You are on page 1of 4

DURASI DURASI DI BIAYA PERCEPATAN

KEGIATAN NORMAL PERCEPAT BIAYA NORMAL ( Rp) SLOPE BIAYA (Rp)


(Rp)
( HARI) (HARI)
A 5 4 Rp 10,000,000 Rp 11,000,000 Rp 1,000,000
B 5 4 Rp 3,000,000 Rp 3,500,000 Rp 500,000
C 4 3 Rp 1,500,000 Rp 2,000,000 Rp 500,000
D 4 3 Rp 2,000,000 Rp 2,800,000 Rp 800,000
E 5 4 Rp 8,000,000 Rp 8,500,000 Rp 500,000
F 3 2 Rp 5,000,000 Rp 5,600,000 Rp 600,000
G 2 1 Rp 2,000,000 Rp 2,500,000 Rp 500,000
H 3 2 Rp 1,500,000 Rp 2,000,000 Rp 500,000
I 3 2 Rp 5,000,000 Rp 5,600,000 Rp 600,000

CC-CN/DN-DC
JALUR KRITIS

DURASI DI
KEGIATAN DURASI PERCEPAT BIAYA NORMAL ( Rp) BIAYA PERCEPATAN SLOPE BIAYA (Rp)
NORMAL (Rp)
(HARI)
( HARI)
A 5 4 Rp 10,000,000 Rp 11,000,000 Rp 1,000,000
B 5 3 Rp 3,000,000 Rp 4,000,000 Rp 500,000
C 4 3 Rp 1,500,000 Rp 2,000,000 Rp 500,000
D 4 3 Rp 2,000,000 Rp 2,800,000 Rp 800,000
E 5 4 Rp 8,000,000 Rp 8,500,000 Rp 500,000
F 3 3 Rp 5,000,000 — —
G 2 2 Rp 2,000,000 — —
H 3 2 Rp 1,500,000 Rp 2,000,000 Rp 500,000
I 3 3 Rp 5,000,000 — —
Rp 38,000,000
DURASI DURASI NORMAL
AKTIFITAS SLOPE BIAYA
CRASH DI PERCEPAT
CRASH (Rp.1000)
(HARI) (HARI)
21
H 1 20 Rp 500,000
E 1 19 Rp 500,000
B 1 18 Rp 500,000
A 1 17 Rp 1,000,000
B 1 16 Rp 500,000
BIAYA LANGSUNG
OVERHEAD
+ BIAYA SLOPE TOTAL BIAYA
(Rp.1000)
KOMULATIF
Rp 38,000,000 Rp 30,000,000
Rp 38,500,000
Rp 38,500,000
Rp 38,500,000
Rp 39,000,000
Rp 38,500,000