Instructions for assembly and use (Method statement)
© by Doka GmbH, A-3300 Amstetten
98113-202-07
© by Doka GmbH, A-3300 Amstetten
User Information Tunnel system DokaCC
2 999811302 - 04/2016
User Information Tunnel system DokaCC
Contents
4 Introduction 44 Assembly instructions
4 Elementary safety warnings 44 General instructions for site-erection
7 Eurocodes at Doka 46 List of tools needed for assembly
8 Doka services
48 Pre-assembly
10 System description 48 Girderframes
10 DokaCC - the economical tunnel formwork 52 Lifting mechanism
system for cut-and-cover 54 Top longitudinal beams
11 System overview 55 Formwork elements
12 Girderframe in detail
14 Height adjustment 56 Assembly
17 Adjusting girderframe spacing 56 Positioning rails and supports
20 Adjusting, aligning and lowering 57 Assembly of the supporting construction
22 Load transfer 68 Mounting the inside formwork
23 Tie rod system 75 Mounting the stop-end formwork
24 Traveller systems 76 Mounting the outside formwork
25 Stop-end formwork construction
26 Safety features 79 Dismantling
96 Component overview
999811302 - 04/2016 3
Introduction User Information Tunnel system DokaCC
Introduction
Elementary safety warnings
User target groups Remarks on this booklet
▪ This booklet is aimed at all persons who will be work- ▪ This booklet can also be used as a generic method
ing with the Doka product or system that it describes. statement or incorporated with a site-specific
It contains information on the standard design for method statement.
setting up this system, and on correct, compliant uti- ▪ Many of the illustrations in this booklet show the
lisation of the system. situation during formwork assembly and are
▪ All persons working with the product described therefore not always complete from the safety
herein must be familiar with the contents of this point of view.
booklet and with all the safety instructions it contains. Any safety accessories not shown in these illustra-
▪ Persons who are incapable of reading and under- tions must still be used by the customer, in accord-
standing this booklet, or who can do so only with dif- ance with the applicable rules and regulations.
ficulty, must be instructed and trained by the cus- ▪ Further safety instructions, especially warnings,
tomer. will be found in the individual sections of this
▪ The customer is to ensure that the information mate- booklet!
rials provided by Doka (e.g. User Information book-
lets, Instructions for Assembly and Use, Operating
Instruction manuals, plans etc.) are up to date and Planning
available to all users, and that they have been made
aware of them and have easy access to them at the ▪ Provide safe workplaces for those using the form-
usage location. work (e.g. for when it is being erected/dismantled,
▪ In the relevant technical documentation and form- modified or repositioned etc). It must be possible to
work utilisation plans, Doka shows the workplace get to and from these workplaces via safe access
safety precautions that are necessary in order to use routes!
the Doka products safely in the usage situations ▪ If you are considering any deviation from the
shown. details and instructions given in this booklet, or
In all cases, users are obliged to ensure compliance any application which goes beyond those
with national laws, standards and regulations described in the booklet, then revised static cal-
throughout the entire project and to take appropriate culations must be produced for checking, as well
additional or alternative workplace safety precau- as supplementary assembly instructions.
tions where necessary.
4 999811302 - 04/2016
User Information Tunnel system DokaCC Introduction
999811302 - 04/2016 5
Introduction User Information Tunnel system DokaCC
▪
slinging means must be used - this is a mandatory
requirement.
Remove any loose parts or fix them in place so that
☞ Important note
Failure to observe this may lead to malfunc-
tion or damage.
they cannot be dislodged or fall free!
▪ All components must be stored safely, following all
the special Doka instructions given in the relevant CAUTION / WARNING / DANGER
sections of this booklet! Failure to observe this may lead to material
damage, and to injury to health which may
Maintenance range up to the severe or even life-threaten-
ing.
Tip
Points out useful practical tips.
Reference
Refers to other documents and materials.
6 999811302 - 04/2016
User Information Tunnel system DokaCC Introduction
Eurocodes at Doka
In Europe, a uniform series of Standards known as The widely used "Permissible stress design" (compar-
Eurocodes (EC) was developed for the construction ing the actual stresses with the permissible stresses)
field by the end of 2007. These are intended to provide has been superseded by a new safety concept in the
a uniform basis, valid throughout Europe, for product EC.
specifications, tenders and mathematical verification. The EC contrast the actions (loads) with the resistance
The EC are the world's most highly developed Stand- (capacity). The previous safety factor in the permissible
ards in the construction field. stresses is now divided into several partial factors. The
In the Doka Group, the EC are to be used as standard safety level remains the same!
from the end of 2008. They will thus supersede the DIN
norms as the "Doka standard" for product design.
Ed Rd
98013-102
999811302 - 04/2016 7
Introduction User Information Tunnel system DokaCC
Doka services
Support in every stage of the project
Doka offers a broad spectrum of services, all with a sin-
gle aim: to help you succeed on the site.
Every project is unique. Nevertheless, there is one
thing that all construction projects have in common –
and that is a basic structure with five stages. We at
Doka know our clients' varying requirements. With our
consulting, planning and other services, we help you
achieve effective implementation of your formwork
assignment using our formwork products – in every one
of these stages.
1 2 3
Project Development Stage Bidding Stage Operations Scheduling Stage
Taking well-founded decisions Optimising the preliminary work Controlled, regular forming oper-
thanks to professional advice and with Doka as an experienced part- ations, for greater efficiency
consulting ner resulting from realistically calculated
formwork concepts
Find precisely the right formwork Draw up potentially winning bids, by Plan cost-effectively right from the
solutions, with the aid of ▪ basing them on realistically calcu- outset, thanks to
▪ help with the bid invitation lated guideline prices ▪ detailed offers
▪ in-depth analysis of the initial sit- ▪ making the right formwork ▪ determination of the commission-
uation choices ing quantities
▪ objective evaluation of the plan- ▪ having an optimum time-calcula- ▪ co-ordination of lead-times and
ning, execution, and time-risks tion basis handover deadlines
8 999811302 - 04/2016
User Information Tunnel system DokaCC Introduction
▪ Transparency
Because our services and costs
Optimum resource utilisation Seeing things through to a posi- are completely transparent, there
with assistance from the Doka tive conclusion is no need for improvisation dur-
Formwork Experts with professional support ing the project – and no unpleas-
ant surprises at the end of it.
999811302 - 04/2016 9
System description User Information Tunnel system DokaCC
System description
DokaCC - the economical tunnel formwork system for cut-and-cover
With the modular Tunnel system DokaCC, rectan- Rapid working
gular or circular cross-sections of cut-and-cover
tunnels can be formed swiftly and using less mate-
rial. The applicability on all common types of foun- assisted by its site-ready system details
dations provides additional benefit in terms of effi- ▪ Less assembly work needed on the site, as there are
ciency only a small number of shoring frames.
▪ Shorter assembly times, as the site is supplied with
pre-assembled units.
Highly cost-efficient ▪ Lifting, lowering and fine-adjusting the tunnel form-
work traveller is made easy by the hydraulic travel-
by optimised system concept ling and lifting appliances.
▪ Small number of shoring frames, made possible by ▪ Fast closing and opening of the formwork elements
statically optimised load-bearing system with either mechanical or all-hydraulic stripping solu-
▪ Less work needed for temporary foundations, as the tion.
system allows loads to be transferred into the wall ▪ A practical slide mechanism makes the stop-end
footings formwork easy to open and close.
▪ Needs less labour, as there are fewer points needing
to be operated.
Versatility
High safety Height-variable and width-variable
▪ Rectangular cross-sections from 4.5 to 8.0 m in
in all stages of the work height and 8.0 to 14.0 m in width.
▪ Detailed project-specific planning by Doka Engineer- Load-variable
ing. ▪ Roof-slab thicknesses for rectangular cross-sections
▪ The parallel girderframe units can be pre-assembled from 0.5 - 1.5 m.
flat on the ground and safely lifted into the vertical ▪ Roof-slab thicknesses for circular cross-sections
because of their bolted and solidly pinned joints. from 0.5 - 1.0 m.
▪ Safe up/down access via integrated caged ladder-
way. Note:
▪ stop-end formwork can be operated in safety from For tunnel projects involving larger sizes, consult your
the spacious working platforms. Doka technician!
▪ Longitudinal gradients of up to 8 % can be negoti-
ated safely (hydraulic drive) Use with different
types of foundation
▪ Wall footings along sides
▪ Full-width invert
98113-223-02 98113-221-03
10 999811302 - 04/2016
User Information Tunnel system DokaCC System description
System overview
Cross-section
P B O
E Q H A K
N
J
F
R
G
98113-202-03
Shown here without outside formwork
Longitudinal section
M
O
B
L
H
D
A
C B
F
G
98113-200-24
999811302 - 04/2016 11
System description User Information Tunnel system DokaCC
Girderframe in detail
D System beam
G
N C Technical data:
A Section modulus: 1,678 cm3
B O
F Moment of inertia: 27,693 cm4
K
Mounted parts
☞
O Connecting pin DokaCC D60 235
Important note:
The vertical struts have to be held in the weak
profile direction at least every 3.0 m to prevent
buckling (see the section headed 'Spindle strut
bracing in longitudinal direction')!
12 999811302 - 04/2016
User Information Tunnel system DokaCC System description
To transfer the vertical loads For transferring loads diagonally from the System beam DokaCC to
the Load distributor DokaCC, or for extending the lifting-mechanism
▪ Bolted to Vertical strut endpiece DokaCC and Load distributor unit.
