Professional Documents
Culture Documents
Complete makeover
T
he Edward W Clark Gener- power industry were dramatically Lower 48’s land area but produced
ating Station transformed different than they are today. At that less than 5% of all the electricity con-
Southern Nevada Power Co time, Nevada had seven small elec- sumed in the US.
from a “wires” company into tric utilities and only 16 generating Clark Station has maintained its
a vertically integrated utility (gen- plants with a total nameplate capaci- leadership position within the com-
eration, transmission, distribution) ty of 597 MW, 98% of that hydro. The pany since commissioning. Recently,
when the state’s first steam/electric only other state in the union that did a complete makeover of the plant’s
plant began operating there in 1955. not have a steam plant was Idaho. assets has helped position NV Energy
By way of background, Edward Clark The mountain states—Montana, among the top utilities in the nation
was the first president of SNPC, Idaho, Wyoming, Colorado, New in terms of environmental perfor-
the company he formed in 1929. Mexico, Arizona, Utah, and Nevada— mance and renewables commitment.
When the 44-MW Unit 1 went into essentially were “undeveloped.” They In brief, generating capability has
service, the country and the electric covered more than one-quarter of the been increased by 117%, to a nominal
Cooling-tower blowdown
Brine concentrator waste Process water from brine concentrator
Unit 8
Unit 7 Fire water Brine concentrator Water treatment
Unit 6 equipment (out of service)
Mfg Co
Peerless
Peerless
Clark Station is located with the city limits of Las Vegas. When the first steam/electric unit began commercial operation
in 1955, the plant stood all alone in the desert. No city would have been visible in an aerial photo like this one. Today the
plant is surrounded by an interstate highway, commercial buildings, and residential neighborhoods. You can even see the
hotels and casinos on Las Vegas Blvd on the horizon. The company’s first three steam units were demolished to make
room for the 12 SwiftPacs, arranged in three blocks of four units each at the bottom of the photo. Two combined cycles
incorporating the four rehabilitated 501B6s (Units 5-8) are at the upper left
58 COMBINED CYCLE JOURNAL, Second Quarter 2009
S W I F T P A C
s Modular Design & Assembly s 0ROVEN &48 ® )ndustrial Gas Turbine
s #onfigurations from 30 – 60+ MW s #OGEneration #APABle
s &AST ,OW
#OST )nstallation s "LACK 3TART #APABIlity
s Permanent or Transportable s $UAL &UEL $ISTILLATE OR 'AS #APABle
W W W . P W . U T C . C O M
PACESETTER UTILITY
1100 MW, while reducing emissions did it while serving admirably as our project gave particularly high marks
by nearly one-half on a tons-per-year plant engineer. I constantly admired to the talented millwrights who call
basis. More specifically: how he always was a calming and Las Vegas their home. About half
n The plant’s four water-injected professional influence on our team of the two-dozen millwrights on the
501Bs with diffusion flame burn- and our vendor partners.” DLN retrofit and all the two-dozen
ers, which had been permitted for Plant history. Three steam/elec- or so assigned to installation of the
103 ppm NOx, have been convert- tric units were the first residents SwiftPacs were affiliated with Local
ed to dry low NOx combustors by at Clark, which was a remote loca- 1827 of the United Brotherhood of
PSM (Power Systems Mfg) LLC, tion when the station was opened. Carpenters and Joiners of America.
Jupiter, Fla, and now operate at In addition to the 44-MW Unit 1, a Interestingly, the Carpenter’s
less than 5 ppm. 60-MW steam/electric Unit 2 began International Training Center,
n Superannuated steam units have operating in 1957, followed by the which trains millwrights and offers
been replaced by12 SwiftPac® 66-MW Unit 3 in 1961. A 54-MW GE an 18-month, university-level Super-
generating units (Pratt & Whit- Frame 7 peaker (designated Unit 4) intendent Career Training Program,
ney Power Systems, East Hart- was added in 1974. is only a proverbial “stone’s throw”
ford, Ct) to provide 600 MW of Three of the four 501 gas tur- from Clark Station.
fast-start, low-emissions peaking bines from Westinghouse Electric An “army” of electricians (162
capacity. Corp were installed in 1979-1980; at peak) was needed to install the
Former Plant Direc- the last in 1982. The gas/oil- SwiftPacs—about 20 times the num-
tor Dariusz Rekowski, fired simple-cycle machines ber required for the DLN retrofit.
