Project Management Unit

Priority River Basins Flood Risk Management Project


Department fo Water Resources and Irrigation

Name of Work : Priority River Basins Flood Risk Management Project


Contract No.: PRBFRMP/WORKS/MK-Basin/CW-01
Name of Contractor:TEAMS-Rajendra-Kumar JV
Date of work Agreement: 2078/03/15 (29 June 2021)
Date of work Start: 2078/04/04 (19 July 2021)
Actual Date of work Completion: 2081/04/03 (18 July 2024)

Work Schedule
2022
SN Work items Description of works
Aug Sep Oct Nov Dec

A Site mobilization and camp establishment


B Pre-construction/verification survey
C Construction drawings
D Approval of construction drawings
E Approval of the borrow area
F Construction materials quality testing
a Sampling and Testing of Gabion Wire & approval
b Sampling and testing of Boulders and approval
c Sampling and testing of Geo-textile and approval

d Sampling and testing of sub-base and base course


materials and approval
G Diversion and dewatering for complete works
H Embankment 1 Site clearance
a Request for Inspection (RFI) & Approval
b Setting out of alignment of the embankment
Cutting, uprooting of grasses, Levelling &
c compaction (site clearance)

2 Earth Work filling for making embankment


a Request for Inspection (RFI) & Approval
Earth Work filling for making embankment with
b excavated (launching apron) and borrrowed pit
soil in 22 cm thick layers

c Compaction and testing in every 22cm thich


layers
Laying of machine made gabion boxes and filling with
3 boulders for launching apron

a Request for Inspection (RFI) & Approval

b Laying of machine made gabion boxes and filling


with boulders for launching apron

4 Laying of geo-textile filter under gabion mattress for


revetment
a Request for Inspection (RFI) & Approval
b Laying of geo-textile
5 Laying of machine made gabion boxes and filling with
boulders for revetment
a Request for Inspection (RFI) & Approval

b Laying of machine made gabion boxes and filling


with boulders for revetment
7 20 cm thick sub-base course
a Request for Inspection (RFI) & Approval
b Laying of 20 cm thick sub-base course
c Compaction and testing and approval
8 10 cm thick base course
a Request for Inspection (RFI) & Approval
b Laying of 10 cm thick base course
c Compaction and testing and approval
30 cm thick ordinary sweet soil and grass sodding in
9 embankment

a Request for Inspection (RFI) & Approval


Earthwork filling with 30 cm thick ordinary sweet
b soil in embankment

Grass sodding & Bio-engineering works in


c embankment
I Spur 1 Construction of gabion spur
a Request for Inspection (RFI) & Approval
Laying of machine made gabion boxes and filling
b with boulders for launching apron in spur
Laying of machine made gabion boxes and filling
with boulders for spur

Public holiday
nit
agement Project
nd Irrigation

Major work
Location: PRTW-00
Embankment: 500 m
Revetment: 500 m
Spur: 10 nos.
Outlet:

2023 Equipments (Nos.)


Water Tipper/
Jan Feb Mar Excavator Loader Roller
Tank Truck

1 1 1 1 2

2 2 1 3
1 2

1 2

1 1