DokaCC.
▪ Bolted to two Diagonal strut endpieces DokaCC or to Lifting
mechanism box DokaCC and Load distributor DokaCC.
Vertical strut endpiece DokaCC (F)
1.00m 0.80m 0.60m Diagonal strut endpiece DokaCC (K)
1.60m 1.40m
Diagonal strut To dissipate the loads from the vertical struts and the diagonal
struts.
▪ Sits against the lowering wedge and is tied back with the rail dis-
tance piece.
Technical data:
Perm. strut load: 480 kN Mounted parts
Valid with max. 3 profile end-face joins, strut length* ≤
7.0 m ▪ Longitudinal beam connector WU14 DokaCC
*) Distance between connecting pins at top and bottom bottom (M)
- Connects Top100tec walings to the Load distrib-
utor DokaCC.
999811302 - 04/2016 13
System description User Information Tunnel system DokaCC
Height adjustment
The individual components combine flexibly, which
means that the overall height of the girderframes can
be adapted to site specifics.
Standard heights
b
α [°] v [m] s [m] b [m] f [mm] Item a [mm]
M 3.80 64.3 2.20 3.00 1.50 41 1 231
4.05 66.0 2.40 3.20 1.50 11 261
60.0 3.60 2.00 5 267
H 4.25 2.60
67.5 3.40 1.50 29 2 243
D 90°
A a 4.45
61.7
2.80
3.80 2.00 34 238
68.8 3.60 1.50 44 228
C
70.0 3.80 1.50 8 264
4.70 3.00
63.3 4.00 2.00 9 263
G 3
4.90 64.6 3.20 4.20 2.00 32 240
B 5.10 60.0 4.60 2.50 21 251
3.40
5.15 65.9 4.40 2.00 2 270
61.4 4.80 2.50 0 272
5.35 3.60
Height of girderframe h [m]
67.0 4.60 2.00 20 4 252
62.6 5.00 2.50 27 245
5.55 3.80
F 68.0 4.80 2.00 37 235
v
14 999811302 - 04/2016
User Information Tunnel system DokaCC System description
0.60m
0.80m
1.00m
0.60m
1.00m
1.60m
2.20m
2.80m
Diagonal strut
Diagonal strut end-
Diagonal strut DokaCC
piece DokaCC 2.2 1 — — — — 1 — —
1.40m 2.4 — 1 — — — 1 — —
1.60m
0.60m
1.00m
1.60m
2.20m
2.80m
2.6 — — 1 — — 1 — —
2.80 2 — — — — — — 2.8 1 — — 1 — 1 — —
3.00 1 1 — — — — — 3.0 — 1 — 1 — 1 — —
3.20 — 2 — — — — — 3.2 1 — — — 1 1 — —
3.40 2 — 1 — — — — 3.4 — 1 — — 1 1 — —
3.60 1 1 1 — — — — 3.6 — — 1 — 1 1 — —
3.80 — 2 1 — — — — 3.8 1 — — — — 2 — —
v [m]
4.00 1 1 — 1 — — — 4.0 — 1 — — — 2 — —
4.20 — 2 — 1 — — — 4.2 — — 1 — — 2 — —
4.40 2 — — — 1 — — 4.4 1 — — — — 1 1 —
4.60 1 1 — — 1 — — 4.6 — 1 — — — 1 1 —
4.80 — 2 — — 1 — — 4.8 — — 1 — — 1 1 —
s [m]
5.00 2 — — — — 1 — 5.0 1 — — — — 1 — 1
5.20 1 1 — — — 1 — 5.2 — 1 — — — 1 — 1
5.40 — 2 — — — 1 — 5.4 — — 1 — — 1 — 1
5.60 2 — — — — — 1 5.6 1 — — 1 — 1 — 1
5.80 1 1 — — — — 1 5.8 — 1 — 1 — 1 — 1
6.00 — 2 — — — — 1 v ... vertical strut length (see table, 'Standard heights')
6.20 1 1 — 1 — 1 —
6.40 — 2 — — 2 — — Note:
6.60 — 2 1 — — — 1 Installation of the lifting mechanism unit is possible only
6.80 1 1 — 1 — — 1 when a Vertical strut DokaCC 1.60m is used as the
7.00 — 2 — 1 — — 1 bottommost part of the vertical strut (see section
s ... diagonal strut length (see table, 'Standard heights') headed 'Assembling girderframe with lifting mecha-
nism').
Vertical strut (girderframe without lifting mecha-
nism)
Vertical strut end-
Vertical strut DokaCC
piece DokaCC
0.60m
0.80m
1.00m
0.60m
1.00m
1.60m
2.20m
2.80m
2.2 1 — — — — 1 — —
2.4 — 1 — — — 1 — —
2.6 — — 1 — — 1 — —
2.8 1 — — — — — 1 —
3.0 — 1 — — — — 1 —
3.2 — — 1 — — — 1 —
3.4 1 — — — — — — 1
3.6 — 1 — — — — — 1
3.8 1 — — — 1 — 1 —
v [m]
4.0 1 — — 1 — — — 1
4.2 — 1 — 1 — — — 1
4.4 1 — — — 1 — — 1
4.6 — 1 — — 1 — — 1
4.8 — — 1 — 1 — — 1
5.0 1 — — — — 1 — 1
5.2 — 1 — — — 1 — 1
5.4 — — 1 — — 1 — 1
5.6 1 — — — — — 1 1
5.8 — 1 — — — — 1 1
v ... vertical strut length (see table, 'Standard heights')
999811302 - 04/2016 15
System description User Information Tunnel system DokaCC
Washer *)
Precision height adjustment by means of:
20mm
15mm
10mm
Bolted
4mm
3mm
2mm
▪ Vertical strut connector DokaCC (50 mm incre-
join
ments)
2 — — — — — 1 2
▪ Packing plates (1 mm increments) 3 — — — — 1 —
▪ Lowering wedge (see section headed 'Adjusting and 4 — — — 1 — — 1
lowering') 5 — — — — 1 1
6 — — — — 2 —
(A)
7 — — — 1 1 —
8 — — — 2 — —
—
9 — — — — 3 —
10 — — 1 — — —
A F 11 — — — 2 1 —
12 — — 1 — — 1
13 — — 1 — 1 — (B) —
14 — — 1 1 — —
15 — 1 — — — —
f
B 16 — — 1 1 — 1 2
17 — 1 — — — 1
1 18 — 1 — — 1 —
D
2 19 — 1 — 1 — —
a a a
20 1 — — — — — 1
3
21 — 1 — — 2 — (C)
4 22 1 — — — — 1
23 1 — — — 1 —
E C 24 1 — — 1 — —
f [mm]
98113-209-09
25 — 1 1 — — — —
26 1 — — — 2 —
a ... 50 mm
27 — 1 1 — — 1
f ... packing plate thickness (0 - 49 mm)
(see table, 'Selection of packing plates') 28 1 — — 2 — —
29 1 — — — 3 —
A System beam DokaCC
30 — 2 — — — — 1
B Packing plate(s)
31 — 1 1 — 2 —
C Vertical strut connector DokaCC
32 — 2 — — — 1
D Connecting pin DokaCC D60 140 (D)
33 — 2 — — 1 —
E Vertical strut DokaCC 34 — 2 — 1 — —
F Bolted join 35 1 1 — — — — —
(see table, 'Selection of packing plates') 36 1 — 1 — 2 —
37 1 1 — — — 1
38 1 1 — — 1 —
WARNING
39 1 1 — 1 — —
Eccentric load application is prohibited! 40 2 — — — — — 1
➤ The axis of the vertical strut must always be 41 1 1 — — 2 —
in line with the axis of the bolted join. 42 2 — — — — 1
(E)
43 2 — — — 1 —
44 2 — — 1 — —
G H G 45 — 3 — — — — —
46 2 — — — 2 —
47 2 — — 1 1 —
48 2 — — 2 — —
(F) —
49 — 3 — 1 — —
*) Number of washers d=3 mm needed additionally
A Screw-set M20x65 8.8
B Screw set for System beam DokaCC 10.9
C Kneebrace screw-set SL-1
D Screw-set M20x90 8.8
E Screw-set M20x100 8.8
F 4 x hexagon screw M20x110 8.8
H 4 x hexagon nut M20 8
98113-209-08 98113-209-13
8 x washer 21 DIN EN 14399-6
G Axis of bolted join
H Axis of Vertical strut DokaCC
16 999811302 - 04/2016
User Information Tunnel system DokaCC System description
98113-209-23
☞▪ Important note:
Always plan one longitudinal beam above
each strut connection.
▪ The need for additional longitudinal beams
depends on the spacing between the diago-
nal strut connectors and the acting axial
force Nperm..
b b b b
A A A A A
F G D
98113-200-20
999811302 - 04/2016 17
System description User Information Tunnel system DokaCC
Pos. 2 Pos. 3
98113-209-04 98113-209-05
A
possible
girderframe spacing a [m]
Waling (A)
Pos. Pos.