who was an active par- were purchased as B3s and Local contractor, Dynalectric Corp of
ticipant in the implemen- upgraded to B5s during the Nevada, said the electricians assem-
tation of both projects, conversion to combined-cy- bled for the peaker project were affili-
said the makeover has cle operation. The upgrade ated with Vegas-based Local 357 of
transformed Clark from to B6 came later. the International Brotherhood of
a base-load facility to an The GTs designated Electrical Workers (IBEW) and clear-
intermediate-generation Units 5 and 6 were con- ly “the best in the West.” This was a
and peaking complex. Its verted to combined cycle in big project for Dynalectric and the
strategic location on the Rekowski
1993 by addition of unfired schedule particularly challenging.
grid, he added, makes the heat-recovery steam genera- Excellent craftsmanship, coordina-
plant ideal for meeting short-term tors (HRSGs) from Zurn Industries tion, and leadership were critical to
customer needs and for backing up Inc, Erie, Pa (since renamed several success, the company said. Dynalec-
intermittent solar and wind resourc- times and now CMI-EPTI LLC) and tric did all above- and below-ground
es. a Westinghouse steam turbine. Addi- electrical work, plus I&C.
Rekowski is a well-liked and tion of bypass stacks enabled each Pipefitters—18 for the DLN proj-
respected leader—an experienced GT to maintain its ability to operate ect and about twice that number for
engineer and manager comfortable simple-cycle. Units 7 and 8 were con- the peaker installation—came from
with dirty hands. He joined the then verted to combined cycle in 1994. Oil Plumbers and Pipefitters United
Nevada Power Co in February 2006 capability was removed from the B6s Association Local 525.
as plant director of the Clark/Sunrise before the millennium.
Complex, just as planning for the Units 1, 2, and 3 were retired in
facility’s future was revving up to 2005. All were demolished in 2006,
full power. Sunrise is five miles from enabling site preparation for the Upgrading
Clark and consists of a 1964-vintage, SwiftPacs. No explosives were used
82-MW steamer and a 501B3 simple- to bring down the boilers; they were legacy GTs
cycle machine. simply pulled down after strategic
Rekowski came from Dynegy Inc cuts were made in support mem-
to meet
where he managed several unregu- bers. This was anticlimactic in a city
lated GT-based plants in Kentucky known for its spectacular implosions
challenging NOx,
and Ohio. He moved to corporate of old casinos. CO permit limits
headquarters at the beginning of Profiles of the DLN retrofit and
I
2009 as O&M director with responsi- peaker projects that follow offer valu- ndustry veterans generally are
bility for work management, outage able guidance for others reviewing aware how differently the EPA
management, and unit availability/ the alternatives at their disposal and powerplant owners define
reliability improvement at the fleet for satisfying the often conflicting the terms “normal maintenance”
level. demands of regulators: Increase gen- and “modifications.” Government
The editors met with Rekowski erating capability within the fence broadly defines the latter as any
and key staff—including Plant Engi- lines of legacy sites, increase avail- physical or operational change that
neer Joe Cook and Operations Man- ability and starting reliability, boost could increase emissions. A “modifi-
ager Steve Page (now acting plant efficiency, reduce emissions, etc. cation” can result in new emissions
director)—several times in the last As you read through the profiles, limits and/or place a legacy unit
nine months to gain the perspective your attention is focused on the con- under the operational requirements
needed to prepare this report. When tributions of NV Energy, EPC con- of NSPS (New Source Performance
Rekowski’s office cleared after one tractor CH2M Hill, PSM, Pratt & Standards) rules.
meeting, he confided: “One of the Whitney, and Peerless Mfg Co to the In June 2007, the Dept of Justice
unsung heroes of our many success- success of these projects. Not readily and EPA announced a major Clean
ful projects here at Clark Station in apparent is the critical role played by Air Act (CAA) New Source Review
the past few years is Joe Cook. Not the talented skilled labor force that (NSR) settlement with Nevada Power
only did he do a great job of manag- did the lion’s share of the field work. Co to resolve alleged CAA violations
ing the PSM project for us, but he One construction manager on the at Clark. As part of the settlement, the
60 COMBINED CYCLE JOURNAL, Second Quarter 2009
Where Superintendents Get Their Powers
The Carpenter’s Now, you can empower your best team
members to become the superintendents
• Leadership, communication, motivation
and negotiation
International you need to perform heroic feats on the • On-the-job experience and professional
job. Just enroll them in CITF’s four-part,
Training Center customized Superintendent Career
mentoring
CITF’s 18-month, university-level Superintendent Career Training Program is available only to our signatory partners.
