837.50
Jumlah Bahan 7,087.50
UPAH :
Pekerja 0.0360 Oh 110,000.00 3,960.00
A001 Tukang Batu 0.0600 Oh 135,000.00 8,100.00
Kepala Tukang 0.0060 Oh 160,000.00 960.00
Mandor 0.0018 Oh 180,000.00 324.00
Jumlah Pekerja 13,344.00
Jumlah Bahan + Pekerja 20,431.50
Dibulatkan 20,430.00
A.10.27 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1"
BAHAN :
P PK05 Pipa PVC AW 1" 1.0000 m' 6,250.00 6,250.00
Perlengkapan 0.3500 hrg pipa 6,250.00 2,187.50
Jumlah Bahan 8,437.50
UPAH :
Pekerja 0.0360 Oh 110,000.00 3,960.00
A001 Tukang Batu 0.0600 Oh 135,000.00 8,100.00
Kepala Tukang 0.0060 Oh 160,000.00 960.00
Mandor 0.0018 Oh 180,000.00 324.00
Jumlah Pekerja 13,344.00
Jumlah Bahan + Pekerja 21,781.50
Dibulatkan 21,780.00
A.10.28 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1,5"
BAHAN :
Pipa PVC AW 1,5" 1.0000 m' 10,500.00 10,500.00
Perlengkapan 0.3500 hrg pipa 10,500.00 3,675.00
Jumlah Bahan 14,175.00
P PK05 UPAH :
Pekerja 0.0360 Oh 110,000.00 3,960.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Tukang Batu 0.0600 Oh 135,000.00 8,100.00
Kepala Tukang 0.0060 Oh 160,000.00 960.00
Mandor 0.0018 Oh 180,000.00 324.00
A001 Jumlah Pekerja 13,344.00
Jumlah Bahan + Pekerja 27,519.00
Dibulatkan 27,510.00
A.10.29 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2"
BAHAN :
Pipa PVC AW 2" 1.0000 m' 13,500.00 13,500.00
Perlengkapan 0.3500 hrg pipa 13,500.00 4,725.00
Jumlah Bahan 18,225.00
P PK05 UPAH :
Pekerja 0.0540 Oh 110,000.00 5,940.00
Tukang Batu 0.0900 Oh 135,000.00 12,150.00
Kepala Tukang 0.0090 Oh 160,000.00 1,440.00
Mandor 0.0027 Oh 180,000.00 486.00
A001 Jumlah Pekerja 20,016.00
Jumlah Bahan + Pekerja 38,241.00
Dibulatkan 38,240.00
A.10.30 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2,5"
BAHAN :
Pipa PVC AW 2,5" 1.0000 m' 20,500.00 20,500.00
Perlengkapan 0.3500 hrg pipa 20,500.00 7,175.00
Jumlah Bahan 27,675.00
UPAH :
Pekerja 0.0360 Oh 110,000.00 3,960.00
Tukang Batu 0.0600 Oh 135,000.00 8,100.00
P PK05 Kepala Tukang 0.0060 Oh 160,000.00 960.00
Mandor 0.0018 Oh 180,000.00 324.00
Jumlah Pekerja 13,344.00
Jumlah Bahan + Pekerja 41,019.00
Dibulatkan 41,010.00
A.10.31 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3"
BAHAN :
Pipa PVC AW 3" 1.0000 m' 34,750.00 34,750.00
Perlengkapan 0.3500 hrg pipa 34,750.00 12,162.50
Jumlah Bahan 46,912.50
UPAH :
Pekerja 0.0810 Oh 110,000.00 8,910.00
Tukang Batu 0.1350 Oh 135,000.00 18,225.00
P PK05 Kepala Tukang 0.0135 Oh 160,000.00 2,160.00
Mandor 0.0041 Oh 180,000.00 738.00
Jumlah Pekerja 30,033.00
Jumlah Bahan + Pekerja 76,945.50
Dibulatkan 76,940.00
A.10.32 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 4"
BAHAN :
Pipa PVC AW 4" 1.0000 m' 48,000.00 48,000.00
Perlengkapan 0.3500 hrg pipa 48,000.00 16,800.00
Jumlah Bahan 64,800.00
UPAH :
Pekerja 0.0810 Oh 110,000.00 8,910.00
Tukang Batu 0.1350 Oh 135,000.00 18,225.00
Kepala Tukang 0.0135 Oh 160,000.00 2,160.00
Mandor 0.0041 Oh 180,000.00 738.00
P PK05 Jumlah Pekerja 30,033.00
Jumlah Bahan + Pekerja 94,833.00
Dibulatkan 94,830.00
A001 A.10.33 MEMASANG 1 BH BAK CUCI PIRING STAILES STEEL
BAHAN :
Bak Cuci Stainless Steel 1.0000 bh 250,000.00 250,000.00
Water Drain + asesories 1.0000 Set 80,000.00 80,000.00
Jumlah Bahan 330,000.00
UPAH :
Pekerja 0.0300 Oh 110,000.00 3,300.00
Tukang Batu 0.3000 Oh 135,000.00 40,500.00
Kepala Tukang 0.0300 Oh 160,000.00 4,800.00
Mandor 0.0015 Oh 180,000.00 270.00
Jumlah Pekerja 48,870.00
Jumlah Bahan + Pekerja 378,870.00
Dibulatkan 378,870.00
A.10.35 MEMASANG 1 BH KRAN DIAMETER 0,75' ATAU 0,5"
BAHAN :
Kran Air 1.0000 bh 25,000.00 25,000.00
A001 Seal tape 0.0250 bh 15,000.00 375.00
Jumlah Bahan 25,375.00
UPAH :
Pekerja 0.0100 Oh 110,000.00 1,100.00
Tukang Batu - Oh 135,000.00 -
Kepala Tukang 0.0010 Oh 160,000.00 160.00
Mandor 0.0005 Oh 180,000.00 90.00
Jumlah Pekerja 1,350.00
Jumlah Bahan + Pekerja 26,725.00
Dibulatkan 26,720.00
A.10.36 MEMASANG 1 BH FLOOR DRAIN
P PK05 BAHAN :
Floor Drain 1.0000 bh 30,000.00 30,000.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Pekerja 1,350.00
Jumlah Bahan + Pekerja 31,350.00
Dibulatkan 31,350.00
A.10.37 1 UNIT SEPTICTANK 4,8 X 2,1 X 2,4 M + REMBESANNYA
Galian tanah 17.1360 m³ 67,220.00 1,151,881.92
Pasir Urug 0.5600 m³ 135,000.00 75,600.00
Lantai kerja 3.7500 m³ 794,930.00 2,980,987.50
Pas. bata 1 PC : 2 PS + Plesteran 60.0000 m² 150,780.00 9,046,800.00
Plasteran Dinding 60.0000 m² 86,120.00 5,167,200.00
P PK05 Plat beton penutup 0.5000 m³ 5,152,970.00 2,576,485.00
Pipa PVC AW 4" 9.0000 m' 48,000.00 432,000.00
Pipa GIP 2" 2.0000 m1 165,000.00 330,000.00
Galian tanah untuk rembesan 5.6250 m³ 67,220.00 378,112.50
Pas. injuk 20.0000 m² 4,000.00 80,000.00
A001 Urugan kerikil 3,5 cm 2.5000 m³ 220,000.00 550,000.00
Pipa PVC AW 4" 10.0000 m' 48,000.00 480,000.00
Urugan kembali perataan tanah 1.8750 m³ 174,540.00 327,262.50
Jumlah Bahan 23,576,329.42
UPAH :
Pekerja Oh
Tukang Batu Oh
Kepala Tukang Oh
Mandor Oh
Jumlah -
Jumlah 23,576,329.42
Dibulatkan 23,576,320.00
A.11.01 1 M2 PASANG RANGKA ATAP BAJA RINGAN
BAHAN :
A001 Baja Ringan 1.1000 m2 160,000.00 176,000.00
Jumlah Bahan 176,000.00
UPAH :
Pekerja 0.0600 Oh 110,000.00 6,600.00
Tukang Besi 0.0060 Oh 135,000.00 810.00
Kepala Tukang 0.0060 Oh 160,000.00 960.00
Mandor 0.0003 Oh 180,000.00 54.00
Jumlah Pekerja 8,424.00
Jumlah Bahan + Pekerja 184,424.00
Dibulatkan 184,420.00
A.11.09 1 M2 PASANG PINTU ALUMINIUM
BAHAN :
Pintu Alluminium 1.0000 m2 75,000.00 75,000.00
Jumlah Bahan 75,000.00
P PK05 UPAH :
Pekerja 1.0500 Oh 110,000.00 115,500.00
Tukang Besi 1.0500 Oh 135,000.00 141,750.00
Kepala Tukang 0.1050 Oh 160,000.00 16,800.00
Mandor 0.0052 Oh 180,000.00 936.00
A001 Jumlah Pekerja 274,986.00
Jumlah Bahan + Pekerja 349,986.00
Dibulatkan 349,980.00
A.11.12 1 M2 PASANG TERALIS BESI
BAHAN :
Besi Plat 2x3 1.0000 m2 1.00 1.00
Jumlah Bahan 1.00
UPAH :
Pekerja 1.2000 Oh 110,000.00 132,000.00
Tukang Kayu 1.2000 Oh 135,000.00 162,000.00
P PK05 Kepala Tukang 0.0120 Oh 160,000.00 1,920.00
Mandor 0.0006 Oh 180,000.00 108.00
Jumlah Pekerja 296,028.00
Jumlah Bahan + Pekerja 296,029.00
Dibulatkan 296,020.00
A.11.18 1 M2 PASANG TALANG DATAR, SENG BJLS 30
LL64 BAHAN :
BT64 Seng Plat 3 x 6 bjls 28 0.5000 lbr 50,000.00 25,000.00
BT18 Paku Biasa Tripleks 0.0150 kg 25,000.00 375.00
Kayu Kelas II Papan 0.0096 m3 5,000,000.00 48,000.00
LL65 Meni Besi/Flincote 0.2500 kg 14,000.00 3,500.00
LL66 Jumlah Bahan 76,875.00
BT67 UPAH :
Pekerja 0.1500 Oh 110,000.00 16,500.00
Tukang Kayu 0.4000 Oh 135,000.00 54,000.00
Kepala Tukang 0.0250 Oh 160,000.00 4,000.00
Mandor 0.0013 Oh 180,000.00 225.00
A080 Jumlah Pekerja 74,725.00
Jumlah Bahan + Pekerja 151,600.00
Dibulatkan 151,600.00
A.11.19 1 M2 PASANG TALANG MIRING, SENG BJLS 28
BAHAN :
BT64 Seng Plat 3 x 6 bjls 28 0.5000 lbr 50,000.00 25,000.00
BT18 Paku Biasa Tripleks 0.0150 kg 25,000.00 375.00
Kayu Kelas II Papan 0.0190 m3 5,000,000.00 95,000.00
Meni Besi/Flincote 0.3000 kg 14,000.00 4,200.00
Jumlah Bahan 124,575.00
BT67 UPAH :
Pekerja 0.0400 Oh 110,000.00 4,400.00
Tukang Kayu 0.4000 Oh 135,000.00 54,000.00
Kepala Tukang 0.0250 Oh 160,000.00 4,000.00
Mandor 0.0013 Oh 180,000.00 225.00
A081 Jumlah Pekerja 62,625.00
Jumlah Bahan + Pekerja 187,200.00
Dibulatkan 187,200.00
A.11.20 1 M2 PASANG TALANG 1/2 LINGKARAN D-10 CM, SENG BJLS 28
BAHAN :
Pekerjaan 1 2 3 4 5 6=(3x5)
BT64 Seng Plat 3 x 6 bjls 28 0.3000 lbr 50,000.00 15,000.00
BT18 Paku Biasa Tripleks 0.1000 kg 25,000.00 2,500.00
Kayu Kelas II Papan 0.0190 m3 5,000,000.00 95,000.00
Besi Strip 0.5000 kg 15,000.00 7,500.00
Jumlah Bahan 120,000.00
BT67 UPAH :
Pekerja 0.1500 Oh 110,000.00 16,500.00
Tukang Kayu 0.2500 Oh 135,000.00 33,750.00
Kepala Tukang 0.0250 Oh 160,000.00 4,000.00
Mandor 0.0013 Oh 180,000.00 225.00
A082 Jumlah Pekerja 54,475.00
Jumlah Bahan + Pekerja 174,475.00
Dibulatkan 174,470.00
A.11.22 1 M2 PEK. RESIDU/TEER RANGKA ATAP/KUDA-KUDA/GORDING
BAHAN :
Teer/residu 0.0300 ltr 20,000.00 600.00
Jumlah Bahan 600.00
UPAH :
A001 Pekerja 0.0080 Oh 110,000.00 880.00
Tukang Kayu 0.0060 Oh 135,000.00 810.00
LL99 Kepala Tukang 0.0120 Oh 160,000.00 1,920.00
BN02 Mandor 0.0060 Oh 180,000.00 1,080.00
Jumlah Pekerja 4,690.00
Jumlah Bahan + Pekerja 5,290.00
LLL01 Dibulatkan 5,290.00
P PK05 A.12.02 1 BUAH PASANG KUNCI TANAM BIASA
BAHAN :
Kunci Tanam biasa 1.0000 bh 75,000.00 75,000.00
Jumlah Bahan 75,000.00
UPAH :
A001 Pekerja 0.0100 Oh 110,000.00 1,100.00
Tukang Kayu 0.5000 Oh 135,000.00 67,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
Mandor 0.0050 Oh 180,000.00 900.00
Jumlah Pekerja 71,100.00
Jumlah Bahan + Pekerja 146,100.00
Dibulatkan 146,100.00
P PK05 A.12.03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI
BAHAN :
Kunci Tanam Kamar Mandi 1.0000 bh 50,000.00 50,000.00
Jumlah Bahan 50,000.00
UPAH :
A001 Pekerja 0.0050 Oh 110,000.00 550.00
Tukang Kayu 0.5000 Oh 135,000.00 67,500.00
Kepala Tukang 0.0050 Oh 160,000.00 800.00
Mandor 0.0025 Oh 180,000.00 450.00
Jumlah Pekerja 69,300.00
Jumlah Bahan + Pekerja 119,300.00
Dibulatkan 119,300.00
P PK05 A.12.04 1 BUAH PASANG KUNCI BULAT
BAHAN :
Kunci Bulat 1.0000 bh 20,000.00 20,000.00
Jumlah Bahan 20,000.00
UPAH :
A001 Pekerja 0.0050 Oh 110,000.00 550.00
Tukang Kayu 0.5000 Oh 135,000.00 67,500.00
Kepala Tukang 0.0050 Oh 160,000.00 800.00
Mandor 0.0003 Oh 180,000.00 45.00
Jumlah Pekerja 68,895.00