Pos. 1a Pos. 1b
98113-208-12
2 3
1.05 1.15 1.10 1.20 Top100 tec waling WU14 0.75m
1.30 1.40 1.35 1.45 Top100 tec waling WU14 1.00m
1.55 1.65 1.60 1.70 Top100 tec waling WU14 1.25m
a 1.80 1.90 1.85 1.95 Top100 tec waling WU14 1.50m
2.05 2.15 2.10 2.20 Top100 tec waling WU14 1.75m
a ... possible girderframe spacing
2.30 2.40 2.35 2.45 Top100 tec waling WU14 2.00m
2.55 2.65 2.60 2.70 Top100 tec waling WU14 2.25m
2.80 2.90 2.85 2.95 Top100 tec waling WU14 2.50m
3.05 3.15 3.10 3.20 Top100 tec waling WU14 2.75m
3.30 3.40 3.35 3.45 Top100 tec waling WU14 3.00m
3.80 3.90 3.85 3.95 Top100 tec waling WU14 3.50m
☞ Important note:
Collision between the waling and the bolted
join of the longitudinal beam connector!
Pinning in the position shown here is not possi-
ble!
98113-209-06
18 999811302 - 04/2016
User Information Tunnel system DokaCC System description
a
C C
a
C
98113-208-09
a
98113-200-24
a ... possible girderframe spacing
a ... ≤ 3.0 m
possible C Spindle strut T7
girderframe spacing a Diagonal strut (B)
☞▪
[m]
1.70 Diagonal strut DokaCC 0.60m Important note:
2.10 Diagonal strut DokaCC 1.00m The vertical struts have to be held in the
2.70 Diagonal strut DokaCC 1.60m weak profile direction at least every 3.0 m to
3.30 Diagonal strut DokaCC 2.20m prevent buckling!
3.90 Diagonal strut DokaCC 2.80m ▪ For detailed statics verification, consult the
Statics department responsible!
999811302 - 04/2016 19
System description User Information Tunnel system DokaCC
98113-208-15
A Supporting construction
B Lowering wedge 1000kN 98113-210-02
☞
Close-up of lowering wedge
Important note:
Use lowering wedges in the horizontal position
only!
▪ If the invert forms a gradient, use flat iron
h
98113-209-31
98113-210-04 98113-210-05
A Adjusting rail distance piece to allow for invert gradient (flat iron
packer)
20 999811302 - 04/2016
User Information Tunnel system DokaCC System description
98113-211-03
C
G
Turning adjusting
Turning adjusting
screw counter-
screw clockwise
clockwise
D
F
H
E
a a
98113-208-14
98113-211-01
98113-211-01
F Lifting-mechanism frame DokaCC
G Hydraulic cylinder SL-1
H Diagonal strut DokaCC
B A A B A B
Max. stroke of the lifting mechanism
Close-up of position indicator:
a ... max. 50 mm
A Rail axis
B Lifting mechanism axis
C Adjusting screw
D Position indicator
999811302 - 04/2016 21
System description User Information Tunnel system DokaCC
Load transfer
☞▪ Important note:
The loads from the roof slab transmitted into
Squared-timber support
the system beams are transferred by the ver- The squared timber is sized on the basis of squared
tical and diagonal struts to the load distribu- timber length a and load Nperm. acting on the support.
tors.
▪ The loads from the load distributor are trans-
98113-210-03
ferred by the anchor to the rail distance piece
and by a squared timber support provided by
site to the side wall kicker.
▪ The structural designer needs advance infor-
mation about the loads to be transmitted into
the wall kicker, in order to prevent overload
damage to the wall kicker and foundation!
▪ Releasing the lowering wedge (stripping the a
roof slab) permits, in combination with the
load-transferring construction (tie rods /
squared-timber supports), simultaneous
Example: Squared timber C24 (by site)
diminution of the horizontal and vertical
loads. 350
A
300
250 B
200
Nperm. [kN]
150
D
100 E
50
0
0.5 1 1.5 2 2.5 3 3.5 4
a
Squared timber length a [m]
C
A Squared timber 18x18 cm
E
G F B Squared timber 16x16 cm
C Squared timber 14x14 cm
F D Squared timber 12x12 cm
G
E Squared timber 10x10 cm
B
A
D Alternative to using squared timber supports:
98113-210-01
▪ Shear bolt
α ... 60 - 70° ▪ Tie together the two opposite load distributors or rail
A Squared timber support (by site) distance pieces.
B Wall kicker
C Load distributor DokaCC Note:
D Rail distance piece DokaCC For using a solution that is an alternative to squared
E Tie rod 20.0mm timber support, consult your Doka technician!
F Bracing bolt DokaCC
G Hexagon nut 20.0
22 999811302 - 04/2016
User Information Tunnel system DokaCC System description
D E
D E
B
B
A C A
C 9732-249-01
9729-246-01
A Top 50 element
A Top 50 element B Tie-rod 20.0
B Tie-rod 15.0 C Super plate 20.0 B
C Super plate 15.0 D Plastic tube 26mm
D Plastic tube 22mm E Universal cone 26mm
E Universal cone 22mm
Tie rod 20.0mm:
Tie rod 15.0mm: Permitted capacity, allowing a 1.6 : 1 factor of safety
Permitted capacity, allowing a 1.6 : 1 factor of safety against failure: 220 kN
against failure: 120 kN Permitted capacity to DIN 18216: 150 kN
Permitted capacity to DIN 18216: 90 kN
999811302 - 04/2016 23
System description User Information Tunnel system DokaCC
Traveller systems
Repositioning with the Flanged wheel
SL-1
For rail-guided repositioning of heavy-duty supporting
units.
▪ Can be either self-powered or travelled with suitable
towing machines.
▪ There must be a firm (e.g. concrete) base that is
capable of supporting the load.
System dimensions:
98113-208-13
a ... 470 mm
b ... 400 mm
Design/construction of rail
A B
a
98113-200-25
24 999811302 - 04/2016
User Information Tunnel system DokaCC System description
F
C
C D
D
F H
E
A
I D G
98113-208-03 98113-217-02
999811302 - 04/2016 25
System description User Information Tunnel system DokaCC
Safety features
Platforms Connection of platforms to the Vertical strut
DokaCC (transverse platform)
Connection of platforms to the Vertical strut e.g. with Longitudinal beam connector WU14 DokaCC
DokaCC (longitudinal platform) bottom.
H D E
98113-208-16
B G
A Vertical strut DokaCC
D Longitudinal beam connector WU14 DokaCC bottom
H F E Multi-purpose waling WS10
F Connecting pin 10cm with Spring cotter 5mm
E
C H Screw-set M20x160 8.8
98113-208-02
26 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
Regular sequence
General instructions on typical use
▪ The depictions and the description of the procedure
set out below are based on use for rectangular tun-
nel cross-sections, but they also apply by analogy to
use for circular tunnel cross-sections.
▪ Sections that apply only to circular tunnel cross-sec-
tions are marked appropriately.
▪ Depending on the project, the actual construction
and the procedure might not be as set out in the
description in this document.
▪ Always proceed in accordance with the execution
drawing or assembly drawing, or consult your Doka
technician.
WARNING
Danger of crushing!
➤ Before all formwork closing/opening
motions, and before the tunnel formwork
traveller is repositioned, a check must be
performed by at least 2 people to ensure that
there are no persons or potential collision
points within the range of motion.
➤ The operators must maintain sight or radio
contact to the trained watchmen at all times.
➤ 'Passenger transportation' is forbidden! (with
the exception of the operator during hydrau-
lic repositioning).
☞▪ Important note:
The first time of putting into service of the
hydraulic system must be supervised by a
Doka supervisor or other authorised techni-
cian.
▪ During closing, stripping and repositioning of
the formwork, the only persons allowed in
the vicinity of the traveller are the trained per-
sonnel tasked with carrying out the reposi-
tioning operation.
999811302 - 04/2016 27
Regular sequence User Information Tunnel system DokaCC
G F E D
A Formwork element
B Tie rod 15.0mm
C Super plate 15.0
D Hexagon nut 15.0
E Fixing bracket SL-1
F Cone screw B 7cm
G Universal climbing cone 15.0
98113-202-08
Removing uplift protection (optional
for circular cross-section)
Back-anchoring through form-tie hole
➤ Remove the Super plate and unscrew the tie rod
➤ Unscrew and remove the tie rod.
from the Anchoring cone 20.0.
➤ Remove threaded rod (or Tie-rod 20.0mm) and Fix-
ing brackets SL-1.
98113-202-09
C
A
F E D
A
B
A Formwork element
B Tie rod 15.0mm C
28 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
C
B
98113-208-03
1 2
A
C
98113-208-05 98113-208-06
98113-208-17
999811302 - 04/2016 29
Regular sequence User Information Tunnel system DokaCC
98113-202-10
B
A Super plate
B Tie rod
98113-210-12
30 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
98113-218-01
98113-210-11
98113-218-02
98113-210-10
999811302 - 04/2016 31
Regular sequence User Information Tunnel system DokaCC
Striping the formwork from the roof-slab ➤ Remove the lowering wedges and the rail distance
(lowering) pieces.
Lashing straps (e.g. Lashing strap 3.7m Art.
☞ Caution on gradients:
Secure the carriage with a counteracting force!
No. 502783090) can be used to secure the rail
distance pieces to the formwork traveller during
the repositioning operation.
Permissible overall gradient of the lifting mechanism:
▪ Permitted lateral gradient: 8%
▪ Permitted longitudinal gradient: 8%
(permitted lateral and longitudinal gradients can occur at the same time)
98113-202-11
98113-202-12
98113-208-19
32 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
Repositioning
Repositioning the inside formwork
98113-202-04
Note:
For repositioning the outside formwork see the section
headed 'Stripping, repositioning and closing the outside
formwork'!
999811302 - 04/2016 33
Regular sequence User Information Tunnel system DokaCC
Note:
Depending on what type of back-anchoring or uplift pro-
tection is planned, the relevant Doka User Information
☞▪ Important note:
There must be a flat, firm (e.g. concrete)
base that is capable of supporting the load.
booklets or Fitting Instructions must be observed. ▪ Caution on gradients:
Secure the carriage with a counteracting
force!