Water analysis
building/LEC
HRSG controller
Bypass Battery
stack house Wash
skid
Air cooler
Unit 9
Steam
turbines
o m
ro
Silencer
tro
Generator
Unit 10 evap cooler
on
C
GAS TURBINES
4-4. Clark site during conversion from simple to combined cycle. Note that only the HRSG for Unit 8 was installed at the time
Ellis continued, “to support the tion zone and the air/fuel mixture is “Tuning-in” CO requires changing
design effort.” “leaned-out,” decreasing NOx. the diameters of different holes—
Unit 8 components were designed The way you make a hole smaller, ones located on the underside of the
as the data gathered from Unit 7 sug- Ellis said, is to first eliminate it alto- TP (refer again to Fig 4-1). While
gested. First tests showed NOx emis- gether by welding in a blank and Unit 5 met the NOx requirement on
sions were “a bit high.” Recall Con- precision drilling a sharp orifice in the first try, after adjusting orifice
roy’s words that no two engines are that blank of the exact size required. size, PSM wasn’t comfortable with
exactly alike. This generally is not The relatively quick process involves the CO results. Ellis said Unit 5
apparent until you get to measure- removing the combustion liners and passed the CO test according to con-
ments requiring parts-per-million sending them to a qualified machine tract terms, but engineers thought a
accuracy. shop for adjustment, and then rein- rapid swing in ambient temperature
Ellis said “tuning” to achieve stalling the parts removed. NO x could push CO above the permit level
the desired NOx emissions is rela- emissions from Unit 8 were exactly at the lower operating limit (LOL,
tively easy, but it adds a step to the on target the second time around. 55% of rated output). “Customer
commissioning process. It is accom- Assuming Unit 5, which was a care” dictated here, he added, and the
plished by changing the diameter of couple of weeks behind the Unit 8 TPs were removed and their dilution
the three liner dilution holes shown schedule, also would test slightly holes opened up a small amount at
in Fig 4-1. Specifically, Ellis added, high on NOx, PSM modified its liners PSM’s expense.
increasing orifice size reduces head- before the initial fit-up. No further
end combustor air flow and makes adjustments were necessary. When Major steps in
the air/fuel mixture more fuel-rich. it came time to make the liners for transitioning to DLN
This increases flame temperature Units 7 and 6, the same dilution
and NOx production. Smaller dilu- holes that Units 8 and 5 ended up To explain in general terms what’s
tion holes restrict the amount of with were incorporated and emis- involved in converting from a dif-
air allowed to bypass the combus- sions were right on target. fusion combustion system to DLN,
Mechanical Water
package injection skid
Wash
Fuel skid water skid
4-5. Demolishing everything in the photo, save the water 4-6. Wash water skid in Fig 5 retained its original founda-
wash skid, was first step tion; PSM provided the new fuel skid
64 COMBINED CYCLE JOURNAL, Second Quarter 2009
CLARK STATION
Ellis walked the editors through four Production LEC III end Existing Turbine-shell inlet-bleed-heat
major work packages that essentially cover, secondary fuel nozzle, combustion (IBH) off-take port added
flow sleeve, and liner wrapper
defined the project:
n 1. Demolition and site prepara- Modified
TP/R1 vane
tion; installation of an LEC fuel mount block
skid and gas conditioning skid
(one each per GT).
n 2. Conversion to LEC-III.
n 3. Inlet bleed heat.
n 4. Control-system upgrade/inte-
gration and combustion dynamics
monitoring (CDMS) systems.
First step was to demolish the Strut
existing mechanical “cab” or “pack- Existing
age interior,” water injection skid, compressor
and fuel delivery piping—essentially case Existing ID New
New 12-port diffuser Torque tube New transition
everything in Fig 4-5 except for the compressor diffuser seal housing piece (TP)
(torque tube) case/12
water wash skid. The mechanical combustor case struts
package contained the GT lube-oil New parts Modified parts No changes LEC parts
system, original OEM fuel gas and oil 4-7. Conversion to LEC-III required replacement of some hot-gas-path parts,
valves, instrument air, etc. modification of others; some remained as is
Fig 4-6 shows the same area as in
Fig 4-5 with the water wash skid in
the foreground on its existing foun-
dation and the new PSM-supplied
fuel skid behind in the location of
the old water injection skid. A new
gas chromatograph was installed by
NV Energy on the incoming natural-
gas main because of the sensitivity
of DLN systems to fuel composition
and liquid hydrocarbons. The gas
conditioning skid was supplied by
NV Energy to CH2M Hill specs. All
fuel-system piping external to the 4-8. Insulation removed from OEM’s 4-9. Wrapper case off; allowed
fuel and gas-conditioning skids was CC case revealed end cover with gas removal of TPs and combustor bas-
designed by CH2M Hill and installed line (large pipe) and other hardware kets
by the general contractor.