Jumlah Bahan + Pekerja 88,895.00
Dibulatkan 88,890.00
P PK05 A.12.05 1 BUAH PASANG ENGSEL PINTU
BAHAN :
Engsel Pintu 1.0000 bh 30,000.00 30,000.00
Jumlah Bahan 30,000.00
UPAH :
A001 Pekerja 0.0150 Oh 110,000.00 1,650.00
Tukang Kayu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
Mandor 0.0008 Oh 180,000.00 135.00
Jumlah Pekerja 17,685.00
Jumlah Bahan + Pekerja 47,685.00
Dibulatkan 47,680.00
P PK05 A.12.06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU
BAHAN :
Engsel Jendela 1.0000 bh 20,000.00 20,000.00
Jumlah Bahan 20,000.00
UPAH :
A001 Pekerja 0.0100 Oh 110,000.00 1,100.00
Tukang Kayu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00 1,600.00
Mandor 0.0005 Oh 180,000.00 90.00
Jumlah Pekerja 16,290.00
Jumlah Bahan + Pekerja 36,290.00
Dibulatkan 36,290.00
P PK05 A.12.09 1 BUAH PASANG KAIT ANGIN
BAHAN :
Kait Angin 1.0000 ps 25,000.00 25,000.00
Jumlah Bahan 25,000.00
UPAH :
A001 Pekerja 0.0150 Oh 110,000.00 1,650.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
Mandor 0.0008 Oh 180,000.00 135.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Pekerja 24,435.00
Jumlah Bahan + Pekerja 49,435.00
Dibulatkan 49,430.00
P PK05 A.12.10 1 BUAH PASANG SLOOT TANAM
BAHAN :
Sloot Tanam 1.0000 bh 20,000.00 20,000.00
Jumlah Bahan 20,000.00
UPAH :
A001 Pekerja 0.0200 Oh 110,000.00 2,200.00
Tukang Kayu 0.2000 Oh 135,000.00 27,000.00
Kepala Tukang 0.0500 Oh 160,000.00 8,000.00
Mandor 0.0025 Oh 180,000.00 450.00
Jumlah Pekerja 37,650.00
Jumlah Bahan + Pekerja 57,650.00
Dibulatkan 57,650.00
P PK05 A.12.11 1 BUAH PASANG GRENDEL JENDELA
BAHAN :
Grendel Jendela/Spring Knob 1.0000 bh 12,000.00 12,000.00
Jumlah Bahan 12,000.00
UPAH :
A001 Pekerja 0.0200 Oh 110,000.00 2,200.00
Tukang Kayu 0.2000 Oh 135,000.00 27,000.00
Kepala Tukang 0.0200 Oh 160,000.00 3,200.00
Mandor 0.0010 Oh 180,000.00 180.00
Jumlah Pekerja 32,580.00
Jumlah Bahan + Pekerja 44,580.00
Dibulatkan 44,580.00
P PK05 A.12.12 1 BUAH PASANG PEGANGAN PINTU + KUNCI PINTU 2 X PUTAR
BAHAN :
Kunci Tanam 2 x Putar 1.0000 bh 150,000.00 150,000.00
Pegangan/Handle Pintu 1.0000 bh 50,000.00 50,000.00
Jumlah Bahan 50,000.00
UPAH :
A001 Pekerja 0.0500 Oh 110,000.00 5,500.00
Tukang Kayu 0.5000 Oh 135,000.00 67,500.00
Kepala Tukang 0.0500 Oh 160,000.00 8,000.00
Mandor 0.0025 Oh 180,000.00 450.00
Jumlah Pekerja 81,450.00
Jumlah Bahan + Pekerja 131,450.00
Dibulatkan 131,450.00
A.12.14 1 BUAH PASANG KUNCI PINTU 2 X PUTAR ( lever handle )
BAHAN :
P PK05 Kunci Pintu 2 x Putar ( lever handle ) 1.0000 bh 150,000.00 150,000.00
Jumlah Bahan 150,000.00
UPAH :
Pekerja 0.0100 Oh 110,000.00 1,100.00
Tukang Kayu 0.5000 Oh 135,000.00 67,500.00
A001 Kepala Tukang 0.0600 Oh 160,000.00 9,600.00
Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 78,740.00
Jumlah Bahan + Pekerja 228,740.00
Dibulatkan 228,740.00
A.12.17 1 M2 PASANG KACA, TEBAL 5 MM
BAHAN :
Kaca Polos 5 mm 1.1000 m2 185,000.00 203,500.00
Jumlah Bahan 203,500.00
UPAH :
Pekerja 0.0150 Oh 110,000.00 1,650.00
Tukang Kayu 0.1500 Oh 135,000.00 20,250.00
Kepala Tukang 0.0150 Oh 160,000.00 2,400.00
P PK05 Mandor 0.0008 Oh 180,000.00 135.00
Jumlah Pekerja 24,435.00
Jumlah Bahan + Pekerja 227,935.00
A001 Dibulatkan 227,930.00
A.12.28 1 KG PEK. KONSTRUKSI BESI SIKU
BAHAN :
P PK05 Besi Siku 50.50.5 panjang 6 m 1.0000 kg 15,000.00 15,000.00
Jumlah Bahan 15,000.00
UPAH :
Pekerja 0.0600 Oh 110,000.00 6,600.00
A001 Tukang Besi 0.0040 org 135,000.00 540.00
Kepala tukang besi profil 0.0010 org 160,000.00 160.00
Mandor 0.0002 org 180,000.00 36.00
Peralatan ( Alat las, dll) 0.1250 lot 22,336.00 2,792.00
Jumlah Pekerja 10,128.00
Jumlah Bahan + Pekerja 25,128.00
Dibulatkan 25,120.00
A.12.34 1 M1 PEK. PAGAR BELAKANG / SAMPING KAWAT DURI
Galian Tanah 0.4500 m³ 51,200.00 23,040.00
P PK05 Urugan Pasir 10 cm' 0.0080 m³ 196,800.00 1,574.40
Pekerjaan 1 2 3 4 5 6=(3x5)
BRC lengkap dengan tiang + klem pengikat. 0.4340 lbr 350,000.00 151,900.00
Jumlah 200,190.63
Dibulatkan 200,190.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 121,590.00
Jumlah Bahan + Pekerja 190,734.00
Dibulatkan 190,730.00
A.13.58 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, PUTIH
BAHAN :
Keramik Porselen 11 x 11 cm 83.0000 bh 542.17 45,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
Jumlah Bahan 59,344.00
UPAH :
P PK05 Pekerja 0.6200 Oh 110,000.00 68,200.00
Tukang Batu 0.5000 Oh 135,000.00 67,500.00
Kepala Tukang 0.0500 Oh 160,000.00 8,000.00
Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 144,240.00
A001 Jumlah Bahan + Pekerja 203,584.00
Dibulatkan 203,580.00
A.13.59 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, WARNA
BAHAN :
Keramik Porselen 11 x 11 cm, Warna 83.0000 bh 602.41 50,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
Jumlah Bahan 64,344.00
UPAH :
P PK05 Pekerja 0.6200 Oh 110,000.00 68,200.00
Tukang Batu 0.5000 Oh 135,000.00 67,500.00
Kepala Tukang 0.0500 Oh 160,000.00 8,000.00
Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 144,240.00
A001 Jumlah Bahan + Pekerja 208,584.00
Dibulatkan 208,580.00
A.13.62 1 M2 PASANG DINDING PORSELEN 10 X 20 CM, WARNA
BAHAN :
Keramik Porselen 10 x 20 cm, Warna 50.0000 bh 1,200.00 60,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
P PK05 Jumlah Bahan 74,344.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.4500 Oh 135,000.00 60,750.00
Kepala Tukang 0.0450 Oh 160,000.00 7,200.00
A001 Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 134,490.00
Jumlah Bahan + Pekerja 208,834.00
Dibulatkan 208,830.00
A.13.63 1 M2 PASANG DINDING PORSELEN 20 X 20 CM, WARNA
BAHAN :
Keramik Porselen 20 x 20 cm, Warna 25.0000 bh 2,400.00 60,000.00
Semen Abu-abu 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
P PK05 Jumlah Bahan 74,344.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.4500 Oh 135,000.00 60,750.00
Kepala Tukang 0.0450 Oh 160,000.00 7,200.00
A001 Mandor 0.0300 Oh 180,000.00 5,400.00
Jumlah Pekerja 139,350.00
Jumlah Bahan + Pekerja 213,694.00
Dibulatkan 213,690.00
A.13.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM,
BAHAN :
Keramik 10 x 20 cm 50.0000 bh 1,100.00 55,000.00
Semen Abu-abu 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
P PK05 Jumlah Bahan 69,344.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.4500 Oh 135,000.00 60,750.00
Kepala Tukang 0.0450 Oh 160,000.00 7,200.00
A001 Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 134,490.00
Jumlah Bahan + Pekerja 203,834.00
Dibulatkan 203,830.00
A.13.68 1 M2 PASANG DINDING KERAMIK 20 X 20 CM,
BAHAN :
Keramik 20 x 20 cm 25.0000 bh 2,400.00 60,000.00
Semen Abu-abu 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
P PK05 Jumlah Bahan 74,344.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0450 Oh 160,000.00 7,200.00
A001 Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 87,240.00
Jumlah Bahan + Pekerja 161,584.00
Dibulatkan 161,580.00
Pekerjaan 1 2 3 4 5 6=(3x5)
A.13.69 1 M2 PASANG DINDING KERAMIK 10 X 20 CM,
BAHAN :
Keramik 10 x 20 cm 50.0000 bh 55,000.00 2,750,000.00
Semen Abu-abu 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
P PK05 Jumlah Bahan 2,764,344.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.1250 Oh 135,000.00 16,875.00
Kepala Tukang 0.0125 Oh 160,000.00 2,000.00
A001 Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 85,415.00
Jumlah Bahan + Pekerja 2,849,759.00
Dibulatkan 2,849,750.00
A.13.74 1 M2 PASANG DINDING BATU TEMPEL
P PK05 BAHAN :
Batu Tempel 1.0500 m2 70,000.00 73,500.00
Semen Abu-abu 11.7500 kg 1,160.00 13,630.00
Pasir Pasang 0.0350 m3 200,000.00 7,000.00
Jumlah Bahan 94,130.00
A001 UPAH :
Pekerja 0.6200 Oh 110,000.00 68,200.00
Tukang Batu 0.3500 Oh 135,000.00 47,250.00
Kepala Tukang 0.0350 Oh 160,000.00 5,600.00
Mandor 0.0030 Oh 180,000.00 540.00
Jumlah Pekerja 121,590.00
Jumlah Bahan + Pekerja 215,720.00
Dibulatkan 215,720.00
A001 A.13.75 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM DN PUTIH POLOS
BAHAN :
Lantai Keramik 30 x 30 cm 11.0000 bh 4,545.45 50,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0420 m3 200,000.00 8,400.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
Jumlah Bahan 69,144.00
UPAH :
Pekerja 0.6200 Oh 110,000.00 68,200.00
Tukang Batu 0.3500 Oh 135,000.00 47,250.00
Kepala Tukang 0.0350 Oh 160,000.00 5,600.00
Mandor 0.0030 Oh 180,000.00 540.00
P PK05 Jumlah Pekerja 121,590.00
Jumlah Bahan + Pekerja 190,734.00
Dibulatkan 190,730.00
A001 A.13.76 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM WARNA / CORAK / ANTI SLIP
BAHAN :
Lantai Keramik 30 x 30 cm Warna/Corak/Anti Slip 11.0000 bh 4,545.45 50,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0420 m3 200,000.00 8,400.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
Jumlah Bahan 69,144.00
UPAH :
Pekerja 0.6200 Oh 110,000.00 68,200.00
Tukang Batu 0.3500 Oh 135,000.00 47,250.00
Kepala Tukang 0.0350 Oh 160,000.00 5,600.00
Mandor 0.0030 Oh 180,000.00 540.00
P PK05 Jumlah Pekerja 121,590.00
Jumlah Bahan + Pekerja 190,734.00
Dibulatkan 190,730.00
A001 A.13.77 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM
BAHAN :
Keramik 40 x 40 cm 6.0000 bh 9,166.67 55,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0420 m3 200,000.00 8,400.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
Jumlah Bahan 74,144.00
UPAH :
Pekerja 0.6200 Oh 110,000.00 68,200.00
Tukang Batu 0.3500 Oh 135,000.00 47,250.00