98113-202-12
34 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
☞
➤ Install the bracing bolts in the load distributor and in
Important note: the rail distance piece.
➤ It is absolutely essential to proceed in the ➤ Work the Tie rods 20.0 into the bracing bolts and
correct sequence for positioning! secure with Hexagon nuts 20.0 (omit this step if the
➤ Position squared timber support, rail distance piece rail distance piece was secured with a lashing strap
and lowering wedge in the sequence shown (1-3) for repositioning).
(see the section headed 'Load transfer'). ➤ Tighten the tie rods.
3
C
B
1 2
A
98113-210-09
98113-208-18
A Squared-timber support
B Rail distance piece DokaCC ➤ Retract the lifting rams of the hydraulic lifting mech-
C Lowering wedge 1000kN anisms. The tunnel formwork traveller should now be
standing on the lowering wedges.
Check that the entire tunnel formwork traveller
is correctly aligned!
98113-208-18
98113-202-11
999811302 - 04/2016 35
Regular sequence User Information Tunnel system DokaCC
CAUTION
WARNING
➤ Do not use the hydraulic cylinders to press
➤ No third persons are allowed anywhere near the formwork against the previously cast
the formwork elements while these are being concrete (wall kicker). (This might push the
tilted outward. The operators must always tunnel formwork traveller sideways).
stay in sight or radio contact.
➤ Start up the hydraulic unit (as described in the Oper-
Mechanical: ating Instructions booklet entitled 'Hydraulic unit for
➤ Use the spindle struts or winches to tilt the wall ele- forming-operations').
ments up to, and press them against, the wall kicker. ➤ As applicable, open the appropriate ball cocks at the
hydraulic distributors.
➤ Use the hydraulic cylinders to tilt the wall panels up
against the wall kicker.
98113-210-10
98113-218-02
98113-210-11
98113-218-01
36 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
☞▪
Note:
Important note:
The outside formwork is (usually) not repositioned until
after the inside formwork has been set up and the wall Do not exceed the max. element weight.
reinforcement is fully installed! ▪ If necessary, divide formwork panels as per
the utilisation plan.
▪ It is absolutely essential to use a load bal-
ancer when lifting a large gang-form with the
crane – check the maximum lifting capacity
of crane and all repositioning equipment.
▪ Do not detach the elements from the crane
until the two bottom rows of formwork ties
have been installed.
➤ Attach the gang-form to the crane by means of the
hoisting points as per the drawing.
➤ Move the gang-form to the next casting section.
➤ Working at ground level, install the two bottom rows
of formwork ties or securely position the gang-form
on the base slab with panel struts.
999811302 - 04/2016 37
Regular sequence User Information Tunnel system DokaCC
98113-224-07
C
B
98113-224-05
98113-221-02
D
98113-221-09
98113-224-04
38 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
➤ Advance the outside formwork to the next casting Fitting the anchors
section.
➤ Install the wall anchors.
98113-202-10
B
A Super plate
B Tie rod
98113-221-06
Follow the directions in the 'Quick-release nut
Closing the outside formwork 20.0' Fitting Instructions.
➤ Operate the winch to tilt the formwork toward the
reinforcement (spacers).
➤ Fully retract the solid tire wheel and remove the
plank from the reinforcement.
98113-224-03
999811302 - 04/2016 39
Regular sequence User Information Tunnel system DokaCC
3
1 2
B
A
98113-208-08 98113-208-07
98113-217-02
98113-208-03
➤ Lift the stop-end panel into place with the crane.
➤ Push the multi-purpose waling of the stop-end form-
A Stripping lever DokaCC work on the anchor to the wall formwork (e.g. Eye-
B Positioning unit DokaCC lug anchor 15.0) and secure with Super plates 15.0.
C Tie rod 15.0mm
D Connecting pin 10cm + Spring cotter 5mm
E Stop-end panel + Spindle strut T7 75/110cm
F Super plate 15.0
98113-210-12
40 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
G F E D
A Formwork element
B Tie rod 15.0mm
C Super plate 15.0
D Hexagon nut 15.0
E Fixing bracket SL-1
F Cone screw B 7cm
G Universal climbing cone 15.0
F E D
B
B
C
A Formwork element
B Tie rod 15.0mm
98113-224-01
C Super plate 15.0
D Hexagon nut 15.0 A Tie rod 20.0mm
E Fixing bracket SL-1 B Super plate 20.0 B
F Threaded rod 20.0mm or Tie-rod 20.0mm C Anchoring cone 20.0
999811302 - 04/2016 41
Regular sequence User Information Tunnel system DokaCC
Pouring
Before pouring
Check the installed parts:
▪ Are all the spindle struts free of play?
▪ Are all the lowering wedges correctly positioned
(± 5 mm) and free of play?
▪ Squared timber supports between rail distance
pieces and wall kicker installed and free of play?
Check the anchoring components:
▪ Are all wall anchors installed/tightened?
▪ Are the ties for back-anchoring installed/tightened?
▪ Are the ties for uplift protection installed/tightened?
(circular tunnel cross-section)
▪ Is the Positioning unit DokaCC secured with eye-lug
anchors and Super plates?
▪ Is the anchorage between the rail distance piece and
the load distributor installed/tightened?
☞ Important note:
The stipulated concrete pressures, as stated in
the utilisation plan, must be complied with in
every case!
98113-202-07
42 999811302 - 04/2016
User Information Tunnel system DokaCC Regular sequence
999811302 - 04/2016 43
Assembly instructions User Information Tunnel system DokaCC
Assembly instructions
General instructions for site-erection
Scope of this document Tools
▪ The depictions and the description of the procedure See the section headed 'List of tools needed for assem-
set out below are based on use for rectangular tun- bly' for a detailed list of necessary tools.
nel cross-sections, but they also apply by analogy to Have one torque wrench with a range of adjustment
use for circular tunnel cross-sections. from 75 - 400 Nm and one torque wrench with a range
▪ Sections that apply only to circular tunnel cross-sec- of adjustment up to 800 Nm ready to hand.
tions are marked appropriately.
▪ Depending on the project, the actual construction
and the procedure might not be as set out in the Setting up the assembly area
description in this document.
▪ Always proceed in accordance with the execution ➤ Arrange for the assembly area to be measured up by
drawing or assembly drawing, or consult your Doka the surveyor. The basis for this is given by the
technician. approved assembly plan.
➤ The loads to be expected at the support points can
be taken from the Doka drawings (e.g. for lowering-
Unloading / intermediate storage area wedges, lifting mechanisms, formwork bracing etc.).
➤ Check the clear width between the rails.
▪ The size of the unloading and intermediate storage ➤ Temporary foundations must be checked and
area must be specified in advance (length x width). approved by the site.
This prevents the assembly work being delayed by
long transport distances or by lack of storage space!
▪ Find out whether base slabs are suitable as interme- Bolted joints
diate storage areas and can be used for this pur-
pose.
All standardised joins are statically dimensioned as
shear / bolt-bearing joins.
Crane capacity and position
▪ When stationary cranes (e.g tower cranes) are used, WARNING
the site must ensure that the storage locations Risk of fracture if unsuitable bolts are used.
(unloading and intermediate storage area) and ➤ Use only the specified 'Screw-sets', without
assembly zones (formwork, assembly bench) lie exception.
within the cranes' range of action. ➤ Use NEW 'Screw-sets' every time the equip-
▪ It must still be possible to lift the loads even when ment is re-assembled.
longer crane outreach is required! ➤ The bolted joints must comply with
▪ The lifting accessories may be used only by experi- EN 1090-2.
enced, trained persons ('crane slingers'). ➤ In the case of 'Screw-sets' with 2 washers
▪ The weights of the components to be lifted are given per bolt:
in the 'Component overview' section of this User Fit one washer next to the nut, and the other
Information booklet. In cases where custom compo- washer next to the bolt-head.
☞
nents have been planned, the weights are stated on
the assembly plan. Important note:
Any attempt to lubricate the screws, e.g. with
Depending on which formwork system is being WD40 spray or the like, is not permitted!
used, follow the directions in either the 'Large-
area formwork Top50' or the 'Large-area form- The Offset pin SL-1 makes it easier to align the
work Top 100 tec' User Information booklet. drilled holes during assembly.
Assembly bench
Fall-protection measures
▪ Pre-assemble the formwork elements on an assem-
bly bench. Its size and load-bearing capacity will
The site must provide the following equipment for car-
depend on the project in question.
rying out the assembly and dismantling work:
▪ a suitable mobile scaffold tower
▪ use personal protective equipment to protect against
falls
44 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly instructions
The sections headed 'Pre-assembly' and 'Assembly' A distinction is made between 2 types of pre-loaded
contain instructions on which activities these items of joints:
safety equipment are compulsory for. ▪ joints with reduced pre-loading force Fp,C*
☞ The basic rule is that whenever there is any
temporary falling-hazard in the course of
assembly operations, a personal fall-arrest sys-
▪ joints with full pre-loading force Fp,C
999811302 - 04/2016 45
Assembly instructions User Information Tunnel system DokaCC
46 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly instructions
999811302 - 04/2016 47
Pre-assembly User Information Tunnel system DokaCC
Pre-assembly
Girderframes
System beam Required tightening torque:
M20: 450 Nm (45 kgm)
☞
M24: 800 Nm (80 kgm)
Important note:
Follow the 'General instructions on high-strength
➤ Make sure that the trestles are steady and
joints of strength grade 10.9' in the section headed
strong enough to take the load!