Second step, conversion to been removed when the units were
LEC-III, is relatively easy to fol- converted from simple- to combined-
low if you keep a mental picture of cycle service.
what combustion-system parts are The upper half of the wrapper
being changed, what ones are being case is off in Fig 4-9 to allow removal
modified, and what parts are being of the OEM combustor baskets and
retained. Fig 4-7 summarizes these TPs; rotor air cooling (RAC) pipe is
activities. exposed after removal of combus-
Conversion begins with the most tion components (Fig 4-10). Rotor
mundane of tasks: removal of insula- was picked off the bearings following
tion. The CC case is exposed in Fig removal of the entire upper casing
4-8. The large flex pipe is for fuel (Fig 4-11); lower-half casings are 4-10. Rotor air cooling pipe visible
gas; the other pipes are for water exposed in Fig 4-12. after removal of combustion compo-
and purge air. The oil piping had GT rotors were sent to Sulzer nents
4-11. Rotor was removed and sent to shop for refurbishment 4-12. Lower-half casings exposed after rotor removal
COMBINED CYCLE JOURNAL, Second Quarter 2009 65
PACESETTER UTILITY
4-13. Upper-half casings reinstalled for casing alignment 4-14. Actual casing centerline was needed to assure
check proper reassembly
4-15. Laser alignment tooling used bearing centers as 4-16. Lower half of original CC case was removed next
reference
4-17. Millwright checks area after removal of 4-18. Lower half of new 12-can CC case lowered into space shown
OEM’s CC case in Fig 4-17
Turbo Services Houston Inc, LaPorte, ing alignment data for the PSM surements to properly set the new
Tex, for refurbishment. All were in field service team (Fig 4-13). The casing, he said.
generally excellent condition. The casing-centerline measurement tool Measurements complete, upper-
first-stage turbine disk for one rotor is shown in Fig 4-14, the laser-align- half casings were lifted again and
was replaced because of the large ment tool at bearing center in Fig the lower-half of the 16-can CC
number of factored starts and operat- 4-15. Ellis stressed the importance case removed (Fig 4-16). Millwright
ing hours experienced since commis- of establishing where the actual cas- stands, with the combustion wrapper
sioning. ing centerline is relative to the true at his back, in the space (Fig 4-17)
Next, the upper-half casings were centerline established by the bear- where the new 12-can lower-half case
reinstalled to collect “as built” cas- ings. You must have baseline mea- will be inserted (Fig 4-18). Fig 4-19
66 COMBINED CYCLE JOURNAL, Second Quarter 2009
CLARK STATION
Torque tube
4-19. Upper seal housing
half of new CC
case in position Diffuser case
with 12-strut dif-
fuser case in fore-
ground Strut
4-21. Alignment rechecked with new CC case installed 4-22. Alignment true, lower casing halves are drilled and
doweled to hold their position
4-23. Upper-half casings removed once again and recon- 4-24. Upper-half casings replaced
ditioned rotor installed
shows the CC case upper half in place final alignment (Fig 4-22), the upper- identified at top dead center on the
with the new 12-strut diffuser case in half casings removed, the refurbished OEM’s CC case.
the foreground (diffuser case details rotor reinstalled (Fig 4-23), and the Following installation of the
are in Fig 4-20). machine reassembled. 12-can CC case (Fig 4-24), upgraded
An alignment check with the Ellis noted that the alignment RAC pipes were installed. Pipe shown
upper-half casings installed was next check with the new CC case installed in Fig 4-25 delivers air cooled by the
to assure correct positioning of the offered the opportunity to improve fin-fan heat exchanger to maintain
new CC case (Fig 4-21). That step centering. Such adjustment was proper disk-cavity temperature. PSM
complete, lower casing halves were made on one of the Clark engines redesigned RAC piping to improve
drilled and dowelled to lock in the to correct a heavy rubbing condition its flexibility and prevent cracking
COMBINED CYCLE JOURNAL, Second Quarter 2009 67
PACESETTER UTILITY
4-25. RAC pipe redesigned by PSM to minimize the likelihood of cracking 4-26, -27. Flow sleeve installed in CC
case
4-30. Liner inserted in flow sleeve 4-31. Cross-fire tube in position 4-32. End covers installed
experienced by many machines in the covers with fuel nozzles in Fig 4-32.