Kepala Tukang 0.0350 Oh 160,000.00 5,600.00
Mandor 0.0030 Oh 180,000.00 540.00
P PK05 Jumlah Pekerja 121,590.00
Jumlah Bahan + Pekerja 195,734.00
Dibulatkan 195,730.00
A001 A.13.78 1 M2 PASANG DINDING KERAMIK 20 X 25 CM,
BAHAN :
Keramik 20 x 25 cm 20.0000 bh 2,750.00 55,000.00
Semen PC (50 kg) 8.4000 kg 1,160.00 9,744.00
Pasir Pasang 0.0180 m3 200,000.00 3,600.00
Semen Warna 0.5000 kg 2,000.00 1,000.00
Jumlah Bahan 69,344.00
UPAH :
Pekerja 0.6000 Oh 110,000.00 66,000.00
Tukang Batu 0.4500 Oh 135,000.00 60,750.00
Kepala Tukang 0.0450 Oh 160,000.00 7,200.00
Mandor 0.0030 Oh 180,000.00 540.00
P PK05 Jumlah Pekerja 134,490.00
Jumlah Bahan + Pekerja 203,834.00
Dibulatkan 203,830.00
P PK05 A.13.83 1 M2 PASANGAN PAVING BLOCK WARNA (6 CM)
BAHAN :
Paving Block Warna 6 cm 1.0100 m2 50,000.00 50,500.00
Pasir Beton 0.1000 m³ 225,000.00 22,500.00
Jumlah Bahan 73,000.00
Pekerjaan 1 2 3 4 5 6=(3x5)
A001 UPAH :
Pekerja 0.2500 org 110,000.00 27,500.00
Tukang Batu 0.5000 org 135,000.00 67,500.00
Kepala Tukang Batu 0.0250 org 160,000.00 4,000.00
Mandor 0.0030 org 180,000.00 540.00
Jumlah Pekerja 99,540.00
Jumlah Bahan + Pekerja 172,540.00
Jumlah 172,540.00
Dibulatkan 172,540.00
A.13.84 1 M2 PASANGAN PAVING BLOCK WARNA (8 CM)
BAHAN :
P PK05 Paving Block Warna 8 cm 1.0100 m2 55,000.00 55,550.00
Pasir Beton 0.1000 m³ 225,000.00 22,500.00
Jumlah Bahan 78,050.00
UPAH :
Pekerja 0.2500 org 110,000.00 27,500.00
A001 Tukang Batu 0.5000 org 135,000.00 67,500.00
Kepala Tukang Batu 0.0250 org 160,000.00 4,000.00
Mandor 0.0030 org 180,000.00 540.00
Jumlah Pekerja 99,540.00
Jumlah Bahan + Pekerja 177,590.00
Jumlah 177,590.00
Dibulatkan 177,590.00
A.13.86 1 M2 PASANGAN PAVING BLOCK NATURAL (6 CM)
BAHAN :
Paving Block Natural 6 cm 1.0100 m² 48,000.00 48,480.00
Pasir Beton 0.1000 m³ 225,000.00 22,500.00
Jumlah Bahan 70,980.00
UPAH :
Pekerja 0.2500 org 110,000.00 27,500.00
P PK05 Tukang Batu 0.5000 org 135,000.00 67,500.00
Kepala Tukang Batu 0.0250 org 160,000.00 4,000.00
Mandor 0.0030 org 180,000.00 540.00
Jumlah Pekerja 99,540.00
Jumlah Bahan + Pekerja 170,520.00
Jumlah 170,520.00
Dibulatkan 170,520.00
A.13.87 1 M2 PASANGAN PAVING BLOCK NATURAL (8 CM)
BAHAN :
Paving Block Natural 8 cm 1.0100 m² 51,000.00 51,510.00
Pasir Beton 0.1000 m³ 225,000.00 22,500.00
Jumlah Bahan 74,010.00
UPAH :
Pekerja 0.2500 org 110,000.00 27,500.00
Tukang Batu 0.5000 org 135,000.00 67,500.00
P PK05 Kepala Tukang Batu 0.0250 org 160,000.00 4,000.00
Mandor 0.0030 org 180,000.00 540.00
Jumlah Pekerja 99,540.00
Jumlah Bahan + Pekerja 173,550.00
A001 Jumlah 173,550.00
Dibulatkan 173,550.00
A.14.12 1 M2 MENI KAYU
BAHAN :
Cat Meni Kayu 0.3500 Kg 12,000.00 4,200.00
Jumlah Bahan 4,200.00
P PK05 UPAH :
Pekerja 0.1000 Oh 110,000.00 11,000.00
Tukang Cat - Oh 135,000.00 -
Kepala Tukang - Oh 160,000.00 -
Mandor 0.0060 Oh 180,000.00 1,080.00
A001 Jumlah Pekerja 12,080.00
Jumlah Bahan + Pekerja 16,280.00
Dibulatkan 16,280.00
A.14.13 1 M2 MENI BESI
BAHAN :
Cat Meni BESI 0.3500 Kg 14,000.00 4,900.00
Jumlah Bahan 4,900.00
P PK05 UPAH :
Pekerja 0.1000 Oh 110,000.00 11,000.00
Tukang Cat - Oh 135,000.00 -
Kepala Tukang - Oh 160,000.00 -
Mandor 0.0060 Oh 180,000.00 1,080.00
A001 Jumlah Pekerja 12,080.00
Jumlah Bahan + Pekerja 16,980.00
Dibulatkan 16,980.00
A.14.14 1 M2 PLAMUR TEMBOK
BAHAN :
Plamir Tembok 0.1000 ltr 20,000.00 2,000.00
Jumlah Bahan 2,000.00
UPAH :
P PK05 Pekerja 0.0200 Oh 110,000.00 2,200.00
Tukang Cat 0.0630 Oh 135,000.00 8,505.00
Kepala Tukang 0.0063 Oh 160,000.00 1,008.00
Mandor 0.0025 Oh 180,000.00 450.00
Jumlah Pekerja 12,163.00
A001 Jumlah Bahan + Pekerja 14,163.00
Dibulatkan 14,160.00
A.14.25 1 M2 PENGECATAN DINDING SEKELAS VINILEX (3x)
BAHAN :
P PK05 Cat Tembok 0.1750 kg 35,000.00 6,125.00
Plamir Tembok 0.1600 kg 20,000.00 3,200.00
Kuas Roll 0.0100 bh 28,000.00 280.00
Ampelas 0.5000 lbr 6,000.00 3,000.00
Jumlah Bahan 12,605.00
Pekerjaan 1 2 3 4 5 6=(3x5)
A001 UPAH :
Pekerja 0.1040 org 110,000.00 11,440.00
Tukang Cat 0.0182 org 135,000.00 2,457.00
Kepala Tukang cat 0.0090 org 160,000.00 1,440.00
Mandor 0.0045 org 180,000.00 810.00
Jumlah Pekerja 16,147.00
Jumlah Bahan + Pekerja 28,752.00
Jumlah 28,752.00
Dibulatkan 28,750.00
P PK05 A.14.26 1 M2 PENGECATAN PLAFOND SEKELAS VINILEX (3x)
BAHAN :
Cat Tembok 0.2000 kg 35,000.00 7,000.00
Plamir Tembok 0.1600 kg 20,000.00 3,200.00
Kuas Roll 0.0100 bh 28,000.00 280.00
A001 Ampelas 0.5000 lbr 6,000.00 3,000.00
Jumlah Bahan 13,480.00
UPAH :
Pekerja 0.2000 org 110,000.00 22,000.00
Tukang Cat 0.0280 org 135,000.00 3,780.00
Kepala Tukang cat 0.0150 org 160,000.00 2,400.00
Mandor 0.0090 org 180,000.00 1,620.00
Jumlah Pekerja 29,800.00
P PK05 Jumlah Bahan + Pekerja 43,280.00
Jumlah 43,280.00
Dibulatkan 43,280.00
A.14.30 1 M2 PENGECATAN BIDANG KAYU (3X) BERIKUT MENI
BAHAN :
Meni kayu 0.1670 kg 12,000.00 2,004.00
Plamir kayu 0.0830 kg 30,000.00 2,490.00
P PK05 Cat Kayu 0.2000 kg 40,000.00 8,000.00
Ampelas 0.4000 lbr 6,000.00 2,400.00
Minyak cat / Thinner 0.1500 ltr 20,000.00 3,000.00
Kwas 0.0500 bh 7,000.00 350.00
Jumlah Bahan 18,244.00
A001 UPAH :
Pekerja 0.2000 org 110,000.00 22,000.00
Tukang Cat 0.0600 org 135,000.00 8,100.00
Kepala Tukang cat 0.0300 org 160,000.00 4,800.00
Mandor 0.0100 org 180,000.00 1,800.00
Jumlah Pekerja 36,700.00
Jumlah Bahan + Pekerja 54,944.00
Jumlah 54,944.00
Dibulatkan 54,940.00
A.14.30'' 1 M2 PENGECATAN BIDANG DINDING ( PLINT )
BAHAN :
Cat Kayu / Besi / Cat minyak 0.2000 kg 40000 8,000.00
Ampelas 0.4000 lbr 6000 2,400.00
Minyak Thinner 0.1500 ltr 20000 3,000.00
Kwas 0.0500 bh 7000 350.00
Jumlah Bahan 13,750.00
UPAH :
Pekerja 0.2000 org 110000 22,000.00
Tukang Cat 0.0600 org 135000 8,100.00
Kepala Tukang cat 0.0300 org 160000 4,800.00
Mandor 0.0100 org 180000 1,800.00
Jumlah Pekerja 36,700.00
Jumlah Bahan + Pekerja 50,450.00
Jumlah 50,450.00
Dibulatkan 50,450.00
A.14.31 1 M2 PENGECATAN BESI (3X)
BAHAN :
P PK05 Meni Besi/Flincote 0.1670 kg 14,000.00 2,338.00
Cat Besi 0.2000 kg 40,000.00 8,000.00
Ampelas 0.4000 lbr 6,000.00 2,400.00
Minyak cat / Thinner 0.1500 ltr 20,000.00 3,000.00
Kwas 0.0500 bh 7,000.00 350.00
A001 Jumlah Bahan 16,088.00
UPAH :
Pekerja 0.2000 org 110,000.00 22,000.00
Tukang Cat 0.0600 org 135,000.00 8,100.00
Kepala Tukang cat 0.0300 org 160,000.00 4,800.00
Mandor 0.0100 org 180,000.00 1,800.00
Jumlah Pekerja 36,700.00
Jumlah Bahan + Pekerja 52,788.00
Jumlah 52,788.00
P PK05 Dibulatkan 52,780.00
B6 MENANAM 1 BATANG TANAMAN BERIKUT PELINDUNGNYA
Tanaman Keras 1.0000 btg 100,000.00 100,000.00
Bambu 1.0000 btg 15,000.00 15,000.00
Pekerja 0.4000 org 110,000.00 44,000.00
Mandor 0.0050 org 180,000.00 900.00
Jumlah 44,900.00
Jumlah 44,900.00
Dibulatkan 44,900.00
E 13 1 M1 TIANG DIPANCANGKAN KE DALAM TANAH LUNAK
Tukang Kayu 0.0400 org 135,000.00 5,400.00
Kepala Tukang 0.0040 org 160,000.00 640.00
Pekerja 1.8000 org 110,000.00 198,000.00
Mandor 0.0430 org 180,000.00 7,740.00
Untuk tanah biasa dihitung = 1, 25 x analis E. 13
Untuk tanah biasa dihitung = 1, 50x analis E. 13
Untuk tanah biasa dihitung = 2, 00 x analis E. 13
Jumlah -
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah -
Dibulatkan -
M.01 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 3M' ( ASUMSI LEBAR JEMBATAN 3M' & TANPA TIANG)
Kayu Bulat f 30 cm 7.5000 btg -
Paku Biasa 0.5600 kg 18,000.00 10,080.00
Pasak Besi f 12 mm 2.8000 kg 5,000.00 14,000.00
Tukang Kayu 1.2000 org 135,000.00 162,000.00
Kepala Tukang Kayu 0.1200 org 160,000.00 19,200.00
Pekerja 4.8000 org 110,000.00 528,000.00
Mandor 0.0120 org 180,000.00 2,160.00
Alat Bantu 0.0100 ls 6,080.00 60.80
Jumlah 2,220.80
Jumlah 2,220.80
Dibulatkan 2,220.00
M.02 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 6M' ( ASUMSI LEBAR JEMBATAN 3M' & DENGAN TIANG)
Kayu Bulat f 30 cm 18.0000 btg -
Paku Biasa 1.1200 kg 18,000.00 20,160.00
Pasak Besi f 12 mm 5.6000 kg 5,000.00 28,000.00
Tukang Kayu 1.4000 org 135,000.00 189,000.00
Kepala Tukang Kayu 0.1400 org 160,000.00 22,400.00
Pekerja 5.3000 org 110,000.00 583,000.00
Mandor 0.0140 org 180,000.00 2,520.00
Alat Bantu 0.0100 ls 6,080.00 60.80
Jumlah 2,580.80
Jumlah 2,580.80
Dibulatkan 2,580.00
M.03 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 9M' ( ASUMSI LEBAR JEMBATAN 3M' & DENGAN TIANG)
Kayu Bulat f 30 cm 28.5000 btg -
Paku Biasa 1.6800 kg 18,000.00 30,240.00
Pasak Besi f 12 mm 8.4000 kg 5,000.00 42,000.00
Tukang Kayu 1.7000 org 135,000.00 229,500.00
Kepala Tukang Kayu 7.0000 org 160,000.00 1,120,000.00
Pekerja 5.9000 org 110,000.00 649,000.00
Mandor 0.0170 org 180,000.00 3,060.00
Alat Bantu 0.0100 ls 6,080.00 60.80
Jumlah 3,120.80
Jumlah 3,120.80
Dibulatkan 3,120.00
M.04 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 12M' ( ASUMSI LEBAR JEMBATAN 3M' & DENGAN TIANG)
Kayu Bulat f 30 cm 39.0000 btg -
Paku Biasa 1.6800 kg 18,000.00 30,240.00
Pasak Besi f 12 mm 11.2000 kg 5,000.00 56,000.00
Tukang Kayu 2.1000 org 135,000.00 283,500.00
Kepala Tukang Kayu 0.2100 org 160,000.00 33,600.00
Pekerja 6.3000 org 110,000.00 693,000.00
Mandor 0.0210 org 180,000.00 3,780.00
Alat Bantu 0.0100 ls 6,080.00 60.80
Jumlah 3,840.80
Jumlah 3,840.80
Dibulatkan 3,840.00
A7.R. UPAH ANGKUTAN 1 ZAK SEMEN PC ( BID. PENGAIRAN )
Jumlah -
Jumlah -
Dibulatkan -
A6 ONGKOS ANGKUT 1 M3 TANAH ( BID. PENGAIRAN )
Sejauh 30 meter
Pekerja 0.3300 org 110,000.00 36,300.00
