NO DESCRIPTION VOLUME BOBOT PROGRESS BOBOT PROGRESS
I PRELIMINARY WORKS
1 Setting out the works (site marking, permission, and site survey) 1,00 ls 0,02385 100% 0,02385
2 Safeguarding the works 1,00 ls 0,03578 100% 0,03578
3 Hoarding Partition dengan Kain Hitam 1,00 ls 0,03578 100% 0,03578
4 Handling material Transportasi pengiriman PP ke PIM 1,00 ls 0,11925 100% 0,11925
5 Material Support & Temporary Scaffolding 1,00 ls 0,03578 100% 0,03578
6 General Cleaning 1,00 ls 0,01431 100% 0,01431
7 Fireproofing Hartindo 0,50 p 0,08109 100% 0,08109
ail
II CIVIL WORKS
1 Supply and Install Single Side Partisi Plywood for Backing Panels 21,97 m 0,18340 100% 0,18340
- Backing for Wood Panel ²
- Plywood 9mm
- Hollow 35 x 35, 0.8mm THK
2 Supply and Install Column Wood Panel (2-3 Sisi) - Walnut Veneer (WD-1) (Shopfront) 13,14 m 0,07208 100% 0,07208
- Width : 100 x 100mm '
4 Supply & Install 3D Lighted Signage THE PALACE (Samping Entrance) 1,00 lo 0,03578 100% 0,03578
- Size "THE PALACE" : 629 x 138 mmH t
- Skirting
6 Supply and Install 1.2mm Thk Gold Stainless Steel Hollow (MT-2) (Shopfront) 5,52 m 0,04213 100% 0,04213
- 1.2mm Thk S/S in Crystal Coat - Golden Laquer Color Fin. '
1,00 100%