'Assembly instructions'.
The weights of the components are given in the
'Component overview' section of this User ➤ Bolt the mounted parts to the system beam.
Information booklet. In cases where custom
components have been planned, the weights Vertical strut connector Diagonal strut connector
are stated on the assembly plan.
➤ Prepare the trestles to carry the system beams.
In this way the system beams and the mounted parts
E
can be bolted on all sides without having to be turned F G
over. D A A
☞ Important note:
➤ Make sure that the system beams are bolted H
together such that groove (C) in the end
plates of all system beams is always on the 98113-203-10 98113-203-11
same side (beam underside).
Longitudinal beam connector top Special support plate*)
➤ Lay the System beams DokaCC on the trestles and
bolt the beams together.
K
I J
A
H
A
98113-203-09
98113-203-08
C
Required tightening torque:
A
B 300 Nm (30 kgm)
Note:
98113-203-07
For selection of the packing plate and the necessary
A System beams DokaCC (see the assembly drawings for the threaded fasteners, see the section headed 'Height
lengths) adaptation'!
B Screw set for System beam DokaCC 10.9
48 999811302 - 04/2016
User Information Tunnel system DokaCC Pre-assembly
☞ Important note:
For each girderframe with lifting mechanism,
335 Nm (33.5 kgm)
Angle of additional rotation: 90°
note the following: Follow the 'General instructions on high-strength
▪ The bottommost part of the vertical strut joints of strength grade 10.9' in the section headed
must be a Vertical strut DokaCC 1.60m. 'Assembly instructions'.
▪ The holes in the Vertical strut DokaCC
1.60m are needed for installation of the lift- ➤ Bolt the mounted parts to the vertical strut.
ing-mechanism unit.
- Until the lifting-mechanism unit is Vertical strut DokaCC spindle
Strut connection DokaCC
connection
installed, install the strut connector for
the top spindle strut in the holes in the E H
next vertical strut up.
See the section headed 'Assembling girder- H
frame with lifting mechanism'. A A
F
➤ Prepare squared timbers to lay the vertical struts 98113-209-34 98113-209-20
(height: 200 mm) and the load distributor on (height:
Longitudinal beam connector bottom
135 mm).
➤ Lay the Vertical struts DokaCC on the squared tim-
ber supports and bolt the struts together. G
D
➤ Lay the Load distributor DokaCC on the squared tim-
ber supports and bolt it to the vertical struts. I
98113-209-33
98113-209-16
999811302 - 04/2016 49
Pre-assembly User Information Tunnel system DokaCC
Diagonal strut
➤ Prepare squared timbers to lay the diagonal struts
(height: 140 mm) and the diagonal strut endpieces
on (height: 170 mm).
➤ Lay the diagonal struts and the diagonal strut end-
pieces on the squared timber supports and bolt them
together.
98113-215-01
C
B
98113-209-17
50 999811302 - 04/2016
User Information Tunnel system DokaCC Pre-assembly
98113-209-07 H
A I F
D
E
C
B
98113-209-14
D F
I A
C
E
B G
I
H 98113-203-06
999811302 - 04/2016 51
Pre-assembly User Information Tunnel system DokaCC
Lifting mechanism
➤ Prepare squared timbers as supports (height: min.
100 mm). WARNING
➤ Lay the Lifting ram DokaCC and the flanged wheel Risk of lifting ram falling out!
on the squared timber supports and bolt them ➤ For transport of the lifting-mechanism unit,
together. always secure the lifting ram to the lifting-
mechanism frame with a lashing strap (by
B A site)!
➤ Work the lifting ram complete with the flanged wheel
C into the lifting-ram guide of the lifting-mechanism box
and secure it with a lashing strap.
98113-219-02
D
E
H
B
D
F
98113-219-03
98113-219-01
98113-219-04
52 999811302 - 04/2016
User Information Tunnel system DokaCC Pre-assembly
98065-214-04 A
98113-219-06
999811302 - 04/2016 53
Pre-assembly User Information Tunnel system DokaCC
98113-207-01
The locking mechanism must engage.
B
A with Positioning unit DokaCC
A
➤ Push the Positioning unit DokaCC on to the WU14
waling and secure it with 2 Eye-lug anchors 15.0 and
Super plates.
➤ Pin the connecting pins for striking and setting up
E and secure with spring cotters.
98113-207-02
J H J A
A Top100 tec walings WU14
B Top100 tec formwork element connector
b
a I
E Connecting pin 10cm + Spring cotter 5mm
98113-204-03
platform
a ... 650 mm
b ... 300 mm
A Top100 tec walings WU14
D Connecting pin 10cm + Spring cotter 5mm
G H Positioning unit DokaCC
A I Tie rod 15.0mm
J Super plate 15.0
K Eye-lug anchor 15.0 without tie rod
F C
98113-204-02
D
A Top100 tec walings WU14
98113-217-01
C Beam support WS10-WU16
D Connecting pin 10cm + Spring cotter 5mm A Top100 tec walings WU14
E 0.5 x Screw-set M20x65 8.8 D Connecting pin 10cm + Spring cotter 5mm
F Railing adapter XP DokaCC L Adjusting plate T
G Handrail post XP
54 999811302 - 04/2016
User Information Tunnel system DokaCC Pre-assembly
Formwork elements
For the specifics of the procedure for installing Initially, install only 2-3 element connectors.
wall and slab formwork elements, follow the This makes the elements easier to fit together.
directions in the assembly drawings and in the Do not mount the remaining connectors until
'Large-area formwork Top 50' or 'Large-area the elements have been finally assembled.
formwork Top 100 tec' User Information book-
let, as applicable to the formwork system used!
Note:
The work steps described below are based on the pre-
assembly of wall elements.
For installation of attachments such as platforms, see
the assembly drawings and/or the appropriate section
detailing the assembly procedure!
98113-216-03
➤ Work the tie rod into position over the length of the
element.
➤ At each side of the element, secure the side multi-
purpose walings (for installation of the stop-end
formwork) with Super plates.
C A
98113-216-04
999811302 - 04/2016 55
Assembly User Information Tunnel system DokaCC
Assembly
Positioning rails and supports
98113-200-02
Close-up
98113-200-21
A Rail
B Rail distance piece S49 DokaCC
C Lowering wedge 1000kN (420kN)
56 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
B
D
C C
98113-200-22 98113-200-21
E
A Strut connection DokaCC or SL-1
B Rail distance piece S49 DokaCC
C Express anchor
➤ With the girderframe lying flat, pin the spindle struts 98113-200-03
(top overturning protection) to the strut connection
D Spindle strut (top overturning protection)
on the vertical strut and secure with cotter pins.
E Spindle strut (bottom overturning protection)
➤ Attach tag-lines to the girderframes. This makes
them easier to position at a later stage.
☞ Important note:
➤ Take suitable precautions to fix the lifting ☞ Important note:
➤ The lifting slings are disengaged by a crew
slings so that they cannot slip. member working from the mobile scaffold
➤ Place lifting slings around the girderframe and lift it tower.
into the upright. ➤ Disengage the lifting slings.
WARNING
There is a risk of the mobile scaffold tower
being knocked over when the crane lifts the gir-
derframe into place!
➤ Do not step onto the mobile scaffold tower
until the girderframe unit has been fixed to
the ground with the spindle struts to prevent
overturning.
➤ No third persons are allowed anywhere near
the supporting construction while it is being
crane-handled.
➤ Crane-lift the girderframe to the erection location.
Position it with tag-lines.
➤ Position the girderframe on the lowering wedges.
➤ Pin the spindle struts (bottom overturning protection)
to the load distributor and to the strut connection on
the ground and secure with cotter pins.
999811302 - 04/2016 57
Assembly User Information Tunnel system DokaCC
Mounting further girderframes ➤ Adjust the spindle struts for the second girderframe
to the correct length as per the assembly drawing.
98113-200-04 98113-200-05
Load distributor / WU14 waling Spindle struts / load distributor / vertical strut
F
A
F E
B
D
98113-209-28
98113-209-32
C
C C
98113-209-01
58 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
98113-200-06
999811302 - 04/2016 59
Assembly User Information Tunnel system DokaCC
☞ Important note:
Follow these directions for pre-assembly of the
girderframe:
1
▪ The bottommost part of the vertical strut A
F 3
must be a Vertical strut DokaCC 1.60m.
▪ The holes in the Vertical strut DokaCC D
1.60m are needed for installation of the lift-
ing-mechanism unit.
- Until the lifting-mechanism unit is C
installed, install the strut connector for B 2
the top spindle strut in the holes in the
next vertical strut up.
98113-200-28
WARNING
Risk of lifting ram falling out!
➤ For transport of the lifting-mechanism unit,
always secure the lifting ram to the lifting-
mechanism frame with a lashing strap (by
site)!
D
➤ Lift the pre-assembled lifting-mechanism unit into
position with the crane. A
➤ Bolt the lifting-mechanism frame to the Vertical strut
DokaCC 1.60m together with the strut connection
I
(part of the lifting-mechanism frame) (1).
➤ Bolt the lifting-mechanism box to the load distributor
(2).
➤ Pin the bottom spindle strut to the bottom strut con- H
nection and secure the connection with the cotter pin
(3). J
➤ Swing the top spindle strut toward the bottom strut
connection, pin the two together and secure the con-
nection with the cotter pin (4).