Mandor 0.0100 org 180,000.00
Lebih dari 30 meter
Jumlah -
Jumlah -
Dibulatkan -
A. R 1 M2 PEK. ANTI RAYAP
BAHAN :
Bahan Anti Rayap 0.0900 Ltr 60,000.00 5,400.00
Alat Semprot 0.0500 lsm - -
Jumlah Bahan 5,400.00
UPAH :
Pekerja 0.0100 Oh 110,000.00 1,100.00
Jumlah Pekerja 1,100.00
Jumlah Bahan + Pekerja 6,500.00
A001 Dibulatkan 6,500.00
A. B 1 M1 PEK. ANGKUR BESI Dia. 10 - 45 cm
BAHAN :
Besi Beton Polos Dia. 10 mm 0.2667 M1 1,083.33 288.89
Jumlah Bahan 288.89
UPAH :
Pekerja 0.0100 Oh 110,000.00 1,100.00
Jumlah Pekerja 1,100.00
Jumlah Bahan + Pekerja 1,388.89
Dibulatkan 1,380.00
A. B 1 M2 PEKERJAAN SALURAN AIR PASANGAN BT BATA ad 1 : 4
BAHAN :
Bata Merah Bakar Kelas I 70.0000 bh 1,000.00 70,000.00
Semen PC (50 kg) 18.9500 kg 1,160.00 21,982.00
Pasir Pasang 0.0430 m3 200,000.00
Jumlah Bahan 91,982.00
UPAH :
Pekerja 0.3200 Oh 110,000.00 35,200.00
Tukang Batu 0.1000 Oh 135,000.00 13,500.00
Kepala Tukang 0.0100 Oh 160,000.00
Mandor 0.0050 Oh 180,000.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Pekerja 48,700.00
Jumlah Bahan + Pekerja 140,682.00
Dibulatkan 140,680.00
L. 01. 01 1 M1 PAS. INSTALASI LISTRIK KABEL UTAMA 3x2,5 NYM
BAHAN :
Kabel 3x2,5mm NYM 1.0000 m' 20,000.00 20,000.00
Pipa konduit dia 5/8 inch 1.0000 m' 6,000.00 6,000.00
Klem kabel 3.0000 bh 100.00 300.00
Isolasi 0.0500 bh 15,000.00 750.00
Jumlah Bahan 27,050.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 48,650.00
Dibulatkan 48,650.00
L. 01. 02 1 TITIK INSTALASI TITIK LAMPU 2x2,5 NYM
BAHAN :
Kabel 2x2,5mm NYM 3.5000 m' 12,000.00 42,000.00
Pipa konduit dia 5/8 inch 4.0000 m' 6,000.00 24,000.00
Klem kabel 16.0000 bh 100.00 1,600.00
Isolasi 0.0500 bh 15,000.00 750.00
Tedoos 1.0000 bh -
Jumlah Bahan 68,350.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 89,950.00
Dibulatkan 89,950.00
L. 01. 03 1 Titik Pas. Instalasi Titik Saklar Tunggal 2x2,5 NYM
BAHAN :
Saklar Tunggal 1.0000 bh 19,000.00 19,000.00
Kabel 2x2,5mm NYM 2.5000 m' 12,000.00 30,000.00
Pipa konduit dia 5/8 inch 4.0000 m' 6,000.00 24,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Inbouwdoos 1.0000 bh 2,500.00 2,500.00
Jumlah Bahan 76,250.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 97,850.00
Dibulatkan 97,850.00
L. 01. 04 1 Titik Instalasi Titik Saklar Double 3x2,5 NYM
BAHAN :
Saklar Double 1.0000 bh 25,000.00 25,000.00
Kabel 3x2,5mm NYM 1.5000 m' 17,000.00 25,500.00
Pipa konduit dia 5/8 inch 4.0000 m' 6,000.00 24,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Inbouwdoos 1.0000 bh 2,500.00 2,500.00
Jumlah Bahan 77,750.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 99,350.00
Dibulatkan 99,350.00
L. 01. 05 1 Titik Pas. Instalasi Titik Stop Kontak 3x2,5 NYM
BAHAN :
Stop Kontak 1.0000 bh -
Kabel 3x2,5mm NYM 1.5000 m' 17,000.00 25,500.00
Pipa konduit dia 5/8 inch 4.0000 m' 6,000.00 24,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Inbouwdoos 1.0000 bh 2,500.00 2,500.00
Jumlah Bahan 52,750.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 74,350.00
Dibulatkan 74,350.00
L. 01. 06 1 Titik Pas. Instalasi Lampu Pijar
BAHAN :
Lampu Pijar 1.0000 bh 20,000.00 20,000.00
Kabel 1x2,5mm NYM 6.5000 m' 9,000.00 58,500.00
Pipa konduit dia 5/8 inch 6.0000 m' 6,000.00 36,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Klem kabel 3.0000 bh 100.00 300.00
Tedoos 1.0000 bh -
Jumlah Bahan 115,550.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 137,150.00
Dibulatkan 137,150.00
L. 01. 07 1 Titik Pas. Instalasi Lampu TL 2x40 Watt + fitting
BAHAN :
Lampu TL 2x40 Watt + fitting 1.0000 bh 200,000.00 200,000.00
Kabel 1x2,5mm NYM 4.5000 m' 9,000.00 40,500.00
Pipa konduit dia 5/8 inch 4.0000 m' 6,000.00 24,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Klem kabel 3.0000 bh 100.00 300.00
Tedoos 1.0000 bh -
Jumlah Bahan 265,550.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 287,150.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Dibulatkan 287,150.00
L. 01. 08 1 Titik Pas. MCB + Box Sekring
BAHAN :
MCB 4.0000 bh 20,000.00 80,000.00
Kabel 1x2,5mm NYM 4.5000 m' 9,000.00 40,500.00
Pipa konduit dia 5/8 inch 10.0000 m' 6,000.00 60,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Box Sekring 1.0000 bh 40,000.00 40,000.00
Jumlah Bahan 221,250.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 242,850.00
Dibulatkan 242,850.00
L. 01. 09 1 M1 Pas. Kabel Antar Bangunan 3x4mm NYY
BAHAN :
Kabel 3x4mm NYY 10.0000 m' 26,000.00 260,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Jumlah Bahan 260,750.00
UPAH :
Tukang 0.8000 Oh 135,000.00 108,000.00
Jumlah Pekerja 108,000.00
Jumlah Bahan + Pekerja 368,750.00
Dibulatkan 368,750.00
L. 01. 10 1 Bh pasang Panel Box Utama +MCB
BAHAN :
Panel Box Utama 1.0000 bh 450,000.00 450,000.00
MCB 6.0000 bh 20,000.00 120,000.00
Kabel 3x2,5mm NYM 5.0000 m' 20,000.00 100,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Jumlah Bahan 100,750.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Jumlah Pekerja 21,600.00
Jumlah Bahan + Pekerja 122,350.00
Dibulatkan 122,350.00
S.D.U 1 M' PAS. SALURAN DRAINASE UTAMA
BAHAN :
Batu kali 0.5000 m3 200,000.00 100,000.00
Plesteran 3.0000 m² 86,120.00 258,360.00
Kabel 3x2,5mm NYM 5.0000 m' 20,000.00 100,000.00
Isolasi 0.0500 bh 15,000.00 750.00
Jumlah Bahan 459,110.00
UPAH :
Tukang 0.1600 Oh 135,000.00 21,600.00
Pekerja 0.2500 Oh 110,000.00 27,500.00
Jumlah Pekerja 49,100.00
Jumlah Bahan + Pekerja 508,210.00
Dibulatkan 508,210.00
A.02.23 1 M2 PASANG GEBALAN RUMPUT
BAHAN :
LL42 Lempengan Rumput 1.0000 m² 40,000.00 40,000.00
Pupuk Kandang 1.0000 ls 10,000.00 10,000.00
Tanah Urug (Tebal 20 cm) 0.2000 m3 125,000.00 25,000.00
Jumlah Bahan 75,000.00
UPAH :
P PK02 Upah Pasang 1.0000 org 110,000.00 110,000.00
P PK19 Mandor 0.0100 org 180,000.00 1,800.00
Jumlah Pekerja 111,800.00
Jumlah Bahan + Pekerja 186,800.00
A052 Dibulatkan 186,800.00
A.01.P.01 1 BH TANAM POHON PELINDUNG
BAHAN :
LL42 Pohon Pelindung 1.0000 btg 100,000.00 100,000.00
Pupuk kandang 1.0000 ls 10,000.00 10,000.00
Jumlah Bahan 110,000.00
UPAH :
P PK02 Upah Tanam 1.0000 org 110,000.00 110,000.00
P PK19 Mandor 0.0100 org 180,000.00 1,800.00
Jumlah Pekerja 111,800.00
Jumlah Bahan + Pekerja 221,800.00
A052 Dibulatkan 221,800.00
A.01.P.02 1 M2 PEMBUATAN TAMAN
BAHAN :
LL42 Pembentukan Lahan Taman 1.0000 Unit 700,000.00 700,000.00
Pupuk Kandang 1.0000 ls 10,000.00 10,000.00
Pohon Perdu/Bunga dll 1.0000 btg 6,000.00 6,000.00
Jumlah Bahan 716,000.00
UPAH :
P PK02 Upah Tanam 1.0000 org 110,000.00 110,000.00
P PK19 Mandor 0.0100 org 180,000.00 1,800.00
Jumlah Pekerja 111,800.00
Jumlah Bahan + Pekerja 827,800.00
A052 Dibulatkan 827,800.00
A.01.P.03 1 BH PENANAMAN POHON HIAS
BAHAN :
LL42 Pohon Hias 1.0000 btg 6,000.00 6,000.00
Pupuk Kandang 1.0000 krg 10,000.00 10,000.00
Jumlah Bahan 16,000.00
UPAH :
P PK02 Upah Tanam 1.0000 org 110,000.00 110,000.00
P PK19 Mandor 0.0100 org 180,000.00 1,800.00
Jumlah Pekerja 111,800.00
Jumlah Bahan + Pekerja 127,800.00
Pekerjaan 1 2 3 4 5 6=(3x5)
A052 Dibulatkan 127,800.00
A.01.P.04 1 M' SELASAR PENGHUBUNG BANGUNAN DENGAN ATAP
BAHAN :
LL42 Kayu Kelas II Balok (Selasar Penghubung) 0.0459 m3 4,000,000.00 183,600.00
Seng Gelombang BJLS 0,3 3.3000 lbr 68,000.00 224,400.00
Seng Plat BJLS 30 lebar 90 cm 0.3000 lbr 50,000.00 15,000.00
Rabat Beton 0.0230 m3 794,930.00 18,283.39
Paku Seng 0.0200 kg 30,000.00 600.00
Mur - Baut dia 10 mm panjang 30 cm 1.6700 bh 10,000.00 16,700.00
Jumlah Bahan 458,583.39
UPAH :
P PK02 Pekerja 0.7500 oh 110,000.00 82,500.00
P PK19 Tukang Kayu 0.5000 oh 135,000.00 67,500.00
Jumlah Pekerja 150,000.00
Jumlah Bahan + Pekerja 608,583.39
A052 Dibulatkan 608,580.00
A.01.P.05 1 M' PEKERJAAN PANCANG CERUCUK BAMBU
BAHAN :
LL42 Bambu 1.0000 m¹ 3,750.00 3,750.00
-
-
-
-
-
Jumlah Bahan 3,750.00
UPAH :
P PK02 Pekerja 1.4286 oh 110,000.00 157,146.00
P PK19 Tukang Kayu oh -
Jumlah Pekerja 157,146.00
Jumlah Bahan + Pekerja 160,896.00
A052 Dibulatkan 160,890.00
A.01.P.06 1 BTG (pj = 45cm) PEKERJAAN PEMASANGAN ANGKUR BESI DIA. 10mm
BAHAN :
LL42 Besi Beton Polos Dia. 10 mm 0.3085 kg 13,000.00 4,010.50
Jumlah Bahan 4,010.50
UPAH :
P PK02 Pekerja 0.1000 oh 110,000.00 11,000.00
P PK19 Tukang Kayu oh -
Jumlah Pekerja 11,000.00
Jumlah Bahan + Pekerja 15,010.50
A052 Dibulatkan 15,010.00
A.01.P.07 1 BH PEKERJAAN BEGHEL U POJOK (BESI POLOS 12MM) + BAUT DIA.10
BAHAN :
LL42 Beghel U Besi Polos Dia. 12mm 1.0000 bh 15,000.00 15,000.00
Baut Dia. 10mm 1.0000 bh 10,000.00 10,000.00
Jumlah Bahan 25,000.00
UPAH :
P PK02 Pekerja oh 110,000.00 -
P PK19 Tukang Kayu 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 38,500.00
A052 Dibulatkan 38,500.00
A.01.P.08 1 BH PEKERJAAN BEGHEL U ALAS KUDA-KUDA (PLAT BAJA 4.40 MM) + BAUT DIA.10
BAHAN :
LL42 Beghel U Besi Plat Baja U 4.40mm 1.0000 bh 35,000.00 35,000.00
Baut Dia. 10mm 1.0000 bh 10,000.00 10,000.00
Jumlah Bahan 45,000.00
UPAH :
P PK02 Pekerja oh 110,000.00 -
P PK19 Tukang Kayu 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 58,500.00
A052 Dibulatkan 58,500.00
A.01.P.08 1 BH PEKERJAAN BEGHEL U ALAS KUDA-KUDA (PLAT BAJA 4.40 MM) + BAUT DIA.10
BAHAN :
Beghel U Besi Plat Baja U 4.40mm 1.0000 bh 35,000.00 35,000.00
Baut Dia. 10mm 1.0000 bh 10,000.00 10,000.00
Jumlah Bahan 45,000.00
UPAH :
Pekerja oh 110,000.00 -
Tukang Kayu 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 58,500.00