501 fleet. Assembled LEC-III combustion
The next series of photos records system is in Fig 4-33; the fuel mani-
the installation sequence for LEC-III folds, flex lines, and piping are shown
components. The lower half of Fig 4-1 in Fig 4-34. Note that the outer ring
is a good reference. Figs 4-26, 4-27 is the primary fuel manifold, middle
show the flow sleeve being installed ring the fuel transfer manifold, and
in the CC case; TP is installed in Fig the inner ring the secondary fuel
4-28. Fig 4-29 shows the flow sleeve manifold. Another upgrade includ-
and TP in position; liner is inserted ed in the retrofit project was the
in flow sleeve in Fig 4-30. Cross-fire replacement of pneumatic IGV (inlet
tubes are installed in Fig 4-31, end guide vane) actuators (Fig 4-35) with 4-33. LEC-III in position
68 COMBINED CYCLE JOURNAL, Second Quarter 2009
CLARK STATION
4-34. Fuel manifolds in foreground: Primary at top, transfer in middle, second- 4-36. Hydraulic IGV actuator
ary at bottom replaced the pneumatic one in Fig 4-35
hydraulic ones (Fig 4-36) to improve ed piping. This included a general handle the LEC-III control logic. The
response and stroke capability. “clean-up” of all engine piping and four gas turbines had been converted
Third step. Installation of the reconfiguration of the pipe rack. from WDPF (Westinghouse Digi-
IBH system, looks somewhat “ho- One example: The OEM’s 11 th- tal Processing Family) to Emerson
hum” in Fig 2, but it had its chal- stage extraction, which provides cool- Process Management’s (Pittsburgh)
lenges. IBH is provided by compres- ing air to turbine R3 and R4 vanes Ovation in 2004.
sor shell air, extracted through the and disk cavities, had two take-off Controls work began with audits
turbine cover (Fig 4-37). To run the points in the lower half of the CC of the existing Ovation I/O cabinets
piping in a manner that would not case. PSM changed this to one extrac- to identify field instruments and
interfere with future maintenance tion in each casing half. The 11th- wiring for demolition. Next, instru-
activities dictated a circuitous route. stage extraction also assists the sixth ment loop drawings were created to
You can get a sense of this in the stage bleed in bypassing compressor provide termination details for new
photo and the diagram: After three air during startups and shutdowns. I/O, including: IBH, CDMS, gas chro-
quick 90-deg turns the pipe angles Another improvement: Changed matograph, new igniters and flame
down the side of the engine, goes from a single- to a multi-port extrac- scanners, redundant instruments for
through the reconfigured mechani- tion arrangement for RAC air sup- critical measurements, and replace-
cal package at the floor level, then ply. ment of old mercury pressure switch-
up, over, and across the air inlet duct Fourth step, DCS modifi- es with transmitters.
before dropping down to the PSM cations. The LEC-III conversion A custom algorithm was designed
manifolds (two per engine). required engineers to remove fuel, by Emerson specifically for PSM to
Dynamic instabilities associat- water injection, and IGV logic from monitor blade-path thermocouples
ed with the combustion process at the existing Ovation® GT control- (TCs) and to calculate the median
lean conditions have the potential to ler and to add a new controller to blade-path temperature, which is
cause excess wear on combus- more stable than average
tion components. A critical blade-path temperature.
function of the CDMS sys- The PSM controls
tem installed on each of the team—Drew Franz, Walt
Clark B6s is to detect harmful Robinson, Jesse Sewell,
pressure pulsations, which and Mitch Cochran—con-
are identified by sophisticat- ducted weekly conference
ed pressure transducers. The calls with CH2M Hill
heart of the CDMS is the Alta and Nevada Power/NV
Systems Inc (San Diego) soft- Energy during the design
ware to analyze combustion phase and maintained
dynamics; it triggers alarms a running action-item
when necessary. list. Note that Cochran
A significant effort was is an independent con-
undertaken during the LEC- trols engineer (Process
III retrofit to improve air Control Solutions LLC,
flow distribution through the Hattiesburg, Miss) and
engine, as well as to improve Ovation expert who was
maintenance access, by more 4-37. Compressor shell air is extracted to heat incoming hired by PSM for the
rigorous design of affiliat- ambient air Clark project. Robinson
COMBINED CYCLE JOURNAL, Second Quarter 2009 69
PACESETTER UTILITY
Combustion
LEC III Ovation® dynamics
controller monitoring
system
4-38. Water analysis building, the first 501B6 control 4-39. Work station sits in front of LEC-III controller and
room, is home to LEC- III controller CDMS
also is an independent electrical/con- tions. Station staff and PSM person- combustors, Rekowski continued,
trols expert. nel simulated, to the degree possible reduces base-load generation by
An onsite design review with using an unmodified GT, the exhaust about 1% and increases heat rate by
Emerson and the utility was conduct- flows and temperatures expected about 0.5%. But this was not of major
ed prior to finalizing the software. during startup, shutdown, and par- concern to NV Energy because the
A two-week factory acceptance test tial and full-load operation when the Clark combined cycles now operate
(FAT) of the Unit 8 software was con- new low-emissions combustion sys- in load-following intermediate-duty
ducted at Emerson’s Riverside (Calif) tem was installed. service. Far more important was
offices. Following that, Emerson rep- That experience and a GateCy- the units’ ability to operate down to
licated control system for Unit 5. cle™ (GE Energy software) study about 55% of rated capacity without
Controls for the remaining two units enabled engineers to make informed exceeding the 5-ppm-NO x permit
were finalized after commissioning decisions on the Rankine cycle hard- requirement.