98113-200-08
60 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
Installing extension of the lifting-mechanism ➤ Adjust the spindle struts for the next girderframe to
unit the correct length as per the assembly drawing.
➤ Position the next girderframe on the lowering wedge.
➤ Bolt the diagonal strut DokaCC to the lifting-mecha- ➤ Bolt the girderframe to the Diagonal strut DokaCC,
nism box as an extension and support it on a trestle pin it to the spindle struts and secure the assembly
(height: approx. 740 mm). in position.
98113-200-27
H
A
98113-209-21
999811302 - 04/2016 61
Assembly User Information Tunnel system DokaCC
98113-209-29
E Spindle strut T7
F Lifting-mechanism frame DokaCC
G Connecting pin 10cm + Spring cotter 5mm
98113-200-09
62 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
☞ Important note:
➤ The longitudinal beams are installed by crew
members working from the mobile scaffold
tower.
➤ Transport the pre-assembled longitudinal beams to
the erection location and position them with the
crane.
Check the spacing between the girderframes!
B
98113-200-10
98113-209-23
999811302 - 04/2016 63
Assembly User Information Tunnel system DokaCC
98113-209-30 A
98113-200-11
☞ Important note:
➤ The H20 beams and the deck-boards are
Note:
For directions on installing the ladder system see the
section headed 'Ladder system'
installed by crew members working from the
mobile scaffold tower.
WARNING
Exposed fall-hazard locations!
Danger to life from fatal falls!
➤ Use personal protective equipment to pro-
tect against falls (e.g. Doka personal fall-
arrest set).
➤ Secure Doka beams H20 in beam supports as
shown in the plan.
➤ Mount deck-boards on the Doka beams H20.
➤ Install guard-rail boards or scaffold tubes, as applica-
ble.
98113-200-14
64 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
A
98113-200-19
98113-213-01
Close-up A:
☞ Important note:
➤ Before and after fitting the tie-rod bracing, I
bracing.
B Tie rod 15.0mm
➤ Secure the tie rod to a fixing bracket with two Hexa-
C Hexagon nut 15.0
gon nuts 15.0.
F Fixing bracket SL-1
➤ At the second fixing bracket secure with a Hexagon
G Split nut SL-1 15.0 or Hexagon nut 15.0
nut 15.0 on the inside and a Split nut SL1 15.0 on the
H Fixing bracket SL-1 screw-set
outside and tighten until free of slippage.
I System beam DokaCC
999811302 - 04/2016 65
Assembly User Information Tunnel system DokaCC
unit platform
Note:
Platform specifics can vary on a project-specific basis,
depending on requirements. E
☞ Important note:
➤ The strut connections + eye-lug anchors are
installed by crew members working from the
mobile scaffold tower.
➤ Secure the strut connection to the underside of the H
system beam.
➤ Pin the eye-lug anchor to the strut connection. G G
D F 98113-200-15
A
D Eye-lug anchor 15.0 without tie rod
E Tie rod 15.0mm
C F Connecting pin 10cm + Spring cotter 5mm
G Multi-purpose waling WS10 Top50
B F H Scaffold tube + screw-on coupler
D
E ➤ Mount Doka beams H20.
➤ Attach the deck-boards.
➤ Install a diagonal plank underneath the decking for
98113-200-26 strength!
A System beam DokaCC
B Strut connection DokaCC
C Screw-set M20x160 8.8
D Eye-lug anchor 15.0 without tie rod
E Tie rod 15.0mm
F Connecting pin 10cm + Spring cotter 5mm
66 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
➤ Position the hydraulic unit on the platform. ➤ Mount the handrail-post uprights and guard-rail
boards.
L
K
98113-200-17
98113-200-18
K Hydraulic unit SL-1 V180
L Guard-rail board
M Handrail clamp S
98113-201-01
999811302 - 04/2016 67
Assembly User Information Tunnel system DokaCC
A B
98113-216-01
☞▪ Important note:
Position the crane slings at points approxi-
mately one-fifth of the overall length from
each end of the formwork element
▪ Brace the hoisting points of the formwork
element against one another (e.g. with 98113-201-10
98113-201-09
Max. load:
see the 'Lifting rod 15.0' Operating Instructions
68 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
A D
C
98113-201-11
A Formwork element
B Spindle strut 40/80cm
C Vertical strut DokaCC spindle connector
D Girderframes
98113-201-02
999811302 - 04/2016 69
Assembly User Information Tunnel system DokaCC
98113-205-09
98113-201-05
70 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
WARNING
Exposed fall-hazard locations!
Danger to life from fatal falls!
➤ Use personal protective equipment to pro- E A A
tect against falls (e.g. Doka personal fall-
arrest set).
☞ Important note:
➤ The load suspension device is detached
98113-201-13
98113-201-06
999811302 - 04/2016 71
Assembly User Information Tunnel system DokaCC
WARNING
Danger from suspended load!
➤ Stand off to one side, on the main platform,
when lifting-in the element. Beside the ele-
ment – not beneath the suspended load.
➤ Detach the formwork element from the crane, and
detach the tag-lines.
98113-220-03
98113-220-05
72 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
98113-220-02
999811302 - 04/2016 73
Assembly User Information Tunnel system DokaCC
☞ Important note:
➤ The infills for the wall are installed by crew
members working from the mobile scaffold
tower or the telescopic working platform!
➤ All persons working on installation of the
infills for the roof-slab formwork must use the
appropriate personal protective equipment!
➤ If necessary, do not install the topmost strips
of formwork sheeting (at the middle of the
formwork traveller) until after the outside
formwork has been positioned (fall protec-
tion).
➤ Install the strips of formwork sheeting between the
wall elements.
➤ Install the strips of formwork sheeting between the
roof-slab elements.
➤ At the wall-to-roof-slab transition, install joint plates
as per the drawing and clamp against squared tim- 98113-201-07
ber with Super plates.
98113-201-14
Example: circular tunnel cross-section
98113-220-01
74 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
F
C
I D G
98113-217-02
C Stop-end panel
D Connecting pin 10cm + Spring cotter 5mm
F Scaffold-tube bracing
98113-201-08 G Adjusting plate T
H Spindle strut T7 100/150cm
I Top100 tec walings WU14
with Positioning unit DokaCC
➤ Set the Spindle strut T7 as per the assembly drawing
and pin it to the WU-14 longitudinal section.
➤ Lift the stop-end formwork element and transport it to
the installation location.
C ➤ Pin the stop-end formwork element to the Adjusting
D plate T and support it with the Spindle strut T7
installed beforehand.
B
➤ Install the scaffold-tube bracing.
F
E
A Mounting the wall stop-end formwork
Note:
For directions on installing the stop-end formwork see
the section headed 'Closing the formwork".
98113-208-03
999811302 - 04/2016 75
Assembly User Information Tunnel system DokaCC
☞▪ Important note:
Do not exceed the max. element weight.
▪ If necessary, divide formwork elements as
per the utilisation plan.
▪ It is absolutely essential to use a load bal-
ancer when lifting a large gang-form with the
crane – check the maximum lifting capacity
of crane and all repositioning equipment.
▪ Do not detach the elements from the crane
until the two bottom rows of formwork ties 98113-205-09
have been installed.
➤ Attach the gang-form to the crane by means of the
hoisting points as per the drawing and transport it to
the place of use.
➤ Working at ground level, install the two bottom rows
of formwork ties or securely position the gang-form
on the bottom slab with panel struts.
76 999811302 - 04/2016
User Information Tunnel system DokaCC Assembly
98113-223-01
98113-221-07
999811302 - 04/2016 77
Assembly User Information Tunnel system DokaCC
C D
98113-225-05
H
98113-225-04
78 999811302 - 04/2016
User Information Tunnel system DokaCC Dismantling
Dismantling
The tunnel formwork traveller is dismantled in the oppo-
site order from that in which it was assembled.
The stability of the individual components must be
ensured during every phase of the dismantling opera-
tions.
999811302 - 04/2016 79
Maintenance and troubleshooting User Information Tunnel system DokaCC
Hydraulic drive SL-1 Check the gear-oil level in the If necessary, top up the gear oil as shown in
sightglass the 'Hydraulic drive SL-1' Operating Instruc-
tions.
If the oil level is too low, contact the respon-
sible Doka branch.
1x per month Lifting-mechanism box DokaCC Relubricate the transverse- It is not permissible to have the form-
or if smooth running is (transverse adjustment) adjustment mechanism between work traveller standing on the travelling
impeded box and guide unit as shown on gear while this operation is in progress!
the info sticker (with Anti-Seez Dealing with coarse soiling (sand, dirt):
Doka ID n° 047110) ▪ Loosen the guide screws and completely
unscrew the guide unit.
▪ Clean the surfaces with a scraper, and
re-grease them.
1x per month Lifting ram DokaCC 220kN Relubricate the lifting-rams as Where coarse soiling (sand, dirt) has
or if squeaky noises occur shown on the info sticker (with occurred, clean the lifting-rams with a
during lifting Anti-Seez Doka ID n° 047110) scraper and re-grease them.
After 100 operating hours Hydraulic drive SL-1 Change the gear oil Follow the maintenance instructions given
(distance travelled 6 km) in the 'Hydraulic drive SL-1' Operating
or Instructions.
1x per year If the oil level is too low, contact the respon-
sible Doka branch.