Dibulatkan 58,500.00
A.01.P.08" 2 BH PEKERJAAN BAUT DIA.10 mm Sambungan gording 5/10 atau 6/12 cm per titik
BAHAN :
Baut Dia. 10mm 2.0000 bh 10,000.00 20,000.00
Jumlah Bahan 20,000.00
UPAH :
P PK02 Pekerja oh 110,000.00 -
P PK19 Tukang Kayu 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 33,500.00
A052 Dibulatkan 33,500.00
A.01.P.09 1 SET PEK BEGHEL, BEGHEL U, PLAT BAJA, BAUT UNTUK 1 BH KUDA2-KUDA
BAHAN :
LL42 Beghel U (Plat Baja U 4.40mm) 3.0000 bh 35,000.00 105,000.00
Beghel U (Besi Polos 12mm) 2.0000 bh 15,000.00 30,000.00
Plat Baja 4.40mm 8.0000 bh 20,000.00 160,000.00
Baut Dia. 10mm (25-30cm) 22.0000 bh 10,000.00 220,000.00
Jumlah Bahan 515,000.00
UPAH :
P PK02 Pekerja oh 110,000.00 -
P PK19 Tukang Kayu 0.1000 oh 135,000.00 13,500.00
Pekerjaan 1 2 3 4 5 6=(3x5)
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 528,500.00
A052 Dibulatkan 528,500.00
A.01.P.10 1 BH PEKERJAAN TIANG DAN RING BASKET BALL KOMPLIT
BAHAN :
Galian tanah 1.2000 m3 51,200.00 61,440.00
Cor beton tumbuk Ad 1:3:5 0.5000 m3 794,930.00 397,465.00
Tiang pipa galvanis dia 3" 1.0000 btg 156,000.00 156,000.00
Papan plank komplit rangka 1.0000 bh 500,000.00 500,000.00
Ring Basket 1.0000 Set 150,000.00 150,000.00
Jumlah Bahan 1,264,905.00
UPAH :
Pekerja oh 110,000.00 -
Tukang 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 1,278,405.00
Dibulatkan 1,278,400.00
A.01.P.11 1 M1 PEKERJAAN HAND RAILING
BAHAN :
Cor beton tumbuk Ad 1:3:5 0.0120 m3 1,142,310.00 13,707.72
Pipa Stainless Steel Dia. 1,5" 1.3200 m¹ 30,000.00 39,600.00
Jumlah Bahan 53,307.72
UPAH :
Pekerja 1.0000 oh 110,000.00 110,000.00
Tukang oh 135,000.00 -
Jumlah Pekerja 110,000.00
Jumlah Bahan + Pekerja 163,307.72
Dibulatkan 163,300.00
A.01.P.12 1 TITIK PEKERJAAN PANCANG CERUCUK BAMBU
BAHAN :
Bambu 0.5000 btg 15,000.00 7,500.00
Kayu Kelas III Papan 0.0033 m3 4,000,000.00 13,333.33
Kawat Beton (Pengikat) 0.0150 kg 15,000.00 225.00
Jumlah Bahan 21,058.33
UPAH :
Pekerja 0.1000 oh 110,000.00 11,000.00
Tukang oh 135,000.00 -
Jumlah Pekerja 11,000.00
Jumlah Bahan + Pekerja 32,058.33
Dibulatkan 32,050.00
A.01.P.13 1 TITIK PEKERJAAN PANCANG CERUCUK KAYU DOLKEN
BAHAN :
Kayu Dolken Dia. 8 cm 0.5000 btg 40,000.00 20,000.00
Kayu Kelas III Papan 0.0033 m3 4,000,000.00 13,333.33
Kawat Beton (Pengikat) 0.0150 kg 15,000.00 225.00
Jumlah Bahan 33,558.33
UPAH :
Pekerja 0.1000 oh 110,000.00 11,000.00
Tukang oh 135,000.00 -
Jumlah Pekerja 11,000.00
Jumlah Bahan + Pekerja 44,558.33
Dibulatkan 44,550.00
A.01.P.14 1 M³ PEKERJAAN BALOK GAPIT
BAHAN :
Kayu Kls. II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Jumlah Bahan 4,400,000.00
UPAH :
Pekerja oh 110,000.00 -
Tukang 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 4,413,500.00
Dibulatkan 4,413,500.00
A.01.P.15 1 M³ PEKERJAAN TATAKAN GORDING/KLOS KAYU
BAHAN :
Kayu Kls. II Balok 1.1000 m³ 4,000,000.00 4,400,000.00
Paku Biasa 0.0500 kg 18,000.00 900.00
Jumlah Bahan 4,400,900.00
UPAH :
Pekerja oh 110,000.00 -
Tukang 0.1000 oh 135,000.00 13,500.00
Jumlah Pekerja 13,500.00
Jumlah Bahan + Pekerja 4,414,400.00
Dibulatkan 4,414,400.00
A.01.P.16 1 M1 PEKERJAAN PINTU GERBANG BESI
BAHAN :
Pintu Gerbang Besi 1.0000 m1 - -
Jumlah Bahan -
UPAH :
Pekerja oh 110,000.00 -
Tukang oh 135,000.00 -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
Bahan
Pekerjaan 1 2 3 4 5 6=(3x5)
Upah
0.3 Org/Mandor Rp Rp -
Alat bantu Rp -
Total Rp 8,217,500.00
Dibulatkan 914,830.00
BAHAN :
UPAH :
Mandor 0.03 Oh 0 0
Jumlah Pekerja 336,000.00
BAHAN :
Dibulatkan 1,088,540.00
1 M2 MENGECAT KAYU
BAHAN :
UPAH :
Jumlah 54,944.00
Dibulatkan 54,940.00
NSM :
NAMA MADRASAH :
Kabupaten :
Propinsi :
Pekerjaan : FURNITURE
1 2 3 4 5 6=(3x5)
M-1 1 UNIT MEJA SISWA TUNGGAL
BAHAN :
Kayu Kelas II 0.0500 m3 5,000,000.00 250,000.00
Paku Ulir 12.0000 bh 1,000.00 12,000.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.0500 kg 17,000.00 850.00
Politur 0.5000 kg 45,000.00 22,500.00
Jumlah Bahan 294,350.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 429,350.00
Dibulatkan 429,350.00
M-3 1 UNIT MEJA BACA INDIVIDU
BAHAN :
Kayu Kelas II 0.0708 m3 5,000,000.00 354,100.00
Paku Ulir 36.0000 bh 1,000.00 36,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.2000 kg 30,000.00 6,000.00
Lem Kayu 0.1500 kg 17,000.00 2,550.00
Politur 0.7500 kg 45,000.00 33,750.00
Jumlah Bahan 450,400.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 585,400.00
Dibulatkan 585,400.00
M-4 1 UNIT MEJA BACA KELOMPOK
BAHAN :
Kayu Kelas II 0.0263 m3 5,000,000.00 131,600.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.2000 kg 30,000.00 6,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.7500 kg 45,000.00 33,750.00
Jumlah Bahan 209,050.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 344,050.00
Dibulatkan 344,050.00
M-5 1 UNIT MEJA BACA SERBAGUNA
BAHAN :
Kayu Kelas II 0.0312 m3 5,000,000.00 156,200.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.2000 kg 30,000.00 6,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.7500 kg 45,000.00 33,750.00
Jumlah Bahan 233,650.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 368,650.00
Dibulatkan 368,650.00
M-6 1 UNIT MEJA PIMPINAN
BAHAN :
Kayu Kelas II 0.1700 m3 5,000,000.00 850,000.00
Knop Tarikan 1.0000 bh 10,000.00 10,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.2000 kg 30,000.00 6,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.7500 kg 45,000.00 33,750.00
Jumlah Bahan 961,450.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,096,450.00
1 2 3 4 5 6=(3x5)
Dibulatkan 1,096,450.00
1 2 3 4 5 6=(3x5)
M-7 1 UNIT MEJA KERJA
BAHAN :
Kayu Kelas II 0.1200 m3 5,000,000.00 600,000.00
Paku Ulir 20.0000 bh 1,000.00 20,000.00
Amplas 4.0000 lbr 6,000.00 24,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.0500 kg 17,000.00 850.00
Politur 1.0000 kg 45,000.00 45,000.00
Jumlah Bahan 698,850.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 833,850.00
Dibulatkan 833,850.00
M-8 1 UNIT MEJA GURU
BAHAN :
Kayu Kelas II 0.0432 m3 5,000,000.00 216,000.00
Paku Ulir 12.0000 bh 1,000.00 12,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.0500 kg 17,000.00 850.00
Politur 0.7500 kg 45,000.00 33,750.00
Jumlah Bahan 277,600.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 412,600.00
Dibulatkan 412,600.00
M-10 1 UNIT MEJA SIRKULASI
BAHAN :
Kayu Kelas II 0.1800 m3 5,000,000.00 900,000.00
Knop Tarikan 1.0000 bh 10,000.00 10,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.2000 kg 30,000.00 6,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 1.0000 kg 45,000.00 45,000.00
Jumlah Bahan 1,022,700.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,157,700.00
Dibulatkan 1,157,700.00
M-11 1 UNIT MEJA PERAGA / DEMONSTRASI
BAHAN :
Kayu Kelas II 0.1720 m3 5,000,000.00 860,000.00
Knop Tarikan 3.0000 bh 10,000.00 30,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.2000 kg 30,000.00 6,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 1.0000 kg 45,000.00 45,000.00
Jumlah Bahan 1,002,700.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,137,700.00
Dibulatkan 1,137,700.00
M-12 1 UNIT MEJA KETIK
BAHAN :
Kayu Kelas II 0.0500 m3 5,000,000.00 250,000.00
Knop Tarikan 1.0000 bh 10,000.00 10,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1500 kg 17,000.00 2,550.00
Politur 0.5000 kg 45,000.00 22,500.00
Jumlah Bahan 318,050.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 453,050.00
Dibulatkan 453,050.00
1 2 3 4 5 6=(3x5)
K-1 1 UNIT KURSI SISWA TUNGGAL
BAHAN :
Kayu Kelas II 0.0200 m3 5,000,000.00 100,000.00
Paku Ulir 25.0000 bh 1,000.00 25,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.0300 kg 17,000.00 510.00
Politur 0.5000 kg 45,000.00 22,500.00
Jumlah Bahan 163,010.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 298,010.00
Dibulatkan 298,010.00
K-2 1 UNIT KURSI BULAT TINGGI
BAHAN :
Kayu Kelas II 0.0027 m3 5,000,000.00 13,500.00
Besi Pipa Galvanis 1/2" 4.5000 m' 165,000.00 742,500.00
Baut dia.10 cm 4.0000 bh 10,000.00 40,000.00
Amplas 0.5000 lbr 6,000.00 3,000.00
Dempul besi 0.0500 kg 6,000.00 300.00
Lem Kayu 0.0200 kg 17,000.00 340.00
Politur 0.1000 kg 45,000.00 4,500.00
Cat besi 0.2000 kg 40,000.00 8,000.00
Jumlah Bahan 812,140.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 947,140.00
Dibulatkan 947,140.00
K-3 1 UNIT KURSI BULAT PENDEK
BAHAN :
Kayu Kelas II 0.0027 m3 5,000,000.00 13,500.00
Besi Pipa Galvanis 1/2" 3.5000 m' 165,000.00 577,500.00
Baut dia.10 cm 4.0000 bh 10,000.00 40,000.00
Amplas 0.5000 lbr 6,000.00 3,000.00
Dempul besi 0.0500 kg 6,000.00 300.00
Lem Kayu 0.0200 kg 17,000.00 340.00
Politur 0.1000 kg 45,000.00 4,500.00
Cat besi 0.2000 kg 40,000.00 8,000.00
Jumlah Bahan 647,140.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 782,140.00
Dibulatkan 782,140.00
K-5 1 UNIT KURSI KERJA
BAHAN :
Kayu Kelas II 0.0134 m3 5,000,000.00 67,200.00
Paku Ulir 20.0000 bh 1,000.00 20,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.0300 kg 17,000.00 510.00
Politur 0.2500 kg 45,000.00 11,250.00
Tripleks 4mm 0.5000 lbr 70,000.00 35,000.00
Karet Busa 1.0000 bh 400,000.00 400,000.00
Imitatie Lear 1.0000 unit 200,000.00 200,000.00
Jumlah Bahan 748,960.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 883,960.00
Dibulatkan 883,960.00
1 2 3 4 5 6=(3x5)
L-1 1 UNIT LEMARI BUKU
BAHAN :
Kayu Kelas II 0.1190 m3 5,000,000.00 595,000.00