of Unit 8. ware modifications and operational A cold start when the B6s were
During installation, NV Energy, changes necessary to accommodate equipped with diffusion-flame burn-
PSM, and support contractors hired the LEC-III retrofit. Important to ers, and NOx limits were more lib-
by CH2M Hill worked collaboratively steam-turbine health was the need eral, was conducted at about 25%
to remove the old field instruments to maintain HP steam temperature of rated output—or a nominal 20
and wiring, install the new, and per- between 800F and 850F during start- MW—and was not time-limited. One
form a complete I/O checkout. PSM up and no higher than 950F during hour was a goal for the units when
provided a mechanical completion operation. retrofitted with the LEC III, because
checklist, an Ovation commissioning In particular, ramp up of steam of the startup exemption when the
procedure, and an Ovation settings temperature during cold starts— unit operates above the emissions
document. All were completed and when turbine metal is less than permit limit.
reviewed prior to first fire. 250F—must be carefully controlled However, the higher exhaust tem-
The additional Ovation controller to avoid differential thermal expan- perature and flow associated with
required to accommodate the LEC- sion between the casing and rotor DLN firing at 50% of rated output on
III, and the CDMS, were installed that could cause damaging rubs. cold starts increased steam tempera-
in the water analysis building (Figs Rekowski said GT exhaust tempera- ture and flow to levels inconsistent
4-38, 4-39). It served as the main ture is higher at part load with LEC- with those required for slow warming
control room when the B6s were III combustors than it was with the of the steamer to avoid the damag-
arranged for simple-cycle service. original diffusion burners. Impact of ing rubs noted above. This despite
Benefit of this location: It is both close the hotter exhaust is to increase both modification of the HRSG attempera-
to the GTs and connected to the main HP steam temperature and LP steam tors to control the temperature of
control room in the steam-turbine production (Fig 4-40). steam entering the secondary super-
building via a fiberoptic network. The Replacing water-injected (for NOx heater to saturation plus 20 deg F
utility saved a great deal of money in control) diffusion burners with dry by increasing spray-water flow from
trenches, cable, and labor by expand-
ing the building’s utility. 800F-850F startup/950F normal operation 4-40. Critical
components in
How conversion to DLN Attemperator steam system are
impacts combined-cycle Secondary HP LP
Induction
control the HP super-
operation superheater valve heater attem-
perator and the
Rekowski, plant director during Gas-turbine Steam induction control
exhaust turbine valve in the LP
most of the DLN conversion work,
said NV Energy had to understand circuit
before work began how the upgraded
engines would impact plant opera- Primary superheater
Deron
Turlington
Eric Hartman
Charlie Ellis
Gerald Raresheid
Mitch
Cochran Walt Robinson
Chris Norley Dan
Jesse Sewell
Knudsen
Santiago Vega
Part of PSM’s site support team takes break, leaving the following at work: Drew Franz, Jim Leahy, Mike Geyer, Esam
Abu-Irshaid, and Janak Raguraman
T
increased steam production in the LP he world’s largest SwiftPac construction to proceed. This was a
circuit for most loads that the Clark project officially began in 2006 major undertaking (Fig 4-41). The
combined cycles would be dispatched with its approval by the Pub- two 300-hp tempering-air fans and
at. lic Utilities Commission of Nevada. other auxiliaries required to support
The LP circuit was set up in the CH2M Hill was selected to engineer, each SwiftPac dictated installation
DCS to operate at 90 psig. During procure, and construct the peaking of more than 23 miles of 4-in.-diam
trial operation with the LEC III, facility and received a limited notice PVC-insulated 480-V cable. There
engineers observed that before the to proceed in January 2007; gas tur- also was a high volume of bus work;
combined cycle reached full load, LP bines were ordered the same month. each block was served by one GSU
steam production would cause the To make room for the 12 units, (generator step-up transformer).
induction control valve shown in Fig which are arranged in three power The electrical equipment supply
40 to travel to the wide-open posi- blocks of nominal 200 MW each, the chain was so constrained, the pre-
tion. original gas-fired steam units installed ferred supplier for the power dis-
When that occurred, the DCS sig- at the station were demolished. Units tribution centers required on each
naled the valve to close. Reason: A 1, 2, and 3 had been retired in 2005. SwiftPac could not bid on the project.
