CONSTRUCTION INDUSTRY DEVELOPMENT BOARD MALAYSIA


CERTIFIED CONSTRUCTION PROJECT MANAGER PROGRAM

QUESTION PAPER

MOHD RASHDAN BIN ROSMAN


CANDIDATE NAME : ______________________________________
IDENTIFICATION NUMBER 890210-14-5169
: ______________________________________
6 DEC 2021- 9 DEC 2021
DATE OF ASSESSMENT : ______________________________________
VIA ZOOM
PLACE OF ASSESSMENT : ______________________________________

PERFORMANCE ASSESSMENT (“PA”)


CERTIFIED CONSTRUCTION PROJECT MANAGER

14 DAYS (From the date of receipt the Question for PA)

DO NOT OPEN THIS PAPER UNTIL YOU ARE TOLD TO DO SO

Please write your full name and your identity card For Examiner Use
number in the box provided.

This question paper contain One (1) question. (Full Question Obtained Mark
mark : 100%)

The marks provided for each question or part of the


question are shown in brackets. 1

Bind the answer sheet together with the question


paper and hand it over to CIDB Holdings Sdn Bhd
upon submission.

This exam paper contains 3 printed pages and 3 unprinted pages


[CONFIDENTIAL]

Performance Assessment
COMPETENCY / LEVEL: Certified Construction Project Manager L6
TOPIC: M13 : Contract Management
TASK NO: M13
DATE:
TIME:
VENUE:
INSTRUCTIONS:
1. Please answer the question provided.
2. This booklet contains one section with printed page, including this page. Please read carefully
the instructions of each question in this booklet. It will be used as evidence in your portfolio.
3. Please answer using the provided answer booklet.

CANDIDATE NAME :

IDENTIFICATION
:
NUMBER
Question Number Please Tick () Total Mark Obtain Mark
Question 1 100

Total Marks

Not Yet
Verification Result : First Second
Competent
Competent First Second

TRAINER REMARKS
Date: Date:
Name and Signature of Trainer: Name and Signature of Trainer:

OFFICE USE: CIDB STAMP

2
Please return the question paper to examiner
[CONFIDENTIAL]

This question paper has only ONE (1) question, for the candidate, which contributes 100
marks.

[Kertas soalan ini mengandungi SATU (1) soalan, untuk dijawab oleh peserta yang
menyumbang 100 markah]

SOALAN 1

Case Study:
As a head of Project Management Office for a contractor, you have received a new Contract
Documents, which consists of the following :

(i) The Letter of Award;


(ii) The Articles of Agreement;
(iii) The Conditions of Contract;
(iv) The Contract Drawings;
(v) The Contract Bills;
(vi) Other documents incorporated in the Contract Documents (if any)

After due discussion with the Top Management and as a matter of risk management, you
have been assigned to read and analyse the said Contract Documents and basically to
prepare the table which include the following:
1. Clauses / Items that in relation to the Contractual Rights;
2. Clauses / Items that in relation to Contractual Obligations;
3. Clauses / Items that in relation to Contractual Liabilities.

3
Please return the question paper to examiner
CLAUSES TYPE
Clause 1.3 : Contractor’s design and responsibilities Contractual Obligations

Clause 2.4 : Failure of Contractor to comply with AI Contractual Obligations

Clause 11.2 : No Variation required by Architect shall vitiate contract Contractual Obligations

Clause 11.3 : Issue of Variation after Practical Completion Contractual Obligations

Clause 11.7 : Additional expenses caused by Variations Contractual Obligations

Clause 15.2 : Certificate of Practical Completion Contractual Obligations


Clause 15.3 : Contractor’s Failure to comply with undertaking Contractual Obligations

Clause 22.1 : Liquidated Damages and Certificate of Non Completion Contractual Rights

Clause 22.2 : Agreed Liquidated Damages Amount Contractual Obligations

Clause 22.3 : Certificate of Non-Completion revoked by subsequent Certificate of EOT Contractual Rights

Clause 23.1 : Submission of Notice and Particulars for Extension of Time Contractual Rights

Clause 23.1 : Submission of Notice and Particulars for Extension of Time Contractual Rights

Clause 23.3 : Insufficient Information Contractual Obligations

Clause 23.6 : Contractor to prevent delay Contractual Obligations

Clause 24.1 : Loss and/or expense caused by matters affecting the regular progress of Contractual Obligations
the works
Clause 30.4 : Set Off by Employer Contractual Rights
Clause 30.7 : Suspension of Works for Non Payment Contractual Obligations

Clause 30.10 : Final Account Contractual Obligations

Clause 30.17 : Interest Contractual Lialibilities

Clause 34 : Adjucation and Arbitration Contractual Rights

Clause 20 A :Insurance of New Building / Work by Contractor Contractual Lialibilities

Clause 20 A :Insurance of New Building / Work by Employer Contractual Lialibilities

Clause 26.7 Contractor Rights and and remedies not prejudice Contractual Rights

Clause 28.1 PC sums nominated sums – Nominated Supplier Contractual Obligations