1x per year Lowering cylinder SL-1 250kN Change the oil as shown in the 'Lowering cylinder SL-1
250kN' Operating Instructions
Carry out annual inspection in consultation with the responsible Doka
Branch
80 999811302 - 04/2016
User Information Tunnel system DokaCC Maintenance and troubleshooting
General instructions:
Only use oil of the correct quality and misci-
bility. Only pump oil into the reservoir
through a filter (not directly from the drum).
Order replacement filters in good time
(return-flow and aeration filters). Order the
seals needed for the oil-change in good
time.
When changing the oil or Change the return-flow filter By making the oil very viscous, very low out-
if the 'Filter clogged' indica- side temperatures may cause the soiling
tor lights up gauge to light up in error. For this reason,
bring the oil up to operating temperature. If
the indicator stays lit up, change the filter
(before the next lifting operation – in consul-
tation with the responsible Doka branch).
When changing the oil. Change the aeration filter
If the oil level falls below the Top up with hydraulic oil See the note on 'Oscillating volume' in the
minimum. Hydraulic unit point headed 'Change the hydraulic oil'.
cuts out automatically. If the oil level is too low, contact the respon-
Control lamp 'Oil level < sible Doka branch.
min.' lights up.
☞ Important note:
If there are clear signs of damage to compo-
nents, the responsible Doka branch must be
notified immediately.
999811302 - 04/2016 81
Maintenance and troubleshooting User Information Tunnel system DokaCC
Before every time of using Winch Do a sight-check Look out for any signs of damage and visi-
ble deformation. Damaged or deformed
winches and mounted parts that do not
meet the following criteria must be with-
drawn from use immediately:
▪ Crack-free and notch-free welds
▪ No deformation
▪ Rating plate in place and clearly legible
▪ Safety catch must function when tested
in unloaded state
Every week Lowering wedge SL-1 420kN or Do a sight-check Lowering-shoes and lowering-wedges do
1000kN not need any particular maintenance. How-
ever, if they suffer any permanent deforma-
tion, they must be exchanged or repaired.
Keep the lowering-wedges grease-free, and
always degrease them immediately if any
grease gets onto them.
If the cheek plates are greased, there is a
risk of the tie rod breaking!
After 5 casting sections Super plate 15.0 Check for increased play in the Change the Super plate if it is difficult to
or thread turn, or if there is increased axial or radial
1x per month play in the thread.
1x per month Winch Grease the pinion-rack The pinion-rack must be extended when it is
greased.
Spindle strut T6 / T7 Relubricate the thread (only if it is Where coarse soiling (sand, dust) has
difficult to turn) occurred, clean the thread and grease it
with Anti-Seez (Doka ID n° 047110).
98113-222-01
82 999811302 - 04/2016
User Information Tunnel system DokaCC Maintenance and troubleshooting
98113-213-02
Scaffold-tube braces Inspect the scaffold-tube braces Have the couplers been tightened?
on the spindle struts, and (where ▪ Clamping connections (swivel couplers,
applicable) also on heavy-duty screw-on couplers)
props etc.
▪ Bolted joints of screw-on couplers
Joints between load-bearing compo- Inspect the bolted joints of the Check the bolted joints on load-bearing
nents supporting construction. components (these joints are pre-loaded to
300 Nm on assembly, and then marked with
blue coloured spray). Using a ratchet and
box nut, check whether the joints can easily
be loosened (but do not undo them)!
98113-203-12
Permanent deformations caused by Check for permanent deforma- Inspect the supporting construction for
e.g. exceeding the permitted form- tion in the supporting construc- increased play and/or permanent deforma-
work load. tion or on the formwork. tion:
▪ Increased play in the connecting plates?
(Causes the joints between the form-
work sheets to widen).
▪ Bent load-bearing components (walings,
spindles, etc.)
If any of these parts are deformed, report
this immediately to the responsible Doka
branch.
999811302 - 04/2016 83
Maintenance and troubleshooting User Information Tunnel system DokaCC
Troubleshooting
84 999811302 - 04/2016
User Information Tunnel system DokaCC Maintenance and troubleshooting
999811302 - 04/2016 85
General remarks User Information Tunnel system DokaCC
General remarks
Hydraulic system
Hydraulic unit SL-1 V180 Hydraulic forming-operations
Is supplied to the site ready for operation. The Hydraulic unit SL-1 V180 is also used for raising,
lowering and stripping out Doka formwork systems with
the aid of hydraulic cylinders.
Note:
If the unit needs to be lifted, it should only be slung Note:
from, and lifted by, the crane hoisting lugs provided.
The European Directive for Machines (2006/42/EC)
stipulates that all formwork systems that are moved
either electrically or hydraulically are subject to manda-
tory CE labelling requirements. For this reason, a risk
assessment and an Operating Instructions manual
must be drawn up for the entire system, in every case.
92840-808
B
Follow the directions in the Operating Instruc-
tions!
9266-123
Up to 2 Hydraulic drives SL-1 can be connected to the Due to the many different strokes and load ratings for
Hydraulic unit SL-1 V180. hydraulic cylinders used in the formwork technology
field, it is difficult or impossible to standardise cylinders.
Note: This is why custom cylinders are often used.
Hydraulic tubes are not included in the scope of supply.
2 pairs of hydraulic tubes are needed for each hydraulic Planning note
drive.
☞
Pair of hydraulic tubes 7.50m 580874000
Pair of hydraulic tubes 10.00m 580875000 When the distribution valves are being switched
over, the switch passes through an intermedi-
ate position which may cause unintentional low-
ering of the load.
Remedy: Fit lowering brake-valves to the load-
side of the hydraulic cylinders.
86 999811302 - 04/2016
User Information Tunnel system DokaCC General remarks
9759-293-01
A Hydraulic cylinder
C Lowering brake-valve
9759-292-01
A Hydraulic cylinder
B Hydraulic distributor
C Lowering brake-valve
999811302 - 04/2016 87
General remarks User Information Tunnel system DokaCC
Hydraulic unit
☞▪ Important note:
The position of the hydraulic unit will mainly
depend on the available space, and should
thus be planned as needed for each individ-
ual project.
▪ Position the hydraulic unit so that the opera-
tor is always looking in the direction of travel
and has a clear view of all moving parts! If
this is not possible, a 2nd person is needed,
who must stay in radio contact with the oper-
ator.
Hydraulic cylinder
☞ Important note:
The size and position of the hydraulic cylinders
must be such that no collisions can occur when
slewing motions are carried out.
Hydraulic hoses
☞ Important note:
➤ Do not kink the hoses.
➤ Arrange the hoses so that nothing rubs
against them during the motion sequences.
(Risk of hoses bursting because of mechan-
ical damage).
➤ In the area near the hydraulic cylinders,
arrange the hoses so that there is sufficient
length of hose available even when the cylin-
der is fully extended (make loops).
➤ Arrange the hydraulic hoses on the tunnel formwork
traveller and fasten them with hose clamps and/or
cable ties.
Note:
See the section headed 'Lifting mechanism' in the
instructions for pre-assembly
88 999811302 - 04/2016
User Information Tunnel system DokaCC General remarks
Ladder system
For safe up-and-down access to the platforms. Pre-assembly
☞▪
Note:
The Ladder system XS must be implemented in such a Important note:
way that all national regulations are complied with. Only pre-assemble max. 2 ladder segments
at a time. (Total length max. 6.7 m).
➤ Pre-assemble each ladder unit on the ground
CAUTION
(placed on two timber supports or on Doka beams).
➤ The Ladders XS may only be used as part of
the XS system, and must NOT be used sep- D
arately (as "lean-to" ladders).
F
98065-225-01
C
A
Tr625-201-04
Close-up
C
B
Tr625-201-03
999811302 - 04/2016 89
General remarks User Information Tunnel system DokaCC
Permanently fixed ladder extension ➤ Fix the Ladder cage XS 1.00m (F) onto the next
➤ Insert the Ladder extension XS 2.30m into the available rung. The safety latches (J) prevent the
uprights of the System ladder XS 4.40m, with its cage being accidentally lifted out. Add further Ladder
hooking brackets facing downwards, and fasten it. cages XS 1.00m, in each case fixing them onto the
Tighten the screws only very slightly! next available rung.
A
C
F
Tr625-202-01
Screws (C) are included in the scope of supply of the System ladder
XS 4.40m and the Ladder extension XS 2.30m.
J
A System ladder XS 4.40m
B Ladder extension XS 2.30m Tr625-201-02
C Screws, width-across 17 mm
☞ Important note:
➤ Always observe all relevant safety regula-
the procedure might not be as set out in the description
in this document.
▪ Always proceed in accordance with the final drawing
tions applying to the use of the Ladder cage
XS in the country in which you are operating or assembly drawing, or consult your Doka techni-
(e.g. in Germany: BGV D 36). cian.
➤ Attach the Ladder cage exit XS (the bottom of the
cage must always be at the same height as the plat- WARNING
form). The safety latches prevent the cage from Exposed fall-hazard locations!
being accidentally lifted out. Danger to life from fatal falls!
➤ Use personal protective equipment to pro-
tect against falls (e.g. Doka personal fall-
arrest set).
D
Installing the connectors on the supporting
construction
➤ With the multi-purpose waling laid flat on the ground,
pin the Connector XS DM/SL-1 into the waling.