Knop Tarikan 4.0000 bh 10,000.00 40,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kunci Lemari 2.0000 bh 18,000.00 36,000.00
Kaca 3mm 1.3200 m2 140,000.00 184,800.00
Engsel Pita 4.0000 psg 7,000.00 28,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,081,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,216,000.00
Dibulatkan 1,216,000.00
L-2 1 UNIT LEMARI KACA GESER
BAHAN :
Kayu Kelas II 0.2176 m3 5,000,000.00 1,088,000.00
Knop Tarikan 4.0000 bh 10,000.00 40,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kunci Lemari 2.0000 bh 18,000.00 36,000.00
Kaca 3mm 1.7000 m2 140,000.00 238,000.00
Rel Pita 4.8000 psg 20,000.00 96,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,695,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,830,200.00
Dibulatkan 1,830,200.00
L-3 1 UNIT LEMARI ARSIP
BAHAN :
Kayu Kelas II 0.1800 m3 5,000,000.00 900,000.00
Knop Tarikan 2.0000 bh 10,000.00 20,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kunci Lemari 1.0000 bh 18,000.00 18,000.00
Grendel 2.0000 bh 12,000.00 24,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,159,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,294,200.00
Dibulatkan 1,294,200.00
L-4 1 UNIT LEMARI PEMBATAS
BAHAN :
Kayu Kelas II 0.1048 m3 5,000,000.00 524,000.00
Knop Tarikan 2.0000 bh 10,000.00 20,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kunci Lemari 1.0000 bh 18,000.00 18,000.00
Engsel Pita 4.0000 psg 7,000.00 28,000.00
Grendel 2.0000 bh 12,000.00 24,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 811,200.00
UPAH :
1 2 3 4 5 6=(3x5)
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 946,200.00
Dibulatkan 946,200.00
L-5 1 UNIT LEMARI ADMINISTRASI
BAHAN :
Kayu Kelas II 0.1190 m3 5,000,000.00 595,000.00
Knop Tarikan 4.0000 bh 10,000.00 40,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kunci Lemari 2.0000 bh 18,000.00 36,000.00
Kaca 3mm 1.3200 m2 140,000.00 184,800.00
Engsel Pita 4.0000 psg 7,000.00 28,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,081,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,216,000.00
Dibulatkan 1,216,000.00
L-6 1 UNIT LEMARI ALAT PERAGA
BAHAN :
Kayu Kelas II 0.2925 m3 5,000,000.00 1,462,720.00
Knop Tarikan 3.0000 bh 10,000.00 30,000.00
Paku Ulir 10.0000 bh 1,000.00 10,000.00
sekrup 5 cm 50.0000 bh 300.00 15,000.00
Besi dia 8 mm 15.0000 m1 12,000.00 180,000.00
Promika 0.2352 lbr 15,000.00 3,527.28
Tripleks 4mm 0.5000 lbr 70,000.00 35,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,835,847.28
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,970,847.28
Dibulatkan 1,970,840.00
L-7 1 UNIT LEMARI OBAT
BAHAN :
Kayu Kelas II 0.2788 m3 5,000,000.00 1,394,000.00
Knop Tarikan 4.0000 bh 10,000.00 40,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kaca 3mm 1.3200 m2 140,000.00 184,800.00
Engsel Pita 4.0000 psg 7,000.00 28,000.00
Tripleks 4mm 0.5000 lbr 70,000.00 35,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,809,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,944,000.00
Dibulatkan 1,944,000.00
L-10 1 UNIT LEMARI KERTAS KERJA
BAHAN :
Kayu Kelas II 0.2925 m3 5,000,000.00 1,462,720.00
Knop Tarikan 30.0000 bh 10,000.00 300,000.00
Paku Ulir 10.0000 bh 1,000.00 10,000.00
sekrup 5 cm 100.0000 bh 300.00 30,000.00
Besi dia 8 mm 15.0000 m1 12,000.00 180,000.00
Promika 0.2352 lbr 15,000.00 3,527.28
Tripleks 4mm 0.5000 lbr 70,000.00 35,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
1 2 3 4 5 6=(3x5)
Jumlah Bahan 2,120,847.28
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 2,255,847.28
Dibulatkan 2,255,840.00
1 2 3 4 5 6=(3x5)
L-11 1 UNIT LEMARI KATALOK
BAHAN :
Kayu Kelas II 0.2925 m3 5,000,000.00 1,462,720.00
Knop Tarikan 30.0000 bh 10,000.00 300,000.00
Paku Ulir 10.0000 bh 1,000.00 10,000.00
sekrup 5 cm 80.0000 bh 300.00 24,000.00
Besi dia 8 mm 15.0000 m1 12,000.00 180,000.00
Promika 0.2352 lbr 15,000.00 3,527.28
Tripleks 4mm 0.5000 lbr 70,000.00 35,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 2,114,847.28
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 2,249,847.28
Dibulatkan 2,249,840.00
L-12 1 UNIT LEMARI KARDEK
BAHAN :
Kayu Kelas II 0.1000 m3 5,000,000.00 500,000.00
Knop Tarikan 8.0000 bh 10,000.00 80,000.00
Paku Ulir 25.0000 bh 1,000.00 25,000.00
sekrup 5 cm 25.0000 bh 300.00 7,500.00
Tripleks 4mm 0.5000 lbr 70,000.00 35,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.0500 kg 30,000.00 1,500.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.5000 kg 45,000.00 22,500.00
Jumlah Bahan 691,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 826,200.00
Dibulatkan 826,200.00
L-13 1 UNIT LEMARI KACA TINGGI
BAHAN :
Kayu Kelas II 0.2588 m3 5,000,000.00 1,294,000.00
Knop Tarikan 2.0000 bh 10,000.00 20,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kaca 3mm 1.5300 m2 140,000.00 214,200.00
Engsel Pita 6.0000 psg 7,000.00 42,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,767,400.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,902,400.00
Dibulatkan 1,902,400.00
L-14 1 UNIT LEMARI GANTUNG/P3K
BAHAN :
Kayu Kelas II 0.1075 m3 5,000,000.00 537,600.00
Knop Tarikan 2.0000 bh 10,000.00 20,000.00
Paku Ulir 10.0000 bh 1,000.00 10,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kaca 3mm 0.4800 m2 140,000.00 67,200.00
Engsel Pita 6.0000 psg 7,000.00 42,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 838,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 973,000.00
Dibulatkan 973,000.00
1 2 3 4 5 6=(3x5)
L-15 1 UNIT LEMARI KUNCI
BAHAN :
Kayu Kelas II 0.1075 m3 5,000,000.00 537,600.00
Knop Tarikan 2.0000 bh 10,000.00 20,000.00
Paku Ulir 10.0000 bh 1,000.00 10,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Sekrup Penggantung 12.0000 bh 200.00 2,400.00
Kaca 3mm 0.4800 m2 140,000.00 67,200.00
Engsel Pita 6.0000 psg 7,000.00 42,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 840,400.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 975,400.00
Dibulatkan 975,400.00
L-16 1 UNIT LEMARI LOCKER
BAHAN :
Kayu Kelas II 0.1392 m3 5,000,000.00 696,000.00
Knop Tarikan 12.0000 bh 10,000.00 120,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
sekrup 5 cm 24.0000 bh 300.00 7,200.00
Kunci Lemari 2.0000 bh 18,000.00 36,000.00
Engsel Pita 24.0000 psg 7,000.00 168,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,244,800.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,379,800.00
Dibulatkan 1,379,800.00
L-17/19 1 UNIT LEMARI PAKAIAN
BAHAN :
Kayu Kelas II 0.1800 m3 5,000,000.00 900,000.00
Knop Tarikan 2.0000 bh 10,000.00 20,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Kunci Lemari 1.0000 bh 18,000.00 18,000.00
Grendel 2.0000 bh 12,000.00 24,000.00
Tripleks 4mm 2.0000 lbr 70,000.00 140,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,229,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,364,200.00
Dibulatkan 1,364,200.00
L-20 1 UNIT LEMARI ASAM
BAHAN :
Kayu Kelas II 0.1075 m3 5,000,000.00 537,600.00
Knop Tarikan 4.0000 bh 10,000.00 40,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Pipa PVC AW 4" 1.0000 m1 48,000.00 48,000.00
Elbow PVC 4" 1.0000 bh 90,000.00 90,000.00
Engsel pita 4.0000 psg 7,000.00 28,000.00
Aluminium 1.0000 m2 75,000.00 75,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 945,800.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
1 2 3 4 5 6=(3x5)
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,080,800.00
Dibulatkan 1,080,800.00
1 2 3 4 5 6=(3x5)
P-1 1 UNIT PAPAN TULIS GANTUNG
BAHAN :
Kayu Kelas II 0.0300 m3 5,000,000.00 150,000.00
Paku Biasa 0.2500 kg 18,000.00 4,500.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Multiplex 9 mm 1.0000 lbr 110,000.00 110,000.00
Jumlah Bahan 321,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 456,200.00
Dibulatkan 456,200.00
P-4 1 UNIT WHITE BOARD GANTUNG/STANDAR
BAHAN :
Kayu Kelas II 0.0300 m3 5,000,000.00 150,000.00
Paku Biasa 0.2500 kg 18,000.00 4,500.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Jabarwood 4 mm 1.0000 lbr 80,000.00 80,000.00
Jumlah Bahan 291,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 426,200.00
Dibulatkan 426,200.00
P-6 1 UNIT PAPAN STATISTIK
BAHAN :
Kayu Kelas II 0.0300 m3 5,000,000.00 150,000.00
Paku Biasa 0.2000 kg 18,000.00 3,600.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Jabarwood 4 mm 1.0000 lbr 80,000.00 80,000.00
Jumlah Bahan 284,300.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 419,300.00
Dibulatkan 419,300.00
P-7 1 UNIT PAPAN JADWAL
BAHAN :
Kayu Kelas II 0.0250 m3 5,000,000.00 125,000.00
Paku Biasa 0.1500 kg 18,000.00 2,700.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Jabarwood 4 mm 1.0000 lbr 80,000.00 80,000.00
Jumlah Bahan 258,400.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 393,400.00
Dibulatkan 393,400.00
P-8 1 UNIT PAPAN PAMERAN
BAHAN :
Kayu Kelas II 0.0300 m3 5,000,000.00 150,000.00
Paku Biasa 0.2200 kg 18,000.00 3,960.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Multiplex 9 mm 1.0000 lbr 110,000.00 110,000.00
Jumlah Bahan 314,660.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 449,660.00
Dibulatkan 449,660.00
1 2 3 4 5 6=(3x5)
P-9 1 UNIT PAPAN JADWAL
BAHAN :
Kayu Kelas II 0.0220 m3 5,000,000.00 110,000.00
Paku Biasa 0.1300 kg 18,000.00 2,340.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Jabarwood 4 mm 1.0000 lbr 80,000.00 80,000.00