minimum pressure drop across the First equipment was delivered in Sep- However, that turned out to be a non-
valve was built into control logic to tember 2007 and the first SwiftPac problem, Forsthoffer said, because
protect against reverse flow—that was commercial before the end of July the winning bidder, Tesla Power &
is, to prevent the induction line from 2008; project was completed by the Automation LP, Houston, proved to
becoming an extraction line. Initially, end of February 2009. be at least equal to any other supplier
plant staff thought to maintain the CH2M Hill’s project manager, in the industry.
pressure drop by bypassing some LP Bob Forsthoffer, said that after the The underground electrical work
steam to the condenser. Planned unit steam units were removed and the was done by a local contractor on
operation would only require this site prepared he had “a big field” to a time-and- materials/self-perform
periodically and the efficiency pen- accommodate the peakers. Site lay- basis. This went so well, Forsthoffer
alty would not be significant on an out was a collaborative effort between said, aboveground electrical work
annual basis. the EPC contractor and the utility to was done the same way. Founda-
But careful re-review of system assure (1) access to underground tion work also was conducted on a
drawings revealed that the LP cir- piping and electrical and control self-directed basis, and by the same
cuit was designed to operate at from cable, (2) ease of maintenance, and firm that did the Allen 4 project (see
90 to 108 psig. Issue was resolved by (3) orientation of engine inlets and Section 7, Arrow Canyon Complex).
changing control logic to maintain a stacks to minimize the possibility of P&W provided detailed foundation
minimum delta p and allow the pres- one engine’s compressor sucking in specifications that included locations
sure to ride up above 90 psig; it will another engine’s exhaust. of grounds, etc.
not reach the condenser dump-valve Forsthoffer recalled that the elec- SwiftPacs can be assembled
set point of 108 psig under any nor- trical work for the Clark peakers was quickly, Forsthoffer continued. They
mal operating scenario. particularly challenging. One reason: fit on one 3-ft-thick foundation pad
72 COMBINED CYCLE JOURNAL, Second Quarter 2009
CLARK STATION
shape in 4-45 and can be completely
installed in three weeks according to
P&W literature (4-46). The control
cab was prewired and factory-tested.
Bala Chitoor, P&W’s project
manager for the Clark SwiftPacs
said he was responsible for timely
delivery of power-island equipment
and for onsite technical support.
Pant-leg duct Schedule was very aggressive, Chi-
toor continued, especially given that
environmental requirements were
among the most challenging in the
Generator nation. Contract specified installa-
tion, testing, commissioning, and
SCR ammonia
injection manifold compliance testing of all 12 units
within 16 months.
Air inlet house NO x emissions are limited to 5
Power ppm, CO to 2 ppm, and ammonia slip
distribution to 5 ppm. Noise criteria are similarly
center FT8-3 package stringent at 85 dBA 3 ft from the
equipment and 5 ft above grade—
4-42. SwiftPacs are installed in a compact arrangement on a 3-ft-thick concrete across the range of 16 Hz to the high-
pad. A savvy crew can complete installation of one unit in three weeks or less est audible frequency. Residences
are within about 100 yards of the
(Fig 4-42) and P&W supplied all to reduce NOx emissions; ammonia is plant property line. It wasn’t always
the interconnecting piping and wir- the reagent for the selective catalytic that way. When the first Clark steam
ing that goes on the mat. No cooling reduction (SCR) system to bring NOx units were installed, the plant was
water is required; a fin-fan cooler emissions within permit limits. remote; today it’s essentially in the
serves the lube-oil system. Follow the SwiftPac erection “middle of town.”
Hook-ups only were required for sequence in Figs 4-43 through 4-46: Peerless Mfg Co, Dallas, was
demineralized water, fire water, and Engine package arrives (4-43); con- P&W’s subcontractor for environ-
ammonia. Demin is used for inlet fog- trol cab is lowered into position (4-44) mental systems. Tim Shippy of Peer-
ging and for injection into the engine with SCR framing at right; unit takes less admitted, “Noise was a par-
4-43. SwiftPacs are delivered in modules ready for instal- 4-44. Control cab is lowered into position
lation. Here a gas-turbine package is brought to its pad
4-45. Erection progresses quickly. Major components 4-46. Nearly complete. The “heavy” work complete, all
and most ductwork are in place that remains is painting
COMBINED CYCLE JOURNAL, Second Quarter 2009 73
PACESETTER UTILITY
Temperature
contours
Pressure
contours
Peerless Mfg Co
4-47. CFD modeling of exhaust gas flow is essential to 4-48. Plexiglas® model confirmed that CFD analysis was
assure meeting emissions limits for NOx and CO correct
ticular challenge.” He said casing glas® model (Fig 4-48). Catalyst was SCR from Cormetech Inc, Durham,
radiated noise and stack exit noise supplied through Peerless: CO from NC.
