B. Sampling
1 Engineer fee Isokinetik 4 5.500.000 22.000.000
2 Fee Instrument 4 825.000 3.300.000
3 Transportation medialab - Airport 2 600.000 1.200.000
4 Transportation Airways (3 engineer) JKT-Palangkaraya 3 2.500.000 7.500.000
5 Transportation Airways (3 engineer) Palangkaraya-JKT 3 2.500.000 7.500.000
6 Cargo Tools (PP) JKT -Palangkaraya 192 275.000 52.800.000
7 Cargo Chemicals (PP) JKT-Palangkaraya 5 300.000 1.500.000
8 Mob Demob 1 Ls 5.500.000 5.500.000
9 Accommodation (Hotel and Meals/days) 1 Ls 6.600.000 6.600.000
C. Reporting Costs
1 Tenaga Ahli (Lumpsum) 1 Ls 14.000.000 14.000.000
2 Pembuatan /Penyusunan Laporan dan Buku TBT (Lumpsum) 1 Ls 7.000.000 7.000.000
Test PCR (2 x 2 engineer)
PAYMENT INFORMATION Sub Total2 225.150.000
Bank Mandiri KCP Bekasi Jatiasih
A/n.: PT MEDIALAB INDONESIA VAT -
A/c No. 156-00-0457633-8 TOTAL (IDR) 225.150.000