Jumlah Bahan 243,040.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 378,040.00
Dibulatkan 378,040.00
P-10 1 UNIT PAPAN ABSENSI
BAHAN :
Kayu Kelas II 0.0230 m3 5,000,000.00 115,000.00
Paku Biasa 0.1250 kg 18,000.00 2,250.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Cat Minyak 1.0000 kg 40,000.00 40,000.00
Jabarwood 4 mm 1.0000 lbr 80,000.00 80,000.00
Jumlah Bahan 247,950.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 382,950.00
Dibulatkan 382,950.00
R-1 1 UNIT RAK TAS DAN BUKU
BAHAN :
Kayu Kelas II 0.1256 m3 5,000,000.00 628,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
sekrup 5 cm 48.0000 bh 300.00 14,400.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 860,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 995,000.00
Dibulatkan 995,000.00
R-2 1 UNIT RAK BUKU SATU MUKA
BAHAN :
Kayu Kelas II 0.1072 m3 5,000,000.00 536,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
sekrup 5 cm 48.0000 bh 300.00 14,400.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 768,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 903,000.00
Dibulatkan 903,000.00
R-3 1 UNIT RAK BUKU DUA MUKA
BAHAN :
Kayu Kelas II 0.1504 m3 5,000,000.00 752,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
sekrup 5 cm 48.0000 bh 300.00 14,400.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 2.0000 lbr 6,000.00 12,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 978,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
1 2 3 4 5 6=(3x5)
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,113,000.00
Dibulatkan 1,113,000.00
1 2 3 4 5 6=(3x5)
R-4 1 UNIT RAK GUDANG
BAHAN :
Kayu Kelas II 0.1504 m3 5,000,000.00 752,000.00
Paku Ulir 48.0000 bh 1,000.00 48,000.00
sekrup 5 cm 48.0000 lbr 300.00 14,400.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 2.0000 kg 6,000.00 12,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 978,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,113,000.00
Dibulatkan 1,113,000.00
R-6 1 UNIT RAK MAJALAH
BAHAN :
Kayu Kelas II 0.0780 m3 5,000,000.00 389,950.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1500 kg 17,000.00 2,550.00
Politur 1.0000 kg 45,000.00 45,000.00
Jumlah Bahan 474,100.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 609,100.00
Dibulatkan 609,100.00
R-7 1 UNIT RAK ATLAS
BAHAN :
Kayu Kelas II 0.1100 m3 5,000,000.00 550,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1500 kg 17,000.00 2,550.00
Politur 1.0000 kg 45,000.00 45,000.00
Jumlah Bahan 634,150.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 769,150.00
Dibulatkan 769,150.00
R-8 1 UNIT RAK ENSIKLOPEDIA
BAHAN :
Kayu Kelas II 0.0273 m3 5,000,000.00 136,620.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.7500 kg 45,000.00 33,750.00
Jumlah Bahan 208,670.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 343,670.00
Dibulatkan 343,670.00
R-9 1 UNIT RAK KORAN
BAHAN :
Kayu Kelas II 0.0528 m3 5,000,000.00 264,000.00
Baut dia.10 cm 1.0000 bh 10,000.00 10,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.7500 kg 45,000.00 33,750.00
Cat besi 0.1500 kg 40,000.00 6,000.00
Jumlah Bahan 352,050.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
1 2 3 4 5 6=(3x5)
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 487,050.00
Dibulatkan 487,050.00
1 2 3 4 5 6=(3x5)
R-10 1 UNIT RAK DORONG
BAHAN :
Kayu Kelas II 0.2176 m3 5,000,000.00 1,088,000.00
Knop Tarikan 4.0000 bh 10,000.00 40,000.00
Paku Ulir 24.0000 bh 1,000.00 24,000.00
sekrup 5 cm 12.0000 bh 300.00 3,600.00
Rel Pita 4.8000 psg 20,000.00 96,000.00
Tripleks 4mm 1.0000 lbr 70,000.00 70,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Dempul kayu 0.3000 kg 30,000.00 9,000.00
Lem Kayu 0.3000 kg 17,000.00 5,100.00
Politur 1.5000 kg 45,000.00 67,500.00
Jumlah Bahan 1,421,200.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,556,200.00
Dibulatkan 1,556,200.00
U-6 1 UNIT DIPAN DIPERIKSA
BAHAN :
Besi Pipa Galvanis dia. 1" 4.5000 m' 322,000.00 1,449,000.00
Multiplex 12 mm 1.0000 lbr 195,000.00 195,000.00
Kasur Busa 1.0000 bh 500,000.00 500,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Cat besi 1.0000 kg 40,000.00 40,000.00
Jumlah Bahan 2,202,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 2,337,000.00
Dibulatkan 2,337,000.00
U-7 1 UNIT DIPAN TIDUR TUNGGAL
BAHAN :
Kayu Kelas II 0.2176 m3 5,000,000.00 1,088,000.00
Multiplex 12 mm 1.0000 lbr 195,000.00 195,000.00
Kasur Busa 1.0000 bh 500,000.00 500,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Cat Kayu 1.0000 kg 40,000.00 40,000.00
Jumlah Bahan 1,841,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 1,976,000.00
Dibulatkan 1,976,000.00
U-8 1 UNIT DIPAN TIDUR GANDA
BAHAN :
Kayu Kelas II 0.4352 m3 5,000,000.00 2,176,000.00
Multiplex 12 mm 1.0000 lbr 195,000.00 195,000.00
Kasur Busa 1.0000 bh 500,000.00 500,000.00
Amplas 3.0000 lbr 6,000.00 18,000.00
Cat Kayu 1.0000 kg 40,000.00 40,000.00
Jumlah Bahan 2,929,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 3,064,000.00
Dibulatkan 3,064,000.00
1 2 3 4 5 6=(3x5)
U-9 1 UNIT DIPAN TIDUR TINGKAT
BAHAN :
Kayu Kelas II 0.6000 m3 5,000,000.00 3,000,000.00
Multiplex 12 mm 2.0000 lbr 195,000.00 390,000.00
Kasur Busa 2.0000 bh 500,000.00 1,000,000.00
Amplas 5.0000 lbr 6,000.00 30,000.00
Cat Kayu 2.0000 kg 40,000.00 80,000.00
Jumlah Bahan 4,500,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 4,635,000.00
Dibulatkan 4,635,000.00
KS 1 UNIT KOTAK SAMPAH
BAHAN :
Kayu Kelas II 0.0300 m3 5,000,000.00 150,000.00
Paku Biasa 0.1000 kg 18,000.00 1,800.00
Amplas 1.0000 lbr 6,000.00 6,000.00
Dempul kayu 0.1000 kg 30,000.00 3,000.00
Lem Kayu 0.1000 kg 17,000.00 1,700.00
Politur 0.3000 kg 45,000.00 13,500.00
Cat Kayu 1.0000 kg 40,000.00 40,000.00
Jumlah Bahan 216,000.00
UPAH :
Tukang Kayu 1.0000 Oh 135,000.00 135,000.00
Jumlah Upah 135,000.00
Jumlah Bahan + Upah 351,000.00
Dibulatkan 351,000.00
1 2 3
1 2 3
A.06.35 1 M3 PASANGAN KONSTRUKSI KUDA - KUDA 8/12 KAYU KAYU LOKAL KLS II 6,792,400.00
A.06.36 1 M3 PASANG KONSTRUKSI GORDING 5/10 KAYU KLS II 6,792,400.00
1 2 3
A.06.37 1 M3 PASANG KASO 5/7 KAYU KLS II 77,700.00
A.06.38 1 M3 PASANG RENG 3/4 KAYU KLS II 77,700.00
A.06.39 1 M1 PASANG KONSTRUKSI NOK TEPI PAPAN 6/12 KAYU KLS II 5,053,300.00
A.06.44 1 M2 PASANG RANGKA PLAFOND BALOK 5/7 KAYU LOKAL KLS II 125,200.00
A.06.50 1 M2 PASANG LISPLANG UKURAN (3 x 30) cm, KAYU LOKAL KLS II 102,120.00
A.06.60 1 M1 PASANG LIST PLAFOND PROFIL KAYU LOKAL KLS II 4/4 22,410.00
A.07.01 1 M3 MEMBUAT BETON TUMBUK, 1 Pc : 3 Ps : 5 Kr 794,930.00
A.07.13 1 M3 MEMBUAT BETON BERTULANG 1 Pc : 2 Ps : 3 Kr 1,142,310.00
A.07.25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR 15,750.00
A.07.28 1 m2 PASANG BEKISTING UNTUK PONDASI 239,260.00
A.07.29 1 m2 PASANG BEKISTING UNTUK SLOOF 96,860.00
A.07.30 1 m2 PASANG BEKISTING UNTUK KOLOM 113,760.00
A.07.31 1 m2 PASANG BEKISTING UNTUK BALOK 197,010.00
A.07.32 1 m2 PASANG BEKISTING UNTUK LANTAI 302,960.00
A.07.33 1 m2 PASANG BEKISTING UNTUK DINDING 449,710.00
A.07.47 1 M3 MEMBUAT SOFI-SOFI 12/15 (220,80 Kg Besi + Bekesting) 5,361,800.00
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM
A.07.48 1 M3 MEMBUAT RING BALOK 15/20 (145,92 Kg Besi + Bekesting) 4,771,100.00
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
A.07.49 1 M3 MEMBUAT KOLOM 20/25 (169,67 Kg Besi + Bekesting) 5,036,140.00
DENGAN TULANGAN 6 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
A.07.50 1 M3 MEMBUAT SLOOF 15/20 (274,22 Kg Besi + Bekesting) 4,975,260.00
DENGAN TULANGAN 4 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
A.07.51 1 M3 PEK. BETON BERTULANG PLAT MEJA, adukan 1 : 2 : 3 4,236,830.00
A.07.52 1 M3 MEMBUAT KOLOM 12/15 (197 Kg Besi + Bekesting) 5,481,800.00
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM
A.07.60 1 M3 MEMBUAT KOLOM SELASAR 15/15 (181,88 Kg Besi + Bekesting) 5,512,680.00
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
A.07.75 1 M3 PEK. PLAT BETON BERTULANG, TULANGAN 1 LAPIS DIA.10 JARAK 10 cm TEBAL 10 cm 5,152,970.00
A.08.02 1 M2 PASANG ATAP GENTENG TANAH 104,340.00
A.08.03 1 M2 PASANG ATAP SPANDEK / GALVALYUM 0,3mm 156,840.00
A.08.05 1 M2 PASANG NOK BUBUNGAN GENTENG TANAH 108,170.00
A.08.06 1 M2 PASANG NOK BUBUNGAN GENTENG METAL 108,990.00
A.08.11 1 M2 PASANG ATAP SENG GELOMBANG BJLS 0,3 mm 71,540.00
A.08.12 1 M2 PASANG ATAP ZYNCALUM 0,3 mm 156,840.00
A.08.13 1 M2 PASANG ATAP GENTENG METAL 0,3 mm 94,140.00
A.08.14 1 M' PASANG NOK SENG POLOS 0,3 mm 29,660.00
A.08.30 1 M1 PASANG NOK TEPI SENG GELOMBANG 81,690.00
A.08.31 1 M1 PASANG NOK TEPI ZYNCALUM 81,690.00
A.08.32 1 M1 PASANG NOK TEPI GENTENG METAL 81,690.00
A.08.33 1 M1 PASANG NOK TEPI GENTENG TANAH 96,020.00
A.08.34 1 M1 PASANG NOK TEPI ATAP SPANDEK/GALVALYUM 81,690.00
A.09.02 1 M2 PASANG PLAFOND TRIPLEKS , TEBAL 4 mm 53,790.00
A.10.01 MEMASANG 1 BUAH KLOSET DUDUK 1,449,560.00
A.10.02 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN 603,860.00
A.10.04 MEMASANG 1 BUAH URINOIR 1,184,460.00
A.10.05 MEMASANG 1 BUAH WASTAFEL 714,710.00
A.10.07 MEMASANG 1 BUAH BAK MANDI FIBREGLASS VOLUME 0,3 M3 562,200.00
A.10.08 MEMASANG 1 BUAH BAK MANDI BATU BATA VOLUME 0,3 M3 1,223,200.00
A.10.16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (30X30) TINGGI 35 CM 607,030.00
A.10.17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (45X45) TINGGI 50 CM 414,370.00