D
J B
A
98065-225-02
C
D Ladder cage exit XS
J Safety latch (lift-out guard)
98065-214-05
A Connector XS DM/SL-1
B Multi-purpose waling WS10 Top50
C Connecting pin 10cm
D Spring cotter 5mm
90 999811302 - 04/2016
User Information Tunnel system DokaCC General remarks
➤ Attach the multi-purpose waling with the pre-assem- Fixing the ladder
bled ladder connector to the crane, transport the
assembly to the supporting construction and install it. ➤ Lift in the Ladder system XS and fasten it to the bot-
tom Connector XS DM/SL-1. (See 'Top connector'
Top connector secured to the multi-purpose waling for step-by-step instructions).
of the working platform, for example with tie rod
➤ Pull out the push-in bolt at the top connector, and
and Super plate:
pivot the two safety hooks out of the way.
➤ Close the safety hooks.
A
➤ Insert the push-in bolt into whichever rung of the lad-
B der is suitable for the height of the platform, and
secure it with a linch pin.
C 98065-205-07
98065-226-02
999811302 - 04/2016 91
General remarks User Information Tunnel system DokaCC
Utilise the benefits of Doka multi-trip packaging Using Doka skeleton transport boxes
on your site. 1.70x0.80m as transport devices
Multi-trip packaging such as containers, stacking pal-
lets and skeleton transport boxes keep everything in Lifting by crane
place on the site, minimise time wasted searching for
parts, and streamline the storage and transport of sys-
tem components, small items and accessories. ➤ Only lift the boxes when their sidewalls are
closed!
9234-203-01
92 999811302 - 04/2016
User Information Tunnel system DokaCC General remarks
Tr755-200-04 Tr755-200-05
A
Tr755-200-02
9206-202-01
999811302 - 04/2016 93
General remarks User Information Tunnel system DokaCC
Doka stacking pallet 1.55x0.85m and Using Doka stacking pallets as transport
1.20x0.80m devices
Lifting by crane
Storage and transport devices for long items:
☞ ▪▪
▪ durable Multi-trip packaging items may only be lifted
▪ stackable one at a time.
Suitable transport appliances: Use a suitable lifting chain
▪ crane (e.g. Doka 4-part chain 3.20m).
▪ pallet stacking truck Do not exceed the permitted load-bearing
capacity.
▪ forklift truck
▪ Load the items centrically.
The Bolt-on caster set B turns the stacking pallet into a ▪ Fasten the load to the stacking pallet so that
fast and manoeuvrable transport trolley. it cannot slide or tip out.
Follow the directions in the "Bolt-on castor set ▪ When lifting stacking pallets to which Bolt-on
B" Operating Instructions! castor sets B have been attached, you must
also follow the directions in these Operating
Instructions!
▪ Spread-angle max. 30°!
= =
a
92815-224-01
Max. load: 1100 kg
Permitted imposed load: 5900 kg a
Doka stacking pallet 1.55x0.85m max. 4.0 m
94 999811302 - 04/2016
User Information Tunnel system DokaCC General remarks
92816-206-01
Max. n° of boxes on top of one another The Bolt-on caster set B can be mounted to the follow-
Outdoors (on the site) Indoors ing multi-trip packaging items:
Floor gradient up to 3% Floor gradient up to 1% ▪ Doka accessory box
3 6 ▪ Doka stacking pallets
It is not allowed to stack empty
pallets on top of one another! Follow the directions in the Operating Instruc-
999811302 - 04/2016 95
Component overview User Information Tunnel system DokaCC
System beam DokaCC 5.00m 640.8 583306000 Packing plate SL-1 2mm 0.69 582864000
System beam DokaCC 4.00m 530.6 583305000 Packing plate SL-1 3mm 1.1 582865000
System beam DokaCC 3.00m 425.0 583304000 Packing plate SL-1 4mm 1.4 582866000
System beam DokaCC 1.00m 167.9 583303000 Futterplatte SL-1
System beam DokaCC 0.50m 99.4 583302000 Galvanised
System beam DokaCC 0.25m 73.5 583301000 Length: 22 cm
Systemträger DokaCC
Width: 22 cm
Painted blue
96 999811302 - 04/2016
User Information Tunnel system DokaCC Component overview
Load distributor DokaCC 168.0 583310000 Strut connection DokaCC 8.1 583316000
Lastverteiler DokaCC Strebenanschluss DokaCC
Galvanised Galvanised
999811302 - 04/2016 97
Component overview User Information Tunnel system DokaCC
Lifting-mechanism frame DokaCC 111.5 583340000 Flanged wheel SL-1 220kN 139.3 582890000
Hubwerkrahmen DokaCC Spurkranzrad SL-1 220kN
Painted blue Length: 47 cm
Width: 22 cm
Height: 40 cm
98 999811302 - 04/2016
User Information Tunnel system DokaCC Component overview
Lowering wedge SL-1 420kN 30.0 582821000 Tie rod 15.0mm galvanised 0.50m 0.72 581821000
Absenkkeil SL-1 420kN Tie rod 15.0mm galvanised 0.75m 1.1 581822000
Painted blue Tie rod 15.0mm galvanised 1.00m 1.4 581823000
Height: 16.8 - 26.8 cm Tie rod 15.0mm galvanised 1.25m 1.8 581826000
Tie rod 15.0mm galvanised 1.50m 2.2 581827000
Tie rod 15.0mm galvanised 1.75m 2.5 581828000
Tie rod 15.0mm galvanised 2.00m 2.9 581829000
Tie rod 15.0mm galvanised 2.50m 3.6 581852000
Tie rod 15.0mm galvanised .....m 1.4 581824000
Tie rod 15.0mm non-treated 0.50m 0.73 581870000
Tie rod 15.0mm non-treated 0.75m 1.1 581871000
Tie rod 15.0mm non-treated 1.00m 1.4 581874000
Tie rod 15.0mm non-treated 1.25m 1.8 581886000
Bracing bolt DokaCC 15.4 583312000 Tie rod 15.0mm non-treated 1.50m 2.1 581876000
Abspannbolzen DokaCC
Tie rod 15.0mm non-treated 1.75m 2.5 581887000
Galvanised Tie rod 15.0mm non-treated 2.00m 2.9 581875000
Tie rod 15.0mm non-treated 2.50m 3.6 581877000
Tie rod 15.0mm non-treated 3.00m 4.3 581878000
Tie rod 15.0mm non-treated 3.50m 5.0 581888000
Tie rod 15.0mm non-treated 4.00m 5.7 581879000
Tie rod 15.0mm non-treated 5.00m 7.2 581880000
Tie rod 15.0mm non-treated 6.00m 8.6 581881000
Fixing bracket SL-1 7.5 582849000 Tie rod 15.0mm non-treated 7.50m 10.7 581882000
Spannkonsole SL-1 Tie rod 15.0mm non-treated .....m 1.4 581873000
Galvanised Ankerstab 15,0mm
Length: 22 cm
Width: 13 cm
Height: 12 cm
Threaded rod 20.0mm .....m 2.5 581477000 Beam support WS10-WU16 5.4 581582000
Gewindestab 20,0mm .....m Trägerauflage WS10-WU16
Galvanised Galvanised
999811302 - 04/2016 99
Component overview User Information Tunnel system DokaCC
Railing adapter XP DokaCC 4.5 583345000 Scaffold tube 48.3mm 0.50m 1.7 682026000
Geländeradapter XP DokaCC Scaffold tube 48.3mm 1.00m 3.6 682014000
Galvanised Scaffold tube 48.3mm 1.50m 5.4 682015000
Scaffold tube 48.3mm 2.00m 7.2 682016000
Scaffold tube 48.3mm 2.50m 9.0 682017000
Scaffold tube 48.3mm 3.00m 10.8 682018000
Scaffold tube 48.3mm 3.50m 12.6 682019000
Scaffold tube 48.3mm 4.00m 14.4 682021000
Scaffold tube 48.3mm 4.50m 16.2 682022000
Scaffold tube 48.3mm 5.00m 18.0 682023000
Scaffold tube 48.3mm 5.50m 19.8 682024000
Handrail post XP 1.20m 4.1 586460000 Scaffold tube 48.3mm 6.00m 21.6 682025000
Geländersteher XP 1,20m Scaffold tube 48.3mm .....m 3.6 682001000
Gerüstrohr 48,3mm
Galvanised
Galvanised
Height: 118 cm
Adjusting plate T 6.5 584393000 Formwork element connector FF20/50 Z 6.0 587533000
Justierlasche T Elementverbinder FF20/50 Z
Painted blue Painted blue
Length: 23.5 cm Length: 55 cm
Stacking plate H20 8.3 580310000 Dokamatic lifting strap 13.00m 10.5 586231000
Aufstocklasche H20 Dokamatic-Umsetzgurt 13,00m
Galvanised Green
Length: 68.8 cm Follow the directions in the "Opera-
ting Instructions"!
Spindle strut 40/80cm 9.4 583247000 Lifting rod 15.0 1.9 586074000
Spindelstrebe 40/80cm Umsetzstab 15,0
Galvanised Painted blue
Height: 57 cm
Follow the directions in the "Opera-
ting Instructions"!
H
S
R
O
N
Q M
L
K P
Ladder cage XS 1.00m 16.5 588643000 Doka stacking pallet 1.55x0.85m 41.0 586151000
Ladder cage XS 0.25m 10.5 588670000 Doka-Stapelpalette 1,55x0,85m
Rückenschutz XS Galvanised
Galvanised Height: 77 cm
Doka is one of the world leaders in developing, manu- technical support are provided swiftly and profession-
facturing and distributing formwork technology for use in ally.
all fields of the construction sector. An enterprise forming part of the Umdasch Group, the
With more than 160 sales and logistics facilities in over Doka Group employs a worldwide workforce of more
70 countries, the Doka Group has a highly efficient dis- than 6000.