were the two main sources. P&W BASF Catalysts LLC, Iselin, NJ; Heart of the SwiftPac is a dou-
hired an independent expert to guide ble-ended generator driven by two
acoustic design and Peerless followed FT8 engines with nine combustors
his recommendations, including: 2. Principal each (refer back to Fig 4-42). The
n Extending stack silencers to the natural-gas-fired, water-injected, dif-
tops of the stacks.
equipment, FT8 fusion-flame Model FT8-3 was speci-
n Soundproofing intakes for temper- peakers, Edward W fied for Clark rather than the FT8-2
ing-air fans.
n Using heavy-gauge steel for duct-
Clark Generating DLN version, Chitoor said, because it
offers a higher output and lower life-
work. Station cycle cost (Figs 4-49, 4-50). He added
n Peerless’ scope of supply for the Commercial operation: November that FT8 fleet starting reliability
CO, VOC, and NO x emissions- 2008-February 2009 exceeds 97%; availability, 95%.
control package included the fol- EPC contractor: CH2M Hill Exhaust exits the FT8-3 with
lowing: Type of plant: Simple cycle about 38 ppm NOx; the SCR lowers
n Expansion joints at turbine outlets. that to the 5 ppm permit limit. Swift-
n Exhaust system from the GT out- Key personnel Pac rated output is 61,196 kW at 59F
lets through the stack. Regional director (acting): and sea level. Simple-cycle heat rate
n Ammonia flow control unit and Steve Page at those conditions is 9266 Btu/kWh,
injection grid. Aqueous ammonia Operations manager: Steve Page which translates to 36.8% efficiency.
is vaporized and injected down- Maintenance manger: Jeff Smith The GT package includes a ship-
stream of the CO grid. Maintenance supervisor: pable engine enclosure containing
n Tempering/purge air skid. It pipes Andy Anderson the gas generator, power turbine,
ambient air into the exhaust duct- Plant engineer: Joe Cook exhaust collector box, inlet plenum,
work just ahead of the pant-leg Gas turbines and lube-oil system. The Clark units
and from underneath. Manufacturer: Pratt & Whitney are equipped with inlet foggers and
n Rectangular 60-ft-high stacks Power Systems an off-line water wash system (one
(equivalent to an 18-ft-diam con- Number of machines: 24 (two portable cart-mounted system for
ventional stack). engines per SwiftPac®) each power block).
When faced with designing to meet Model: FT8-3 Highlights of the Clark GT pack-
emissions limits for NOx and CO in Control system: Ovation® (Emer- age specification include the follow-
the low single digits, Shippy said, son Process Management) ing:
you really have to do your homework Fuel: Gas only n Fin-fan lube-oil cooler designed for
and can take nothing for granted. It Water injection for NOx control? operation at 120F ambient.
is important to get good distribution Yes n Two ac and one dc lube-oil pumps
of exhaust gas flow across the entire Water injection for power per turbine.
duct cross section to assure optimum augmentation? No n Air-to-air exchanger for engine
contact with catalyst. Likewise, the Generators, type: Air-cooled cooling designed for 120F ambi-
ammonia injection grid and spray Manufacturer: ent.
nozzles must provide even distribu- Brush Turbogenerators Inc n Two-stage air-inlet filtration sys-
tion of reagent in the flow stream. GSUs (one per block of four tem—prefilter and second stage
Peerless engineers left no ques- SwiftPacs): Siemens AG with high-efficiency media. Capture
tions unanswered with extensive Inlet-air cooling system, type: efficiency of 99.7% for all particles 5
CFD (computational fluid dynamics) Fogging microns or larger; 95% for all par-
analysis (Fig 4-47) and validation Manufacturer: Mee Industries Inc ticles 2 microns or larger—under all
of their proposed design with Plexi- environmental conditions.
74 COMBINED CYCLE JOURNAL, Second Quarter 2009
Put a power plant in your pocket!
Make a Power Plant
Trading Card™
for your facility.
The first plant cards were published in 1998. Since
then, cards have been completed for 115 plants.
They are a big hit on station tours, and a user-
friendly way to communicate with internal and
external stake holders.
industcards
5605 Bent Branch Rd
Be sure to visit the industcards on-line photograph Bethesda MD 20816 USA
industcards
TM