A.10.18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (60X60) TINGGI 65 CM 645,980.00
A.10.19 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,5" -
A.10.20 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,75" 309,240.00
A.10.21 MEMASANG 1 M' PIPA GALVANIS DIAMETER 1" 459,090.00
A.10.22.a MEMASANG 1 M' PIPA GALVANIS DIAMETER 1,5" 700,180.00
A.10.22 MEMASANG 1 M' PIPA GALVANIS DIAMETER 2" 939,130.00
A.10.23 MEMASANG 1 M' PIPA GALVANIS DIAMETER 3" 250,630.00
A.10.24 MEMASANG 1 M' PIPA GALVANIS DIAMETER 4" 2,192,490.00
A.10.25 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 0,5" 19,410.00
A.10.26 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 0,75" 20,430.00
A.10.27 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1" 21,780.00
A.10.28 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1,5" 27,510.00
1 2 3
A.10.29 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2" 38,240.00
A.10.30 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2,5" 41,010.00
A.10.31 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3" 76,940.00
A.10.32 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 4" 94,830.00
A.10.33 MEMASANG 1 BH BAK CUCI PIRING STAILES STEEL 378,870.00
A.10.35 MEMASANG 1 BH KRAN DIAMETER 0,75' ATAU 0,5" 26,720.00
A.10.36 MEMASANG 1 BH FLOOR DRAIN 31,350.00
A.10.37 1 UNIT SEPTICTANK 4,8 X 2,1 X 2,4 M + REMBESANNYA 23,576,320.00
A.11.01 1 M2 PASANG RANGKA ATAP BAJA RINGAN 184,420.00
A.11.09 1 M2 PASANG PINTU ALUMINIUM 349,980.00
A.11.12 1 M2 PASANG TERALIS BESI 296,020.00
A.11.18 1 M2 PASANG TALANG DATAR, SENG BJLS 28 151,600.00
A.11.19 1 M2 PASANG TALANG MIRING, SENG BJLS 28 187,200.00
A.11.20 1 M2 PASANG TALANG 1/2 LINGKARAN D-10 CM, SENG BJLS 28 174,470.00
A.11.22 1 M2 PEK. RESIDU/TEER RANGKA ATAP/KUDA-KUDA/GORDING 5,290.00
A.12.02 1 BUAH PASANG KUNCI TANAM BIASA 146,100.00
A.12.03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI 119,300.00
A.12.04 1 BUAH PASANG KUNCI BULAT 88,890.00
A.12.05 1 BUAH PASANG ENGSEL PINTU 47,680.00
A.12.06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU 36,290.00
A.12.09 1 BUAH PASANG KAIT ANGIN 49,430.00
A.12.10 1 BUAH PASANG SLOOT TANAM 57,650.00
A.12.11 1 BUAH PASANG GRENDEL JENDELA 44,580.00
A.12.12 1 BUAH PASANG PEGANGAN PINTU + KUNCI PINTU 2 X PUTAR 131,450.00
A.12.14 1 BUAH PASANG KUNCI PINTU 2 X PUTAR ( lever handle ) 228,740.00
A.12.17 1 M2 PASANG KACA, TEBAL 5 MM 227,930.00
A.12.28 1 KG PEK. KONSTRUKSI BESI SIKU 25,120.00
A.12.34 1 M1 PEK. PAGAR BELAKANG / SAMPING KAWAT DURI 142,150.00
A.12.34a 1 M1 PEK.PAGAR BRC Ø 6 mm 200,190.00
A.13.42 1 M2 PASANG LANTAI KERAMIK 10 X 20 CM 195,730.00
A.13.44 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM 200,730.00
A.13.45 1 M2 PASANG LANTAI KERAMIK 25 X 25 CM 195,730.00
A.13.46 1 M2 PASANG LANTAI KERAMIK 15 X 20 CM 200,730.00
A.13.47 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM 190,730.00
A.13.48 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM ANTISLIP 190,730.00
A.13.58 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, PUTIH 203,580.00
A.13.59 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, WARNA 208,580.00
A.13.62 1 M2 PASANG DINDING PORSELEN 10 X 20 CM, WARNA 208,830.00
A.13.63 1 M2 PASANG DINDING PORSELEN 20 X 20 CM, WARNA 213,690.00
A.13.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM, 203,830.00
A.13.68 1 M2 PASANG DINDING KERAMIK 20 X 20 CM, 161,580.00
A.13.69 1 M2 PASANG DINDING KERAMIK 10 X 20 CM, 2,849,750.00
A.13.74 1 M2 PASANG DINDING BATU TEMPEL 215,720.00
A.13.75 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM DN PUTIH POLOS 190,730.00
A.13.76 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM WARNA / CORAK / ANTI SLIP 190,730.00
A.13.77 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM 195,730.00
A.13.78 1 M2 PASANG DINDING KERAMIK 20 X 25 CM, 203,830.00
A.13.83 1 M2 PASANGAN PAVING BLOCK WARNA (6 CM) 172,540.00
A.13.84 1 M2 PASANGAN PAVING BLOCK WARNA (8 CM) 177,590.00
A.13.86 1 M2 PASANGAN PAVING BLOCK NATURAL (6 CM) 170,520.00
A.13.87 1 M2 PASANGAN PAVING BLOCK NATURAL (8 CM) 173,550.00
A.14.12 1 M2 MENI KAYU 16,280.00
A.14.13 1 M2 MENI BESI 16,980.00
A.14.14 1 M2 PLAMUR TEMBOK 14,160.00
A.14.25 1 M2 PENGECATAN DINDING SEKELAS VINILEX (3x) 43,280.00
A.14.26 1 M2 PENGECATAN PLAFOND SEKELAS VINILEX (3x) 43,280.00
A.14.30 1 M2 PENGECATAN BIDANG KAYU (3X) BERIKUT MENI 54,940.00
A.14.31 1 M2 PENGECATAN BESI (2X) 52,780.00
A. R 1 M2 PEK. ANTI RAYAP 6,500.00
1 2 3
A. B 1 M2 PEKERJAAN SALURAN AIR PASANGAN BT BATA ad 1 : 4 140,680.00
L. 01. 01 1 M1 PAS. INSTALASI LISTRIK KABEL UTAMA 3x2,5 NYM 48,650.00
L. 01. 02 1 TITIK INSTALASI TITIK LAMPU 2x2,5 NYM 89,950.00
L. 01. 03 1 Titik Pas. Instalasi Titik Saklar Tunggal 2x2,5 NYM 97,850.00
L. 01. 04 1 Titik Instalasi Titik Saklar Double 3x2,5 NYM 99,350.00
L. 01. 05 1 Titik Pas. Instalasi Titik Stop Kontak 3x2,5 NYM 74,350.00
L. 01. 06 1 Titik Pas. Instalasi Lampu Pijar 137,150.00
L. 01. 07 1 Titik Pas. Instalasi Lampu TL 2x40 Watt + fitting 287,150.00
L. 01. 08 1 Titik Pas. MCB + Box Sekring 242,850.00
L. 01. 09 1 M1 Pas. Kabel Antar Bangunan 3x4mm NYY 368,750.00
L. 01. 10 1 Bh pasang Panel Box Utama +MCB 122,350.00
S.D.U 1 M' PAS. SALURAN DRAINASE UTAMA 508,210.00
A.01.P.01 1 BH TANAM POHON PELINDUNG 221,800.00
A.01.P.02 1 M2 PEMBUATAN TAMAN 827,800.00
A.01.P.03 1 BH PENANAMAN POHON HIAS 127,800.00
A.01.P.04 1 M' SELASAR PENGHUBUNG BANGUNAN DENGAN ATAP 608,580.00
A.01.P.06 1 BTG (pj = 45cm) PEKERJAAN PEMASANGAN ANGKUR BESI DIA. 10mm 15,010.00
A.01.P.07 1 BH PEKERJAAN BEGHEL U POJOK (BESI POLOS 12MM) + BAUT DIA.10 38,500.00
A.01.P.08 1 BH PEKERJAAN BEGHEL U ALAS KUDA-KUDA (PLAT BAJA 4.40 MM) + BAUT DIA.10 58,500.00
A.01.P.08" 2 BH PEKERJAAN BAUT DIA.10 mm Sambungan gording 5/10 atau 6/12 cm per titik 33,500.00
A.01.P.09 1 SET PEK BEGHEL, BEGHEL U, PLAT BAJA, BAUT UNTUK 1 BH KUDA2-KUDA 528,500.00
A.01.P.10 1 BH PEKERJAAN TIANG DAN RING BASKET BALL KOMPLIT ### 1,278,400.00
A.01.P.11 1 M1 PEKERJAAN HAND RAILING 163,300.00
A.01.P.12 1 TITIK PEKERJAAN PANCANG CERUCUK BAMBU 32,050.00
A.01.P.13 1 TITIK PEKERJAAN PANCANG CERUCUK KAYU DOLKEN 44,550.00
A.01.P.14 1 M³ PEKERJAAN BALOK GAPIT 4,413,500.00
A.01.P.15 1 M³ PEKERJAAN TATAKAN GORDING/KLOS KAYU 4,414,400.00
A.01.P.16 1 M1 PEKERJAAN PINTU GERBANG BESI -
Kode Sekolah :
Sekolah : 0.000
Desa : 111000.000
Kecamatan : 0.000
Kabupaten : 0.000
Propinsi : 0
No Diameter Berat Besi No Diameter Berat Besi No. Diameter Berat Besi
mm Kg / m1 mm Kg / m1 mm Kg / m1
1. Beton Kolom Praktis 12 X 15 cm' pakai tulangan 4 batang dia. 10 beugel dia. 6 jarak 15 cm
Panjang 1 m3 ukuran 12 x 15 cm = 1 : 0,12 : 0,15 = 55.56 m1
Besi 4 batang dia. 10 = 4 x 55,56 x 0,62 kg = 152.66 kg ( A)
Besi beugel dia. 6 jarak 15 cm = ( 55,56 : 0,15 ) x ( 0,08+0,08+0,1+0,1+0,1) x 0, 22 kg = 37.48 kg ( B )
2. Beton Kolom Selasar 15 X 15 cm' pakai tulangan 4 batang dia. 10 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 15 x 15 cm = ( 1 : 0.15 : 0.15 ) = 44.44 m1
Besi 4 batang dia. 10 = 4 x 44,44 x 0,62 kg = 122.62 kg ( A)
Besi beugel dia. 8 jarak 15 mm = ( 44,44 : 0,15 ) x( ( 4 x 0,10 )+0,1) x 0, 40 kg = 59.26 kg ( B )
3. Beton Sloof Selasar 15 X 20 cm' pakai tulangan 4 batang dia. 12 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 15 x 20 cm = ( 1 : 0.15 : 0.20 ) = 33.33 m1
Besi 4 batang dia. 12 = 4 x 33,33 x 0,89 kg = 132.91 kg ( A)
Besi beugel dia. 8 jarak 15 mm = ( 33,33 : 0,15 ) x ( 2 x 0,10 ) + ( 2 x 0,15 ) x 0, 40 kg = 53.33 kg ( B )
4. Beton Sloof Utama 20 X 25 cm' pakai tulangan 6 batang dia. 12 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 20 x 25 cm = ( 1 : 0.20 : 0.25 ) = 20.00 m1
Besi 6 batang dia. 12 = 6 x 20,00 x 0,89 kg = 122.82 kg ( A)
Besi beugel dia. 8 jarak 15 mm = ( 20,00 : 0,15 ) x ( 2 x 0,15 ) + ( 2 x 0,20 ) x 0, 40 kg = 42.67 kg ( B )
5. Beton Kolom Utama 20 X 25 cm' pakai tulangan 6 batang dia. 12 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 20 x 25 cm = ( 1 : 0.20 : 0.25 ) = 20.00 m1
Besi 6 batang dia. 12 = 6 x 20,00 x 0,89 kg = 122.82 kg ( A)
Besi beugel dia. 8 jarak 15 mm = ( 20,00 : 0.15 ) x (( 2 x 0.15 ) + ( 2 X 0,20 )) X 0,40 kg = 42.67 kg ( C )
6. Beton Balok Linetel 12 X 20 cm' pakai tulangan 4 batang dia. 10 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 12 x 20 cm = ( 1 : 0.12 : 0.20 ) = 41.67 m1
Besi 4 batang dia. 10 = 4 x 41,67 x 0,62 kg = 115.73 kg ( A)
Besi beugel dia. 8 jarak 15 mm = ( 41,67 : 0.15 ) x (( 2 x 0.08 ) + ( 2 X 0,15 )+0,1) X 0,40 kg = 62.22 kg ( C )
BERAT BESI BETON UNTUK UKURAN 12 x 20 CM DALAM 1 M3 = 177.96 kg/m3 ( A + B + C )
7. Beton Ring Balok 15 X 20 cm' pakai tulangan 4 batang dia. 10 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 15 x 20 cm = ( 1 : 0.15 : 0.20 ) = 33.33 m1
Besi 4 batang dia. 10 = 4 x 33,33 x 0,62 kg = 92.59 kg ( A)
Besi beugel dia. 8 jarak 15 mm = ( 33,33 : 0.15 ) x (( 2 x 0.1 ) + ( 2 X 0,15 )+0,1) X 0,40 kg = 53.33 kg ( C )
8. Beton Sofi-Sofi 12 X 15 cm' pakai tulangan 4 batang dia. 10 beugel dia. 6 jarak 15 cm
Panjang 1 m3 ukuran 12 x 15 cm = ( 1 : 0.12 : 0.15 ) = 55.56 m1
Besi 4 batang dia. 10 = 4 x 55,56 x 0,62 kg = 152.66 kg ( A)
Besi beugel dia. 6 jarak 15 mm = ( 55,56 : 0.15 ) x (( 2 x 0.08 ) + ( 2 X 0,10 )+0,1) X 0,22 kg = 37.48 kg ( C )